You are on page 1of 7

Managing Risk of Tunneling in Cobbly,

Bouldery Ground
Steven W. Hunt
CH2M Hill, Henderson, Nevada, USA
Tunneling Technology Lead – CH2M Hill North American Tunneling and Earth Engineering Group

ABSTRACT
Risks of obstruction, cutter damage, excessive abrasion and steering problems result when tunneling in ground with
cobbles and boulders. To properly manage this risk, cobble and boulder occurrence should be properly investigated and
conditions baselined and specifications should be prepared to help ensure that the tunnel boring machine selected has
the features needed. An overview is given on best practices for subsurface investigation, baselining, prescriptive
specifications and payment items for managing risk of tunneling in cobbly, bouldery ground. After phased subsurface
investigation and cobble and boulder volume ratio determination, cobble and boulder quantities, rock clast properties and
soil matrix properties, particularly gravelly matrix soil, can be baselined for tunnel reaches. Risks can then be managed
by specifying tunneling equipment and contractor requirements that are suited to the risks involved. Some potential
planning and design and construction phase mitigation measures are given.

RÉSUMÉ
L’excavation de tunnels en sols comprenant des galets et rochers est susceptible aux risques d’obstruction, d’abrasion
excessive et d’impact sur le contrôle de la direction. Afin de bien gérer ces risques, la présence de galets et rochers
devrait être l'objet d’examens appropriés et les conditions de base devraient être établies. Les normes du projet doivent
être préparées en conséquence pour assurer qu’une excavatrice de tunnel disposant des fonctionnalités nécessaires est
sélectionnée pour le projet. Ce document présente un aperçu des meilleures pratiques d’investigation des sols,
d’établissement des conditions de base et de préparation de normes prescriptives afin de gérer les risques de
l’excavation de tunnels en sols comprenant des galets et rochers. Suivant le parachèvement de l’examen des sols et la
détermination du rapport en volume de rocher, il est possible d’estimer la quantité de galets et rochers, les propriétés
selon les classifications de la roche et des sols, spécifiquement pour sols graveleux, afin d’établir les conditions de base
pour chaque section de tunnel. Les risques peuvent alors être gérés en spécifiant l’équipement approprié pour
l’excavation de tunnels et des exigences contractuelles qui sont adaptés aux risques encourus. Ce document présente
aussi certaines mesures d’atténuation de risque qui peuvent être implémentées durant la période de planification et de
conception et durant la phase de construction..

1 INTRODUCTION ground condition data; characterize the cobble,


boulder and matrix conditions; quantify cobble
Tunneling in ground with cobbles and boulders involves and boulder volume ratios, sizes, shapes,
risks. Primary risks include: obstruction; reduced advance distributions, abrasivity and rock clast strengths.
rates; steering difficulties; increased risk of excessive lost 3. List hazards, potential consequences and
ground settlements or sinkholes and associated damage; resulting risks - use a risk register to thoroughly
impact or vibration damage to cutter housings or TBM identify and quantity the risks.
gears; increased abrasion and wear of cutters, cutterhead 4. Determine mitigation methods – list mitigation
and mucking system; and lower utilization resulting from options and work with prospective contractors
intervention time to remove obstructions and repair worn and the owner to determine how best to mitigate
tunneling components. The importance of these risks the unacceptable risks through prescriptive
depends on extent of cobbly-bouldery ground and the specifications, baselining, payment items and
tunneling means and methods employed. Assessment of construction administration.
risk severity requires specialized subsurface investigation,
identification of potential hazards, quantification of 2 UNDERSTAND RISKS FROM COBBLES AND
probably of occurrence and potential consequences. BOULDERS
Once risk severity has been determined, mitigation
measures can be selected and implemented. Tunneling risks are not only dependent on the ground
conditions, but also on the site conditions and tunneling
In order to properly manage risks of tunneling in ground methods employed. Site condition factors include: tunnel
with cobbles and boulders, four steps should be followed: depth, surface access constraints (land use and
1. Understand the risks – identify the ground easement restrictions), utility interferences to potential
hazards and associated potential consequences rescue or obstruction removal shafts, dewatering and
for the tunneling methods being considered. ground improvement limits, settlement limits, vibration
2. Characterize and quantify – use special limits and ground contamination. Tunneling method
subsurface investigation methods to collect factors involve: tunnel size and shape; face stability
control measures (open mode vs. closed and pressurized Many hazards and potential consequences are listed
mode); required ground improvement (dewatering, in Table 1. Quantification of the potential consequences in
grouting, freezing, etc.) excavation tools (TBM cutters, terms of safety, cost or delay is much more difficult and
spades, backhoes, rotary milling heads, etc); available depends on specific ground and site conditions. Some of
power (TBM torque-speed, backhoe and milling head the more common severe consequences include:
horsepower, etc); face access (ease of access and free obstructed advance (stuck TBM) requiring an abandoned
air vs. hyperbaric intervention pressurized face access); tunnel drive or rescue shaft or hyperbaric intervention;
mucking system; severe cutter, cutterhead, mucking system or gear
In general, cobble and boulder impact risks are less for damage from impacts or abrasion resulting in a need for a
large tunnels with free air (open-mode) access and higher rescue shaft or hyperbaric intervention to make major
for smaller tunnels with pressurized face (closed-mode) repairs; and much slower than anticipated advance rates
access. This concept relative to obstruction risk is or maintenance delays result in much longer tunneling
illustrated in Figure 1. time and costs.

