CONTROLLED FILL CERTIFICATE - LEVEL 1 INSPECTION & TESTING
PROJECT Lot Number: 158 TAT REF 3949,001
Stage 1 and 2, Adresse Estate
Point Cook
cuENT Sunland Developments No 11 Pty Ltd DATE + November 2014
Suite 0101, 4 Riverside Quay,
Southbank, VIC, 3006
SUMMARY
Tonkin & Taylor Pty Ltd conducted Level 1 inspection and testing, in accordance with AS3798-2007,
Guldelines on earthworks for commercial and residential developments, during the filing of Stage 1 and 2
at the Adresse Estate in Point Cook
So far as its able to be determined, the site derived and imported Clay fll was placed in accordance with
the Specification that required a minimum density ratio of 95% of HILF Density (AS1289.5.7.1) to be
achieved within moisture content limits of 2.596 wet and 2.5% dry of optimum moisture content (OMC).
UMITATIONS
‘This Certificate has been commissioned by our client Sunland Developments No 11 Pty Lt, forthe filing of
the lots within Stage 1 and 2 at the Adresse Estate in Point Cook. No responsibility or liability will be
accepted for the use of this report for any purpose other than that for which Tonkin & Taylor Pty Ltd was.
engaged, specifically for Level 1 Inspection and Testing ofthe structural fill excluding top soil),
‘This report is based on the conditions present and factors affecting the soil as at the time of Inspection,
which was within the construction period of 7 December 2013 to 6'" October 2014. No responsibilty or
liability will be accepted and Tonkin & Taylor Pty Ltd is indemnified to the full extent permitted by law in
respect of the use of this Certificate where there has been a change in the nature of the project, or in the
site conditions, since the site testing,
TONKIN & TAYLOR PTY LTD
Kiler Dunlh
Robert Barden Tim Chadwick
Project Manager Project Director
(22014181 Py Lit No part of i pubean may be epredcns, ses a tev yn varity fm yey
for above,