Professional Documents
Culture Documents
Toda la información contenida en este manual es de propiedad del Señor Kadri Dagdelen y cualquier reproducción parcial o total de la misma será sancionada legalmente.
Introduction to Mining Practices- Case Studies
Open Pit Mining Terminology
Pit Geometry and Slope Angles
Open Pit Mine Planning Concepts - Circular Analysis
Geologic Block Modeling Techniques
Assay and Composite Sections and Block Modeling
Geostatistical Resource Estimation Techniques
Dispatch Systems
In Pit Crushing and conveying systems
Mineral Processing
Case Study
General Information
Surface Mine Design
2
General Information
3
General Information
4
General Information
Layout
Surface Mine Design
5
General Information
Geology
Surface Mine Design
6
General Information
7
Mine Plan
8
Mine Plan
Typical Mining Sequence
Surface Mine Design
9
Mine Plan
10
Mine Plan
12
Drilling
14
Blasting
17
Loading
19
Haulage
per minute.
•3 to 4 weeks are required to move the crusher.
•-10 in crushed rock is fed directly to a 72-in
conveyor.
•The belt is 5 mile ling to Copperton concentrator
and capable of carrying 10,000 tph at 900 ft/min
speed. 21
Road Maintenance
22
Open Pit Mining Fundamentals
2
Terminology (Cont.)
• BENCH HEIGHT: Vertical distance between the
highest point on the bench (crest) and the lowest
point or the bench (toe). It is influenced by size of
the equipment, mining selectivity, government
Surface Mine Design
3
Terminology (Cont.)
4
Terminology (Cont.)
• BERM: Horizontal shelf or ledge within the
ultimate pit wall slope left to enhance the stability
of the a slope within the pit and improve the safety.
Berm interval, berm width and berm slope angle are
Surface Mine Design
5
Terminology (Cont.)
6
Terminology (Cont.)
7
Terminology (Cont.)
• HAUL ROADS: During the life of the pit a haul
road must be maintained for access.
• HAUL ROAD - SPIRAL SYSTEM: Haul road is
arranged spirally along the perimeter walls of the
Surface Mine Design
pit.
8
Terminology (Cont.)
• HAUL ROAD – SWITCH BACK SYSTEM:
Zigzag pattern on one side of the pit.
• HAUL ROAD WIDTH: Function of capacity of the
road and the size of the equipment. Haul road width
Surface Mine Design
9
Haul Road Effect on Pit Limits
Surface Mine Design
10
Terminology (Cont.)
• ANGLE OF REPOSE: Maximum slope of the
broken material.
11
Terminology (Cont.)
• ULTIMATE PIT LIMITS: Vertical and lateral
extend of the economically mineable pit boundary.
Determined on the basis of cost of removing
overburden or waste material vs. the mineable value
Surface Mine Design
of the ore.
12
Terminology (Cont.)
• STRIPPING RATIO: Expressed in tons of waste to tons of
ore in hard rock open pit operations. Critical and important
parameter in pit design and scheduling
13
Single Working Bench
Surface Mine Design
14
Shovel in Working Bench
Surface Mine Design
15
Two Working Benches
Surface Mine Design
16
Surface Mine Design
17
Cresson Mine – Year 2001
Surface Mine Design
18
Cresson Mine – Year 2007
Surface Mine Design
19
Cresson Mine – Year 2011
Surface Mine Design
20
Surface Mine Design
21
Surface Mine Design
22
Surface Mine Design
23
Surface Mine Design
24
Section of Pit Sequence
Surface Mine Design
25
Open Pit Mine Planning and
Design: Fundamentals
Cumulative frequency
distribution of measured
bench face angles (Call, 1986).
Parts of a bench
2
Geometrical Considerations
Surface Mine Design
3
Geometrical Considerations
Surface Mine Design
Double benches at final pit limits. Catch bench geometry (Call, 1986).
4
Geometrical Considerations
Surface Mine Design
5
Geometrical Considerations
Surface Mine Design
8
Geometrical Considerations
Surface Mine Design
9
Geometrical Considerations
Surface Mine Design
10
Geometrical Considerations
Surface Mine Design
12
Geometrical Considerations
Surface Mine Design
13
Geometrical Considerations
Surface Mine Design
14
Geometrical Considerations
Surface Mine Design
15
Geometrical Considerations
Surface Mine Design
20
Geometrical Considerations
Surface Mine Design
(Continued).
21
Geometrical Considerations
Surface Mine Design
22
Geometrical Considerations
Surface Mine Design
(Continued).
23
Geometrical Considerations
Surface Mine Design
(Continued).
24
Geometrical Considerations
Surface Mine Design
25
Geometrical Considerations
Initial geometry for the push back example.
26
Geometrical Considerations
Surface Mine Design
27
Geometrical Considerations
Surface Mine Design
28
Geometrical Considerations
Surface Mine Design
29
Geometrical Considerations
Surface Mine Design
30
Geometrical Considerations
Surface Mine Design
31
Geometrical Considerations
Surface Mine Design
32
Geometrical Considerations
Surface Mine Design
DAYLIGHTING WEDGE
Circular Failure
l Soils
l Stock piles
l Reclamation piles
l Waste dumps
l Highly weathered overburden rocks
Toppling and Step-Path
Modes
Toppling Mixed modes
(e.g. Toppling & Step-Path)
Overall Slope Design
l Identify geological sectors; their strength
characteristics and possible mode of failures
l Determine maximum height and angle for inter-
ramp design
l Determine bench geometry
l Incorporate bench geometry into Inter-ramp
design
l Overall slope design
Failure Modes in Different
Sectors
Pit Slope Monitoring
- What to look for
l Overhang rock
l New geological structures
l Swell and/or increased rock fall activity on highwall
l Heavy precipitation
l Signs of stress
l Tension cracks
l Movement (acceleration)
l Increased water levels
Tension Crack Measurements
l The formation of cracks behind slope is a sign of instability
(Safety Factor ˜ 1)
l Monitoring changes in crack width and direction can provide
information on extent of unstable area
Inclinometers
l Inclinometers measure horizontal
deflections of a borehole
l They can
- Locate failure surface
- Determine nature of failure surface
(rotational or planar)
- Measure movement along failure
surface and determine if
movement is accelerating
Borehole extensometer
l Consists of tensioned rods
anchored at different points in a
borehole.
l Measures changes in distance
between anchors, as well as collar
l Provides displacement
information across discontinuities.