3 INVESTIGATING, CHARACTERIZING AND


Risk of obstruction

BASELINING COBBLE AND BOULDER


CONDITIONS
MTBM-TBM with no face
access and no disc cutters
Managing risks of tunneling in cobbles and boulders
MTBM-TBM with face requires an adequate understanding of ground conditions
access and the geologic setting. Too often, the site and
subsurface investigation program is not customized to
provide suitable information on cobble and boulder
Open face conditions. In most cases, a routine subsurface
TBM - shield investigation program will not provide the information
needed. What is needed is a geologic desk study followed
by a customized, phased, subsurface investigation
program where each phase is evaluated in a geologic
0% ~ 30% ~70% 100% setting and the next phase is designed to reduce
Relative boulder size remaining uncertainties. All the relevant collected data
should be presented in a geotechnical data report (GDR).
Figure 1 – Risk of boulder obstruction Key cobble, boulder and matrix ground conditions should
be baselined in a geotechnical baseline report (GBR).

Table 1 – Boulder encounter hazards and potential consequences for TBM excavated tunnels
Hazard or Condition Potential consequence
Boulder(s) over ~ 20-30% diameter, no face- Stuck TBM, rescue shaft or shaft-tunnel required
chamber access or disc cutters or TBM-tunnel abandoned
Boulders composed of much harder, stronger Severe pump and slurry line wear resulting in
rock than expected pump failure or line rupture
Cobble and boulder quantities much greater than Severe cutter wear, higher tool replacement cost,
expected potential stuck TBM
Matrix ground or cobbles and boulders are much Severe mucking system wear resulting in
more abrasive than anticipated stoppages for repair or replacement
Boulders in weak-loose matrix resulting in Severe cutterhead wear or rock crusher bar wear,
plucked boulder rolling on cutterhead reduced advance rate, stuck TBM
Mixed face heading weak soil zone adjacent to Steering difficulty, TBM shield deflected beyond
hard bouldery ground line or grade limits
Advance rate higher than allowed for disc cutters Broken cutters or cutter housings and/or cutter
causing plucked rock arms or damaged gears from high impact forces
Plucked boulders extending beyond perimeter or Perimeter voids, excess lost ground, sinkholes,
at face result in voids and ground loss damaging settlements
Perimeter boulder(s) not cut by gage cutters or Pipe or lining damage from passed perimeter
plucked from perimeter boulder causing high contact stresses
Attempt to blast or split boulders at heading in Face instability and excess ground loss at face
free air and unstable soil resulting damaging settlements or sinkholes
Large oblong boulders pass through cutterhead Boulders jam inside rock crusher or excavation
opening chamber requiring an intervention to remove
3.1 Geologic Desk Study and Setting percussion borings; and large diameter auger borings.
Generally less effective methods include cone
An investigation of cobble and boulder conditions should penetrometer probes, cross-hole and surface seismic
be completed in the context of a geologic setting to be refraction, and ground penetrating radar.
effective. The occurrence of cobbles and boulders is Another potentially very effective method to consider is
dependent on geologic processes which affect the horizontal directional drilling or directional-horizontal
character of geologic units. As a result, different geologic boring with coring capability. This method can result in
units tend to have characteristic ranges in cobble and much more sample recovery from the proposed tunnel
boulder conditions. Each geologic unit should be zone and therefore better baselining of cobble and
specifically baselined and as a result, the subsurface boulder conditions.
