You are on page 1of 18

1.

) Marquez v Elisan Credit  Petitioner:


Facts:  Petitioner argues that the principal has already been
 Marquez took a loan with Elisan Credit for 53k payable fully paid as the payments that were received by Elisan
within 180-days. Credit which they issued O.R.s for did not specify to
 Marquez executed a promissory note to pay on weekly where the payments were made. This is based on article
installment on 25% annual interest, 10% penalty 1235 which states that payment receipts without
interest on failure to pay in due time, and 25% on reservation to the interest shall presume that the
attorney fees for judicial and extra-judicial expenses in interest has been paid.
case of default.
 Marquez also executed a mortgage for a motor vehicle ISSUE: Has Marquez fully paid the second loan and should
which had a stipulation that it will be a security for the the mortgaged motor vehicle be returned?
first loan which will be also a security for all obligations
already incurred and shall be incurred in the future Ruling:
 First loan was fully paid  Court: Article 1176 as per petitioners argument applies
 A second loan was applied for and was approved for to payment receipts made without reservation to the
55k. A promissory note was also executed with the same interest, thus it implies that the interest has been
terms and conditions as the first one waived
 The second loan matured with an outstanding balance of  Court: Article 1253 resolves doubt as to interest-bearing
25k debts and provide a hierarchy as to where the payment
 Marquez was allowed to pay daily installments until the would first go; it will first be applied to the interest.
obligation is fully paid. 21 months after the due date,  Court: Article 1176 only applies when creditor waives
Marquez has paid a total of 56k on the 55k loan interest
 Despite the payments made, Elisan Credit made action  There is no waiver of interest by respondent
for foreclosure on the mortgaged property asserting that  It was not proven that the respondent accepted the
Marquez has not yet fully paid the second loan as the payment for the principal and waives the interest
55k interest accrued 10% penalty interest and 25%  Since the payment was overdue, interest has
attorneys fees accrued and since no waiver has been made,
 Elisan Credit applied for the issuance of the writ of Marquez payments would be applied to the
replevin and the mortgaged motor vehicle was seized interest first
and delivered to the Respondent
 On the issue of mortgage being carried over to the
CONTENTIONS: second loan: The fulfillment and extinguishment of the
 Respondent: first obligation, extinguishes the stipulation on the
 Elisan Credit argues that the payments made by mortgage
Marquez shall first be deemed as payment to the  The mortgage was an accessory obligation in
interest first before the principal as per Article 1253 of nature, and when the obligation to pay the first
the Civil Code which states that if a debt produces loan was fulfilled, it was extinguished as well
interest, then payments made would first be deducted
for the interest. Thus, the principal has not yet been  Court Partially Grant petition to pay 25k unpaid
fully paid balance. Interest reduced to 2% Interest and 2%
 Respondent further argues that the mortgage covers the penalty interest
second loan as the promissory note on the first loan had
a stipulation that says “obligations that may hereafter
be incurred”
2.) Bautista v Lindo 3.) Boysaw v Interphil
Facts: Facts:
 Bautista sold a free-patent land to the respondent  Boysaw signed a contract to fight Elorde
 Fight is to be held on september 30 1961 or if extended, is within
 3 years after the sale, due to CA 141 which gives rights
30 days.
to repurchase free patent land within 5 years of
 Contract stipulated that Boysaw should not fiht in another contest
conveyance, filed an action to repurchase the land before the fight
 Respondents enetered to a compromise agreement  After signing, Boysaw went to Las Vegas for a boxing contest
where they agree to cede part of the land to petitioner  Manager was also changed
that they later dismissed as there was a failure to state  Due to this change in fight date, they rescheduled the fight date to
the value of the property November 4, then to October 28 to be within he 30days stipulation
 Boxing fight never materialized
Contentions:  Boysaw sued Interphil for damages since the fight in the contract
didn't happen
Petitioner:
 Right to repurchase based on CA 141 and that it is
Issue:
incapable of pecuniary estimation  Does Boysaw have the right for damages?

Repondent: Contentions:
 Cannot repurchase as land is not purely agricultural  Petitioner: Fight did not happen as per contract because of refusal
anymore. of Interphil, thus they are entitled to damages
 That it should be capable of pecuniary estimation  Respondent: Fight did not happen as it was the breach of contract
 That petitioner wants to resell it for a higher profit which that postponed the fight, change of manager and fight in Vegas
is against the spirit of CA 141 to preserve land
Ruling:
 Under the law, when there is a unilateral substitution of the
Issue: obligor by another, the creditor is jot bound to deal with the
 Does Bautista have the right to repurchase the land? substitute

Ruling:  Since there was a breach by Boysaw and Instead of rescinding the
 He has a right to repurchase the same as per CA 141 contract, Interphil postponed the fight with justifiable reason since
 While the sipulation to repurchase is not written in the DAS, Elorde got injured.
it is deemed in effect as contracts are governed by relevant  The renegotiation of the contract for its postponement could not
laws be said to be unlawful or unreasonable
 They even placed the fight date within the 30 days stipulation
 cannot dismiss as complainants have actively participated in
 Boysaws breach of contract has forfeited them of any right to its
proceedings, estoppel enforcement; It gave Interphil the right to rescind the contract
 Their adjustment of the date was, given the circumstances, within
Petition Granted the rights of Interphil

