You are on page 1of 11

Different options for Installing

Multi Radio BTS


Bharti Project

Installation options for Multi Radio/Vikas Dhar


Option 1
Feederless Solution for multi Radio
On Platform
GSM Mount

RF Module
System Module Antenna

BTS
Jumper of longer Length
Platform for Installing BTS

Installation options for Multi Radio/Vikas Dhar


Option
Feederless Solution for multi Radio 1
Solution for installing the BTS on Platform:-

1. The Installation of the Base or System module will be on the Platform


provided on the top of the Tower.
2. All the Antenna’s Mount will be close to the Platform.
3. we will only use longer length Jumpers to make a connectivity
between BTS and Antenna’s.
4. In this solution there is no need of feeder cables, all the 3 Antennas
will be connected with the RF module inside the BTS with 6 - 7 mtr
lengths of Jumpers only.
5. The Power, Grounding Cables will get routed from the BTS system
module which is on the top of the Tower to the Shelter, where we
have power plant and the Grounding Busbar’s
6. Alarm cables will get extended from BTS and will be connected inside
the Shelter.
7. For alarms and power cables connectivity we will use IP55 boxes

Installation options for Multi Radio/Vikas Dhar


Option 2
Feederless Solution for multi Radio
On Pole over the top of the BTS
GSM Mount

Antenna

System Module
RF Module
BTS

Mount for Installing BTS

Jumper of longer Length

Note: This pole can be the Existing antenna mount or new proposed mounts.

Installation options for Multi Radio/Vikas Dhar


Option 3
Feederless Solution for multi Radio
Distributed or Remote Radio Head (RRH)
GSM Mount

RF Module Antenna

BTS
Jumper of longer Length
Platform for Installing RF Module

Note:- In this option the RF module will be on the top of the Tower and the system module will be
installed either on the wall or on the tower leg. In this configuration also we will not use any feeder
cable.

Installation options for Multi Radio/Vikas Dhar


Option 4
Solution for multi Radio
On Foundation

BTS RF Module
System Module

Foundation for Installing BTS

Note:- This option can be used at that place where there is an existing foundation of existing BTS
and space is there for installing new BTS. In this option we will use Feeder cables for connectivity
between BTS and Antenna.

Installation options for Multi Radio/Vikas Dhar


Option 4
Solution for multi Radio
On Wall or shelter wall

System Module
BTS

RF Module
Note:- this option can be used at that place where there is no place inside the shelter to install this BTS

Installation options for Multi Radio/Vikas Dhar


Option 4
Solution for multi Radio
On Pole Site (Rooftop pole )

System Module
BTS

RF Module
Note:- This option can be used at that place where there is no place inside the shelter to install this
BTS and if there is space to put the BTS inside the Shelter we will install the same inside see option
number 5 in these slides.
Installation options for Multi Radio/Vikas Dhar
Option
1
Solution for installing the BTS On Pole Site (Rooftop pole ) :-

1. The Installation of the Base or System module will be on the wall of


the shelter or room where Power system is installed.
2. The bts will be at one particular point from there we will connect all
the antenns with feeder cables and jumpers.
3. The Power, Grounding Cables will get routed from the BTS system
module to the Shelter, where we have power plant and the Grounding
Busbar’s
4. Alarm cables will get extended from BTS and will be connected inside
the Shelter.

Installation options for Multi Radio/Vikas Dhar


Option 5
Feederless Solution for multi Radio
Inside Shelter

1. If the existing site is Flexi BTS and is


partally filled or running with a configuration
of 444 then we can install this multi radio
BTS inside the Flexi cabinet.
2. In Case of Ultra BTS as existing Site we
have to look for the space for new BTS
adjesent to the existing BTS as shown in
pic.
3. All the Antennas will be connected with the
Feeder cable and jumpers.
Note :
Ultra bts cabinet can not be used for installing this Multi
radio BTS because the inner dimensions are not 19” rack
compatible.

Installation options for Multi Radio/Vikas Dhar


Flexi WCDMA BTS power consumption Rel.2 HW
SW support since RU10

Flexi WCDMA BTS Min Typical Typical Max


@ W per carrier 10% Load [W] 30% Load [W] 50% Load [W] 100% Load [W]
(FSMD, FRGF, FTHA)
1+1+1 @ min. 20 W carrier 420 460 500 580 FSMD (Rel.2)
1+1+1 @ min. 40 W carrier 510 595 675 845
FRGF (Rel.2)
• W2100
1+1+1 @ min. 60 W carrier 530 650 755 985
• 20/40/60W
2+2+2 @ min. 20 W carrier 510 595 675 845
2+2+2 @ min. 40 W carrier 858 1025 1185 1525
2+2+2 @ min. 60 W carrier 895 1135 1345 1805
3+3+3 @ min. 20 W carrier 765 890 1010 1260
4+4+4 @ min. 20 W carrier 855 1025 1185 1525

Rel.2 HW:
FSMD, System Module, HW capacity 500CE, HSPA+ and LTE compatible
FRGF, RF-module, 20/40/60W antenna output, HSPA+ and LTE compatible
FTHA, Transport Module, 16 x E1, HSPA+ and LTE compatible