New and Emerging Technologies
l Automated Total Station Network (robots)
l Non-reflective Laser scanners (Lidar systems:
Cyra, Riegl, I-Site)
l Radar Technologies
l GPS (Local sensors with multiple antenna)
l TDR (Time Domain Reflectometry)
l Digital photogrammetry
l Arial photography (Kodak)
Automated Total Station Network in
Chuquicamata Mine, Chile
Bluebox
Switch
Energy
SHELTER 2
ARTURO ESTE
ARTURO OESTE
SHELTER 1
SHELTER 4
SHELTER 6
SHELTER 5
SHELTER 3
ARTURO ESTE
ARTURO OESTE
SHELTER 1
SHELTER 4
SHELTER 6
SHELTER 5
SHELTER 3
CONTROL
CONTROL ROOM
ROOM
Total Station and Prism Locations in
Chuquicamata Mine, Chile
Caseta
Oeste
Caseta
Este
GPS Surveyed Control Stations in
Chuquicamata Mine, Chile
S2
S3
S1 S4
S5
“D” (PR-1)
D4
D5 Cota : 2846.745
Coordenadas de la
Estación de Monitoreo
APS(N;E;Z)
Slope Stability Radar Technology
from GroundProbe of Australia
Complete Pit Wall Coverage from
Remote Locations
Slip Area
Displacement (mm)
23:22 8th October 2003
ime
ith t
nt w
Cyrax 2400
Other Application in Laser Technologies
Riegl Z 210i Lidar Laser Scanner
Specifications
Specifications
Specifications
Displacement (cm)
150 May continue mining
(displacement rate is constant)
100
50
Benches sloped
toward toe
Slope crest
DO
RM
AN
T
55
60
BL
IND
EMILY
RO
60
DE
O
S
CR
JB
EE
K
CHRISTY
PATS
RO
DE
S
O T
CR
EE IGH
K DN
MI 60
N-00-B
G
60
DIN
60
PLO
75
EX
78
ANFO
85 LAST LA
UGH
PO
ST
60 25
FLOWER PATC
H
50
POW
AMANDA
ERF
AN
JE
D
UL
AN
GR
50
BL
IND
RO
DE
O
CR
RO EE
DE K1
O
CR
80 EE
T
K
OS
TIP
AN
Unload Side
l Even though unloading has been a common
response, in general it has been
unsuccessful.
Buttress
Rock Bolts
Anchors, Tiebacks, and
Shotcrete
1. Reinforced concrete dowel to
prevent loosening of slab at
crest
2. Tensioned rock anchors to
secure sliding failure along crest
3. Tieback wall to prevent sliding
failure on fault zone
4. Shotcrete to prevent raveling of
zone of fractured rock
5. Drain hole to reduce water
pressure within slope
6. Concrete buttress to support
rock above cavity
Mesh & Bolts
Buttressing
Buttressing
NE Wall Sept 2002
unwting cut
N-00-B
2% ramp & buttress
mudslide
4880 buttress
4640
4280
NE Wall Un-weighting Cut
MOVEMENT IN (INCHES/DAY)
2/1
/0
-2.00
-1.80
-1.60
-1.40
-1.20
-1.00
-0.80
-0.60
-0.40
-0.20
0.00
0.20
2/1 2
5/0
2
3/1
/0
3/1 2
5/0
3/2 2
9/0
4/1 2
2/0
4/2 2
6/0
5/1 2
0/0
5/2 2
4/0
2
6/7
/02
6/2
1/0
2
7/5
/0
#3
7/1 2
9/0
2
8/2
/02
8/1
6/0
8/3 2
0/0
DATE
9/1 2
3/0
9/2 2
7
10 /02
/11
10 /02
/25
/0
11 2
/8
11 /02
/22
PRISM DATA - All In Movement Area
/0
12 2
/6
12 /02
/20
/02
1/3
/0
1/1 3
7/0
1/3 3
1/0
2/1 3
Prism Data Feb 2002 to Feb 2003
4/0
2/2 3
#4
8/0
3
TN 98
TN 97
TN 72
TN 80
TN 149
TN 144
TN 127
TN 115
TN 114
TN 101
TN010119
TN010095
TN000089
TN000084
Blasting
Line
Production
drill
holes Face
holes
Use of less
Pre-splitting Line drilling charges
next to toe
Slide Management Example
PUSHBACK DEVELOPMENT Displacement rate
Normal 2 a 5 cm/day
Only ore production stripping 5 a 10 cm/day
Stop push-back development > 10 cm/day
D5 300
DESPLAZAMIENTO (cm)
BENCH 250
y = 63.213x - 2E+06
200
150
y = 16.016x - 597363
SAFETY
y = 8.7432x - 326060
100
Failure
BERM
y = 5.6082x - 209126
Catch
50
Berm, ± 40
0
1/2/02 6/2/02 11/2/02 16/2/02 21/2/02
TIEMPO
Took out
m. H13 shovel
BENCH Access D5
& H13 closed
PUSHBACK
Contingency Planning
l Provide multiple access to production faces
l Maintain double access to working benches,
whenever possible
l Stockpile ore/rock
l Design to prevent noses in the plan geometry
l Provide for failure costs in scheduling and budgeting
l Add lag times in production scheduling
l Plan step-outs
Conclusions
l New Radar and Lidar based technologies applied
to pit slope monitoring appears to be very
promising in providing cost effective and accurate
real time data .
l Accurate and reliable slope displacement
information coupled with proper pit slope
management practices has a potential to prevent
unexpected catastrophic pit slope failures.
Haul Road Design
pit.
2
Haul Road Design
• HAUL ROAD – SWITCH BACK SYSTEM:
Zigzag pattern on one side of the pit.
• HAUL ROAD WIDTH: Function of capacity of the
road and the size of the equipment. Haul road width
Surface Mine Design
3
Haul Road Effect on Pit Limits
Surface Mine Design
4
Considerations for Haul Road
Design
• Visibility
• Stopping distances
• Vertical alignment
Surface Mine Design
• Horizontal alignment
• Cross section
• Runaway-vehicle safety
provisions
5
Sight Distances and Stopping
Distances
• Vertical and horizontal curves designed
considering sight distance and stopping
distance
Surface Mine Design
6
Sight Distances and Stopping
Distances
• On vertical curves, road surface limits sight
distance
• Unsafe conditions remedied by lengthening curve
Surface Mine Design
7
Sight Distance Diagrams
⇒
Surface Mine Design
8
Stopping Distances
9
Stopping Distance
Characteristics
For example,
stopping
distance
characteristics
Surface Mine Design
of vehicles of
200,000 to
400,000 pounds
GVW
10
Stopping Distances
performance capabilities
11
Vertical Alignment
12
Vehicle Performance Chart
Surface Mine Design
13
Vehicle Retarder Chart
Surface Mine Design
14
Vertical Alignment
15
Vertical Alignment
16
Vertical Curves
17
Stopping Distance vs. Vertical
Curve
For example,
vertical curve
controls 9 ft eye
height (usually
Surface Mine Design
minimum height
for articulated
haulage trucks of
200,000 to
400,000 pound of
GVW)
18
Horizontal Alignment
superelevation
• Cross slopes also should be considered in the
design
19
Curves, Superelevation, and
Speed Limits
• Superelevation grade recommendations vary
but should be limited to 10% or less because
of traction limitations
Surface Mine Design
20
Curves, Superelevation, and
Speed Limits
• CAT suggests higher slopes with traction
cautions and 10% maximum caution
• Again, where ice, snow, and mud are a
Surface Mine Design
21
Curve Superelevation
Surface Mine Design
(CAT)
22
Recommended Superelevation
Rates
If superelevation is not used, speed limits should be set on curves.
