litem ronmental protection
Efforts to reduce cooling water consumption in a
region with limited water supply
The water treatment plant
typically referred to as an
auxiliary plant — is essential
for ensuring the continuity
of production and plant
‘operations in a steelmaking
facility. If water resources are
limited, a non-conventional
‘approach is needed to design a
water treatment plant with low
‘water consumption. For a steel
plant in a desert area cooling
equipment with low water
‘consumption and internal
recycle of treated water drains
hhas been adopted to reduce
raw water consumption down
to approximately only 120 m¥sh
ona daily average. This allowed
to respect the limits imposed by
the availability of water on site
and to maintain a safety margin
for an extension planned for
‘the future
Silvia Cattarino, Marco Colautt, Sandro
Mansutt,Perteco sr, Tavagnacco, UD, Italy
Contact: wwm.perteco.com
Email info@perteco.com
54 Merintenations 5208
‘ae
4] ees,
Dram
eoling towers
_fvaporated
i ret cling
Hi] Product
iy to
1 |cateren creas)
i
there dane
iain from
feoling towers
Figure 1. Simplified process diagram of a traditional water treatment plant
In a steel plant, the water resoure
is vital to the operations since water
is used as cooling fluid for the equip-
ment and the steel. Although referred
toas “auxiliary equipment”, the water
treatment plant is essential for ensur-
Ing the continuity of production. Even
though water saving hasbecomean in-
creasingly felt need, usually no partic-
ularattention is paid to it in the design
process for production facilities. A co
ventional water treatment plant uses
open cooling circuits, with cooling tow-
ersand the resulting evaporative water
loss (figure 1).
Perteco, an engineering company
based in Italy, dealt with acasein which
the water shortage called for a non-tra-
ditional approach, An unconventional
water treatment plant was cequired to
serve a steelmaking facility under con.
struction in a desert area. The extreme
environmental conditionsand thestrin-
gent water consumption limits made
the study and the implementation of
this projecta real engineering challenge,
which has meanwhile been successful:
ly coped with. To comply with the re
quired limits of water consumption, it
‘was necessary to fully review the usual
approach, studying ad hoc solutions,
both with regards to process and equip:
ment selection,
Cooling requirements
For the project on hand, the demand-
ed cooling water capacity is approxi:
‘mately 10,000 m*/h, for several users:
EAE (capacity: 170 9,
lade furnace (capacity: 170),
six-strand continuous casting ma
chine,
airseparation plant,
ment plant,
rs (compressed air station,
sve),
The total water capacity is divided up
into several circuits. The totalamount of
thermal power to be removed is in the
‘order of 200 MW. it dedicat-
ed to the cooling ofthe fume treatment
plant distinguishes tselffrom the others
in terms of the temperatures required,
In particular, the input temperature is
higher than the others (55°C instead of
35°C or 40°C). The capacity and thermal
power of this circuit corresponds to ap-
proximately half of the total
Adverse factors for the design of the
water treatment plant are the climatic
conditions, scarcity of raw waterand the
margin required. The steelmaking plant
was designed to produce 1,500,000 t/
year of billets and is placed in a desert
area, characterized by an annual tem:
perature range between -16"Cand 445°C.Environmental protection
and very adverse climatic conditions.
‘The maximum wet bulb temperature i
25°C and the maximum dry bulb tem-
perature is 45°C (design values). These
{temperatures define the lower unseach-
able limit of water cooling by evapora:
ton (traditional solution with evapo-
rative cooling towers) and dry coolers
(coolers with closed circuits) respect
ly. These temperatures have to be con
sidered for the design of cooling equip:
ment with an adequate margin, which
is typically of 5°C, So it wll not be pos.
sible to reach temperatures below 30°C.
and 50°C, adopting the traditional evap-
orativecooling towers or the dry coolers
as alternative solution.
The raw water available on site comes
froman upstream civil waste-watertreat-
ment plant, Raw water consumption has
been strictly limited to 180.m2/h (max
‘mum value as average daily water flow).
ditionally, a margin of 2096 in raw wa-
terconsumption hasto be taken intoac
count for future expansions planned for
‘thestee site. So the maximum rave water
consumption Is below 180 m"/h.
Areverse osmosis treatments applied
to treat the raw waterand produce make-
‘up water in the quantity and quality re-
quired to compensate water lossesin the
plant. Also chemicals have to be added
othe make-up water to improve its char-
acteristics and to avoid scale and corro-
sion problems inside the circuits. With
the traditional solution, raw water con:
sumption is estimated to amount to ap-
proximately 600 m/h (worst day case.
