Enter Deadline Date

If you use Tasks Constraints, you limit your scheduling flexibility, where MS Project 2013
will fix a particular start or finish date of the task according to the constraint. It is a better
idea to use a Deadline Date which has no effect on the scheduling of a task or summary
task. MS Project will alert you with a red exclamation symbol in the indicators column, if
the scheduled completion of the task exceeds its deadline date.

Click Task Tab -> double-click the required Task under Task Name column -> Task
Information dialog box opens -> Advanced Tab.