 Lower court decision affirmed that dismissed the complaint


 Excuses of misconduct of manager and rotten logs are not
4.) U.P. v Delos Angeles sufficient excuse for non payment
Facts:  There is breach of contract, not justifiably excused,
 U.P. entered into a logging agreement with ALUMCO for 5 rescission does not necessarily need a judicial suit, Petition
years with extendable period of another 5 years for certiorari granted.
 ALUMCO started and has done its logging operation and
incurred an unpaid account of 219k
 Despite demands, ALUMCO failed to pay. UP then
threatened to rescind the contract.
 ALUMCO executed an Acknowledgement of Debt and
Proposed Manner of Payments which was approved by
president of UP
 It stipulated that ALUMCO was to pay the balance and that
failure to pay shall give UP the right to rescind contract
without any judicial suit
 ALUMCO continued ops and again incurred an unpaid
account of 61k
 Due to this, UP informed ALUMCO that their contract is
deemed rescinded
 UP already acquired another concessionaire to take over
 ALUMCO then filed seveal motions to enjoin petitioner from
conducting bidding

Issue:
 Is the rescission of the contract valid?

Contentions:
 Petitioner: argues that bc of BOC, they had the right to
rescind it without judicial decree bc their contract says so
 Respondent: argues that their non payment was due to
their former general manager not turning over to
management the payments.
 Further they assert that the logs they got were rotten and
could not be sold
 And that the rescission by UP without a court order is invalid

Ruling:
 Contract expressly stipulates the right to rescind even
without judicial suit
 Nothing in the law that prohibits it; it is not necessary to go
to courts for rescission
 The injured party may extra judicially rescind it to protect
its interest
5.) De Mistica v Naguiat 6.) Fil-Estate v Vertex
Facts:
 Petitioner was an owner of land leased to respondent a Facts:
portion thereof was entered into CTS payable in 10 years  FEGDI is engaged in dev of golf courses, sold to RSACC then
and 12% penalty interest in case of failure to pay to Vertex shares of Forest Hills for 1.1m
 After dp and initial payment resp failed to make any  Vertex enjoyed membership privileges being a recognized
payments shareholder but demands delivery of stock cert
 Despite demands, no stock cert issied, Vertex filed for
Contentions: rescission
 Petitioner filed a complaint for rescission due to non  During case, Stock cert was issued but Vertex refused it
payment meaning obligation not fulfilled
 Resp contests it cannot be rescinded as there was a 12% Contentions:
penalty interest stipulated. Further asserts he offered to pay  Petitioners: Argues stock cert non delivery was not a
balance but was refused substantial breach since they are a recognized shareholder
and enjoys its facilities. Thus, the non delivery is not
Issue: substantial
 Does Petitioner have the right to rescind contract?  Respondents:
 Vertex argues the non delivery of stock cert is substantial
Ruling: and its delay of 3 years gave them the right to rescind
 Contract was found to be contract of sale
 Rescission to be allowed should be bc of breach that is Issue:
substantial and fundamental to the fulfillment of obligation  Whether the stock cert delay was a substantial breach
 In his case, the failure to pay within 10 yrs is not
substantial as there was a penalty interest Ruling:
 Further there were no demands made and that the offered  Previous jprudence stated that physical delivery cert is one
payment was refused, thus it was not unexcused of essential requisites for transfer of ownersip of stocks
 Court ruled rescission not possible.  The law states so as well
 Thus the non delivery of stock cert was a substantial breach
 Fegdi failed to deliver it, there was substantial breach,
entitled Vertex to rescind
 Mutual restitution is required for rescission
7.) BPI v Sanchez  They asserted that their negligence was demonstrated when
Facts: they issued the original title despite onlu a 50k payment by
 Sanchezes owned land in Panay Ave qc, Garcia offered to Garcia
buy the property. Offer was only good for 7 days but did not
come to an agreement Ruling:
 Felisa Yap, Widow of one of the Sanchezes agreed to sell  Surrender of title despite 50k payment was not negligence
the property thereafter for 1.85m cash after occupants have but rather simply to comply with their obligation. Further,
vacated property the Sanchezes did not relinquish possession of the said
 Garcia was to process documents for transfer as well property, it was Garcia who took it without their consent
 Yap then turned over title and asked occupants to vacate  There was also no bad faith on the end of the Sanchezes as
 After vacation, Garcia without Yaps knowlefge took can ne seen that they did take action to the construction of
possession of the lot and demolished the house therein Garcia with HLURB on the said lot
 Despite demands, Garcia failed to pay the balance  Garcia are the ones that are in bad faith as they built on the
 Garcia then issued 6 PDCs in favor of Yap, 4 of which was lot knowing that he lot was still in the ownership of the
deposited without issue, but the last two were dishonored Sanchezes
for insifficiency of fumds  Third parties were also purchasers in bad faith as the names
 Yap asked for the replacement of the two cheques but was in the title thy boght were under the Sanchezes yet they
not responded by Garcia didnt question it.
 Yap informed Garcia that she is rescinding the agreement.  BPI were also mortgagee in bad faith as he property for
Garcia then offered to pay 300k which was flatly refused security was in the name of the Sanchezes
 Garcia refused to return documents and to vacate the  The failure of Garcia to pay he Sanchezes entitled he latter
property to rescind contract
 Further, Garcia posted an advertisement in MB offering to  Decision: Restore the titles to the name of Sanchezes and
sell units to reurn documents
 Yap wrote to HLURB that resp illegally constructed on the
property
 HLURB issued a cease and desist order to Garcia from
further developing, Garcia stopped construction.
 Garcia managed to cancel previous TCT and acquired a new
one in the name of TSEI. This is apparently to entice buyers
to buy the units
 Records reveal that the units were sold to numerous buyers
but the TCT was covered by the title of the Sanchezes
 TSEI (Garcia) loaned with FEBTC which then merged wih
BPI.
 Upon default BPI foreclosed the lot of Garcias title

Issue:
 Can the Sanchezes recover the land?