Surface Mine Design
23
Curves, Superelevation, and
Speed Limits
• Centrifugal forces of vehicles on curves are
counteracted by friction between tire an road and
vehicle weight as a result of superelevation
Surface Mine Design
24
Combinations of Alignments
25
Cross Section
26
California Bearing Ratio
Surface Mine Design
27
Subbase Construction
Surface Mine Design
28
Cross Slopes
29
Cross Slopes
30
Recommended Rate of Cross-
Slope Change
31
Width
• Number of lanes
• Recommended vehicle clearance, which ranges
from 44 to 50% of vehicle width
32
Minimum Road Design Widths
for Various Size Dump Trucks
Surface Mine Design
33
Typical Design Haul Road
Width
Typical
design haul-
road width
for two-way
Surface Mine Design
traffic using
77.11-t (85-
st) trucks
34
Typical Haulageway Sections
Surface Mine Design
35
Width
36
Haulageway Widths on Curves
⇒
Surface Mine Design
37
Safety Provisions - Berms
material
• Redirects vehicle onto roadway
• Minimum height at rolling radius of tire
38
Berms
39
Runaway Provisions
40
Runaway Provisions
41
Runaway Precautions
Surface Mine Design
42
Median Runaway-Vehicle
Provision Berms
• Vehicle straddles collision berm and rides
vehicle to stop
• Made of unconsolidated-screened fines
Surface Mine Design
43
Median Runaway-Vehicle
Provision Berms
• Requires maintenance in freezing conditions
• Agitation to prevent damage to vehicle
• May cover berm in high rainfall areas
Surface Mine Design
44
Escape Lanes
45
Escape Lanes
46
Surface Mine Design
Escape Lanes
47
Maintenance
vehicles.
• A good road maintenance
program is necessary for
safety and economics.
48
Safety Considerations
49
Economic Considerations
50
Dust Control
• Dust may infiltrate brakes, air filters,
hydraulic lifts, and other components of
machinery.
•
Surface Mine Design
51
Deterioration Factors
• Weather
• Vehicles follow a
similar path
Surface Mine Design
• Spillage
52
Motor Graders
• A motor grader
should be used to
maintain cross slopes,
Surface Mine Design
53
Road Drainage
54
Haul Road Design
2
Plan View of a Portion of the
Open Pit
Surface Mine Design
3
Example of Mapping Procedure
Surface Mine Design
4
Midbench Elevation
Surface Mine Design
5
Plan View of Midbench Elevation
Surface Mine Design
6
Map Based on Midbench Contours
Surface Mine Design
7
Procedure to Convert Midbench to
Toe and Crest Contours
Surface Mine Design
8
Representation of Crests and Toes
Surface Mine Design
9
Designing a Spiral Ramp Inside
the Wall
Surface Mine Design
10
Completing the new crest lines
Surface Mine Design
11
Pit Layout Including Ramp
Surface Mine Design
12
Design of a Spiral Ramp Outside
the Wall
Surface Mine Design
13
Pit Layout Including Ramp
Surface Mine Design
14
Design of a Switchback
Surface Mine Design
15
Design of a Switchback
Surface Mine Design
16
Design of a Switchback
Surface Mine Design
17
Pit Layout Including Ramp
Surface Mine Design
18
Example of Two Switchbacks
Surface Mine Design
19
Plan and Section Views of Pit
Without Ramp
Surface Mine Design
20
Plan and Section Views of Pit
With Ramp
Surface Mine Design
21
Road Volume in the Ramp
Surface Mine Design
22
Block Modeling and Ore Reserves
Estimation
Surface Mine Design
1
Basic Block Model Information
• Topography Data
• Drill Data
Surface Mine Design
• Sampling
• Assays
2
Topography Data
Surface Mine Design
3
Drill Data
•Collar Coordinates
Surface Mine Design
•Geologic Logs
•Down Hole Surveys
•Lab Tests
4
Samplings
Sampling Data
•Rock Types
Surface Mine Design
•Alteration Types
•Metal Grades
•Attributes
5
Samplings (Cont.)
Surface Mine Design
Data Collections
6
Assays
Surface Mine Design
8
Geological Interpretation
Surface Mine Design
9
Geological Interpretation
Surface Mine Design
10
3D Geological View
Surface Mine Design
11
Composites
Surface Mine Design
12
3D Block Models
Surface Mine Design
13
Block Estimation
Surface Mine Design
14
Block Values
Surface Mine Design
15
Block Models
Surface Mine Design
16
Ore Reserve Estimation
Surface Mine Design
17
Economic Pit Limits
Surface Mine Design
18
3D View of Economic Pit Limits
Surface Mine Design
19
Mine Planning Application
(Open Pit Mine)
Surface Mine Design
20
Geologic Resource Modeling Techniques
21
Frequency and Cumulative Frequency Plots
•Classical Statistics
•Data Posting and Display
Surface Mine Design
•Histograms
•Cumulative Histograms
•Probability Plots
22
Inverse Distance Technique
1
• In general, n
vˆ = ∑ n
di p
vi
1
i =1
∑
i =1 d p
i
1
d ip n
wi = n
vˆ = ∑ wi vi
n
∑
1 ∑ wi = 1
i =1 d i
p i =1 i =1
23
Inverse Distance Technique
(pg257)
v4 v2
v̂ Inverse Distance Square
d3 d2 1
2
1
2
1
2
1
2
vˆ = v1 + v2 + v3 +
d1 d2 d3 d4
v4
d4 4 4 4 4
v1 d
1 ∑
i =1
1
di2 ∑
i =1
1
di2 ∑
i =1
1
di 2 ∑
i =1
1
di2
v3
24
Inverse Distance Square Example
V3=0.5
v1= 0.2 d1 =1
Surface Mine Design
V1=0.2
vˆ = ?
25
Inverse Distance Square Example
1 1
22 4
w2 = = 4
=
1
+ 1
+ 1 21
21
12 22 42 16
1 1
42 1
w3 = = 16
= Note:
1
+ 1
+ 1 21
21
12 22 42 w1 + w2 + w3 = 1
16
26
Inverse Distance Square Example
• Then, calculate v̂
16 4 1
vˆ = × 0.2 + × 0.3 + × 0.5 = 0.233
Surface Mine Design
21 21 21
27
Estimation Error
28
Histogram of Errors
Surface Mine Design
29
Scatter Graph
0.90
0.80
0.70
Surface Mine Design
0.60
E s t i mated (%)
0.50
0.40
0.30
0.20
0.10
0.00
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90
True (%)
30
Surface Mine Design
MNGN312 - MNGN512
Lecture 5
September 14, 2004
Surface Mine Design
Instructor
Dr. Kadri Dagdelen
Geologic Block Modeling
2
Geologic Block Modeling
• Estimate the grade of the block (block size 75ft x 75ft)
for exploration data set.
Estimate the
Surface Mine Design
center point
75ft
v̂1 v̂2
75ft
3
Geologic Block Modeling
• Rectangular search neighborhood of 37.5ft x 37.5ft.
Surface Mine Design
37.5ft
75ft
37.5ft
37.5ft 37.5ft
75ft
Use all the exploration holes within a given block (For this
block, use 3 exploration samples)
4
Inverse Distance Technique
• Inverse distance technique is the simplest interpolation
method.
• Give more weight to the closest samples, and less to
those that are farthest away.
Surface Mine Design
• In general, 1
n
di p
vˆ = ∑ n vi
1
Unknown point
i =1
∑
i =1 d p
Sampling points
i
1 Weights
d ip n
wi = n
vˆ = ∑ wi vi
n
∑
1 ∑ wi = 1
i =1 d i
p i =1 i =1
5
Inverse Distance Technique
v4 v2
v̂ Inverse Distance Square
d3 d2 1
2
1
2
1
2
1
2
vˆ = v1 + v2 + v3 +
d1 d2 d3 d4
v4
d4 4 4 4 4
v1 d
1 ∑
i =1
1
di2 ∑
i =1
1
di2 ∑
i =1
1
di 2 ∑
i =1
1
di2
v3
6
Inverse Distance Square Example
V3=0.5
v1= 0.2 d1 =1
Surface Mine Design
V1=0.2
vˆ = ?