investigation program should be designed to help define
geologic units. 3.3 Cobble and Boulder Baselining
A site reconnaissance and geologic desk study should
be completed to determine to scope of the initial Cobble and boulder conditions can and should be
subsurface investigation phase. The desk study should baselined for most tunnel projects even where
obtain and include review of available: geologic maps, pressurized face tunneling results in very little or no
reports and papers; previous subsurface investigation access to the heading to determine actual ground
reports from any source in the vicinity; a Phase 1 conditions encountered for comparison to baselines.
Environmental Site Assessment; a geologic site Despite challenges in measuring cobble and boulder
reconnaissance, an initial phase subsurface utility study; conditions encountered, baselines are still essential to
and a review of reports from previous underground help bidders understand anticipated conditions and better
construction projects (shaft and tunnels) in the project manage risks by selecting suitable means and methods,
vicinity. This information should be evaluated to establish estimating reasonable advance rates and planning
an initial geologic setting and a crude risk register (at least mitigation costs.
a list of potential hazards and risks). The scope of the first 3.3.1 What to Baseline
phase of subsurface investigation should be designed to
verify the interpreted geologic conditions, the desk study The primary cobble and boulder (rock clast in soil matrix)
information and to reduce specific uncertainties. related conditions to consider baselining include:
• Quantities and size ranges for anticipated cobbles
3.2 Subsurface Investigation Program
A subsurface investigation program that includes • Quantities and size ranges for anticipated boulders
assessment of cobble and boulder conditions should be
phased and should include multiple exploration methods. • Cobble, boulder distributions and concentrations
After each phase, the geologic setting should be refined along tunnel (isolated vs. clustered) for each
and remaining uncertainties for the anticipated geologic unit
underground construction methods identified. The
subsequent phase should be designed to reduce • Rock clast mineralogy and rock type descriptions
uncertainties and improve geologic condition reliability. including both native and erratic clasts
Conventional 100 to 200 mm diameter rotary wash or
hollow stem auger borings with split spoon sampling is • Rock clast unconfined compressive strength
rarely adequate alone for investigation of cobble and ranges (histogram)
boulder conditions. Conventional borings and sampling
should be completed and can be enhanced by drilling • Cerchar abrasivity index (CAI) ranges for rock
observations such as determination of ‘relative drilling clasts
resistance’ as defined in Hunt 2014.
• Soil matrix types, strength (including degree
In most cases, conventional borings should be
cemented), density, abrasivity and permeability.
supplemented by additional subsurface investigation
methods. The effectiveness and relative cost of ten
Additional conditions to consider baselining include:
subsurface investigation methods was discussed in Hunt
cobble and boulder angularity and shapes.
and Del Nero (2010) and is discussed in more detail in
Cobble and boulder quantities are generally best
Hunt (2014). The most cost-effective additional method is
baselined as boulders per length of tunnel for each
often rotosonic coring. It allows continuous coring and
selected size range, however cobble and boulder volume
sampling and cobbles and boulders. Cobble and boulder
ratios for geologic units should also be given. Other items
sizes and quantities can be determined by careful logging
require baselining of ranges and mean-averages. When
