Quality Management Plan

1.2

1.2
Quality Management Plan
Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
The Gerald Desmond Bridge Replacement Project Proposal

1.2 Quality Management Plan


RFP ITP Appendix B § 1.2; D § 1.1.2

1.2.1 Overview SFI Advantages


■ Extensive risk management experience on large
1.2.1.1 Quality Approach infrastructure projects.
■ Potential savings on Builders Risk Policy
The SFI Team’s Policy commits the resources premium.
required to effectively implement and maintain, ■ Reduced risks on schedule, environment, qual-
the Quality Management Plan (QMP) and to ity, and safety.
continually improve its effectiveness. FCC,
Impregilo and Arup each has ISO 9001 certifi- exceed the requirements of the Port (“Owner”),
cation of their Quality Management Programs, as well as those of Caltrans and FHWA. Excel-
and these Quality Programs, along with the lent quality will be obtained through appropriate
Port’s Quality Manual Template (Exhibit 2-2- planning and control of work operations and
A), form the basis of this QMP. through a comprehensive quality control
The SFI joint venture will have full responsibil- process that will provide the right level of
ity for the overall quality assurance and quality resources to review work plans and procedures,
control for both the design and construction check materials and physical conditions of
elements. This will include managing the quality adjoining and adjacent work items, plan and
of the Work and materials by designers, sub- perform inspections and testing, and quality
contractors, fabricators, suppliers, vendors, and surveillance/auditing.
all other entities involved with the design and SFI will monitor its performance against the
construction elements of the Project. quality goals and continuously look for ways to
SFI will ensure that the QMP meets or exceeds improve the quality process.
the requirements of the contract documents. In addition to the focus on project quality, the
The implementation and enforcement of the QMP will also be coordinated with SFI’s design
procedures, inspections, and controls of the and construction activities to promote safety,
QMP have the unconditional support of SFI’s with minimal impact to traffic flow, on
project management team and the Executive schedule, and within budget.
Management Committee. The Quality Manager,
who reports directly to the Executive Manage- In accordance with the requirements of the
ment Committee, will be responsible for the contract documents, the QMP will be imple-
implementation of the QMP. SFI will support mented with focus on the following objectives:
the Quality Manager with all the necessary ■ Implementing a well-designed quality pro-
resources to ensure a high-quality Project. gram and continually improving all aspects
The Executive Management Committee has of the process as the Project progresses.
committed to establishing a strong Quality ■ Establishing a Quality Partnering Charter
Management Policy, including quality objec- committed to team values of honesty,
tives, communicating the importance of meet- quality, pride, professionalism, integrity and
ing regulatory requirements, conducting project listening to successfully achieve the quality
quality reviews on a quarterly basis, providing goals.
resources to meet project quality requirements
and continually improving the work process and ■ Partnering with the Port to make the design,
deliverables. construction, and management processes
open to inspection and oversight.
1.2.1.2 Quality Management ■ Demonstrating our commitment to quality
Goals throughout the design and construction of
SFI’s quality management goals will result in the Project.
quality products and services that meet or ■ Effectively communicating the QMP to all

Volume 2 – Section 1 – page 31


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
Gerald Desmond Bridge Replacement Project Proposal

members of the design and construction and elements of the Work complies with the
team, so that the QMP is implemented as requirements of the Contract Document. The
part of the triangle with schedule and budget. QMP will also ensure that all materials
incorporated into the Work will perform
■ Basing decisions on factual information satisfactorily for the purpose intended.
gathered in a manner that is open to inspec-
tion to prevent undue influence of personnel The approach of the QMP will be to outline a
tasked with meeting schedule and budget strict set of requirements for ensuring the work
goals, potentially at the expense of quality. is properly planned and checked. This process
will focus more on the initial steps before the
■ Empowering quality personnel through actual construction of the Work. This includes
support from upper management and from quality reviews during design of the Project,
clear definition and communication of preparation of detailed work plans prior to each
quality roles. of the significant construction operations,
■ Bringing subcontractors and suppliers to the review of all necessary details to perform each
team who are as committed to providing a operation, and ensuring all controls are in place
superior end product and meeting the to verify work is compliant.
project quality requirements.
Quality management will be handled through a
■ Implementing improved electronic series of steps that will include the following:
document and data management that is
accessible to the Port and that continues ■ Preparatory – At this step, the upcoming
effectively from the design through sequence of definable work will be evaluated
construction phases. by the effected parties. The work items will
be reviewed to ensure all submittals,
1.2.1.3 Continual Improvement materials, personnel, and plans are in place to
properly perform the Work.
Continual improvement will require the com-
mitment of all of the SFI project staff. SFI ■ Preliminary – At this step, the necessary
management will work to create a culture that parties will be brought back together to
encourages people to actively seek opportunities review that all items identified during the
for improvement of performance in processes, Preparatory step have been completed and
activities, and quality of products. are ready for the work to proceed.
Authority will be effectively delegated so that ■ Production – Activities preceding this step
project staff are empowered and accept will have met all of the requirements of the
responsibility to identify opportunities where Preparatory and Preliminary steps. Work will
the design and construction teams can improve be underway and all quality processes will be
their performance. fully employed.
SFI will create this job culture by recognizing The QMP will describe the processes, proce-
achievements in the area of quality dures and details of reviews and checks that will
improvements. Improvement opportunities and be performed on the design of the Project
suggestions will be sought on an ongoing basis. components. The QMP will also outline the
Review and evaluation of suggestions will be inspections and tests that will be performed on
timely and as thorough as necessary. construction materials and workmanship to
Improvement plans will be based upon review ensure the overall quality of the constructed
of all available or necessary data and project.
implementation will be efficient and effective. The QMP will meet the Port’s directives and
requirements, provide independent confirma-
1.2.1.4 Approach tion that Project deliverables satisfy specific
The QMP that will be implemented for this Contract requirements, and promote a seamless,
Project will encompass the policies, program, transparent interface with the Port, allowing the
organizational responsibilities, procedures, and Port’s staff to observe all deliverables for the
means of ensuring that all disciplines, aspects, Project as they are developed.

Volume 2 – Section 1 – page 32


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
The Gerald Desmond Bridge Replacement Project Proposal