7
Inverse Distance Square Example
1
+ 1
+ 1 21
21 21
12 22 42 16
1 1
42 1
w3 = = 16
=
1
+ 1
+ 1 21
21
12 22 42 16
• Then, calculate v̂
16 4 1
vˆ = × 0.2 + × 0.3 + × 0.5 = 0.233
21 21 21
8
Geologic Block Modeling
Surface Mine Design
d1
25
g1 25
d1 = 25 2 + 25 2 = 35.36
9
Geologic Block Modeling
0.0008
0.0032
Surface Mine Design
10
Geologic Block Modeling
11
Geologic Block Model
Reconciliation
• Determine the average grade of 75ft by 75ft grid blocks
for the blasthole data set (blasthole2004.txt) by averaging
the grades of 9 blast holes that fall within each block.
Surface Mine Design
Block 1 Grade
= (0.42+0.35+0.24+0.33+
… + 0.46) / 9
=0.35
12
Geologic Block Model
Reconciliation
• Error estimation between estimation (Exploration data)
and true value (Blasthole data).
13
Geologic Block Model
Reconciliation
• Histogram of Error (Example of 100ft x 100ft estimation)
Histogram of Estimation Errors (Estimation - True)
60.00%
2
0 3 55.56% 50.00%
0.05 3 88.89% 1.5
40.00%
0.1 0 88.89%
1 30.00%
0.15 0 88.89%
0.2 1 100.00% 20.00%
0.5
0.25 0 100.00% 10.00%
More 0 100.00% 0 0.00%
-0.2 -0.15 -0.1 -0.05 0 0.05 0.1 0.15 0.2 0.25 More
Bin Frequency
Cumulative %
14
Geologic Block Model
Reconciliation
• Scatter Graph (Example of 100ft x 100ft estimation)
True grades agai n s t E s t i mated grades
estimation line.
0.70
0.60
E s t i mated (%)
0.50
0.40
0.30
0.20
0.10
0.00
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90
True (%)
15
Univariate Distribution of
Errors
• Error = Estimated Value - True Value
• We also refer to these error as residuals.
• If error is positive, then we have overestimated the true;
if error is negative, then we have underestimated the
Surface Mine Design
true.
If m=0, then Unbiased Estimates
Overestimates and underestimates
are balanced.
We typically prefer to have a
symmetric distribution.
16
Univariate Distribution of
Errors
• We would like to see the error distribution has small
spread.
Surface Mine Design
a) b)
a) b)
Estimation
Estimation
Estimation
Estimation
Estimation
True True
20
Floating Cone Algorithm
Surface Mine Design
1
Basic Procedure
Top
-1 +1 -1 -1 -1
-1 -1 +3 -1 -1
Surface Mine Design
Bottom
Left Right
-1 -1
-1 -1 -1 -1
Heuristic procedure
2
Floating Cone Steps
• The cone is floated from left to right along the top row of blocks in the section. If
there is a positive block it is removed.
• Move to the second row. Start from the left and search for the first positive block. If
the sum of all blocks falling within the cone is positive, the blocks are removed
(mined).
Surface Mine Design
• Follow the floating cone process moving from left to right and top to bottom of the
section until no more blocks can be removed. Then go back to the top again and repeat
the process for a second iteration. If during a given iteration no positive blocks can be
mined, stop.
• The profitability of the mined area can be found by adding the values of the blocks
that are to be removed.
• Overall stripping ration can be determined by dividing the number of positive blocks
by the total number of negative blocks.
3
Example
-1 -1 -1 -1 -1 +1 -1 Ore
-2 -2 +4 -2 -2
Surface Mine Design
+7 +1 -3 Waste
4
Example
-1 -1 -1 -1 -1 +1 -1 Ore
-2 -2 +4 -2 -2 Waste
Surface Mine Design
+7 +1 -3 Mined
Step 1
5
Example
-1 -1 -1 -1 -1 +1 -1 Ore
Surface Mine Design
-2 -2 +4 -2 -2 Waste
+7 +1 -3 Mined
Step 2
6
Example
-1 -1 -1 -1 -1 +1 -1 Ore
-2 -2 +4 -2 -2 Waste
Surface Mine Design
+7 +1 -3 Mined
Step 3
7
Example
Final Pit
-1
Surface Mine Design
-2 -2
+1 -3
8
Shortcomings
Missing Combinations of Profitable Blocks
-1 -1 -1 -1 -1 -1 -1 Ore
-2 -2 -2 -2 -2
Surface Mine Design
9
Shortcomings
Missing Combinations of Profitable Blocks
-1 -1 -1 -1 -1 -1 -1 Ore
-2 -2 -2 -2 -2 Waste
Surface Mine Design
Step 1
10
Shortcomings
Missing Combinations of Profitable Blocks
-1 -1 -1 -1 -1 -1 -1 Ore
-2 -2 -2 -2 -2 Waste
Surface Mine Design
Step 2
11
Shortcomings
Missing Combinations of Profitable Blocks
-1 -1 -1 -1 -1 -1 -1 Ore
-2 -2 -2 -2 -2 Waste
Final Pit
-3
Correct solution
12
Shortcomings
Over-mining
-1 -1 -1 -1 -1 Ore
+5 -2 -2
Surface Mine Design
+5 Waste
13
Shortcomings
Over-mining
-1 -1 -1 -1 -1 Ore
+5 -2 -2 Waste
Surface Mine Design
+5 Mined
14
Shortcomings
Over-mining
-1 -1 -1 -1 -1 Ore
+5 -2 -2 Waste
+5 Mined
Surface Mine Design
Final Pit
-1 -1
-2 -2
+5
Correct solution
15
Shortcomings
Combination of problems
-1 -1 -4 -1 -1 Ore
+5 -4 +5
Surface Mine Design
+3 Waste
16
Shortcomings
Combination of problems
-1 -1 -4 -1 -1 Ore
+5 -4 +5 Waste
Surface Mine Design
First Step
17
Shortcomings
Combination of problems
-1 -1 -4 -1 -1 Ore
+5 -4 +5 Waste
Surface Mine Design
Second Step
18
Shortcomings
Combination of problems
-1 -1 -4 -1 -1 Ore
+5 -4 +5 Waste
Surface Mine Design
+3 Mined
Wrong Solution
Everything is mined out.
