Professional Documents
Culture Documents
Using Physical and Duration Percent Complete Types in Primavera P6
Using Physical and Duration Percent Complete Types in Primavera P6
pablojvg@gmail.com
March 2, 2015 By TheP6Pro
https://tensix.com/2015/03/using-physical-and-duration-percent-complete-types-in-primavera-p6/ 1/12
21/9/2018 Using Physical and Duration Percent Complete Types In Primavera P6
Primavera P6 Scenario
Your task is to update the schedule for the
structural phase of a building construction
project, Figure 1.
Figure 1
Figure 2
https://tensix.com/2015/03/using-physical-and-duration-percent-complete-types-in-primavera-p6/ 4/12
21/9/2018 Using Physical and Duration Percent Complete Types In Primavera P6
Figure 3
https://tensix.com/2015/03/using-physical-and-duration-percent-complete-types-in-primavera-p6/ 5/12
21/9/2018 Using Physical and Duration Percent Complete Types In Primavera P6
Figure 4
After entering the remaining duration, and,
therefore, the project status for the rst
week, move the data date and recalculate
the schedule. Your project should look
similar to Figure 5.
Figure 5
Week Two Steps Physical Update
Continue to highlight the Lay Foundation
activity in the activities view. Go back to the
Steps tab in the bottom view and check off
the Lay Rebar and Pour Concrete steps as
being complete, Figure 6.
Figure 6
Then go to the Status tab and check off the
Lay Foundation activity as being complete,
Figure 7.
https://tensix.com/2015/03/using-physical-and-duration-percent-complete-types-in-primavera-p6/ 6/12
21/9/2018 Using Physical and Duration Percent Complete Types In Primavera P6
Figure 7
After entering the status for week two,
move the Data Date, and recalculate the
schedule, Figure 8.
Figure 8
Week Three Status Duration Update
The status for week three is quite simple.
First select the Strike Forms activity in the
activities view then simply select the Status
tab and mark the Strike Forms activity as
Started and Finished, Figure 9.
Figure 9
This is the rst non-milestone and non-
level of effort duration % complete type in
the project schedule. Again, move the Data
Date and recalculate the schedule, Figure
10.
https://tensix.com/2015/03/using-physical-and-duration-percent-complete-types-in-primavera-p6/ 7/12
21/9/2018 Using Physical and Duration Percent Complete Types In Primavera P6
Figure 10
Week Four Status Physical Update
We again want to use the Physical %
Complete Type to describe the progress of
our schedule. The activity is to construct
the exterior walls. This project has a non-
uniform productivity distribution. This is
because of the required mobilization of
material and equipment on day-1 of this
activity. The crew was also new to
constructing this type of wall, so they had a
learning curve. In other words the crew
took 5-days to construct 41.67% of the
wall and only 5-days to construct the
remaining 58.3% of the wall.
Figure 11
As usual, the remaining duration is still
listed as the entire length of the project.
https://tensix.com/2015/03/using-physical-and-duration-percent-complete-types-in-primavera-p6/ 8/12
21/9/2018 Using Physical and Duration Percent Complete Types In Primavera P6
Figure 12
Week Five Status Physical Update
Make certain the exterior walls activity is
highlighted in the activities view. Check the
Finished toggle to enter status, move the
Data Date, and recalculate the schedule.
The schedule will now appear similar to
Figure 13.
Figure 13
Figure 14
Figure 15
Week Seven Status Duration Update
Continue to highlight the interior walls
activity. Now set the duration % complete
to 100% and Primavera P6 will calculate
the remaining duration as 0-days, Figure
16.
Figure 16
https://tensix.com/2015/03/using-physical-and-duration-percent-complete-types-in-primavera-p6/ 10/12
21/9/2018 Using Physical and Duration Percent Complete Types In Primavera P6
Figure 17
Summary
Primavera P6 has different percent
complete types to suit the needs of the
status update.
UPCOMING CLASSES
Primavera P6 Primavera P6 Primavera P6
Training Professional EPPM
Fundamentals Fundamentals
BI Publisher for
Primavera P6
https://tensix.com/2015/03/using-physical-and-duration-percent-complete-types-in-primavera-p6/ 12/12