BILL OF QUANTITY PEKERJAAN STRUKTUR

PEKERJAAN JASA KONSULTANSI PERENCANAAN DETAIL TEKNIS 10 PASAR RAKYAT


PD. PASAR JAYA

BILL OF QUANTITY
PEKERJAAN STRUKTUR
GUDANG RANGKA BAJA 66 X 20 M

No Uraian Pekerjaan Satuan Qty Harga Satuan Jumlah Harga

PEKERJAAN STRUKTUR
A Pekerjaan Persiapan
1 Pekerjaan Direksi Keet & Gudang m2 48.00 750,000 36,000,000
2 Air Kerja & Listrik Kerja Bln 3.00 1,500,000 4,500,000
3 Mobilisasi Peralatan Dan Pekerja Ls 1.00 15,000,000 15,000,000
4 Keselamatan Kerja K3 dan Rambu rambu ls 1.00 5,000,000 5,000,000

B Pekerjaan Galian & Pondasi


1 Galian tanah biasa sedalam 1 m m3 24.19 65,000 1,572,480
2 Buang tanah sejauh ±15 m m3 14.52 45,000 653,184
3 Urug kembali tanah galian m3 9.68 25,000 241,920
4 Urugan pasir urug m3 1.45 275,000 399,300
5 Lantai kerja beton tumbuk 1:3:5; t. 50 mm m2 1.45 42,500 61,710
Pilecap P1 uk. 300/1000/1000
6 -Beton Readymix K-300 m3 6.00 975,000 5,850,000
7 -Bekisting Pondasi m2 28.80 245,000 7,056,000
-Tulangan besi U-24
8 -dia. 10 mm kg 370.00 11,500 4,255,000
Kolom uk. 1000/1440/1000
9 -Beton Readymix K-300 m3 1.98 975,000 1,930,500
10 -Bekisting Kolom m2 26.40 245,000 6,468,000
-Tulangan besi U-24
11 -dia. 8 mm kg 85.32 11,500 981,180
12 -dia. 10 mm kg 153.92 11,500 1,770,080

C Pekerjaan Tie Beam


1 Galian tanah biasa sedelam 1 m m3 44.64 65,000 2,901,600
2 Buang tanah sejauh ±15 m m3 17.86 45,000 803,520
3 Urug kembali tanah galian m3 26.78 25,000 669,600
4 Urugan pasir urug m3 4.65 275,000 1,278,750
5 Lantai kerja beton tumbuk 1:3:5; t. 50 mm m2 93.00 42,500 3,952,500
Tiebeam TB1 uk. 200/400
6 -Beton Readymix K-300 m3 29.76 975,000 29,016,000
7 -Bekisting Pondasi m2 297.60 245,000 72,912,000
-Tulangan besi U-24
8 -dia. 8 mm kg 979.60 11,500 11,265,400
9 -dia. 12 mm kg 1,990.20 11,500 22,887,300

D Pekerjaan Plat lantai dasar


1 Pemadatan tanah m2 1,320.00 7,500 9,900,000
2 Urugan pasir urug m3 66.00 275,000 18,150,000
3 Lantai kerja beton tumbuk 1:3:5; t. 50 mm m2 1,320.00 42,500 56,100,000