19
Shortcomings
Combination of problems
-1 -1 -4 -1 -1 Ore
+5 -4 +5 Waste
+3 Mined
Surface Mine Design
Final Pit
-4
+3
Correct Solution
20
Example
Initial Data
21
Example
Geologic Model
22
Example
Block Values
P = Price
s = Sales Cost Ore Block:
BV = ( P − s) * g B * y − c − m
Surface Mine Design
c = Processing Cost
y = Recovery
Waste Block:
m = Mining Cost
gB = Block Grade
BV = −m
BV = Block Value
23
Example
Economic Model
24
Example
Economic Model
25
Example
Economic Model
26
Example
Economic Model
-1 18 -1 -1 -1 -1 -1
Surface Mine Design
-1 19 17 17 -1
17 17 -1
27
Example
Floating Cone Algorithm
-1 18 -1 -1 -1 -1 -1
1
Surface Mine Design
-1 19 17 17 -1
17 17 -1
1st Increment
28
Example
Floating Cone Algorithm
-1 18 -1 -1 -1 -1 -1
1 2 2
Surface Mine Design
-1 19 17 17 -1
2
17 17 -1
2nd Increment
29
Example
Floating Cone Algorithm
-1 18 -1 -1 -1 -1 -1
1 2 2 3
Surface Mine Design
-1 19 17 17 -1
2 3
17 17 -1
3rd Increment
30
Example
Floating Cone Algorithm
-1 18 -1 -1 -1 -1 -1
1 2 2 3 4
Surface Mine Design
-1 19 2
17 17 -1
3 4
17 17 -1
4th Increment
31
Example
Floating Cone Algorithm
-1 18 -1 -1 -1 -1 -1
5 1 2 2 3 4
Surface Mine Design
-1 19 17 17 -1
5 2 3 4
17 17 -1
5
5th Increment
32
Example
Floating Cone Algorithm
-1 18 -1 -1 -1 -1 -1
5 1 2 2 3 4
Surface Mine Design
-1 19 17 17 -1
5 2 3 4
17 17 -1
5 6
6th Increment
33
Example
Floating Cone Algorithm
-1
Surface Mine Design
-1
-1
34
Example
Total Economic Value
169,400 173,000
35
Example
Pit Reserves
36
Manual Pit Design
Surface Mine Design
1
Manual Pit Design
Stripping Ratio
2
Manual Pit Design
Example
Ore Grade (%Cu) 0.90 0.85 0.75 0.70 0.65 0.50 0.40
Conc. Recovery (%) 0.900 0.900 0.900 0.900 0.900 0.900 0.900
Smelt. Recovery (%) 0.980 0.980 0.980 0.980 0.980 0.980 0.980
Ref. Recovery (%) 0.990 0.990 0.990 0.990 0.990 0.990 0.990
Total Recovery (%) 0.873 0.873 0.873 0.873 0.873 0.873 0.873
Recovered Quantity (lb/ton) 15.7 14.8 13.1 12.2 11.3 8.7 7.0
Surface Mine Design
Total cost ($/ton) 7.50 7.05 6.74 6.56 6.41 6.35 6.30
Stripping cost ($/ton) 0.66 0.66 0.66 0.66 0.66 0.66 0.66
12.00
10.00
Surface Mine Design
8.00
Stripping Ratio
0.00
0.40 0.50 0.60 0.70 0.80 0.90
-2.00
-4.00
% Cu
4
Manual Pit Design
Hypothetical Cross Section
Topo
X'
Surface Mine Design
X
X'
SR =
Y' X
SR =
Y
Y' Orebody
Y
A B
5
Manual Pit Design
S.R. in Section
First First
X’ = 30 X = 10
Current Price = 0.90
Y’ = 5 Y=5
$/lb
S.R. = 6 S.R. = 2
Surface Mine Design
G = 0.67% G = 0.48%
Second Second
X’ = 39.6 X = 15
Y’ = 6 Y=3
S.R. = 6.6 (Breakeven) S.R. = 5 5 : 1 < 6.6 : 1 OK
G = 0.70% G = 0.70%
6
Manual Pit Design
Repeat for All Sections
Pit contour
Surface Mine Design
or Final pit
7
Cutoff Grade Optimization
Surface Mine Design
1
Factors Influencing The Cutoff
Grades
• As the Cutoff Grade increases in a given operation cash flow
also increases
2
What Is Cutoff Grade
1. Cutoff Grade is defined as the grade that is normally used to
discriminate between ore and waste within a given deposit
2. Cutoff Grade is the dial that is used to adjust the cash flow
coming from the mining operations in a given year
3.
Surface Mine Design
3
Economic Objectives And The
Cutoff Grade
• The cash costs related to mining, milling and refining along with
the commodity price determines the lower limit to cutoff in a
given period.
Surface Mine Design
• Processing every ton of ore that pays for itself will maximize the
undiscounted profits for the operation.
4
Economic Objectives And The
Cutoff Grade (Cont.)
• The mining rate, milling rate, the ultimate rate of production for
the commodity being sold, and the production costs determine
how far the cutoff grade has to be adjusted upwards to maximize
the NPV.
5
Ultimate Pit Cutoff
6
Ultimate Pit Cutoff
• Recovery (y) 90 %
• Mining Cost (m) $ 1.20/ ton
• Overhead
(Included in c and m )
7
Ultimate Pit Cutoff
$10 + $1.2
gm = = 0.0315 oz / ton
($400 − $5) * 0.9
8
Milling Cutoff
9
Milling Cutoff
Milling Cost
gc =
(Pr ice − Sales Cost ) * Re cov ery
Surface Mine Design
$10
gc = = 0.0281 oz / ton
($400 − $5) * 0.9
10
Block Value
Block Grade = gB
if gc < gm < gB then
Block Value = (P-S)* gB * y – c – m
Surface Mine Design
11
Block Value
Block Grade = gB
if gc < gB < gm then
Block contains marginal ore.
Surface Mine Design
12
Block Value Calculation Example
a) Ore Block
Block grade = gB = 0.11 oz/ton
gc < gm < gB
Surface Mine Design
13
Block Value Calculation Example
b) Waste Block
Block Grade = gB = 0.01 oz/ton
gB < gc < gm
Surface Mine Design
therefore
Block Value = - $1.20/ton
= Mining Cost
14
Mine Design Parameters For The
Case Study
• Price (P) $600/oz
• Sales Cost (s) $5 /oz
• Processing Cost (c) $ 19/ ton ore
• Recovery (y) 90 %
•
Surface Mine Design
15
Calculation of Ultimate Pit
Cutoff Grade
$19 + $1.2
gm = = 0.038 oz / ton
($600 − $5) * 0.9
16
Calculation of Milling Cutoff
Grade
Milling Cost
gc =
(Pr ice − Sales Cost ) * Re cov ery
Surface Mine Design
$19
gc = = 0.035 oz / ton
($600 − $5) * 0.9
17
Grade Tonnage Distribution
Avg. Interval
Grade Interval KTons KTons Grade
Grade
0.000 - 0.020 70,000 0.0100
0.020 - 0.025 7,257 0.0225
89,167 Waste
0.025 - 0.030 6,319 0.0275
0.030 - 0.035 5,591 0.0325
Surface Mine Design
19
Profit
Profits ($M) = (P – s ) x Qr – Qc x c – Qm x m
P – Price
Surface Mine Design
S – Sales Cost
Qm – Total Material Mined
Qc – Ore Tonnage Processed By The Mill
Qr – Recovered Ounces
c – Milling Costs ($/ton)
m – Mining Costs ($/ton)
20
Shortcomings of the traditional
cutoff grades
• They are established to satisfy the objective of
maximizing the undiscounted profits from a given
mining operation.
Surface Mine Design
21
Traditional
$19 + $10 + $3
gc = = 0.060 oz / ton
($600 − $5) * 0.9
22
Nontraditional ????????
$19 + $10
gc = = 0.054 oz / ton
($600 − $5) * 0.9
23
Constant Cutoff Grades
Yearly Tons and Grade Schedules
Table 4
Year Cutoff Avg Qm Qc Qr Profits
Grade Grade $M/year
1 0.060 0.153 6.90 1.05 144.60 57.8
2 0.060 0.153 6.90 1.05 144.60 57.8
3 0.060 0.153 6.90 1.05 144.60 57.8
4 0.060 0.153 6.90 1.05 144.60 57.8
Surface Mine Design
24
Declining Cutoff Grades
25
Declining Cutoff Grades
$19 + $7.95
gc = = 0.050 oz / ton
($600 − $5) * 0.9
26
Declining Cutoff Grades
27
Declining Cutoff Grades
Milling Cost
gc =
(Pr ice − Sales Cost) * Re cov ery
Surface Mine Design
$19
gc = = 0.035 oz / ton
($600 − $5) * 0.9
28
Declining Cutoff Grades
Yearly Tons and Grade Schedules.