of core samples and extrapolation of sizes from pieces in
sufficient data exists, histograms are generally the best
the core. A study of various exploration methods within
method of baselining. Histograms show both the data
glacial soils in Columbus, Ohio, USA (Frank & Chapman
range and predominant values.
2001) also found rotosonic coring to be the most cost-
The thoroughness of the subsurface investigation
effective supplementary method.
program (available data) and risks involved should guide
Other methods that should be considered and utilized
decisions on how many of these items to baseline. Where
when practical include: test pits (particularly when the
data from a site specific subsurface investigation program
tunnel zone geologic unit can be reached); accessible
is lacking, regional typical value data obtained from the
construction excavations, shafts or quarries; Becker
desktop study might be used. For example, if data from Table 2 – Relative Drilling Resistance (RDR)
other projects or from geologic studies of similar rock
types indicates typical unconfined compressive strengths RDR Term Criteria Typical Ground Conditions
range from 135 to 200 MPa, and site specific data is 1 Very No chatter, Very soft to soft silts and
lacking, the typical local values should be baselined. Easy very little clays; very loose to loose silts
Regarding cobble and boulder quantities, ultimately, resistance, and sands; no gravel,
bidders want to know baseline quantities for expected size very fast and cobbles, boulders or rubble
steady drill
ranges. If the excavated tunnel diameter is known, the advance rate
quantities for selected size ranges along each tunnel
reach can be baselined. Alternatively, cobble volume 2 Easy No chatter, Firm to stiff silts and clays;
some loose to medium dense silts
ratio (CVR) and boulder volume ratio (BVR) can be
resistance, fast and sands; little or no gravel,
baselined for anticipated geologic units or tunnel reaches. and steady drill no to very few cobbles,
3.3.2 Volume Ratio Baselining advance rate boulders or pieces of rubble
3 Mod Some chatter, Stiff to very stiff silts and
Volume ratio methods involve analysis of geologic and erate firm drill clays; dense silts and sands;
subsurface investigation data to determine cobble volume resistance with medium dense sands and
ratio (CVR) and boulder volume ratio (BVR) values for moderate gravel; occasional cobbles or
specific geologic units. The data can often include a advance rate rubble pieces (2-3
percentage per length drilled in cobbly-bouldery ground occurrences per 10 ft)
within conventional borings and CVR-BVR determinations 4 Hard Frequent Very stiff to hard silts and
from a second source such as rotosonic cores, test pits, chatter and clays with some gravel and
or large diameter auger bores. variable drill cobbles; very dense to
To improve interpretation of conventional small resistance, extremely dense silts and
diameter borings, the author developed a BVR correlation slow advance sands with some gravel;
rate dense to very dense sands
chart using cobble and boulder indications such as high
and gravel; very weathered,
Standard Penetration Test (STP) blow counts, Relative soft bedrock; frequent
Drilling Resistance (RDR) - (Hunt & Angulo, 1999; Hunt, cobbles and boulders or
2002; Hunt & Del Nero, 2010; Hunt 2014). Figure 2 shows rubble pieces (3-4 per 10 ft)
the correlation between small diameter conventional 5 Very Constant Hard to very hard silts and
boring indication of boulders and BVR. Tables 2 and 3 Hard chatter, clays with some gravel; very
provide charts for RDR and STP for use in indicating variable and dense to extremely dense
cobble and boulder occurrence. very slow drill gravelly sand or sandy
advance, gravel; very frequent cobbles
nearly refusal and boulders (at least 5 per
10 feet); weathered, very
jointed bedrock