The QMP will not be revised without prior tion/routing plan, and procedures for archiving
written approval from the Port. However, the documents.
QMP is a living document, subject to ongoing Documents shall be controlled by the document
review and revision to better meet the needs of control staff. The document control staff will
the interested parties over the life of the Project. include project engineers, administrative assis-
Revisions to improve the quality procedures and tants, and clerical office personnel.
processes are expected and will promote the
ability to meet Project requirements. The Quality Manager shall verify that the pro-
cedures for document control are maintained
Quality is assured by assigning full-time, dedi- through auditing the document control system
cated, and competent staff to perform the qual- on a periodic basis.
ity functions of inspection, testing, surveillance,
training, and auditing of quality processes and 1.2.1.8 Design Management
procedures used during the design and con-
struction work. The Design team will perform QA/QC during
the design process in accordance with the
1.2.1.5 Design and project QMP. They will perform QA/QC func-
Construction Quality tions with a comprehensive and systematic
examination of the design documents. They will
Management evaluate the design requirements and provide a
design to meet those requirements, and identify
Quality Control (QC) problems and propose solutions. The compo-
Under direction of the Quality Manager, the nents of the design shall consist of drawings,
Design Quality Manager (DQM) and Con- specifications, and calculations.
struction Quality Manager (CQM) shall imple- All technical documents developed by the
ment the quality processes and procedures for design engineer, contractor, or subcontractor
their respective areas of responsibility. Quality shall bear the stamp of a Professional Engineer
control shall include reviews, checks, tests, and registered in the State of California where
inspections of the work processes, procedures, required.
inputs, and outputs.
The Design Manager will direct the overall
Quality control is a continuous process that design development and review the Detail
cannot be excluded from any part of the design Design Drawings and Specifications through all
or construction activities that are performed. phases of the design and will be familiar with all
Quality control will be performed through aspects of the Detail Design Drawings and Spe-
mechanisms such as Inspection and Test Plans, cifications. The Design Manager will review
internal plan and process reviews, factory these documents for general conformance to
inspections, and audits. the Contract Documents. All deficiencies will
be corrected promptly. Deficiencies found dur-
1.2.1.6 Quality Assurance (QA) ing review of the design components and the
Quality assurance is an additional process above corresponding corrections shall be properly
the quality control processes. The quality assur- documented with the associated correction.
ance process ensures that project quality control The Design Manager will document these find-
is functioning correctly and has been properly ings during review of the design components.
implemented for all aspects of the work from Documents will be available for audit by SFI
design to construction. and Port representatives.
1.2.1.7 Document Control 1.2.1.9 Organization Roles &
Document control shall follow specific proce- Responsibilities
dures to be used for the review, distribution, RFP ITP Appendix B § 1.2(b); D § 1.1.2

processing, and filing of documents generated The quality management team will consist of a
for the Project. These procedures will include a Quality Manager (QM), a DQM, a CQM, Qual-
Project specific numbering system, a distribu- ity Reviewers, Quality Inspectors, sampling and

Volume 2 – Section 1 – page 33


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
Gerald Desmond Bridge Replacement Project Proposal

testing personnel and an Independent Testing ■ Mr. Mehta will report directly to SFI’s
Laboratory. The staffing levels will be adjusted Executive Management Committee and
on an as needed basis depending on the work produce a monthly report specifically for the
being accomplished on each day, so that all Committee’s review.
work will be reviewed, inspected and tested
according to the QMP. ■ Mr. Mehta will have no responsibilities in the
production of the Work.
Work will not be permitted to proceed without
the proper level of Quality Organization (QO) ■ Mr. Mehta has more than 15 years of quality
personnel to inspect and test the materials and management experience on complex infra-
workmanship during construction. structure projects, including nine years of
experience on large urban freeways (SR-
The QO will be comprised of Quality Control 241/SR-261) and transit design-build
and Quality Assurance staff. SFI’s Executive projects (Orange Line BRT).
Management Committee is committed to
Dan Devlin, P.E.—Design Quality Manager
assigning personnel in the QO with the
necessary qualifications, training, and Responsible for quality activities related to the
experience. design:
The QO operates under the oversight of the ■ Mr. Devlin will report directly to the Quality
Quality Manager, who reports directly to the Manager and will have no responsibilities in
Executive Management Committee. The DQM the production of the Work. Mr. Devlin will
directs design quality. Construction quality is provide the same role as the Design Quality
under the direction of the CQM. These two Assurance Manager in Quality Manual
individuals will report directly to the QM, Template’s Exhibit 2-2-A.
limiting the influence of schedule, performance,
and cost on project quality requirements. ■ Mr. Devlin has 28 years experience in the
design and engineering of transportation
The QO will provide the QC procedures and structures, has 18 years experience as lead
QA review, testing, and inspections necessary to designer responsible for transportation
ensure the project quality meets contract projects similar in scope to the Project.
requirements and the Executive Management
Committee’s Quality Management Policy. ■ Mr. Devlin will audit the design documents
to verify that the inter-discipline design
Quality Organization Key Positions reviews, independent technical reviews and
and Qualifications constructability reviews have been fully
completed.
Personnel assigned to perform quality inspec-
tion, testing, or monitoring of characteristics for Scott Beyma, P.E.—Construction Quality
acceptance shall not be those performing or Manager
directly supervising the Work being reviewed. Responsible for quality activities related to the
The QM and the Quality staff shall have no construction of the Project:
responsibilities in the production of the design
or construction of the Work. ■ Mr. Beyma will report directly to the Quality
Manager and shall have no responsibilities in
Material Testing/Inspection staff and Material the production of the Work. Mr. Beyma shall
Testing labs are required to possess the neces- provide the same role as the Construction
sary technical industry certifications and the Quality Assurance Manager in the Quality
Port certifications for the Work they are Manual Template’s Exhibit 2-2-A.
inspecting or material they are testing as
discussed below. ■ Mr. Beyma has more than 15 years of man-
agement experience on complex infrastruc-
All QO personnel shall have the minimum qua- ture projects, which includes five years of
lifications and duties listed below: experience on urban freeway and design-
Piyush Mehta—Quality Manager
build highway projects (SR-241/SR-261 and
Orange Line BRT).
Responsible for the overall quality activities:

Volume 2 – Section 1 – page 34


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
The Gerald Desmond Bridge Replacement Project Proposal

■ Mr. Beyma is licensed as a Professional ACI, ICC, NICET, or Caltrans.


Engineer in the State of California.
Quality Inspectors
■ Mr. Beyma will ensure that all quality control
inspections and lab tests are independently Responsible for the inspection and testing of
completed. the construction work and supervising quality
testing:
Critical Activity Points Manager
■ Quality Inspectors will report directly to the
Responsible for all critical activity point Construction Quality Manager.
inspections and testing before moving on to the ■ Quality Inspectors will have no responsibili-
next element of construction: ties in the production of the Work.
■ The Critical Activity Points Manager will be ■ Quality Inspectors will have separate areas of
a licensed Professional Engineer in the State expertise for drainage/utilities, structural
of California and have the applicable concrete, structural steel, electrical, and traf-
Caltrans technical certifications for the Work fic/roadway.
performed under the Critical Activity Points.
■ Quality Inspectors will have sufficient expe-
■ The Critical Activity Points Manager may rience and education to perform the quality
add other critical activity point inspectors as inspections related to the work. This will
required by the construction schedule. include possessing a college degree in a
Configuration Manager closely related field or certification by recog-
nized certifying agencies such as ACI, ICC,
Responsible for collection and distribution of all NICET, or Caltrans.
released-for-construction plans, approved shop
drawings, approved requests for information Quality Testing Technicians
with changes to plans and approved specifica- Responsible for the testing of materials and
tions: workmanship to verify quality:
■ The Configuration Manager will report ■ The Quality Testing Technicians will report
directly to the Quality Manager directly to the appropriate Quality Inspector.
■ The Configuration Manager will coordinate ■ The Quality Testing Technicians will have no
with the Document Control Manager for responsibilities in the production of the
distribution of documents Work.
■ The Configuration Manager will keep a hard ■ The Quality Testing Technicians will have
copy of all approved documents and keep sufficient experience and education to per-
the electronic document control web site up- form the required quality testing during con-
to-date. struction of the work. Quality Testing Tech-
Quality Testing Supervisor nicians will have appropriate certification by
recognized certifying agencies such as ACI,
Responsible for overseeing all materials testing: ICC, NICET, or Caltrans.
■ The Quality Testing Supervisor will report
Quality Personnel Resumes
directly to the Construction Quality Man-
ager. We have not included resumes for inspectors at
this point. We will subcontract with
■ The Quality Testing Supervisor will coordi- UDBE/DBE firms after contract award and
nate all off-site and source manufacturing scope has been determined.
testing for the Materials Control Schedule.
■ The Quality Testing Supervisor will have QUALITY ORGANIZATION’S
sufficient experience and education to per- AUTHORITY TO STOP WORK
form the quality inspections related to the It is important to note that the key quality staff
work. This will include possessing a college listed above has sufficient authority and organi-
degree in a closely related field or certifica- zational freedom to identify quality problems
tion by recognized certifying agencies such as and to initiate, recommend, provide, and verify