Table 5
Year Cutoff Avg QM Qc Qr **Profits
Grade Grade $M/year
Determination Of
Optimum Cutoff Grades
Surface Mine Design
30
Formula for Optimum Cutoff
Grade
c + f + Fi
gc (i) =
(P − S ) * y
Surface Mine Design
• Where
Fi = d x NPVi /C
f = fa/C
and fa is annual fixed costs
31
Optimum Cutoff Grades
Yearly Tons and Grade Schedules
Table 6
Year Cutoff Avg QM Qc Qr **Profits NPV
Grade Grade $M $M
Traditional 0.102 125.8 36.70 2.43 4453.4 218.5 35 n/a n/a n/a n/a
Surface Mine Design
Heuristic 0.125 125.8 28.44 3.42 1127.4 355.7 28 3.6 3.6 63.0 63.0
(Depr)
Heuristic 0.164 125.8 18.11 5.95 885.6 357.1 18 20.4 23.3 0.3 63.4
(Depr and
Fixed Costs)
Lanes's 0.235 125.8 9.45 12.31 743.4 413.8 9 16.0 35.6 15.9 89.0
Approach
33
Cutoff Grade Optimization
One Constraint
Cutoff Grade
Surface Mine Design
Optimization Algorithm
34
Steps Of The Algorithm
2. Define: P - Price
C - Milling Capacity
Surface Mine Design
s - Marketing Costs
m - Mining Costs
c - Milling Costs
fa - Fixed Costs
d - Discount Rate
35
Steps Of The Algorithm (Cont.)
• Where
Fi = d x NPVi /C
f = fa/C
and fa is annual fixed costs
36
Steps Of The Algorithm (Cont.)
37
Steps Of The Algorithm (Cont.)
5. Set
Qc = C if Tc > C
Surface Mine Design
Qc = T c if Tc < C
And
Qm = Qc(1+sr)
38
Steps Of The Algorithm (Cont.)
6. Determine the annual profit (Pi) by using the
following equation
Pi =(P-s) x Qc x gc x y – Qc x (c + f) – Qm x m
P - Price
Surface Mine Design
s - Marketing Costs
Qm - Total material mined
Qc - Ore tonnage processed by the mill
c - Milling Costs ($/ton)
m - Mining Costs ($/ton)
gc - Average Grade (Opt)
y - Recovery
f - Fixed Cost ($/ton) 39
Steps Of The Algorithm (Cont.)
40
Steps Of The Algorithm (Cont.)
N Pj
Surface Mine Design
NPVi = ∑ j −i +1
j =i (1 + d )
41
Steps Of The Algorithm (Cont.)
otherwise
Stop the cutoff grade gc (i) for years i = 1,
1
N is Optimum Policy.
42
Open Pit Sequencing and
Production Scheduling
Surface Mine Design
2
Declining Stripping Ratio
Method
1 1 1
2 2 2
Stripping
3 3 3
Volume
Surface Mine Design
4 4 4
5 5 5
6 6 6
7 7 7
Time
Orebody
Waste
3
Increasing Stripping Ratio
Method
Surface Mine Design
Orebody
Waste
4
Constant Stripping Ratio
Method
Surface Mine Design
Orebody
Waste
5
Long Term Production
Scheduling
•Long term production scheduling is usually carried out
from the initial condition of the deposit (i.e. initial
topography) to the ultimate pit limit, in periods of at least
one year.
Surface Mine Design
operating efficiency.
•To accomplish this objective, short term production
scheduling has to comply with restrictions imposed by the
long term plan, equipment availability, blending of different
materials from different sites within the mine, and the
availability of exposed ore.
7
Objectives in Open Pit Mine
Planning
8
Objectives in Open Pit Mine
Planning (cont.)
9
Objectives in Open Pit Mine
Planning (cont.)
• To ensure a feasible schedule in terms of mining practice. This
implies mining exposed material sequentially, keeping
appropriate mining widths, maintaining access to the mining
areas, and maintaining stable pit walls.
Surface Mine Design
10
Objectives in Open Pit Mine
Planning (cont.)
• To mine the orebody in such a way that for each year the cost to
produce a given kilogram of metal is at minimum.
• To develop an achievable start-up schedule with respect to
manpower training, equipment deployment, infrastructure and
Surface Mine Design
11
Objectives in Open Pit Mine
Planning (Cont.)
• To maximize design pit slope angles in response to adequate
geotechnical investigations, and yet through careful planning
minimize the adverse impacts of any slope instability, should it
occur.
Surface Mine Design
12
Pit Sequence Planning
• Orebodies are normally mined in stages, so as to defer waste
stripping and maximize the net present value of the surface
mining venture.
• These stages are commonly called sequences, expansions,
Surface Mine Design
13
Procedure to obtain the
pushbacks
14
Example of how to obtain the
pushbacks
•% Recovery through mill and smelter 90%
•Value of recovered copper $1.10/lb
•Stripping and haulage to dump (level 1) $0.50/ton
Surface Mine Design
15
Example of how to obtain the
pushbacks (Cont.)
Level
Surface Mine Design
1 0.00 0.10 0.15 0.08 0.05 0.00 0.00 0.05 0.03 0.00 0.05 0.05 0.05 0.05 0.05 0.05
2 0.00 0.22 0.08 0.25 0.15 0.13 0.10 0.13 0.45 0.20 0.20 0.32 0.10 0.15 0.24 0.21
3 0.05 0.05 0.12 0.13 0.02 0.14 0.11 0.08 0.22 0.09 0.08 0.15 0.22 0.20 0.14 0.05
4 0.04 0.15 0.12 0.45 0.08 0.09 0.25 0.20 0.29 0.14 0.15 0.04 0.24 0.05 0.02 0.04
5 0.05 0.08 0.15 0.12 0.30 0.21 0.09 0.79 0.10 0.45 0.32 0.23 0.01 0.01 0.01 0.01
6 0.08 0.10 0.08 0.01 0.05 0.34 0.45 0.02 0.01 0.04 0.38 0.00 0.00 0.00 0.01 0.15
16
Example of how to obtain the
pushbacks (Cont.)
Economic Model showing block values in $/ton
Original copper price of $1.10/lb
1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50
2 -0.60 1.06 -0.60 1.65 -0.60 -0.60 -0.60 -0.60 5.61 0.66 0.66 3.04 -0.60 -0.60 1.45 0.86
Surface Mine Design
3 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 0.96 -0.70 -0.70 -0.70 0.96 0.56 -0.70 -0.70
4 -0.80 -0.80 -0.80 5.41 -0.80 -0.80 1.45 0.46 2.24 -0.80 -0.80 -0.80 1.25 -0.80 -0.80 -0.80
5 -0.90 -0.90 -0.90 -0.90 2.34 0.56 -0.90 12.04 -0.90 5.31 2.74 0.95 -0.90 -0.90 -0.90 -0.90
6 -1.00 -1.00 -1.00 -1.00 -1.00 3.03 5.21 -1.00 -1.00 -1.00 3.82 -1.00 -1.00 -1.00 -1.00 -1.00
17
Example of how to obtain the
pushbacks (Cont.)