Contentions:
 Petitioner: Asserts that Sanchezes should bear all losses
due to their negligence and that there was no intent to
rescind agreement.
8.) Wellex v United Airlines  Does he First MoA ceased to be in effect?
Facts:
 Wellex owned shares of APIC, PEC, ESB, APC Ruling:
 Uland airlines, a taiwanese airlines, entered to a  Petition denied
memorandum of agreement to expand their respective  under he first MOA, the share purchase agreement was
airline ops im asia necessary before there be a purchade of the stocks
 MoA stipulates to develop a long term business relationship  There should be agreement first before Uland can be
 Moa stipulates ULand to buy shares of stock from Wellex for obliged to pay for the stocks
APIC, PEC, ESB for a certain amount.  No agreement yet thus no final price, thus no obligation to
 MoA stipulates that parties shall enter into a joint pay yet
development agreement  When the 40 days lapsed, they were released from their
 Further, First MoA stipulaes that wihin 40 days, hey shall obligations to negotiate for the share purchase agreement
execute a share purchase agreement for the sale of the
stocks  No express novation of the original obligation
 Further First MoA stipulated to enter into a joint  No subsequent agreement inconsistent with the provisions
development agreement for housing and real estate of the first MoA
development. Buying of stocks as well
 stipulation that if the agreements are not agreed upon
within 40 days, then the First MoA shall cease to be
effective.
 Second MoA was executed as a disclosure to Uland that
Wellex is in he process of acquiring its shares of stock of
APIC

 40 day period lapsed without coming to an agreement


 Despite its absence Uland remitted 8m to Wellex.
 Due to this stock certs were delivered and titles in return
 Despite transactions, no agreements were signed
 Uland then demanded return of 7.5m

Contention:
 Respondent: First MoA is without effect as 40 days has
lapsed and still no agreement. Thus hey should both return
what has been delivered. tHey argue that they would only
pay demandable amount once the share purchase
agreement has been agreed upon

 Petitioner: Petitioner asserts there is already a partial


implementation of the First MoA. Further they assert that
the agreements were not finalized bc of financial problems
on Ulands side. Further the supposed payment of 17.5m for
the stocks were not fully paid.

Issue:
9.) Swire v Yu 10.) Fong v Duenas.
Facts: Facts:
 Swire entered into a CTS with resp. Yu  Duenas is owner of business in baking, food, and retail
 Price is 7.5m on monthly installments plus parking slot for business, old acquaintance of Fong
600k  Entered into verbal joint venture contract where they
 Respondent Yu paid 7.5m fully while dp 20k on parking slot agreed to do food business and create a holding company
 Swire failed to deliver the unit on time. with capital of 65m where they would contribute equal parts
 Resp. Yu is filing for rescission with damages due to failure  Fong started remitting his share of 5m
to deliver  Fong then sent a letter to Duenas that he is limiting his
share to 5m from 32.5m
Contentions:  Despite letter and contribution, duenas has not given
 Petitioner: Petitioner argues breach is not substantial to the financial docs on the valuation of his Danton and Bankcom
contract, thus is not a ground for rescission shares Further the company is yet to be incorporated
 Duenas decided he will cancel the joint venture but he could
 Respondent: Failure to deliver the unit on time is a not return immediately the 5m as it was used in the
substantial breach and is a ground for rescission expenses of his businesses
 After demands and failure to return 5m, Fong filed for
Issue: collection of sum of money and damages
 Is rescission proper in the case?
Contentions:
Ruling:  Petitioner: Asserts he 5m and its appropriation to Duenas
 There is a right to rescind since here was a failure to deliver business amounted to unjust enrichment
said unit and he specific performance became impossible  Respondent: Duenas said the expenses are not for his own
 License to Sell has expired and yet during the inspection of good as his two companies were part of the Alliance
HLURB, the units were done yet and missing cabinets and corporation and that it was Fong who breached contract by
fixtures reducing his shares to 5m which made the incorporation
 Further some of the installed amenities were not what was not push through
agreed upon such as he flooring and swimming pool
 Amenities not yet installed, units not yet done during ocular Ruling:
inspection that is beyond the period of dev under the license  Petition granted
to sell.  Though it was entitled action of money, it was actually a
 The delay of the project as well as the delay in the delivery complaint for rescission by the nature of its body
of the unit are breaches lf statutory and contractual  Duenas failed to submit he valuation of Danton and
obligations which are substantial which entitles for Bankcom shares
rescission.  Court said Fong never agreed for his share to be applied to
 Petition denied with damages. the two companies but to Alliance which is to be used for its
incorporation and initial capital subscription
 He money should have been used for registration
 Duenas further failed to deliver valuation, his delay in
incorporating plus this resulted in his breach
 The Court also notes that there is also breach in the end of
Fong
 He change from 32.5 to 5m is a breach on his end which 11.) Cupino v Pacific Rehouse
happened before he decided to rescind the joint venture Facts:
agreement  Cupino entered to a deed of conditional sale with resp.
 Art 1192, first breach is offset by second breach  Resp. to buy land from petitioner for 6m
 However the Court deemed hat both substantially breached  Resp. made dp of 1.8m and the rest upon fulfillment of
that led to non-incorporation conditions: 1.) Completion of all docs necessary for transfer
 The Court declared each shall bear his own damages 2.) removal of tenants
 Petition granted, to return 5m, respective claims for  Petitioners failed to submit necessary docs despite
damages extinguished. demands
 Petitioner then said they wanted to rescind and refused to
take additional payment
 Respondent found out that petitioners are negotiating sale
with other buyers for higher price