Volume 2 – Section 1 – page 35


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
Gerald Desmond Bridge Replacement Project Proposal

implementation of the solutions. The QO staff The Discipline Engineers will ensure copies of
does not report to and is not under the all transmittal letters relating to approval of
authority of any design or construction staff material or equipment are properly filed. SFI
that is engaged in production of the Work. The will maintain a record of suppliers used to
QO has full authority to stop work if quality is furnish approved permanent materials and
being compromised. Even though the QO will equipment as necessary.
not be influenced by any potential impact of
implementation on the project schedule or The purchase of permanent materials incorpo-
budget, the QO shall be cognizant of the rated into the work will be performed through
construction team’s need to anticipate these the use of procurement documents. These doc-
issues and facilitate schedules, maintain budget, uments will be in the form of purchase agree-
and improve organization delivery performance. ments or purchase orders as appropriate. These
documents will include information either
Design Quality Organization Charts directly or by reference as to the following: spe-
RFP ITP Appendix B § 1.2(a) cification section, item description, quantity,
required documentation, technical requirements,
The Design QA/QC organization chart and resumes
for key QA/QC personnel are included at the end of this material standards, quality assurance, quality
subsection. control requirements, dimensions when appli-
cable, packaging specifics, and date required.
The Design Quality Manager will oversee
Design Quality Assurance Engineers who will 1.2.1.11 Subcontractors
verify that the various design checks are
completed. Subcontractors and suppliers will be required to
submit their respective Quality Management
Construction Quality Organization Plans to SFI for review or adopt the QMP as
Charts their own. In general, suppliers will be required
RFP ITP Appendix B § 1.2(a); B § 1.2(b); D § 1.1.2 to furnish material certificates, product data,
installation instructions, warranties, personnel
The Construction QA/QC organization chart and qualifications, and results of independent labor-
resumes for key QA/QC personnel are included at the
end of this subsection. atory tests. Subcontractors will be required to
adhere to all applicable aspects of the QMP
The Construction Quality Manager will oversee relating to their work and may also furnish sup-
all construction quality assurance activities. plemental personnel to perform various field
Reporting to the Construction Quality Manager tests, inspections, and documentation.
are the Quality Testing Supervisor, the Struc- The Quality Manager will work with subcon-
tural Concrete Lead Inspector, the Structural tractors and suppliers regarding their quality
Steel Lead Inspector, Drainage/Utility Inspec- control activities. Each subcontractor will
tor, Electrical Inspector, Roadway/Traffic receive quality training and quality indoctrina-
Inspector and the Quality Testing Supervisor. tion on procedures before they are allowed to
We will add technicians as needed to conduct start work. Throughout the duration of the
tests with the independent lab. Project, we will hold quarterly quality meetings
1.2.1.10 Procurement with all subcontractors to go over current pro-
cedures, critical activity inspections, scheduling
The Discipline Engineers under the direction of of inspections and testing and any other issues
the superintendents will have the responsibility related to subcontractors’ work quality.
for procurement of all permanent materials and
equipment. This responsibility includes order- The Quality Manager will work with the
ing, receiving, and storage. Permanent materials Construction Manager and the subcontractors
and equipment documentation will be submit- and suppliers to ensure they follow the quality
ted to the Port as required by the Contract requirements of the Contract Documents.
Documents. Only those suppliers who are able 1.2.1.12 Inspection
to meet the requirements of the Contract and
Design Documents will be utilized to furnish Testing and inspection of work and materials
such materials and equipment. shall be performed in accordance with the

Volume 2 – Section 1 – page 36


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
The Gerald Desmond Bridge Replacement Project Proposal

Project’s quality management procedures and inspections and tests.


per the Contract Documents. Specific testing The Construction Quality Manager will oversee
and inspections shall be detailed in the individ- the activities of the testing lab on the Project
ual Inspection and Test Plans that are devel- site. Testing technicians and Special Inspectors
oped for each definable feature of work. provided by the independent testing lab will be
Testing and inspection will include Factory scheduled on an as-needed basis.
Tests, Quality Control Inspections, Installation The qualifications of the independent testing
Verification Tests, and Acceptance Tests. lab, resumes of the agency’s managing engineer,
Quality Control inspections are performed by other professional engineers on staff, and the
the full-time quality control staff and will con- certified field and laboratory testing technicians
firm that materials and equipment, installation, to be used will be provided before the start of
and workmanship meet the requirements of the work. The Quality Manager will select the
Project. independent testing lab and will submit its
credentials to the Port.
Installation verification tests will be performed
to ensure work meets the requirements of the The independent testing lab will:
specifications. This can include tests on partial ■ Have the proper AASHTO accreditation,
sections of a system to verify each part of the credentials, certifications and experience to
system is compliant before final completion perform inspection and testing as required.
testing.
■ Have accreditation by r the California
Acceptance tests are performed on-site and Council of Testing and Inspection Agencies,
shall be complete before any ITS system State of California, Department of General
integration tests are done. Services, Laboratory Evaluation and Accep-
1.2.1.13 Testing & Independent tance Program.
Laboratories ■ Have AASHTO accreditation in ASTM
C1077-92, “Practice for Laboratories Testing
The Quality Manager, Construction Quality Concrete and Concrete Aggregates for Use
Manager and the Quality Testing Supervisor will in Construction and Criteria for Laboratory
write a Materials Control Schedule (MCS) that Evaluation,” ASTM D3740, “Practice for
outlines the roles and responsibilities for sam- Evaluation of Agencies Engaged in Testing
pling and testing of materials. The MCS will and/or Inspection of Soil and Rock as Used
cover sampling and testing that will be per- in Engineering Design/Construction,” and
formed by SFI and the Port. The MCS will ASTM D3740, “Specifications for Minimum
assure and verify that all materials, equipment, Requirements for Agencies Testing and
and elements of the Work will perform satis- Inspecting Bituminous Paving Materials.”
factorily and meet the requirements of the con-
tract documents. ■ Have a sufficient number of inspectors and
technicians appropriately certified for the
Special attention will be given to the role of off- work they will be inspecting and testing.
site testing at the source and fabrication
facilities to assure that tests and certifications ■ Have an accredited and certified facility
are completed before material is delivered to the located near the Project.
site. ■ Confirm that specified verifications, sam-
SFI will use an independent testing lab to pling and testing of materials are in accor-
perform shop and field inspections and material dance with the standards governing the dif-
testing as needed or required by the Contract ferent sections of the Contract.
Documents. The independent testing lab will ■ Immediately inform the Quality Manager
not be owned by or affiliated with SFI or its upon verification, sampling, testing of any
partners. The independent testing lab will materials (supplied or furnished) or work
provide services for ensuring calibration of field performed by SFI or our subcontractors, per
testing equipment, checking the results of field- the specified requirements, if it does not fully
testing, and reports presenting the results of meet the Project specifications.

