KZ611-00-4102-SC-0007-00 MS FOR NIGHTSHIFT WORKS — CIVIL ad 42 43 a4 4S 46 AT 48 4g Table of Contents SCOPE AND PURPOSE REFERENCES DEFINITIONS AND ABBREVIATIONS. ROLES AND RESPONSIBILITIES Project Manager (PM) Deputy Project Manager and General Construction Manager (DPM_GCM). Project HSE Manager (PHSEM) HSE Supervisor (HSE_SUP) HSE Inspector (HSE_INS) Project Quality Manager (PQM) Quality Inspector (QC_INS) Field Engineering Manager (FEM) Area Construction Manager (ACM) 4.10 Construction Discipline Superintendent (D_SUPT): ant Construction Discipline Supervisor (O_SUP}: 5 TOOLS AND EQUIPMENT. 6 LIST OF DIRECT PERSONNEL INVOLVED IN THE EXECUTION OF WORK. 7 METHODOLOGY 74 72 73 74 78 76 Excavation Works, Rebar Fabrication and Installation Works Formwork Activity Concreting Works. Painting Works Backfiling and Compactions Works. 8 HSE REQUIREMENTS 9 QUALITY CONTROL. © ane ayVNNNyaaaonne 10 "1 12 13 13 14 15 KZ611-00-4102-SC-0007-00 MS FOR NIGHTSHIFT WORKS — CIVIL 1. SCOPE AND PURPOSE The purpose of this document is to delineate the methodologies associated in the nightshift works in all areas included in the KGDBN project. These construction civil activities are included in the work packages that the CONTRACTOR received from the COMPANY in accordance with Section ‘12 “Initiation and Execution of Works” of Schedule H "Administration Requirements" of the project contract This method statement was prepared to comply with the required technical documentations and to serve as a construction guideline that the CONTRACTOR shall execute to perform the affiliated works in a manner that is safe and conformant to the expected results of the COMPANY. Prior to performing the associated Works, COMPANY shall handover the predefine areas in which the pertinent civil construction works shall be executed. CONTRACTOR shall conduct a site verification to assure that the pertinent area conforms to the issued latest IFC drawings. This site verification will allow the CONTRACTOR to have awareness of the topology as well as providing an idea of the necessary equipment, tools and manpower to be utilized in the performance of the Work In cases where an obstruction or construction constraint is discovered during the site verification, CONTRACTOR shall immediately inform the COMPANY by providing necessary reports and supporting documentations. Section 9.0 “Variation Procedure” of the project documents shall be implemented if the CONTRACTOR deems that these discovered obstacles and constraints will impede the planned civil construction activity Encompassed in this document are the major activities related to the nightshift works to be performed in the KGDBN project © Excavation works + Rebar fabrication and installation © Formwork activity © Conereting works Painting Works + Backfiling and Compaction works During the execution of the associated work the CONTRACTOR reserves the right to conduct variations in the construction execution to suit unforeseen conditions. The initiation and execution of the work variations shall be conducted as per the pertinent sections of the contract documents. 2__ REFERENCES DOCUMENT Ref. n. STANDARD KPO-ALIAS PRO-DO00S-E LOAD HAULAGE SAFETY PROCEDURE KPO-AL-HSE-PRO-00025-E RIGGING OPERATIONS: KKPO-AL-HSE-PRO-00026-E ‘SAFE USE OF CRANES kZ611-00-0803-SC-0001 PROJECT QUALITY PLAN KKPO-AL-QAC-PRO-00043 CONSTRUCTION MATERIAL CONTROL KPO-00-ENG-SPC-00038-E CONCRETE MATERIALS AND CONSTRUCTION SPRK 103-038-2013 ‘GEODESIC WORKS IN CONSTRUCTION RULES OF LABOUR PROTECTION AND SAFETY DURING CONSTRUCTION PROCEDURE FOR SURVEY AND SETTING OUT IN SN RK1.03-05-2011 KZ611-00-2002-SC-0001 PIPELINE, KPO-AL-OAC-PRO-D003E EARTHWORKS. KPO-AL-QAC-PRO-00039) CONCRETE WORKS page fof 15 KZ611-00-4102-SC-0007-00 MS FOR NIGHTSHIFT WORKS — CIVIL 3 DEFINITIONS AND ABBREVIATIONS COMPANY PROJECT KPC Rok CONTRACTOR PM DPM_GCM PHSEM DHSEM HSE_SUP HSE_INS EC ENV_LE RS_SUP POM AQM Qc_INS Ls FEM upcc INT MAN ACM D_SUPT D_SUP DFOR PPE PTW TMP aac acP TP NFI BS IFC uc HDD TkMMO Mg uw Sid RE E KPO Karachaganak Petroleum Operating BV Karachaganak Processing Complex Gas Debottlenecking Projact Karachaganak Processing Complex Republic of Kazakhstan Orenburg Gas Processing plant Brown Field Green Field Pipeline Material Take Off Tool Box Talk Private entity/Company who owns the property where the crossings are situated. KKS Sicim LLP Project Manager Deputy Project Manager and General Construction Manager Project Health, Safety and Environment Manager Deputy Health, Safety and Environment Manager HSE Supervisor HSE Inspector Emergency Coordinator Environmental Lead Engineer Road Safety Supervisor Project Quality Manager Area Quality Manager QC Inspector Lead Survey Field Engineering Manager Lead Document Control Center Interface Manager Area Construction Manager Construction Discipline Superintendent (Civ., Mec. Pip., ELE/INS.) Construction Discipline Supervisor (Civ., Mec. Pip., ELE/INS.) Discipline Foreman Personnel and Protective Equipment Permit to Work Traffic Management Plan Quality Assurance / Quality Control Quality Control Procedure Inspection Test Plan Notice for Inspection Block Valves Stations Issued for Construction Underground Horizontal Directional Drilling Titanium-mixed metal oxide Magnesium Isolation Joint Isolation Joint Test Station Reference Electrode Electrode Over voltage protection page Sof 5

You might also like