Contention:
 Petitioner: They alleged that Pacific was in default as the
real purchase orice was 11.9m instead of 6m which was
stated in the DAS and its addendum.
 Respondent: Denied hat the price is 6m and that the
Addendum stating that failure to pay 4.1m within 6 months
or is in default would mean the refund of the money, is not
acknowledged since it was not signed by their authorized
rep

Issue:
 Does the petitioner have the right to rescind?

Ruling:
 Petition Denied
 The Deed of Conditional Sale clearly stipulated that the
price was to be 5.9m and the conditions of documents and
vacation of tenants
 The Addendum was not signed by their authorized
representative

 The respondents have partially fulfilled there obligation and


he petitioners have not, there was already a payment on
the end of Rehouse whilst petitioner has not delivered the
necessary documents
 Thus, it is respondent that is the injured party which entitles
them a right to either performance thereof or rescission
 Court ruled that after OB of 1.5m, a DAS should be issued
in favor of petitioner
 Petition denied
12.) Gutierrez v Gutierrez (1932) 13.) Vasquez v. Borja (1944)
Syllabus: Syllabus:
 Upon the showing of negligence, if there is an injured party  One who is party to the contract is the one liable for breaching
he has the right to recover damages said contract, even if the negligence is on the party’s agent so
 Both culpa aquiliana and culpa contractual are sources of long as it does not constitute culpa aquiliana.
obligation for damages.
Facts:
Facts:  Action to recover by Borja (plaintiff) from Vazquez (defendant).
 Vazquez obligated to sell to plaintiff 4000 cavans of palay at
 Plaintiff action to recover damages against five defendants
2.10 per cavan
for physical injuries due to automobile accident
 Plaintiff paid 8400 for the total price of the palay. However,
 Passenger truck and automobile of private ownership Vazquez was only able to deliver 2488 cavans of palay of 5.2k
collided while passing on a narrow bridge value and refused to deliver the remaining palay even with
 The automobile was being driven by the youth Bonifacio demands from plaintiff.
Gutierrez, an incompetent chauffer who was driving at an
excessive speed, and that upon approaching the bridge he Contentions:
lost his head.  Vazquez: Denies having entered into the contract in his
 As a result the plaintiff, Narcisso Gutierrez, a passenger of individual and personal capacity as the agreement was
the truck, was injured (fractured right leg which required between Borja and Natividad-Vazquez Corporation where he
medical attention) was the acting manager.
 Court found that the collision was due to negligence  De Borja: Cause of action is breach of contract due to non-
 Plaintiff is suing both parties, (the truck and the private car) performance by not delivering the remaining cavans of rice.
whereas the truck and the car is suing each other.
Issue:
Issue:  Did the negligence resulting to the non-delivery of the cavans
 Is there liability on the end of the car? The truck? of palay made Vazquez personally liable for such breach of
contract?
Ruling:
Ruling:
 Gutierrez (Car) is liable due to negligence (culpa aquiliana)
 Court found that the contract is between De Borja and the
whereas Velasco (Truck) is liable due to negligence (culpa
corporation, not Vazquez in his personal capacity
contractual)
 No reason to hold Vazquez liable as there is no finding of bad
 Court found that the case is that neither of the drivers faith and intent to defraud the plaintiff
wanted to give way of each other at the narrow passage,  Fact of the case is that there is negligence on the end of the
thus resulting to the collision. corporation but this negligence is culpa contractual (that
 Defendants claim that Gutierrez (passenger) has negligence which causes non-fulfillment of a pre-existing
contributory negligence consisting of him sticking his leg out obligation) as opposed to culpa aquiliana (that negligence
the truck, court found this to be contradictory in the which is the very source of the obligation, “quasi-delict”).
extreme and leads to speculative matters  Since it was the corporation’s contract, and it was their
 Court awards damages to plaintiff, both the truck and car negligence, they are liable for it’s non-fulfillment and
are jointly liable. not their mere agent (as he was not the one with the
obligation).
 Court noted, if it was culpa aquiliana only then would Vazquez
be personally liable.
 Complaint dismissed; no cause of action for counterclaim
14.) Federal Builders (FBI) v. Foundation Specialist (FSI)  Further, FBI in the construction of the diaphragm wall, was
Syllabus: obligated to do a site inspection which they failed to do
 Damages cannot be ascribed to a party if there are foreseen even after the request of FSI to do the same.
circumstances that may cause harm to one party especially  Thus, FSI non-completion of the 3% was justified (no
by the lack of showing of negligence. negligence on their part) and FBI’s non payment of the
amount due was unjustified
Facts:
 FBI entered into an agreement with FSI, where the latter  Petition denied. Lower Court decision of FBI to pay FSI the
will be a subcontractor of the former who would construct missing amount plus interest is affirmed with modification
walls and beams for the Trafalgar Plaza in Makati. that the interest be reduced from 12% to 6%
 Contract price was for 7m.
 FSI filed a complaint for sum of money seeking to collect
1.6m from the petitioner.
 This was based on the fact that the project was 97% done
and FBI has refused to pay the said despite demands
 FBI argues that the project is only 85% complete and that
FSI has failed to construct the works according to plans and
specifications and that because of this, FBI’s overall Project
has been delayed.