Volume 2 – Section 1 – page 37


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
Gerald Desmond Bridge Replacement Project Proposal

■ Ensure test reports are submitted to the accordance with Caltrans’s four volume
Quality Manager within two working days template that has been provided by the Port.
after each test is complete.
1.2.2.1 Management QMP
1.2.1.14 Coordination with the Review
Port The QMP will be reviewed quarterly throughout
The QM will be responsible for coordinating the life of the Project for the express purpose of
the QMP with the Port. The QM will maintain assessing the suitability, adequacy, and effec-
continual communications with the Port on all tiveness of the program. The Port shall be
matters of Project quality. invited to participate in the reviews.
The QM will coordinate all testing, inspection, 1.2.2.2 Quality Manual—Design
and observation with the Port to satisfy the
requirements of the QMP. The design section of the Quality Manual will
include the required quality program procedures
1.2.1.15 QMP Inspection and to ensure the design is properly planned and
Test Procedures meets the contract requirements. The design
section of the quality manual will incorporate
The QMP procedures will be established based the following items into the quality procedures:
on the final design of the Project. Each QMP
procedure shall follow a predetermined format. 1. Quality will be achieved through accurate
Each procedure may be written to include addi- planning, coordination, supervision, and
tional items as needed to ensure quality is prop- technical direction; proper definition of job
erly maintained. The predetermined format requirements and procedures; and the use of
includes the following items: appropriately skilled personnel performing
their work functions with care. Quality pro-
1. Scope cedures define the planning that achieves its
2. References quality goals through a transparent process
3. Assignment of Quality Personnel of open communication, trust, and a part-
4. Inspection Procedures nering atmosphere that addresses concerns
5. Testing Requirements promptly, before they become problems.
6. Quality Criteria
7. Quality Documentation 2. The design team will prepare the design doc-
8. Special Equipment uments at Conceptual, Intermediate, Full and
9. Required Certifications Release-For-Construction (RFC) phases for
review to ensure the design progresses
1.2.2 Quality Manual correctly, using the established design criteria
for the Project and appropriate inter-
A Quality Manual will detail all of the quality discipline and Task Force coordination (via
requirements and procedures of the QMP for regular scheduled meetings, written
the design and construction of the Project. The communications, etc.). Task Forces (which
Quality Manual will be approved and endorsed include representatives from SFI, the Port,
by SFI’s Executive Management Committee and local agencies as needed) meet as agreed
before implementation. upon during the design phase and
periodically thereafter. Some task forces may
The Quality Manual will be maintained by the be added, combined, or eliminated as design
Quality Manager, who will review and update progresses. The Task Forces will generally be
the manual at least every three months as discipline-specific.
necessary, based on the discussion and findings
of quality management meetings. The Quality 3. All design documents will be subjected to an
Manual is considered a living document and is inter-discipline design checking process. For
subject to revision as necessary to facilitate and design documents where inter-discipline
improve the quality process for the Project. The design checks are warranted, an Inter-
QM will prepare the Quality Manual in Discipline Design Review (IDR) is per-
formed. All documents that affect construc-

Volume 2 – Section 1 – page 38


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
The Gerald Desmond Bridge Replacement Project Proposal

tion activities are subjected to a Constructa- Design Quality Control


bility Review. Before delivery to the Port, all
design documents shall be subject to the The Team’s design review will be performed at
Independent Technical Review. The design scheduled review points of Conceptual, Inter-
documents will be reviewed using the mediate, Full and RFC completion. Each of
appropriate forms as required. these design review milestones is crucial to the
efficient production towards the next milestone.
4. Checker corrections and comments and These thorough reviews will enable the design
review comments will be evaluated and to proceed with higher efficiency towards an
incorporated into the documents by the acceptable design with no repeat work. The
design team as appropriate. overall design review elements are:
5. The design team will prepare the RFC ■ Criteria Review
documents and will submit the RFC package ■ Design Validation Reviews
to the DQM. The DQM audits and certifies ■ Internal Design Review
the documents, indicating that the ■ Interdisciplinary Review
documents are approved for release. ■ Constructability Review
6. The DM will transmit the signed and sealed ■ As-built Review
RFC Documents to Document Control ■ Quality Record Review
along with the DQM’s certification that the The quality control check will review, at a
design package may be released for minimum, the following:
construction. The documents are then distri-
buted. ■ Design assumptions and design criteria.
■ Analysis assumptions, modeling, and results.
Design QA/QC System ■ Design calculations and criteria compliance.
■ Drawing coordination with other disciplines.
The Quality Manual will address internal engi- ■ Drawing consistency with calculations.
neering and subconsultant organizations’ roles ■ Drawing consistency; plans and details.
and responsibilities, reporting authority, ■ Drawing and specifications; coordination,
interfacing responsibility, engineering processes, completeness, clarity and constructability.
and quality control measures necessary to verify
that design documents are developed and issued An Independent Structural Design Team will
in accordance with the contract requirements perform a check of all structural design
and execution procedures. Design quality con- elements between the Intermediate and Full
trol will be implemented from preliminary engi- submittals including the preparation of an
neering through design development and independent set of calculations. The plans and
approval for construction. The design team, details will be carefully checked by this
including design subconsultants, will be independent team. The Independent Structural
responsible for implementing design quality Design Team will then check the special
requirements through design, requests for provisions and compare them with the plans.
information (RFIs), and disposition of The independent review will verify that input
nonconformance reports. Design quality from all design-build team members has been
assurance will be performed through parallel but incorporated and coordinated.
independent oversight of the quality control Design team internal quality control reviews will
implementation throughout the design process. be coupled with inter-discipline, independent
The Design QA/QC process of the Quality technical and constructability reviews incorpo-
Manual will contain the following program rating the skills of the full design-build team to
elements: design planning, design input, design meet all of the QMP objectives.
change, technical checking, verification of Inter-Discipline Design Reviews: These reviews
design output (reports, calculations, plans, etc.), are accomplished by routing the design docu-
internal audits and oversight, and document ments of one discipline to all other disciplines
control, distribution and records management. for review and comment.
Independent Technical Reviews: The technical

Volume 2 – Section 1 – page 39


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
Gerald Desmond Bridge Replacement Project Proposal

