Professional Documents
Culture Documents
Critical Path Method PDF
Critical Path Method PDF
Method
www.projectbaseline.in 1
History
www.projectbaseline.in 2
Application
www.projectbaseline.in 4
Basic Technique
www.projectbaseline.in 5
Basic Technique
• In project management, a critical path is the
sequence of project network activities which add up to
the longest overall duration.
• This determines the shortest time possible to
complete the project.
• Any delay of an activity on the critical path directly
impacts the planned project completion date (i.e.
there is no float on the critical path).
• A project can have several, parallel, near critical
paths.
• An additional parallel path through the network with
the total durations shorter than the critical path is
called a sub-critical or non-critical path.
www.projectbaseline.in 6
PERT Chart
A B
5 12
LS LF LS LF
www.projectbaseline.in 7
Activity Relationships
Finish-to-Start (FS):
A relationship between activities in which the start of a successor
activity depends on the finish of its predecessor activity.
B
Start-to-Start (SS)
A relationship between activities in which the start of a successor
activity depends on the start of its predecessor.
www.projectbaseline.in 8
Activity Relationships
Finish-to-Finish (FF):
A relationship between activities in which the finish of a
successor activity depends on the finish of its predecessor.
A
B
Start-to-Finish (SF):
A relationship between activities in which a successor activity
cannot complete until its predecessor starts.
A
Lags (or Leads):
An offset or delay from an activity to its successor. A Lag can be
positive or negative
www.projectbaseline.in 9
Activity Box
ES EF
A
5
LS LF
ES = Early Start
EF = Early Finish
LS = Late Start
LF = Late Finish
A = Activity Name
5 = Duration Of Activity
www.projectbaseline.in 10
Activity Network Diagram
ES EF ES EF
B C
10 8
LS LF LS LF
ES EF ES EF
A E
5 7
LS LF LS LF
ES EF
D
12
LS LF
Activity Name
A. Ordering of Pump
Assumptions
B. Pump Manufacturing
• 7 day work week
C. Pump Transportation
• FS – Relationships
D. Pump Foundation
• No Lag or Leads
E. Pump Erection
www.projectbaseline.in 11
Forward Pass
In Forward Pass Early Dates are calculated
Forward Pass
B C
10 8
LS LF LS LF
ES=1 EF=5 ES=24 EF=30
A E
5 7
LS LF LS LF
ES=6 EF=17
D
12
LS LF
www.projectbaseline.in 12
Backward Pass
In Backward Pass Late Dates are calculated
B C
10 8
LS=6 LF=15 LS=16 LF=23
A E
5 7
LS=1 LF=5 LS=24 LF=30
ES=6 EF=17
D
12
LS=12 LF=23 Assuming LF = 30
Backward Pass
www.projectbaseline.in 13
Total Float
Total Float = The amount of time the activity can be delayed before delaying
the Project Finish Date
B C
10 8
LS=6 LF=15 LS=16 LF=23
www.projectbaseline.in 14
Critical Path – Scenario-I
Scenario – I Late Finish of the project = 30
Activities with Total Float =< 0 are on the Critical Path
B C
10 8
LS=6 LF=15 LS=16 LF=23
www.projectbaseline.in 15
Critical Path – Scenario-II
Scenario – II Late Finish of the Project is greater than 30 i.e. 40
Activities with Total Float =< 0 are on the Critical Path
B C
10 8
LS=16 LF=25 LS=26 LF=33
B C
10 8
LS=0 LF=9 LS=8 LF=17
www.projectbaseline.in 17
Total Float
www.projectbaseline.in 18