Issue:
 Who has the right to demand fulfillment of the other party’s
obligation?

Contentions:
 Petitioner: They assert that the wall constructed by FSI was
defective and out-of-specifications and that they had to re-
do it at their own expense.

Ruling:
 Court found that indeed FSI has done 97% of their
obligation and that the non-completion of the rest was due
to FBI’s own fault such as the failure to deliver the needed
cement for the construction
 The agreement stipulated that FBI was to supply for the
cement to be used for the capping beams yet they failed to
deliver it despite requests of FSI to deliver the same.

 There were also issues on the misaligned diaphragm wall


and erroneous location of the rebar dowels
 This issues were however anticipated by the parties, FSI
knew that there were going to be misalignments thus the
Court found that they cannot ascribe to FSI the defects as
they knew and agreed to work on a remedy together.
15.) NPC v CA the debtor, b.) event must either be unforeseeable or
Facts: unavoidable, c.) event must render it impossible for the
 Respondents are filing for claim of damages versus Napocor debtor of the normal fulfillment of the obligation, d.)
for the loss of lives and destruction to property to the town debtor must be free from any participation or
of Norzagaray, Bulacan. aggravation of the injury to the creditor
 Due to a typhoon, the water volume in the hydroelectric  The Court further cited that: If upon the happening of a
plant of NPC was at optimum levels and they had to fortuitous event there concurs a corresponding fraud,
suddenly release the water. negligence, or delay on the end of the obligor, then the
 This resulted to destruction of property and loss of lives. obligor cannot escape liability.
 The court further cited that to be free from liability: The
Issue: obligor must be free from negligence or misconduct when
 Is Napocor liable for damages even though there was an act the act of God happened.
of God? Or fortuitous event?  In this case, there were findings that NPC didn’t maintain
safe water levels and the written notice was inadequate,
Contentions: thus negligence- even though there is a fortuitous even
 Respondents: argue that despite the knowledge that a they are still liable as they have negligence.
typhoon was to come, they failed to exercise due diligence  The Court noted that since there was participation of man in
in monitoring the water levels of the dam the injury, then the whole event, even with a fortuitous
 Respondents: Because of their failure to monitor the water event, is humanized.
levels, they had to suddenly and recklessly release water  Petition Dismissed.
from the dam that resulted to destruction of property and
loss of lives.
 Petitioners: claim that they exercised due care and diligence
in the operation of the hydroelectric plant which is shown
from the written notices sent to different municipalities prior
to the release and that the damages incurred by the private
respondents were due to a fortuitous event.

Ruling:
 Court found negligence in the end of NPC:
 They should have given room for allowances in the Angat
Dam to expected torrential rains; findings show they
maintained a reservoir water elevation beyond its max safe
level giving no sufficient allowance.
 The written notice was not proper as well as it was only
given to a policeman and not to the proper authorities who
could have disseminated the warning properly; it is as if the
notice has not been served

 The Court citing the decision of Nakpil and Sons v. CA that


for an obligor to be exempt from liability the breach of an
obligation due to an “act of God”, the following must occur:
a.) cause of the breach must be independent of the will of
16.) Nakpil v CA  Further the Court noted that out of the numerous buildings
Facts: in Manila, only a handful including theirs were the ones
 Plaintiff Philippine Bar Association decided to construct office damaged. To follow their reasoning that the earthquake was
building; Construction was undertaken by United overwhelming may not prosper as only some including
Construction Inc; Plans and specifications designed by Juan theirs were destroyed; it cannot be said that God singled
Nakpil & Sons (petitioner). out their building in particular.
 An earthquake hit Manila, the building sustained damages  The Court further held that their negligence was tantamount
and tilted dangerously, because of this the building had to to bad faith as there was gross negligence.
be vacated  Court ruled that UCI and Nakpil are solidarily liable for the
 PBA moved for the demolition of the building as it may damages and to indemnify PBA to cover the damages.
topple down in case of another earthquake, which in fact
the building was demolished.
 A Commissioner was tasked to investigate on the technical
issues and found that: there were defects of the plans and
specifications of the architect and UCI also had fault due to
deviations from plans & specifications, and failure to
observe requisite workmanship in the construction of the
building.

Issue:
 Who is liable for the damage? Or are the parties excused
due to a fortuitous event?

Contentions:
 PBA alleges that it was UCI who was at fault due to defects
in the construction and failure to follow specifications
 UCI alleges that it was Nakpil & Sons who was at fault due
to defects in said plans and specifications
 Nakpil & Sons assert it was an act of God that caused the
failure of the building, which should exempt them from
liability.