Table 3 – Standard Penetration Test (STP)


Approximate Average Corrected N value
Relative Density of Soil indicating probable
Matrix cobbles and/or boulders
(blows/ft)
Loose > 25
Medium dense > 50
Dense > 75
Very Dense > 100

An interpretation of the data and determination of the


ratio between CVR and BVR is also needed for each
geologic unit. CVRs are generally higher than BVRs. For
several Milwaukee projects studied, cobble volume ratios
were estimated to be approximately 1.5 to 2 times the
BVRs which resulted in much higher cobble quantities due
to their smaller sizes. On the Bradshaw 8 project in
Sacramento, the cobble volume ratios ranged from 25 to
Figure 2 – BVR vs. % bouldery ground in borings (Hunt, 50 percent and were much greater than BVRs due to
2002) fluvial sorting – CVRs typically ranged from 5 to 10 times
greater than the BVRs. On two other projects in California,
CVRs ranged from 3 to 5 times the BVRs. On the
Chengdu Metro project in China, CVRs ranged from 60 to 3.4 Probabilistic methods
85 percent in some geologic units. On the BWARI project
in Columbus, Ohio, a back analysis by the author Attempts to predict boulder quantities using statistical or
indicated an approximate CVR of 0.22% and a BVR of probabilistic methods date back to at least 1976 when
0.34% - a ratio of 0.65 to 1. Estimated total average CVR Stoll 1976 attempted to use a random probabilistic
to BVR ratios for 23 projects studied vary from method. Tang & Quek 1986 published the results from a
approximately 0.5 to 10 and average about 2. statistical evaluation of the lengths of boulders taken from
Once a percentage of cobbly and bouldery ground per boreholes in sedimentary deposits in Singapore. They
unit boring length for each geologic unit is determined showed a statistical correlation of lengths in boreholes
from conventional borings, CVRs and BVRs can be with excavated boulder sizes. Probabilistic methods were
estimated for each geologic unit using Figure 2. The also used for the Storebaelt Tunnel in Denmark (Ditlevsen
resulting estimates should be compared to CVR and BVR 1997, 2006) and more recently for a tunnel in Italy (Felletti
date from the other subsurface exploration sources as 2009).
well as data from previous shaft and tunnel excavations in The most extensive study of subsurface exploration for
the same geologic units. Any inconsistencies should be tunneling in bouldery ground and development of an
rectified if possible, but ultimately the more reliable and approach to predict boulder quantities and sizes for
often the more conservative interpretations are used. baselining was completed by Frank & Chapman, 2001
Specific quantities of cobbles and boulders can be during the early to mid-2000’s for the BWARI project in
estimated for shaft and tunnel excavation volumes in each Columbus, Ohio. They developed an exponential
geologic unit using a spread sheet. The size ranges distribution relationship similar to that used for the
desired and maximum anticipated boulder size must first Storebaelt Tunnel. The number of clasts (boulders)
be selected. Figure 3 shows BVR data evaluation expected is computed as N=C/V•d where: N = no. clasts,
completed for a tunnel reach using a negative exponential V = volume excavated, C is a constant correlated with
distribution function within an Excel spreadsheet. sample size data, and d is a constant correlated with clast
Subsurface investigation data analysis is used to estimate size distribution ([Frank & Chapman, 2005). The method
the mean size and standard deviation for each tunnel requires a significant amount of reliable sample data from
reach in a geologic unit. An “area factor” calculation is the subsurface investigation. The constant d is evaluated
completed to convert computed boulder volumes into from boulder sizes found in the investigation. The
boulder quantities for each size range. The result is an constant C is calculated from boulder volume data. The
estimate of the total number of boulders for the reach number of clasts for selected sizes is then computed
being analyzed. The resulting boulder quantities can then using the formula with these constants. Tunneling results
be baselined. indicated that boulder quantities were slightly over-
predicted, but accurate estimates of actual boulders

Figure 3 – Boulder size distribution for anticipated BVR value


encountered were difficult to make from the broken rock severe when the difference in density and strength
and very large quantities of muck. between the rock clasts and matrix are more extreme,
such as when cobbles and boulders are in a loose, soft
3.4.1 Baselining Conclusions matrix.
Which aspects of cobble and boulder conditions to 4.3.1 Risk Assessment
baseline and whether or not to directly baseline conditions
or use functional baselines depends on the ground Hazards and potential consequences from encountering
conditions, anticipated methods of construction and anticipated cobble and boulder conditions for each
project owner’s preference for risk sharing. The method to tunneling method being considered should be analyzed
use for evaluating data to predict quantities for baselining using a risk register. This form of risk assessment
should depend on the size of the project and the quality requires reliable data on cobble and boulder conditions
and quantity of data available. When desired to baseline from a thorough, phased subsurface investigation
quantities, the CVR and BVR method is generally more program and tunneling experience provided by tunnel
practical than probabilistic methods for most projects. engineers, contractors and TBM manufacturers. Once risk
Probabilistic methods are viable for larger projects with a levels have been determined, risk allocation and
significant amount of quality data. In either case, the mitigation measures can be determined.
method should consider the geologic setting, geologic
variability and local experience. 5 MITIGATION METHODS