The floating cone algorithm was used to find
the ultimate pit limit
Pit
1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 1
2 -0.60 1.06 -0.60 1.65 -0.60 -0.60 -0.60 -0.60 5.61 0.66 0.66 3.04 -0.60 -0.60 1.45 0.86 2
3 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 0.96 -0.70 -0.70 -0.70 0.96 0.56 -0.70 -0.70 3
Surface Mine Design
4 -0.80 -0.80 -0.80 5.41 -0.80 -0.80 1.45 0.46 2.24 -0.80 -0.80 -0.80 1.25 -0.80 -0.80 -0.80 4
5 -0.90 -0.90 -0.90 -0.90 2.34 0.56 -0.90 12.04 -0.90 5.31 2.74 0.95 -0.90 -0.90 -0.90 -0.90 5
6 -1.00 -1.00 -1.00 -1.00 -1.00 3.03 5.21 -1.00 -1.00 -1.00 3.82 -1.00 -1.00 -1.00 -1.00 -1.00 6
7
The ore block left at the right cannot be mined due to slope constraints. All ore blocks are mined in the first iteration. 8
9
1 10
2 11
3 12
4 13
5 14
6 15
18
Example of how to obtain the
pushbacks (Cont.)
To find a smaller pit reduce the copper price to 0.60/lb
Economic block model
1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50
2 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 1.56 -0.60 -0.60 0.16 -0.60 -0.60 -0.60 -0.60
3 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70
Surface Mine Design
4 -0.80 -0.80 -0.80 1.36 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80
5 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 4.93 -0.90 1.26 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90
6 -1.00 -1.00 -1.00 -1.00 -1.00 -1.00 1.16 -1.00 -1.00 -1.00 0.40 -1.00 -1.00 -1.00 -1.00 -1.00
19
Example of how to obtain the
pushbacks (Cont.)
The floating cone algorithm was used to find
the limit of the pit at $0.60/lb
1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50
2 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 1.56 -0.60 -0.60 0.16 -0.60 -0.60 -0.60 -0.60
3 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70
4 -0.80 -0.80 -0.80 1.36 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80
Surface Mine Design
5 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 4.93 -0.90 1.26 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90
6 -1.00 -1.00 -1.00 -1.00 -1.00 -1.00 1.16 -1.00 -1.00 -1.00 0.40 -1.00 -1.00 -1.00 -1.00 -1.00
1
2
3
4
5
6
20
Example of how to obtain the
pushbacks (Cont.)
To find an intermediate pit reduce the copper price to $0.86/lb
Economic Block Model
1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50
Surface Mine Design
2 -0.60 0.11 -0.60 0.57 -0.60 -0.60 -0.60 -0.60 3.67 -0.60 -0.60 1.65 -0.60 -0.60 0.42 -0.60
3 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70
4 -0.80 -0.80 -0.80 3.47 -0.80 -0.80 0.37 -0.80 0.99 -0.80 -0.80 -0.80 0.22 -0.80 -0.80 -0.80
5 -0.90 -0.90 -0.90 -0.90 1.04 -0.90 -0.90 8.63 -0.90 3.37 1.35 -0.90 -0.90 -0.90 -0.90 -0.90
6 -1.00 -1.00 -1.00 -1.00 -1.00 1.56 3.27 -1.00 -1.00 -1.00 2.18 -1.00 -1.00 -1.00 -1.00 -1.00
21
Example of how to obtain the
pushbacks (Cont.)
To find an intermediate pit reduce the copper price to $0.86/lb
Economic Block Model
1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 Pit
2 -0.60 0.11 -0.60 0.57 -0.60 -0.60 -0.60 -0.60 3.67 -0.60 -0.60 1.65 -0.60 -0.60 0.42 -0.60 1
3 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 2
Surface Mine Design
4 -0.80 -0.80 -0.80 3.47 -0.80 -0.80 0.37 -0.80 0.99 -0.80 -0.80 -0.80 0.22 -0.80 -0.80 -0.80 3
5 -0.90 -0.90 -0.90 -0.90 1.04 -0.90 -0.90 8.63 -0.90 3.37 1.35 -0.90 -0.90 -0.90 -0.90 -0.90
6 -1.00 -1.00 -1.00 -1.00 -1.00 1.56 3.27 -1.00 -1.00 -1.00 2.18 -1.00 -1.00 -1.00 -1.00 -1.00
The ore block left at the right cannot be mined due to slope constraints. All ore blocks are mined in the first iteration.
1
2
3
4
5
6
22
Example of how to obtain the
pushbacks (Cont.)
The three pits shown in together
1 $0.60/lb
2
3 $0.86/lb
4 $1.10/lb
Surface Mine Design
5
6
23
Hypothetical Deposit and Pit
Development Sequence
Design Phase Limits Ultimate Pit
Surface Mine Design
Rock Type I
B A D
F C
Rock Type II E
Ore
24
Tonnage Inventory by Phase
Thousands of tonnes
25
Summary by Phase
Thousands of tonnes
26
Time (Years)
-10 -5 0 5 10 15 20 25
250
Phase "D" ore = 125 M tonnes Earlier ore development
100
Development Sequence
Developed Ore
150 E
C
F
D
100 50
B 76
C
A
50 27 31
B
A 0
-10 -5 0 5
1.08
1.24
3.04
0
1000
500
Surface Mine Design
- Production period
F 50 M tonnes / year
A proposed stripping D
schedule
750 - Pre-production period
Cumulative Stripping
4 yrs. Yr 1 25 M
(Millions of tonnes)
27
Time (Years)
-10 -5 0 5 10
Earlier ore development
Phase "D" ore = 125 M tonnes due to the proposed
Phase "D" life = 5 years stripping schedule
It requires 128 M tonnes stripping
150 E
(Millions of tonnes)
Developed Ore
Cushion = 0.34 years
100
0
1.08 3.04
1.24 5.00
Surface Mine Design
750
E
Cumulative Stripping
- Production period
(Millions of tonnes)
50 M tonnes / year
500
D
- Pre-production period
4 yrs. Yr 1 25 M
2-3 50 M
4 75 M
C
250 200 M
B
75 A Minimum waste stripping
50 required to sustain
ore deliveries
50
25
0
-10 -5 1 2 3 40 5 10
Time (Years)
Pre-production
Period 28
Period 2 Period 1
$72M $81M
Period 1
$50M
Period 3 Period 8
$63M $9M
Period 2
Period 4 $37M Period 4
$61M Period 5 Period 6 Period 7 $52M Period 3 $60M $50M
Period 7 $37M $32M Period 5 $49M
Period 8 $19M Period 6
$43M $50M
($398M) ($366M)
Period 4
$65M
Period 1
$46M Period 2
$32M
Period 2
$42M Period 3
$71M
Period 3
$63M
Period 7 $43M Period 4 $51M
Period 1 $42M
Period 5 Period 8 $16M
Period 7 $57M Period 5 $57M
$51M Period 6
Period 8 $11M Period 6 $52M
$48M
($374M) ($372M)
Long Term Planning and
Sequencing
Equipment Selection
• Facility layout and Permitting
2
Long Term Planning and
Sequencing
• Create a geologic model
• Define structural domains and stratigraphy
• Chemistry
• Long and short term variability
Surface Mine Design
3
Long Term Planning and
Sequencing
• Determine mineable resource boundaries
• Haul road layout
• Define long term reclamation needs
Surface Mine Design
4
Midlothian Cement Quarry:
Case Study
• Current production 1.8 million tons of limestone
• One 50ft to 60ft bench operation
• In pit crushing - 1000 ton/per hour capacity
Surface Mine Design
6
Midlothian Cement Quarry:
Case Study
• Determine next 50 years life of mine plans
• Sequencing plan to come up with the right
blend limestone that meets the minimum of
Surface Mine Design
7
Quarry Development and
Sequencing