Ruling:
 Court noted that generally, no one shall be responsible for
events which could not be foreseen or is unavoidable.
 Obligor may be exempt from liability if there is an act of
God and the obligor does not have any participation to the
injury to the creditor
 If there is participation of man in the injury, may it be fraud
or negligence, the whole occurrence is humanized and
exemptions from liability does not apply
 Negligence of UCI and Nakpil were established beyond
dispute, which has been stated earlier.
17.) Fil-Estate v Ronquillo  Court held that the asian financial crisis was not
Facts: unforeseeable and beyond the control of a business
 Petitioner Fil-Estate Properties Inc., is owner and developer operation.
of Central Park Place Tower  They note that a real estate enterprise engaged in selling
 Respondent spouses Ronquillo purchased from petitioners condominium units should be a master of projections on
condo unit for 5.1m commodities and currency movements and business risks.
 Respondents has paid 1.5m downpayment and had been  Fluctuating movement of the PH-peso happens everyday
paying 63k monthly amortizations and fluctuations therein cannot be identified as a fortuitous
 Upon learning that construction works of the condo had event.
stopped, respondents stopped paying their monthly
amortization as well  Court: Petition partly granted. No fortuitous event,
 Total payment before stoppage was at 2.2m rescission with damages granted. Refund with interest rate
 Respondents demanded full refund with interest due to the lowered from 12% to 6%.
stoppage of construction
 Petitioner reason out that the delay in the construction was
due to the 1997 financial crisis
 Relevant law: PD 957 states that the buyer of a condo unit
has the right for reimbursement if the unit has not been
developed in accordance to the approved plan’s time limit.

Issue:
 Can the 1997 asian financial crisis be considered as a
fortuitous event which would warrant the exemption of Fil-
Estate from liability?

Contentions:
 Fil-Estate asserts that they cannot be held liable for the
delay as it was caused by a fortuitous event, which is the
financial crisis

Ruling:
 Court ruled that the Asian financial crisis is not a fortuitous
event that would excuse petitioners from performing their
contractual obligation
 Cause of action of Ronquillo’s are the right granted by PD
957
 Due to non-performance, non-exemption, unjustified non-
fulfillment of obligation by Fil-Estate, The respondent
spouses have the right to rescind the contract
ART. 1233. A debt shall not be understood to have been paid
unless the thing or service in which the obligation consists has + 1170, 1165
been completely delivered or rendered, as the case may be. ..........Generic Thing 0,,0,0,63
ART. 1246. When the obligation consists in the delivery of an
 A debt may refer to an obligation to deliver money, to indeterminate or generic thing, whose quality and
deliver a thing (other than money), to do an act, or not to circum￾stances have not been stated, the creditor cannot
do an act. demand a thing of superior quality. Neither can the debtor deliver a
thing of inferior quality. The purpose of the obligation and other
1.) Integrity of the prestation - This requisite means that the circumstances shall be taken into consideration.
prestation be fulfilled completely
 Partial or irregular performance will not produce the â— If the obligation consists in the delivery of a specific thing, the
extinguishment of an obligation as a general rule. very thing due must be delivered. (Art. 1244.) However, if the
2.) Identity of the prestation” This second requisite means that the obligation is to deliver a generic thing, the purpose of the
very prestation due must be delivered or performed obligation and other circumstances shall be taken into
consideration to determine the quality or kind of thing to be
..........Specific / Determinate Thing delivered.
ART. 1244. The debtor of a thing cannot compel the creditor to â— Article 1246 is a principle of equity in that it supplies justice in
receive a different one, although the latter may be of the same cases where there is lack of precise declaration in the obligation of
value as, or more valuable than that which is due. the quality or kind of thing to be delivered.
In obligations to do or not to do, an act or forbearance can￾not
be substituted by another act or forbearance against the obligees
will. ..........Preserve 0,,0,0,64
◠Substitution can be made if the obligee consents. Diligence of a good father of a family. — In obligations to give
(real obligations), the obligor has the incidental duty to take care
ART. 1177. The creditors, after having pursued the property in of the thing due with the diligence of a good father of a family
possession of the debtor to satisfy their claims, may exercise all pending delivery. The phrase has been equated with ordinary care
the rights and bring all the actions of the latter for the same or that diligence which an average (a reasonably prudent) person
purpose, save those which are inherent in his person; they may exercises over his own property.
also impugn the acts which the debtor may have done to
de￾fraud them. + 1163
..........Deliver all its Accessions 0,,0,0,65
â— Remedies of creditor if debtor fails to fulfill obligation: 1166, 1164
1.) exact fulfillment (specific performance) with the right to ..........Interest 0,,0,0,66
damages; ART. 1177. The creditors, after having pursued the property in
2.) pursue the leviable (not exempt from attachment under the possession of the debtor to satisfy their claims, may exercise all
law) property of the debtor the rights and bring all the actions of the latter for the same
3.) after having pursued the property in possession of the purpose, save those which are inherent in his person; they may
debtor,’’ exercise all the rights (like the right to redeem) also impugn the acts which the debtor may have done to
and bring all the actions of the debtor (like the right to collect from de￾fraud them.
the debtor of his debtor) except those inherent in or personal to ...........Marquez v Elisan Credit 0,,0,0,76
the person of the latter. ..........Deliver all Accessories 0,,0,0,67
4.) ask the court to rescind or impugn acts or contracts which the + 1166
debtor may have done to defraud him when he cannot in any other ..........Analogous Circumstances 0,,0,0,68
manner recover his claim.
â— ART. 1191. The power to rescind obligations is implied in subsequently, the other also violated his part of the obligation. In
reciprocal ones, in case one of the obligors should not comply with this
what is incumbent upon him. case, the liability of the fi rst infractor should be equitably reduced.
The injured party may choose between the fulfillment and the ● First infractor cannot be determined. — One party violated
rescission of the obligation, with the payment of damages in either his obligation followed by the other, but it cannot be determined
case. He may also seek rescission, even after he has chosen which of them was the fi rst infractor. The rule is that the contract
fulfillment, if the latter should become impossible. shall be deemed extinguished and each shall bear his own
The court shall decree the rescission claimed, unless there be just damages.
cause authorizing the fi xing of a period.
This is understood to be without prejudice to the rights of third ART. 1170. Those who in the performance of their obligations are
persons who have acquired the thing, in accordance with Articles guilty of fraud, negligence, or delay, and those who in any manner
1385 and 1388 and the Mortgage Law. contravene the tenor thereof, are liable for damages.