4 HAZARDS, POTENTIAL CONSEQUENCES AND When assessment indicates high, unacceptable tunneling
RESULTING RISKS risks from cobbles and boulders, they should be avoided,
mitigated or allocated. Avoidance and mitigation
The occurrence of cobbles and boulders creates a large measures generally involve both planning and design
variety of hazards that may result in concernable risk decisions and construction actions.
depending on the ground conditions, surface conditions
and tunneling method. In general, these risks can be 5.1 Planning and Design Mitigation Measures
grouped into three categories: obstruction, abrasion and Significant cobble and boulder risk avoidance and
impact vibration. Hunt 2014 provides a detailed discussion mitigation may occur during planning and design. Reliable
of these risks. A general overview is given below. data on anticipated cobble and boulder ground conditions
4.1 Obstruction Risk and tunneling methods is required. Planning and design
phase avoidance and mitigation measures may include:
Obstruction risks are those that may obstruct or stop the • Vertical and horizontal alignment changes to
tunnel advance, significantly slow the rate of advance or avoid or minimize extent of tunneling in
result in steering problems. A large boulder or clusters of adversarial ground conditions.
cobbles and boulders may stop tunnel advance if the • Horizontal alignment changes to minimize
energy required to break and ingest the rock clasts overhead interferences and obstructions that
exceeds the capabilities of the TBM and cutters. TBM would prevent a rescue shaft if needed.
obstruction and advance rate reduction are very common • Tunnel depth changes to avoid zones with high
tunneling risks (Hunt and Mazhar 2004). A serious risk of CVRs and BVRs or minimize adversarial ground
MTBM stalling from excess intake of gravel, cobbles and conditions such as high permeability.
boulders exists where the matrix is mostly gravel or where • Spacing and locating shafts to reduce drive
the CVR exceeds ~30 percent. Hunt et al 2013 provides a lengths and associated wear impacts and to
thorough discussion of this risk and methods of mitigation. allow for easier repairs and maintenance of TBM
4.2 Abrasion Risk components.
• Spacing and locating ground improvement ‘safe
Abrasion risks are related to wear or breakage of zones’ to allow open mode interventions for
components that come into contact with the ground and cutter changes and cutterhead repairs.
muck including: cutters, cutterhead, crusher and mucking • Increasing the allowable or specified tunnel
system. The occurrence of cobbles and boulders can diameter to improve potential TBM power, face
significantly increase the rate of abrasion of components access and intervention options.
beyond that caused by the abrasiveness of the matrix soil • Use of prescriptive specifications to require
(Gharahbagh et al 2012). The increase is dependent on bidders-contractors to have minimum essential
the abrasiveness of the cobble and boulder rock clasts TBM system components. This might involve:
and the CVR and BVR magnitudes. cutter types, cutterhead armoring, cutterhead
4.3 Impact Risk opening ratio restrictions, excavation chamber
access, hyperbaric intervention requirements,
Excavating and ingesting cobbles and boulders causes TBM torque-speed requirements, conditioning or
impact forces and vibrations. Impacts tend to cause cutter slurry requirements to minimize abrasion, TBM
and cutter housing breakage and may cause cutter type restrictions, purpose-build new TBMs vs.
bearing or gear-pinion failures. The risk of impact refurbished used TBM requirements, advance
consequences increases with boulder size and CVR and
BVR magnitudes. Impact forces also tend to be more
probing and grouting from TBM requirements, REFERENCES
and more.
Ditlevsen O. 1997. Probability of boulders. In: Storebaelt
5.2 Construction Actions East Tunnel, N.J. Gimsing, (Ed). A/S
Depending on specification requirements, contractors and Storebæltsforbindelsen, Copenhagen, (1997) 39–41.
TBM manufactures have a considerable to full range of Ditlevsen O. 2006. A story about distributions of
potential mitigation measures to manage cobble and dimensions and locations of boulders, Probabilistic
boulder risks. Again, reliable data on anticipated cobble Engineering Mechanics, Elsevier-Science Direct, (21-
and boulder ground conditions is essential to allow 1) (2006), 9-17.
effective construction phase risk mitigation. Felletti F. & Pietro-Beretta G. 2009. Expectation of