expertise of senior staff of the project team is sentatives of the Project design leads and design
added to the design through this review. These subcontractors to track the progress and
reviewers are chosen for their extensive back- content of the design. Specifically, these
ground and experience on similar projects. meetings will address design interfaces,
Reviewers are not involved directly in the progress, schedule, design quality, system safety,
project design; their reviews focus on assuring mandatory formats, quality assurance and code
that the design uses the best technology and compliance. All drawings and supporting
methodology available. calculations will be required to follow the
document control process and be submitted in
Constructability Reviews: The experience and the format specified by the Project scope.
expertise of the Construction Manager and the
construction team is incorporated into the SFI’s Executive Management Committee has
design through these reviews. At each scheduled overall responsibility for all systems integration
review point, the constructability review pro- irrespective of who is providing the design or
vides comments to the Design Manager. construction effort. The appropriate design and
construction organizations will review parallel
The design team will conduct interdisciplinary, efforts of engineering design work of
independent technical reviews, constructability subconsultant’s facilities, as well as the design
and formal quality reviews before every sub- documentation, functional definition, and speci-
mittal milestone. The review comments will be fication of the systems elements. During the
documented and tracked for incorporation design phase, the Design Quality Manager will
and/or responses. Meetings will be conducted conduct oversight of integrated quality control.
to resolve and reach agreement on comment The subconsultant work will be reviewed, and
incorporation in a timely manner. Documenta- an Interface Report will be prepared that details
tion of these meetings, redlined plans with any interface issues that need resolution.
comments, and the comment responses
matrices will all become part of the quality 1.2.2.3 Quality Manual –
records for the Project, to track changes during
design progression. Construction
Design Quality Assurance The construction section of the Quality Manual
shall provide the quality requirements for the
Design quality assurance involves verifying that construction phase of Work. The construction
all the elements of the QMP are applied to section of the Quality Manual will incorporate
design activities to ensure accurate tracking and the following items into the quality procedures:
development of design, expediting approvals for
RFC documents, and ultimately, final design 1. The protocol for encouraging and striving
acceptance. These QA activities include the for continuous improvement of construc-
procedures for use in the completion of design tion processes, methods, materials, and
documents—calculations, reports, plans, and workmanship.
specifications. 2. Training and continuing education of the
At the Project outset, training sessions will be SFI construction and quality staff regarding
conducted by the Design Quality Manager for their role in assuring quality on the Project.
the entire design team to ensure that the 3. Development of construction work plans to
required procedures and processes are explained ensure that each individual work element is
consistently to all team members. properly planned. The QO will develop
The Design Quality Manager will verify that Inspection and Test Plans that will be
Design Review corrections and comments are integrated with the construction work plans.
addressed and documented by the Design To show compliance with the Port’s
Manager at each scheduled review point. requirements, workers will be directed to
identify quality problems during design and
Design QA/QC Integration construction, and to show improvement
during the design and construction process.
The Design Manager will conduct regular design
meetings with Port representatives and repre- 4. Procedures for ensuring subcontractors and

Volume 2 – Section 1 – page 40


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
The Gerald Desmond Bridge Replacement Project Proposal

suppliers meet the requirements set forth by mented to verify all Work is in accordance with
SFI in their work and all materials supplied contract documents. Inspections shall be con-
for the project. Subcontractors and suppliers ducted in accordance with prepared Quality
will be required to provide quality control Control and Quality Assurance Inspection
plans that will be reviewed and incorporated instructions and inspection frequency checklists.
with SFI’s program. Work shall not proceed without inspection
instructions and checklists in place for the
5. Procedures that require complete and specific work element.
transparent communication with the Port.
This means that all testing and inspection Inspection planning shall be prepared in concert
results will be provided. It is SFI’s intent to with the construction schedule and shall include
work side by side with the Port to ensure all identification of prerequisite requirements.
work and materials are of superior quality These may include approved submittals,
and that any improvements that can be made material certifications, verification of personnel,
will be done. certifications for special processes, equipment
calibration verification, applicable inspection
1.2.2.4 Construction Work instructions and checklists, and the number of
Plans inspectors required.
SFI will prepare Construction Work Plans Each inspector shall document the results of
(CWP) for all major individual Work elements daily inspections and surveillances on daily
such as placement of cast-in-place concrete, inspection reports that include the applicable
construction of deep foundations, stressing of quality inspection checklists. All inspection
cables, and erection of structural steel members. documents shall be maintained on the job-site
The CWPs are presented and discussed among as quality records and will be available to the
the design and construction teams and the QO Port upon request.
before the start of the individual Work element. Inspection personnel shall have sufficient orga-
The subject Work may not proceed until the nizational freedom to identify and report non-
CWP is approved by all parties. conforming conditions and have sufficient
Please see Section 1.1.3 “Construction Management
training, knowledge and experience to perform
Plan,” for more details. specific inspections.
Quality Control inspection efforts on all items
1.2.2.5 Inspection and Test of work shall meet or exceed the Port’s
Plan expected inspection levels as shown on inspec-
tion frequency checklists.
Quality Control and Quality Assurance Inspec-
tions will be performed on all Work to ensure A Stop Work notification will be issued if there
compliance with the contract documents. All is evidence that the QMP or work procedures
Work will be subject to continuous inspection are not being followed, or if the materials or
during all work shifts and for off-site work workmanship do not meet the contract
activities as needed. Assignment of inspection requirements. The notification will remain in
personnel will be consistent with the level of effect until appropriate quality procedures have
activity and complexity of work to be been established and implemented.
performed. QC inspections shall be done by 1.2.2.6 Control of Special
individuals other than those responsible for
performing the Work. Work activities subject to Processes and Job Control
inspection include but are not limited to Testing
material and equipment receiving, in-process
and final construction activities, in-process tests, Special processes and job control testing asso-
qualification tests, equipment installation and ciated with hardware fabrication or construction
tests, and system integration testing and shall conform to applicable Government Rules
acceptance. and Standards, Industry Standards and the Port
contract requirements. Examples of special
Sufficient inspection points shall be imple- processes and job control tests may include, but

Volume 2 – Section 1 – page 41


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
Gerald Desmond Bridge Replacement Project Proposal

are not limited to: inspections have been performed and provided
passing data. The CAPM will invite the Port to
■ Special Processes be present for verification that the work has
□ Welding been performed to the requirements of the
□ Non-destructive Testing Project. Once it has been determined that the
□ Coatings work meets the Project Requirements, and
□ Painting proper documentation has been completed and
□ Piling signed by the CQM, the CAPM will sign off on
□ Cable Tensioning the Critical Activity Point.
■ Job Control Testing Examples of Critical Activity Points are:
□ Concrete
□ Corrosion Control ■ For concrete pavement—ensure that dowel
□ Soils bars, tie bars and dowel baskets are inspected
□ Asphalt and released.
□ Waterproofing ■ For CIDH Piling—the CIDH Pile
□ Drilling Placement Plan is approved; Pre-placement
□ Layout Control Inspection is signed off; and the hole has
Inspection and test laboratories performing been drilled and is awaiting rebar placement.
special processes or job control testing shall ■ For Prestressing Concrete—Approval of
have appropriate certification that is current and Prestress shop drawings; sign off of duct
issued by a recognized regulatory agency. The placement, vents, bearing plate alignment,
laboratory shall be reviewed and approved by and rebar before completing formwork for
the Port before Work starts. Special process stems; testing of duct is complete before
inspections and tests shall be accomplished by concrete placement.
qualified technicians, certified inspectors or
other qualified or certified individuals as speci- Once the CAPM has signed off at the Critical
fied in the Governing Rules or Standards, Activity Point, work may proceed to the next
Industry Standards, the Port Specifications or activity.
other applicable controlling documents. The
credentials of the technicians or inspectors per- 1.2.3 Document and Data
forming special process inspections or tests and
job control tests shall be reviewed for com- Control
pliance to applicable codes, standards, special Quality records are documents that document
training/tests etc. and accepted by SFI before results of design reviews, inspections and tests,
inspections and tests are performed. Records of and include all other related documents. Quality
credentials shall be maintained by SFI at the records are considered valid only if stamped or
jobsite and available to the Port upon request. signed by an authorized individual. Corrections
The Critical Activity Points Manager (CAPM) or revisions to quality records shall receive the
will be on-site before the start of any critical same level of review and approval as the
construction operation to ensure that the original document. All quality records shall be
proper inspection and testing has been available for review by the Port upon request.
performed before proceeding to the next stage Quality records and other project documents
of construction activity. The Critical Activity shall be properly identified, collected, indexed
Points will be held at the operations detailed in and stored in a manner that precludes damage,
Caltrans’ Construction Quality Testing and loss or deterioration. Hard copies and electronic
Inspection Plans. copies of quality records and other documents
At a defined Critical Activity Pont, the CAPM will be maintained by SFI. Storage of the hard
will review the Construction Quality Inspection copy documents will be protected from expo-
and Testing Plan to determine the testing sure to water, fire, wind or other damaging envi-
and/or inspection procedures and ronmental effects as is practical. Electronic
documentation that is required. The CAPM will documents will be maintained on a central
then ensure that the required tests and/or server with automated backup to prevent loss of