â— Reciprocal obligations are those which arise from the same â— Fundamental in the law on damages is that one injured by a
cause and in which each party is a debtor and creditor of the other, breach of a contract, or by a wrongful or negligent act or omission
such that the performance of one is designed to be the equivalent shall have a fair and just compensation commensurate to the loss
and the condition for the performance of the other. sustained as a consequence of the defendant’s act.
â— The general rule is that they are to be performed
simultaneously or at the same time such that each party may treat Recovery of Damages
the fulfillment of what is incumbent upon the other as a suspensive ● A breach upon the contract confers upon the injured party a
condition to his obligation. valid cause for recovering that which may have been lost or
â— Remedy is either action for specific performance or rescission, suffered. The remedy serves to preserve the interests of the
both with damages. promisee:
â— Breach of an obligation occurs when there is a failure or 1.) Expectation interest, which is his interest in having the benefit
refusal, by a party without legal reason or excuse to perform, in of his bargain by being put in as good a position as he would have
whole or in part the obligation or undertaking which is incumbent been had the contract been performed;
upon him. 2.) Reliance interest, which is his interest in being reimbursed for
â— Under the rule of exceptio non adimpleti contractus, the party loss caused by reliance on the contract by being put in as good a
who has not performed his part of the agreement is not entitled to position as he would have been had the contract not been made.
sue. 3.) Restitution interest, which is his interest in having restored to
â— Generally, to rescind a contract is not merely to terminate it, him any benefi t that he has conferred on the other party.
but to abrogate and undo it from the beginning.
◠To rescind is to declare a contract void and to abrogate it from ● The award of the different kinds of damages cannot be
its inception. lumped together (e.g., to pay plaintiff actual, moral and exemplary
● Rescission has likewise been defined as the “unmaking of damages in the amount of P100,000). The damages as well as
a contract, or its undoing from the beginning, and not merely its attorney’s fees must each be independently identified and
termination. justified

ART. 1192. In case both parties have committed a breach of the ● Excuse from ensuing liability. — The effect of every
obligation, the liability of the fi rst infractor shall be equitably infraction is to create a new duty, that is, to make recompense to
tempered by the courts. If it cannot be determined which of the the one who has been injured by the failure of another to observe
parties first violated the contract, the same shall be deemed his contractual obligation.
extinguished, and each shall bear his own damages.
● First infractor known. — One party violated his obligation;
● Duty of obligee to minimize his damages. — An obligee is ..........Reciprocal Obligations 0,,0,0,89
duty bound to minimize the damages for which he intends to hold ART. 1192. In case both parties have committed a breach of the
any obligor responsible. (see Art. 2203.) He cannot recover obligation, the liability of the fi rst infractor shall be equitably
damages for any loss which he might have avoided with ordinary tempered by the courts. If it cannot be determined which of the
care. If his negligence was contributory to the loss, the court may parties fi rst violated the contract, the same shall be deemed
equitably mitigate the damages. extinguished, and each shall bear his own damages.
.......Negligence 0,,0,0,90
Damages recoverable when obligation is to pay money ART. 1172. Responsibility arising from negligence in the
● Penalty interest for delay or non-performance. — Damages performance of every kind of obligation is also demandable, but
may be recovered under Article 1170 when the obligation is to do such liability may be regulated by the courts, according to the
something other than the payment of money but when the circumstances.
obligation which the debtor failed to perform consists only in the
payment of money, the rule of damages is that laid down in Article â— The damages or liabilities due to negligence is at the discretion
2209 of the Civil Code. of the courts to determime or mitigate.
● If the obligation consists in the payment of a sum of money, ◠The reason for this is because in cases of negligence, the
and the debtor incurs in delay, the indemnity for damages, there circumstances of a particular case are given great weight
being no stipulation to the contrary shall be the payment of the â— Also, in comparison to fraud, it may be mitigated as there is no
interest agreed upon, and in the absence of stipulation, the legal bad faith or deliberate intention for injury.
interest, which is six per cent per annum. â— If both parties have negligence, their liabilities may cancel each
â— The damage dues (or penalty interest) do not include and are other. Courts may issue an equitable decision based on unjust
not included in the computation of interest as the two are distinct enrichment.
claims which may be demanded separately. While interest agreed
upon forms part of the consideration of the contract itself, damage Validity of waiver of action for negligence
dues are usually made payable only in case of default or non- â— Stipulation for waiver of damages to future negligence may be
performance of the contract. instituted so long as the nature of the contract does not need
● Rate of the penalty interest. — The rate of the penalty extraordinary diligence
interest payable shall be that agreed upon. In the absence of â— Negligence that is gross or shows bad faith os considered and
stipulation of a particular rate of penalty interest, then the treated as fraud, thus waiver for future negligence damages is void
additional interest shall be at a rate equal to the regular monetary
interest; and if no regular interest had been agreed upon, then the Kinds of negligence according to source of obligation
legal interest shall be paid. The payment of the regular interest 1.) Contractual negligence (culpa contractual) - Negligence in
constitutes the price or cost of the use of money and thus, until the contracts resulting to the breach of contract. Negligence that is
principal due is returned to the creditor, such interest continues to incurred during the performance of a pre existing obligation which
accrue since the debtor continues to use such principal amount results to breach of contract or non fulfillment.
â— By virtue of the authority granted to it under Section 1 of Act 2.) Civil negligence (culpa aquiliana) - Negligence that is the
No. 2655, as amended, otherwise known as the “Usury source of an obligation without any pre-existing contract. Also
Law,” the Monetary Board, in its Resolution No. 1622, dated July know as tort or quasi delict.
29, 1974, has prescribed that the rate of interest for the loan or > Negligence within a pre-existing contract may still be considered
forbearance of any money, goods or credits and the rate allowed in as culpa aquiliana. This happens if the negligent act may be an
judgments, in the absence of express contract as to such rate of actionable tort independent of the contract.
interest, shall be 12% per annum 3.) Criminal Negligence (culpa criminal) - Negligent act that results
..........Unilateral Obligations 0,,0,0,88 in a commission of a crime.
ART. 1171. Responsibility arising from fraud is demandable in all
obligations. Any waiver of an action for future fraud is void.
â— A single negligent act may constitute a criminal negligence and
civil negligence at the same time. ........Effects Of Negligence 0,,0,0,91
◠They may claim negligence through criminal action or civil ART. 1170. Those who in the performance of their obliga￾tions
action but may only choose one as the law disallows to recover are guilty of fraud, negligence, or delay, and those who in any
damages twice for the same negligent acts. manner contravene the tenor thereof, are liable for damages.