Genius solution to a
challenging task
Itis evident that the required con:
sumption (below 180 m¥h) is much
lower than that obtainable with a tradi-
Airoutlet Cold water
oe ee enn
Hot water
Ce
old
Y in i
Dry cater example)
tional approach, including reverse os-
mosis for the raw water treatment and
chemicals addition to make-up water
(approximately 600 m3/h). The target is
toidentify a configuration for the water
treatment plant which:
respects the limits imposed on the
available raw water,
~ ensurescontinuous and reliableoper-
ation,
= provides an acceptable solution in
terms of investment and manage-
ment costs
The solution was found by acting on
two fronts: Furst, appropriate equip-
ment had to be chosen for water cool-
ing. Second, discharges from the water
treatment plant had to be recovered by
\way of an appropriate treatment to en-
able re-use within the same water treat-
‘ment plant.
Appropriate equipment. Dry coolers
and hybrid-cooling towers (figure 2)
represent viable alternatives to reduce
water cooling consumption. Infact, the
dy coolers coo! the water circulating in
a closed coil without leakage. Cooling,
Airoutlet
yr cooler (example)
Figure 3 Closed ciruit coolers and comparison with the traditional evaporative coolers
56 Mer iseraationa! 5208
Evaporative Hybrid
Figure 2. Hybrid towers of a water
‘treatment plant
occurs by heat exchange through forced
flow of ambient ar, with the use of fans
Included in the cooling equipment.
‘The hybrid-cooling towers repre.
sent an intermediate solution between
the traditional cooling towers and dry
coolersand can operate in either wet or
dry mode depending on climatic condi-
tions. Even in such equipment the wa-
terintended for the cooling ofthe plants
circulates in a closed coll. Cooling can
be performed by spraying cooling water
{awet) from the outside or by forced ven.
Ulation only (ary)
For the purpose of comparisons be-
tiween the different equipment, it was
assumed that the same thermal power
hhas to be removed and that there were
‘no environmental limits for closed cir.
cuits coolers that would prevent their
use. Information derived from data
from different suppliers has been taken
into account. Figure 3 indicates the re
sults based on data from different sup:
pllers. It seems that the dry solution Is,
the best option,
In reality, the typeof equipment used
thas to take into consideration the site
Se AGIOS NMR mean
ig
00 | 7
* noe
Fa a 7
»
DryEnvironmental protection
Foure 4 Selected equipment with closed circuit for low water consumption
wie
Equipment
toberocted
itterent reat
: Gimplified
: arawing) |
i Evaporated water
stream with,
aracteistie
Concentrate!
Figure 5. DR:WTP included in a water treatment plant
conditions. According to the climatic
conditions and the required inlet tem-
perature at the various consumption
points, it was not possible to instal the
day coolers in ll ciscuits. Their applica
tion turned out tobe ideal only for coot-
ing the circuit for the fume treatment
plant, due the high temperature accept-
ced here, The equipment to be adopted
‘was therefore selected as shown in fig
ure 4: dry coolers for the FTP circuit and
hybrid towers forall other circuits.
‘With theadoption of thé above-men-
tioned equipment, the estimated con
sumption of raw water also considering
the asmosis process for its initial treat
58 Mrrletematonsl 208
‘ment, wasstill not within limits, In fact
the estimated dally average consump-
tion was approximately 160 m/h and
theadequate safety margin was not met,
In order to achieve additional saving,
Of raw water, a recovery facility of the
drains (drains recovery water treatment
plant: DR-WTP) was adopted, using the
experience gained by Perteco techni-
cians during the provision of a similar
facility serving a direct reduction plant
also located in a desert territory.
Drain recovery. Figure 5 shows the
simplified process diagram with refer
tence to the circuits cooled with hybrid
Hybrid coolers
installed in all circuits
except in the FTP circuit
= 18 coolers with different sizes
+ the biggest:
11 mx 2.2 m x 4.2 (H)
2 fanseach, 11 kvWifan
Dry coolers
stalled only in FTP circuit
=30 coolers with the same size:
ola
12.5 mx 2.4 mx2.8 m(H)
18 fansleach, 3.1 kW/fan
coolers and the adoption of a plant for
the recovery of drains. The design flow
rate forall drainstreated by the DR-WT?.
is 63 m'/h, as maximum capacity. This
capacity includes the drains from the
various hybrid cooling towers and the
concentrate discharged from the reverse
‘osmosis that treats the raw water, Much,
more than 50% of the discharges can
be recovered from the recovery system,
through adequate pre-treatment and
dedicated reverse osmosis, obtaining
approximately 40 m*fh as average daily
‘water with quality similar to raw water,
‘This recovered flow rate corresponds
to the raw water saved by adopting the
DRWTP. The DRWTP was integrated in
the water treatment plant process flow
iagram, achieving a consumption of
imately 120 ne/h as
a daily average. It was considered as the
final solution to the challenging task
(table 1).
raw water of appro
Comparison with traditional
solutions
‘The final comparison between the so-
lution adopted and the traditional one is,
summarizedin table 2, glvingadvantag-
esand disadvantages. Although elect
cal energy consumption willincrease by
approximately 25%, evaluated as yearly
average, resulting in additional energy
costs compared to the traditional solu
tion, itis interesting to note that both
in the traditional and in the adopted so.
lution the main part, namely more than