Volume 2 – Section 1 – page 42


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
The Gerald Desmond Bridge Replacement Project Proposal

documents. Specific retention times and loca- audits in the field to verify that the correct
tion will be designated and the records shall be version of plans and specs are being used.
accessible for use. Quality records and other
project documents will be identified by title, 1.2.4 Design Coordination
contract number, revision, date, and signed by
an authorized individual. All documents related SFI will participate in design coordination
to the Project will be maintained onsite until the activities with the Port and other stakeholders.
completion of the Project. SFI believes an open and transparent partner-
ship with the Port and other stakeholders will
SFI will utilize a web-based project management benefit all parties and ensure quality work is
system for document control management and provided.
for distribution of release-for-construction
plans. SFI will use e2020 to develop the web- 1.2.4.1 Over-the-Shoulder
based system for the Project. It will be Reviews
customized to suit the needs of the Project both
during the design and construction phase. Over-the-shoulder reviews are generally cursory
reviews and are intended to minimize disruption
The main items for the design phase include: to ongoing design work while providing timely
■ Complete Sequential Document control comments and feedback on the design. The
■ Agency supply documents scope of an over-the-shoulder review may be
■ Meeting minutes more comprehensive should the Port feel it is
■ Submittal schedules warranted.
■ Design submittals—configured so that the Over-the-shoulder reviews by the Port’s repre-
Port can input their comments directly into a sentatives (and other approved Project stake-
database. holders, as appropriate) will occur through vari-
■ Reports ous reviews, meetings, and through routine day-
■ Design exceptions to-day interaction. Feedback will be docu-
■ Permits mented in meeting minutes when appropriate.
■ Geotechnical explorations
The main items for the construction phase 1.2.4.2 In Process Design
include (but are not limited to): Workshops
■ Executive Dashboard During the design process, SFI or the Port may
■ Agency supply documents request an In Process Design Workshop. These
■ Reports workshops will be used to determine design
■ Document Control progress and resolve questions and issues.
■ Meeting minutes
■ Contacts 1.2.4.3 Other Stakeholder
■ RFIs
■ Submittals Reviews
■ Change Orders As applicable, stakeholder organizations,
■ Design Clarifications including municipalities, counties, watershed
■ Issues management organizations, or utilities, to name
■ Drawings Released for Construction a few, will be given access to review and com-
■ Schedules ment on the design. These reviews can be sche-
■ Inspectors’ Daily Reports duled and scoped per the Port’s direction.
■ Progress Photo Logs
■ Permits 1.2.5 Design Package
■ Geotechnical explorations
Submittals
With a web-based document control system,
superintendents and field engineers (as well as Design package submittals will include concept
the Port) will be able to quickly verify that they designs, intermediate designs, final designs, and
have the correct version of RFC plans. In RFC documents. The design package submittals
addition, the Quality Manager will perform will be reviewed by the Port. Following the

Volume 2 – Section 1 – page 43


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
Gerald Desmond Bridge Replacement Project Proposal

Port’s review, SFI will incorporate comments may also be subject to inspection and testing by
and other necessary items to ensure the designs the Port. In addition, when any local agency or
are in conformance with the contract document utility owner is to accept any portion of the
requirements. SFI will not proceed with Work Work, its respective representatives have the
until RFC document submittals are approved by right to inspect the Work. Upon request from
the Port. the Port, SFI shall furnish necessary
Shop drawings and working drawings will be information to inspection personnel as
reviewed by SFI’s design engineers for approval designated and shall provide access to all parts
before use in the field. Shop and working of the Work that is to be inspected.
drawings will be processed in accordance with The Port may impose inspection critical activity
the contract requirements of the Project and the points to verify compliance to contract docu-
QMP. SFI will submit all shop and working ments during all phases of Work. SFI will not
drawings to the Port. proceed with Work until each critical activity
point has been released by the appropriate QO
1.2.6 As-Built Documents personnel. It should be noted that inspections
by the Port will not relieve SFI from performing
SFI will maintain up-to-date as-built drawings contractually required inspections.
during construction of the Project. The as-built
drawings will depict the final completed Work. SFI will not relinquish its obligations to perform
The as-built drawings will include all necessary the Work in accordance with the contract
information related to Work that was done on documents by reviews, tests, inspections or
the Project including utility locations, grades, approvals performed by others. SFI acknowl-
line, controls, etc. As-built drawings will be edges that the reviews, inspections, tests, and
prepared in accordance with the requirements approvals conducted by the Port, Government
of the contract documents. The Port will be agencies and others does not necessarily con-
furnished with all as-built documents at the stitute acceptance of the materials or Work
completion of the Project. Reviews of the as- reviewed, tested or inspected.
built documents will be performed to ensure SFI will make available to the Port all
they are being properly maintained. The Port inspection-ready construction before the
shall have access to review the as-built required tests and inspections. Should work
documents during the duration of the Project. inadvertently be covered before a required
examination by the Port or representative of the
1.2.7 Port Access and Port, SFI shall make all work available to be
Testing examined as necessary. Once the required
examinations are complete and the Work is
All Work performed by SFI under this contract found to be compliant, SFI shall continue with
shall be subject to oversight inspection and the Work. If the Work exposed or examined is
testing by the Port and other persons designated not in conformance with the requirements of
by the Port. Items to be inspected shall include the contract documents, then the Work will be
material and equipment received, in-process and repaired or corrected so that it complies with
final construction activities, in-process tests, the contract requirements.
qualification tests, equipment installation and
tests, and systems integration testing and 1.2.8 Review and
acceptance to ensure consistent compliance to
contract documents. Disposition of Non-
Results of inspections and tests shall be vali- Conforming Product
dated by printed name, signature and date on Non-conforming Work is Work that does not
the test document by the test technician, conform to the requirements of the Contract
reviewing test engineer or appropriate responsi- Documents. All Work that is determined to be
ble individual and the inspector who witnessed non-conforming by the QO or the Port shall be
the test. handled by the same quality procedures detailed
All materials and each part or detail of the Work in the QMP.

