You are on page 1of 9

Analisis Simulasi Debit untuk Operasi Pintu Bendung

Nama Bendung : Alue Ubay

Elevasi Mercu Bendung : 36.269 m Jumlah Pintu Pengambilan : 1 bu

Elevasi Ambang intake : 35.269 m Lebar Pintu Pengambilan :

Debit
Bendung/Penguras Bendung

Elevasi Muka Air Sungai, EMAS (m)


hb Qb* Qb**
EMAS h1/a 0.00 0.05
- - - 35.269 0.00 0.00
- - - 35.319 0.05 0.00
- - - 35.369 0.10 0.00
- - - 35.419 0.15 0.00
- - - 35.469 0.20 0.00
- - - 35.519 0.25 0.00
- - - 35.569 0.30 0.00
- - - 35.619 0.35 0.00
- - - 35.669 0.40 0.00
- - - 35.719 0.45 0.00
- - - 35.769 0.50 0.00
- - - 35.819 0.55 0.00
- - - 35.869 0.60 0.00
- - - 35.919 0.65 0.00
- - - 35.969 0.70 0.00
- - - 36.019 0.75 0.00
- - - 36.069 0.80 0.00
- - - 36.119 0.85 0.00
- - - 36.169 0.90 0.00
- - - 36.219 0.95 0.00
- - - 36.269 1.00 0.00
Air Sungai Mulai Melimpah Melalui Mercu Bendung
0.05 1.99 0.16 36.319 1.05 0.00
0.10 5.62 0.46 36.369 1.10 0.00
0.15 10.33 0.85 36.419 1.15 0.00
0.20 15.91 1.30 36.469 1.20 0.00
0.30 29.22 2.40 36.569 1.30 0.00
0.40 44.99 3.69 36.669 1.40 0.00
0.50 62.88 5.15 36.769 1.50 0.00
0.60 82.65 6.77 36.869 1.60 0.00
0.70 104.15 8.54 36.969 1.70 0.00
0.80 127.25 10.43 37.069 1.80 0.00
0.90 151.84 12.45 37.169 1.90 0.00
1.00 177.84 14.58 37.269 2.00 0.00
1.10 205.17 16.82 37.369 2.10 0.00
1.20 233.77 19.16 37.469 2.20 0.00
1.30 263.60 21.61 37.569 2.30 0.00
1.40 294.59 24.15 37.669 2.40 0.00
1.50 326.71 26.78 37.769 2.50 0.00
1.60 359.92 29.50 37.869 2.60 0.00
1.70 394.18 32.31 37.969 2.70 0.00
1.80 429.47 35.20 38.069 2.80 0.00
1.90 465.75 38.18 38.169 2.90 0.00
2.00 503.00 41.23 38.269 3.00 0.00
2.10 541.19 44.36 38.369 3.10 0.00
2.20 580.31 47.57 38.469 3.20 0.00
2.30 620.32 50.85 38.569 3.30 0.00
2.40 661.21 54.20 38.669 3.40 0.00
2.50 702.96 57.62 38.769 3.50 0.00
2.60 745.56 61.11 38.869 3.60 0.00
2.70 788.99 64.67 38.969 3.70 0.00
2.80 833.22 68.30 39.069 3.80 0.00
2.90 878.25 71.99 39.169 3.90 0.00
3.00 924.07 75.74 39.269 4.00 0.00
Elevasi Muka Air Banjir Rencana = 43,31 m
3.25 1041.95 85.41 39.519 4.25 0.00
3.50 1164.46 95.45 39.769 4.50 0.00
3.75 1291.43 105.85 40.019 4.75 0.00
4.00 1422.70 116.61 40.269 5.00 0.00
4.25 1558.14 127.72 40.519 5.25 0.00
4.50 1697.63 139.15 40.769 5.50 0.00
4.70 1812.05 148.53 40.969 5.70 0.00
ngambilan : 1 buah Lebar Penguras = 2

gambilan : 2 m Kapasitas Saluran Indu

De

Tinggi Muka Air di Peilschal, h1 (m) Tinggi Bukaan Pintu P

0.10 0.15 0.20 0.25 0.30 0.35 0.40


ar Penguras = 2 x 2,5 m = 5 m Cd =

pasitas Saluran Induk Maksimum : 4.114 m3/det Beff =

Debit Pintu Pengambilan

ggi Bukaan Pintu Pengambilan, a (m) Tinggi Muka Air di Atas Mercu Ben

0.45 0.50 0.55 0.60 0.65 0.70 0.75


1.71

61 m

di Atas Mercu Bendung, hb (m)

0.80 0.85 0.90 0.95 1.00 1.05 1.10


KEPALA RANTING PAYA BAKONG
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
KABUPATEN ACEH UTARA
ZULKIFLI YUSUF, A.Md
Penata Muda Tingkat I / NIP. 19720711 199703 1 004