Tugas Jembatan
Tugas Jembatan
2 m w = 700 cm = 7
ht = 640 cm = 6.4 m h = 500 cm = 5
t1=t2 = 70 cm = 0.7 m
t3 = 60 cm = 0.6 m
Beban:
h. Aspal = 10 cm = 0.1 m y = 2.2 t/m3
h. Beton = 15 cm = 0.15 m y = 2.5 t/m3
h. Tanah = 200 cm = 2m y = 1.8 t/m3
h. Kendaraan = 60 cm = 0.6 m yb = 2.5 t/m3
285 cm = 2.85 m
P = 11.25 t/m
a1 = h. Tanah x Ka x y
= 2x 0.271 x 1.8 = 0.976
a2 = a1 + ( h. Total x y x Ka )
= 0.976 + ( 2.85 x 1.8 x 0.271 )
= 2.366
W = Q1 - Wt
= 5.945 - 23.25
= -17.3 t/m
M1-4 = M2-3 = L x ( 3x a2 + 2x a1 )
60
= 5.7 x ( 3x 2.366 + 2x 0.976 )
60
= -0.1 x ( 7.097 + 1.951 )
= -0.1 x 9.048
= -0.86 tm
M4-1 = M3-2 = L x ( 2x a2 + 3x a1 )
60
= 5.7 x ( 2x 2.366 + 3x 0.976 )
60
= 0.095 x ( 4.731 + 2.927 )
= 0.095 x 7.658
= 0.728 tm
M4-3 = M3-4 = 1x W x L2
12
= 0.083 x -17.3 x 7.6 2
= -83.3 tm
Fixed and Moment:
FEM1-2 = FEM2-1 = q x L2 + P x L
12 8
= 5.945 x ( 7.6 )2 + 11.25 x 7.6
12 8
= 28.62 + 10.69
= 39.3 t/m
FEM1-4 = FEM2-3 = q x L2 + P x L
23 30
= 0.976 x ( 5.7 )2 + 1.39 x 5.7
23 30
= 1.38 + 0.264
= 1.642 t/m
FEM4-1 = FEM3-2 = q x L2 + P x L
23 30
= 0.976 x ( 5.7 )2 + 1.39 x 5.7
12 20
= 2.64 + 0.396
= 3.038 t/m
FEM4-3 = FEM3-4 = q x L2
12
= 8.951 x ( 7.6 )2
12
= 43.09
= 43.09 t/m
Kekakuan Relatif:
K1-2 = K4-3 = 4x 2,858,333.3 = 15,043.9 ### 2367
760 220
K1-4 = K2-3 = 4x 1,800,000.0 = 12,632 ### 1185
570 225
Konstruksi simetri Cl
Jadi cukup ditunjukkan 1/2 konstruksi
0.5
0.333
1.104
0.8
1.904
2.4
13.92