Volume 2 – Section 1 – page 44


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
The Gerald Desmond Bridge Replacement Project Proposal

Areas of non-conformance within any part of approval by the Port before affected Work
the Work will cause a Non-Conformance proceeds.
Report (NCR) to be written and processed. The The status of non-conforming items shall be
non-conformance will be described and docu- maintained and status reports distributed as
mented by an authorized person of the QO. needed. The status report will track and analyze
The QM and CQM for construction non-con- all NCRs that are issued on the Project to make
formances, or QM and DQM for design non- inferences of the data to aid in the continuing
conformances, will review and sign off on the improvement process. SFI’s senior management
NCR when the non-conformance is corrected. and the Port will be provided the NCR status
All NCRs will be processed through the QM. report at least monthly or as determined to be
Non-conformances may be identified or dis- necessary. Records associated with non-con-
covered through many mechanisms such as forming items shall be maintained and available
contractor labor, QO personnel, project man- to the Port upon request.
agement, the Port’s representatives, etc. All
non-conforming work or materials that are dis- 1.2.8.2 Port Issued Non-
covered shall be referred to the QO. The res- Conformances
ponding QO individual will issue a NCR that
thoroughly describes the non-conformance and SFI shall respond to the Port issued noncon-
proposes corrective actions that should be taken formance reports, quality action requests and
to resolve the deficiency. other documented reports of non-conforming
or indeterminate conditions within the time
SFI will promptly take all actions necessary to period specified. The response shall include a
prevent similar non-conformances from occur- description of investigative actions, statement of
ring in the future. the cause of the problem, action to correct the
problem and to prevent recurrence to the
1.2.8.1 Control of Non- satisfaction of the Port.
Conforming Items
Non-Conformance Reports will be segregated 1.2.9 Corrective and
and controlled until the non-conforming Preventative Action
condition(s) is analyzed, dispositioned,
corrected and the corrective action verified. SFI will determine the cause of non-confor-
Only then may the items be returned to use or mances identified by the Quality Program and
Work on the non-conforming area be contin- the Port. Corrective Actions will be developed
ued. SFI will investigate the cause of non-con- and implemented to prevent recurrences. If four
formances and will initiate corrective actions occurrences or more of the same non-confor-
including implementing steps to prevent recur- mance are found, the CM or DM will develop a
rence. The cause of the problem, disposition, plan and/or process changes to eliminate the
and corrective action shall be documented and non-conformance in the future, a schedule for
available to the Port upon request. implementation, required training, and schedule
a follow-up review once the new procedure is in
Non-conforming hardware and materials shall place.
be reviewed by qualified and authorized indi-
viduals to determine the appropriate disposition The corrective action will be focused on elimi-
and corrective action. Disposition of non-con- nating the root cause of the problem. There are
forming items and materials may include: many ways to determine the cause of the non-
conformity, including analysis by an individual
■ Rework to meet the original design. or by assignment to a corrective action project
■ Repair to achieve fitness for use. team.
■ Accept the condition as-is if project quality is
not compromised. The procedure for corrective and preventative
■ Reject the condition and return the hardware action will be included in the quality procedures
and material to the supplier. of the QMP.
Repair and accept-as-is dispositions will require

Volume 2 – Section 1 – page 45


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
Gerald Desmond Bridge Replacement Project Proposal

tions are being implemented per the QMP for


1.2.10 Internal Quality each of the areas of design and construction
Audits quality management.
Quality audits and surveillances shall be sche- 1.2.10.2 Internal Audits
duled, planned, and conducted on an ongoing
basis covering all project quality related activi- It is the policy of the SFI to conduct internal
ties and project phases. The audit/surveillance audits of the QMP. The Quality Manager is
schedule will be maintained current and availa- responsible for planning and carrying out the
ble to the Port upon request. Internal quality audits. The audits will focus on conformance to
audits will be performed at least quarterly. The the quality requirements established by SFI and
Port Quality Management may participate as an the requirements of the QMP. The audit results
observer on audits/surveillances. Quality audits will be part of the review input given to the
consist of an evaluation of the effectiveness of a Executive Management Committee. Internal
specific process such as purchasing, document audits to be completed during the Project
control, submittals, risk management, etc. include the following:
Quality surveillances consist of an evaluation of ■ Audits of deliverables to the Port or other
the effectiveness of a specific activity and follow stakeholders before they are delivered.
up of actions required in a previously performed
audit. ■ Audits of the document control system.
Qualified, trained and experienced quality per- ■ Periodic informal spot-audits of Port com-
sonnel independent of those responsible for the ment forms, internal comment forms, RFIs,
activity being audited shall conduct audits and and Design Change paperwork to spot
surveillances. trends, problem areas, or
inefficiencies.
Results of quality audits Benzene Plume Mitigation
and surveillances shall be ■ Audits of quality
During procurement design, SFI mitigated activities.
documented and distri- the impacts to the benzene plume through
buted to the manager of reducing foundations.
the audited activity and 1.2.11 Risk
the QM for reporting to Management
the Executive Management Committee. The
responsible person of the audited department Plan
shall conduct investigative actions to determine
and document the cause of any problems that We have found that identifying and managing
are found during the audit and implement risks early in the Project leads to a better quality
corrective actions to resolve the problem and Project. In order to bring additional value to the
prevent recurrence. Port and facilitate quality design and construc-
tion, SFI will implement a Risk Management Plan
1.2.10.1 Quality Assurance (RMP). SFI will internally identify risks early in
the design, and work internally and externally to
Audits resolve risks before they impact safety, quality,
Quality assurance audits will be performed by schedule, or costs.
the DQM and CQM to ensure that the respec- SFI is committed to prepare and implement an
tive staff have properly followed the quality RMP in accordance with the guidelines of the
procedures and that all applicable reviews and Project Risk Management Handbook edited by
quality requirements have been implemented. Caltrans on May 2, 2007. In addition, SFI will
These audits will be performed on a quarterly follow the benchmarks established by the Code
basis to review design processes and their out- of Practice for Risk Management of Tunneling Works,
puts as well as construction processes and their edited by the International Tunneling Insurance
outputs. These audits shall be separate from the Group (ITIG) in 2006. The ITIG Code is one
internal audits that are performed by the QM. of the most advanced codes available in the
construction industry. While the Code was
QA audits shall verify that quality control func- developed for underground works, it is not

Volume 2 – Section 1 – page 46


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
The Gerald Desmond Bridge Replacement Project Proposal

limited to that and is applicable to any type of ■ Approve risk mitigation plans and authorize
infrastructure project. the necessary resources for implementation.
This approach will be an invaluable tool availa- ■ Collaborate with the Risk Manager and the
ble to the Port during its negotiations with the Port on any matter related to risk manage-
provider of the Builder Risk Policy. ment.
The same approach has been instrumental on Risk Manager
the Lake Mead Project (NV) to allow the
Owner (Southern Nevada Water Authority The responsibilities of the Risk Manager are
(SNWA) to save over 20% of their budgeted summarized as follows:
premium cost for the same policy. ■ Develop and implement the Project RMP.
Purpose and Scope of the Risk ■ Organize and promote Risk Identification
Management Plan (RMP) and Evaluation.
The purpose of the RMP is to identify the ■ Organize and Implement Risk Control and
processes and methods that will be imple- Monitoring.
mented to properly manage the project risks ■ Implement Risk Reporting.
and opportunities throughout the duration of
the contract. Risk Owners

Risk management is a process of identification, The assigned Risk Owners responsibilities will
evaluation, mitigation, communication, and include:
monitoring, and involves the following ■ Implement risk mitigating measures once
approach: approved by the Project Manager.
■ Proactive and early identification, evaluation, ■ Identify and evaluate potential risks within
and management of risks in all phases and at their area of responsibility.
all levels of the Project.
■ Propose risk mitigating measures for newly
■ Anticipation and mitigation of risks, rather identified risks.
than correction of unexpected issues.
Risk Management Facilitator
■ Continuous control and monitoring of risks
and opportunities and detailed reporting. The Risk Management will be facilitated as part
of the Partnering Process. The facilitator’s
■ Proactive communication among all the par- responsibilities will include:
ties involved with the Project in an effort to
facilitate problem solving. ■ Review the RMP.
■ Full integration of the RMP into the overall ■ Facilitate the initial project risk workshop
project management process. and subsequent brainstorming sessions.
■ Assess the RMP’s implementation and
Organizational Roles effectiveness.
Project Manager
Risk Management Process
The Project Manager’s responsibilities con-
cerning risk and opportunity management are as The risk management process is separated into
follows: the following steps:
■ Ensure that the RMP is implemented in RISK IDENTIFICATION
compliance with the contract requirements ■ Risk identification throughout all phases of
and the standards of the companies that project design and construction involving
comprise SFI. senior engineers and managers of SFI, the
■ Assign the Risk Manager. Port, consultants, subcontractors, or any
team member, at any level of the organiza-
■ Assign the individual Risk Owner. tion.