PT ARTEFAK ARKINDO PARAF: 1


BILL OF QUANTITY PEKERJAAN STRUKTUR
PEKERJAAN JASA KONSULTANSI PERENCANAAN DETAIL TEKNIS 10 PASAR RAKYAT
PD. PASAR JAYA

No Uraian Pekerjaan Satuan Qty Harga Satuan Jumlah Harga

4 Beton Readymix K-300 m3 264.00 975,000 257,400,000


5 Tulangan wiremesh M8-150 m2 1,320.00 71,000 93,720,000

I. PEKERJAAN PONDASI & PERSIAPAN Sub jumlah Rp. 672,696,024

II. PEKERJAAN ATAP


A Pekerjaan Struktur Baja
1 Kolom KB1 WF 250x125X5X8 kg 8,131.20 18,500 150,427,200
2 Rangka Kuda-kuda WF 250X125X5X8 kg 4,065.60 18,500 75,213,600
3 Rangka Kuda-kuda WF 125x60x6x8 kg 475.20 18,500 8,791,200
3 Rangka Ikatan antar Kuda Kuda kg 660.00 18,500 12,210,000
4 Gording C 125x50x20x3,2 kg 12,880.56 22,000 283,372,320
5 Trekstang Besi beton Ø 12 kg 510.03 18,500 9,435,617
6 Ikatan angin Besi beton Ø 12 kg 470.80 18,500 8,709,800
7 Besi siku L 40x40x4 kg 217.88 18,500 4,030,854
8 Baud Ø 12 bh 520.00 22,500 11,700,000
9 - Base Plate t.16 mm kg 233.13 24,500 5,711,563
10 - Stiffener t.10 mm kg 609.84 24,500 14,941,080
11 - Angker Baut Ø19 p.600 mm bh 144.00 45,000 6,480,000
12 Cat meni Besi kg 28,918.24 3,000 86,754,727
13 Atap Zinkalum Spandex 0,35 mm kg 1,632.00 59,000 96,288,000
14 Nok ZinKalum m 68.00 45,000 3,060,000
15 Talang Air m1 136.00 65,000 8,840,000
16 Plat Penutup Talang Rangka L 40x40x4 m1 136.00 45,000 6,120,000
17 Atao Canopy 6000x3000 m2 144.00 650,000 93,600,000

B Pekerjaan Penggantian Atap Bangunan Lama


1 Bongkar Atap m2 966.00 25,000 24,150,000
2 Atap Zinkalum Spandex 0,35 mm m2 966.00 59,000 56,994,000
3 Nok ZinKalum m 42.00 45,000 1,890,000
4 Talang Air m 42.00 65,000 2,730,000
-

II. PEKERJAAN ATAP Sub jumlah Rp. 971,449,960

III. PEKERJAAN LANTAI DAN DINDING


1 Pas. Batako 40x20x10 m3 873.20 87,500 76,405,000
2 Plesteran + Acian Dinding m3 1,746.40 56,400 98,496,960
3 Kolom Praktis 10x10 m1 1,364.00 45,000 61,380,000
4 Pasangan Keramik Lantai 30x30 cm m2 1,320.00 185,000 244,200,000
5 Pintu Besi Plat D1 m2 18.00 750,000 13,500,000
6 Pintu Besi Plat D2 m3 43.20 750,000 32,400,000
7 Kusen Jendela Alumunium Bh 34.00 1,450,000 49,300,000
8 Pekerjaan Cat Dinding m2 3,492.80 22,500 78,588,000
9 Ventilasi Wiremesh Rangka Siku 80x585 Unit 22.00 1,624,000 35,728,000
10 Rabat Beton Tritisan Keliling Bangunan m1 176.00 245,000 43,120,000

PT ARTEFAK ARKINDO PARAF: 2


BILL OF QUANTITY PEKERJAAN STRUKTUR
PEKERJAAN JASA KONSULTANSI PERENCANAAN DETAIL TEKNIS 10 PASAR RAKYAT
PD. PASAR JAYA

No Uraian Pekerjaan Satuan Qty Harga Satuan Jumlah Harga

III.PEKERJAAN LANTAI DAN DINDING Sub jumlah Rp. 733,117,960

IV. PEKERJAAN INSTALASI LISTRIK & AIR HUJAN


A Pekerjaan Listrik
1 Instalasi Titik Lampu NYM 2x2,5 mm ttk 22.00 185,000 4,070,000
2 Lampu Kap Industri Bh 22.00 145,000 3,190,000
3 Instalasi Stop Kontak NYM 3x2,5 mm Ttk 11.00 245,500 2,700,500
4 Saklar seri bh 8.00 45,000 360,000
5 Saklar Engkel bh 4.00 32,500 130,000
6 Instalasi Penangkal Petir (Lightening Protection) Unit 2.00 4,500,000 9,000,000
7 Box MCB Unit 2.00 7,500,000 15,000,000
8 Kabel Toefoer m1 32.00 87,500 2,800,000

IV. PEKERJAAN INSTALASI LISTRIK & AIR HUJAN Sub jumlah Rp. 37,250,500

REKAPITULASI

I. PEKERJAAN PONDASI & PERSIAPAN 672,696,024

II. PEKERJAAN ATAP 971,449,960

III.PEKERJAAN LANTAI DAN DINDING 733,117,960

IV. PEKERJAAN INSTALASI LISTRIK & AIR HUJAN 37,250,500

1.8 - PASAR BIDADARI SUB TOTAL.....Rp. 2,414,514,444

PT ARTEFAK ARKINDO PARAF: 3