Contractors and TBM manufactures have the most boulder frequency when tunneling in glacial till: A
control over TBM robustness and components to statistical approach based on transition probability,
eliminate or resist cobble and boulder impacts. These Elsevier-Science Direct, Engineering Geology, (108)
measures have a cost that must be managed through (2009), 43-53.
bidding, pay items and contractor controlled risk Frank G. and Chapman D. 2001. Geotechnical
management. Investigations for Tunneling in Glacial Soils, In:
Some of the contractor and TBM manufacture cobble Proceedings of 2001 Rapid Excavation and Tunneling
and boulder risk mitigation measure options are: Conference. W.H Hansmire & I.M Gowring (Eds),
• TBM type and component design: cutter types, SME, Littleton, Colorado, (2001-26), 309-324.
cutter access, excavation access, cutterhead Frank G. & Chapman D. 2005. New Model for
and mucking system materials and armoring, Characterizing the Cobble and Boulder Fraction for
grizzly bars, rock crusher, EPB screw design, Soft Ground Tunneling, Hutton J.D. & Rogstad D.
face access, air locks, etc. (Eds), In: Proceedings 2005 Rapid Excavation and
• TBM and mucking system operation measures: Tunneling Conference., SME, (2005-60), 780-791.
advance rates, cutterhead rotation speed-torque, Gharahbagh, E.A., Frank G., DiPonio M. A., Shinouda. M.
conditioner use, slurry design, mucking system M. and Rostami, J. 2012. Cutterhead Wear Study for
features, and advance probing and grouting EPB TBMs in Glacial Soils. Proceedings of North
capability. American Tunneling Conference. 2012. SME.
• Shaft spacing and locations affecting drive N2012.13, 100-108.
lengths including additional shafts or safe zones Hunt S.W. and Angulo M. 1999. Identifying and Baselining
for interventions. Boulders for Underground Construction. In: G.
• Frequency of inspection and maintenance Fernandez & R.A. Bauer (Eds), Geo-Engineering for
activities. Underground Facilities. ASCE, Reston Virginia, 1999,
255-270.
Hunt S.W. 2002. Compensation for Boulder Obstructions.
6 SUMMARY AND CONCLUSIONS In: Proceedings of The North American Tunneling
2002, Ozdemer L., (Ed), Rotterdam: Balkema, (2002-
3), 23-36.
During the past twenty years, the tunneling industry has
Hunt S.W. & Mazhar F.M. 2004. MTBM and Small TBM
made considerable improvements in capability to
Experience with Boulders. In: Proceedings of North
successfully microtunnel and tunnel in cobbly-bouldery
American Tunneling 2004, Ozdemir L. (Ed.), SME,
ground. Subsurface investigations have gotten more
Littleton, Co., (2004-6), 47–64.
varied and focused to obtain necessary data. A database
Hunt S.W. & Del Nero, D.E. 2010. Two Decades of
of typical cobble and boulder volume ratios for common
Advances Investigating, Baselining and Tunneling in
soil types has grown. Designers have developed practical
Bouldery Ground. Proceedings of World Tunnelling
and statistical methods to predict cobble and boulder
Congress. Vancouver, ITA-TAC, 2010, 8p.
occurrences. These methods have been used with
Hunt, S., Del Nero, D. & Finney A. 2013. Microtunneling in
reasonable success on many projects. Baselining and
Gravel, Cobbles, and Boulders, In: Proceedings 2013
pay items (where applicable) have helped to significantly
Rapid Excavation and Tunneling Conference, SME,
reduce the contractual and cost risk of excavating through
R2013.18, 226-239.
cobbly-bouldery ground. Risk management methods
Hunt S.W. 2014. Tunneling in Cobbles and Boulders.
should be used to assess cobble and boulder risks along
Proceedings of Breakthroughs in Tunneling Short
all portions of the alignment. Where the consequences of
Course. Colorado School of Mines, September 15-17,
getting stuck are high or where the cost of interventions to
2014, 38p.
change cutters is excessive, contract documents might
Stoll U.W. 1976. Probability That A Soil Boring Will
require more robust TBMs or MTBMs with face access
Encounter Boulders. In: Conference on Better
and combination roller and scraper cutters. Where
Contracting for Underground Construction, Michigan
conditions are bad and risks are high, redundancy and
Section of ASCE, Detroit (1976), 34-48.
backup plans should be designed with appropriate pay
Tang W., Quek S.T. 1986. Statistical model of boulder
items to manage uncertainties and risks.
size and fraction. Journal of Geotechnical and
Geoenvironmental Engineering, 112 (1), ASCE (1986)
79–90.

You might also like