Volume 2 – Section 1 – page 47


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
Gerald Desmond Bridge Replacement Project Proposal

■ Dedicated workshops conducted periodically □ Passively Accept – Accept the risk.


and before the start of any significant Risk Transfer tools (such as insurance) are
activity. not considered an adequate response. They
RISK EVALUATION are only tools to be used in case the response
is not effective.
■ Evaluation of probable risk and opportuni-
ties, including impact on the Project in terms ■ The decision to implement a mitigation plan
of safety, quality, environment, schedule, will be subject to the Project Manager’s
cost, performance, and protection of the approval. When a risk mitigating action has
affected third parties. been identified, it will be planned and added
into the project schedule and budget. The
■ Each risk will have a specific response plan, Risk Owner is then responsible for imple-
identifying the mitigating measures that will mentation of the plan.
be implemented and a timeline for each
action. Identification of the residual risk ■ Status of the Risk Action Plans will be eva-
remaining after the implementation of the luated during periodic review meetings and
mitigating measure will also be part of the described in the PRR. Decisions and
process. required completion dates will also be indi-
cated whenever relevant to ensure focus on
RISK MONITORING AND REPORTING actions that require immediate attention.
■ Issuance of the Project Risk Register (PRR), When a Risk Action Plan is implemented, the
which will be developed at the initial project risk probability/severity (after action imple-
risk workshop, and subsequent action logs. mentation) will be reduced accordingly. The
■ Risk monitoring at periodic intervals to quantitative evaluation will be updated to take
update the status of the implementation of into account the effect of the risk control
the mitigation plan and its effectiveness, action.
and/or actions decided. Risk Breakdown Structure
■ Updating of the Project Risk Register. An initial Risk Breakdown Structure has been
RISK EVALUATION AND CONTROL developed during the preparation of the Pro-
posal, and will be further expanded during the
■ During the identification process to develop preparation of the project-specific RMP.
the project risk register, qualitative scoring
will be implemented, using a scale of 1 to 5, Examples of a RMP and PRR already implemented by
to evaluate the probability of occurrence and SFI members are enclosed in Volume 4: Confidential
and Proprietary information – Technical.
potential impact of each risk and to prioritize
project focus. The probability and impact
ratings are then multiplied to give a score for Risks Reporting Tools
each risk between 1 and 25. The PRR will include the risks identified by SFI
■ Mitigation plans will be developed to control during the preparation of the proposal. The
risks. These plans will be detailed after the PRR will be a “working document” and will be
risks are identified during the sessions indi- updated during the various phases of the
cated above or by the individual Risk Owner Project until the last risk has been eliminated.
in cooperation with the Risk Manager. The PRR will be organized as follows:
■ Responses will be classified as follows: ■ Classification by categories and sub-
categories will be in accordance with the
□ Avoid – Eliminating the risk by eliminat- identified Risk Breakdown Structure.
ing the cause.
■ Risks will be identified by a description and
□ Mitigate – Reduce either the probability risk trigger, when appropriate.
or the impact.
■ Risks will be scored in accordance with their
□ Actively Accept – Develop a mitigating probability and severity.
plan subject to trigger event.

Volume 2 – Section 1 – page 48


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
The Gerald Desmond Bridge Replacement Project Proposal

■ Severity will be assessed with respect to on time, cost or within other established para-
impacts on cost, schedule, traffic and navi- meters. One of the key advantages of using a
gational impacts during construction, database is that the mass of information col-
impacts to the environment and surrounding lected is reported concisely and in a manner that
community and other factors, including is easy to understand. Another advantage of
health and safety, quality, performance, and using a database is its unique ability to query
third parties. information in an infinite number of ways. Sta-
tistical analysis of the data can be performed on
■ Each risk will be scored within the above categorical and continuous variables to answer
categories in accordance with the matrix other performance management questions,
included in the RMP. enabling SFI to better manage Project risks.
■ Each risk will have a Risk Response Plan
identified, including the mitigating measure RISK ACTION LOGS
to be implemented and an estimated timeline Actions identified to control risk and approved
for each of the above measures. by the Project Manager will be archived in a
■ A scoring of the residual risks following dedicated project log maintained by the Risk
implementation of the mitigating measure Manager. This project log will be used to
identified will be included. monitor the status of risk actions and
implementation during the course of the
■ The ownership of each risk will be identified Project.
within the SFI organization. SFI believes that
the PRR is a tool to properly manage the risk PROJECT RISK REPORTS
associated with the Project and does not Project Risk Reports will include a summary of
consider the PRR a contractual tool to the activities for the last period and that of the
address or resolve potential disputes. next. Included in the Reports will be new risks
SOFTWARE and opportunities identified and main actions
decided during the period, as well as risks closed
The PRR for the GDB Project will be managed and those risks that actually were realized and
using a job-specific custom database program impacted the Project. This document will also
written in Microsoft Access. The Access data- present the status and actions taken on the top
base can be customized to analyze risks based risks.

Volume 2 – Section 1 – page 49


Shimmick Construction Company, Inc./FCC Construcción S.A./Impregilo S.p.A., a Joint Venture
The Gerald Desmond Bridge Replacement Project Proposal

Executive Management Executive Management


Committee Committee
Paul C.Camaur Paul C.Camaur
Jaime Freyre Jaime Freyre
Fulvio Castaldi Fulvio Castaldi

Project Manager Project Manager


Giorgio Desideri Giorgio Desideri
Quality Manager Quality Manager
Deputy Project Deputy Project
Piyush Mehta Piyush Mehta
Manager Manager
William A. Corn, P.E. William A. Corn, P.E.
Deisgn-Build Manager
Robert M. Schraeder,
P.E.

Design Quality Critical Activity Point Construction Quality


Manager Manager Manager Configuration Manager
Dan Devlin, P.E. Name, P.E. Scott Beyma, P.E.

Design Manager/
DQCM
John Karn, P.E.

Roadway/Traffic Structural Concrete Lead Structural Steel Lead Quality Testing


Electrical Inspector Drainage/Utility Inspector
Inspector Inspector Inspector Supervisor
Cable-Stayed Bridge
Inter-Discipline & Lead Designer
Constructability Review Sena Kumarasena, PhD,
P.E.

Structural Concrete Structural Steel


Independent Labs
Inspectors/Technicians Inspectors/Technicians
Approach Bridge Lead
Design Quality Assurance
Designer
Engineer
Kwong Cheng, P.E.

Geotechnical Engineer
of Record & Lead
Geotechnical Engineer
Kul Bhushan, P.E.

Lead Civil Engineer


Duanne Gilmore, P.E.

Roadway Lead
Design Quality Assurance
Designer
Engineer
Luis Garcia, P.E.

Maintenance Facility
Lead
Designer
Bruce McKinlay, P.E.

Figure 1.2-1: Design quality organization chart. Figure 1.2-2: Construction quality organization chart.

Volume 2 – Section 1 – Quality Management