â— Sufficient establishment of diligence in culpa aquiliana may â— If the negligence is gross or shows bad faith, it's effects are the
extinguish liability whereas it may only mitigate in culpa same as fraud.
contractual â— Gross negligence is negligence characterized by want or
â— When there is negligence in the injured party where his absence of or failure to exercise even slight care or diligence, or
negligence is the proximate cause of his injury he cannot recover the entire absence of care, acting or omitting to act on a situation
damages. where there is a duty to act, not inadvertently but willfully and
â— But if his negligence is only contributory to the injury with the intentionally. It evinces a thoughtless disregard of or conscious
other party having negligence as well, then the recovery for indifferences to consequences insofar as other persons may be
damages may be mitigated. affected, without exerting any effort to avoid them.

ART. 1173. The fault or negligence of the obligor consists in the ART. 1174. Except in cases expressly specified by the law, or when
omission of that diligence which is required by the nature of the it is otherwise declared by stipulation, or when the nature of the
obligation and corresponds with the circumstances of the persons, obligation requires the assumption of risk, no person shall be
of the time and of the place. When negligence shows bad faith, the responsible for those events which could not be foreseen, or which,
provisions of Articles 1171 and 2201, paragraph 2, shall apply. though foreseen, were inevitable.
If the law or contract does not state the diligence which is
to be observed in the performance, that which is expected of a â— A fortuitous event is any extraordinary event which cannot be
good father of a family shall be required. foreseen, or which, though foreseen, is inevitable. In other words,
it is an event which is either impossible to foresee or impossible to
Tests for negligence avoid.
1.) Reasonable care and caution expected of an ordinary prudent
person. â— The essence of a fortuitous event consists of being a happening
2.) No hard and fast rule for measuring degree of care.; depends independent of the will of the obligor and which happening, makes
on nature of obligation, the circumstances of person, time, and the normal fulfillment of the obligation impossible.
place.
● Acts of man. — Strictly speaking, fortuitous event is an
â— If contractual breach is in good faith, the liabilities are those event independent of the will of the obligor but not of other human
that are natural and probable consequences of the breach of wills.
obligation and those that were foreseen or could have reasonably ● Acts of God. — They are those events which are totally
foreseen independent of the will of every human being.

Kind of diligence required Requisites:


1.) that agreed upon by the parties, orally or in writing; 1.) Must be independent of human will or the obligor's will
2.) in the absence of stipulation, that required by law in the 2.) The event could not have been foreseen or even if foreseen, is
particular case (like the extraordinary diligence18 requinred of unavoidable
common carriers); 3.) Event makes it impossible for the obligor to normally fulfill
3.) if both the contract and law are silent, then the diligence obligation
expected of a good father of a family (par. 2.) or ordinary diligence
4.) The obligor must be free from any participation in, or the
aggravation of the injury to the obligee.

â— In order to be exempt from liability arising from a fortuitous


event, there should have been no human participation amounting
to a negligent act.
â— Generally, a person is not reponsible for damages caused by
fortuitous events except when: expressly specified by law or
declared by stipulation.

You might also like