Surface Mine Design
8
Holnam Quarry Mining Sequence:
First Bench Development
Surface Mine Design
9
Holnam Quarry Mining Sequence:
Second Bench Development
During the First Three Years
Surface Mine Design
10
Holnam Quarry Mining Sequence:
First and Second Bench Development
Surface Mine Design
11
Holnam Quarry Mining Sequence:
First and Second Bench Development
Surface Mine Design
12
Holnam Quarry Mining Sequence:
First and Second Bench Development
Surface Mine Design
13
Midlothian North Area Quarry
Progress Contours Year1
Surface Mine Design
14
Midlothian North Area Quarry
Progress Contours Year 2
Surface Mine Design
15
Midlothian North Area Quarry
Progress Contours Year 3
Surface Mine Design
16
Midlothian North Area Quarry
Progress Contours Year 4
Surface Mine Design
17
Midlothian Quarry Block
Model Definition
Surface Mine Design
18
Midlothian Quarry Block
Model Definition
Surface Mine Design
19
Midlothian Quarry Sequence: One
Year Increments on Elevation 790
Surface Mine Design
20
Midlothian Quarry Sequence: One
Year Increments on Elevation 780
Surface Mine Design
21
Midlothian Quarry Sequence: One
Year Increments on Elevation 770
Surface Mine Design
22
Midlothian Quarry Sequence: One
Year Increments on Elevation 760
Surface Mine Design
23
Midlothian Quarry Sequence: One
Year Increments on Elevation 750
Surface Mine Design
24
Midlothian Quarry Sequence: One
Year Increments on Elevation 750
Surface Mine Design
25
Midlothian Quarry Sequence: One
Year Increments on Elevation 730
Surface Mine Design
26
Midlothian Quarry Sequence: One
Year Increments on Elevation 720
Surface Mine Design
27
Midlothian Quarry Sequence: One
Year Increments on Elevation 700
Surface Mine Design
28
Midlothian Quarry Sequence: One
Year Increments on Elevation 690
Surface Mine Design
29
Equipment Selection
30
Loader - Truck Fleet Evaluation
and Cost Analysis Year 1
Surface Mine Design
31
Loader - Truck Fleet Evaluation
and Cost Analysis Year 2
Surface Mine Design
32
Loader - Truck Fleet Evaluation
and Cost Analysis Year 3
Surface Mine Design
33
Loader - Truck Fleet Evaluation &
Cost Analysis Haul Road Profile
Surface Mine Design
34
Loader - Truck Productivity
Calculations
Assumptions
• 90 % Loader and truck availability resulting
in 81 % fleet availability
Surface Mine Design
• 92 % Operator efficiency
• 75 % bucket fill factor
• 2400 scheduled hrs
• 0.55 min. loader cycle time
35
Loader - Truck Productivity
Calculations
Assumptions (Cont.)
• 0.1 min. first bucket dump time
• 0.7 min. hauler exchange time
Surface Mine Design
37
Option 1: Cat 992G Loader -
775D Trucks
The truck cycle time for four different
conditions:
• Year 1: 9.67 minutes
Surface Mine Design
39
Option 2: Cat 992G Loader -
777D Trucks
The truck cycle time for four different
conditions
• Year 1: 12.16 minutes
Surface Mine Design
41
Operating Cost for the Loader
and Trucks
42
Operating Cost for the Loader
and Trucks
43
Loader - Truck Capital
Requirements
44
Loader - Truck Capital
Requirements
• At the start of the production from bench
two, $2.1 M is needed to purchase 1 Cat
992G Loader and 775D truck.
Surface Mine Design
45
Loaders and Shovels
Comparative Analysis
Surface Mine Design
• Hard Digging
• Poorly shoot material
• Selective loading
Surface Mine Design
3
Hydraulic Shovel
Favorable Site Conditions
• Single loading face
• Tight digging materials
• Face height equals to stick
Surface Mine Design
length
• Some will dig below and
above
• Soft floors
4
Hydraulic Shovel
Unfavorable Site Conditions
• High benches
5
Wheel Loader Applications
• Highly mobile/versatile
• High bucket fill factors
Surface Mine Design
7
Wheel Loader
Favorable Site Conditions
• Multi-face loading
8
Wheel Loader
Unfavorable Site Conditions
9
Comparison Shovels vs.
Loaders
Hydraulic Shovel Wheel Loader
% Operating Weight
8-11% 18-21%
as bucket payload
Cost/CY of capacity
100-120 60-80
Surface Mine Design
($1000)
Economic life (1000
30-60 30-60
hours)
10
Mobility
Wheel Loader
Surface Mine Design
Hydraulic
Shovel
11
Breakout Force
• The shovel can apply the force over its reach of the face.
12
Bucket Fill Factors
13
Power and Fuel
14
Two-to-Three Minute Rule
15
Loading Tool Preferences
Region
Surface Mine Design
16
Hydraulic Shovel Production
Range
17
Wheel Loader Production
Range
Production Range
Model
(tons/hour)
18
Conclusions
operational needs.
19
Types of Mobile Surface Mining Equipment
•Dozers
•Scrapers
•Trucks
•Front-end Loaders
•Hydraulic Excavators
•Electric Shovels
•Draglines
•Bucket Wheel Excavators
•Blast Hole Drills
Other Bulk Material Handling Systems
•Belt Conveyors
•Rail Haulage
Types of Underground Mining Equipment
Fait-Allis 41B with single shank ripper leveling dragline spoil piles.
CAT D11, Black Thunder Mine, Wyoming, Spring 2002
CAT D11, Black Thunder Mine, Wyoming, Spring 2002
CAT D11, Black Thunder Mine, Wyoming, Spring 2002
Scrapers
The scraper is a rather unique machine because of its ability to
excavate material in thin horizontal layers, transport the material a
considerable distance, and then discharge it in a spreading action.
When trucks are used to haul overburden, the mine normally has an
open pit or area mine plan with dumping off of spoil benches.
Because the FEL has generally not been considered to have the
digging ability of a shovel in consolidated digging faces, it finds
many of its applications in softer formations, coal/ore and
stockpile work.
The larger sizes are more rugged and powerful, and are proving
themselves in difficult digging.
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Applications
The primary mine applications are the following:
•Loading and/ or transporting topsoil
•Loading and/ or transporting coal/ ore from the digging face
•Loading and/or transporting coal/ore from stockpile
•Loading and/or transporting overburden and waste
In all of the above loading can be into trucks, hoppers, railroad cars,
or belt loaders.
With its long reach and ability to dig to substantial depths below
itself, it has had broad applications on many irrigation
projects and, in more recent years, in surface mining.
The hydraulic hoe has, to some extent, replaced the smaller sized
diesel draglines but the larger diesel and/ or electric machines
retain their popularity.
Interest in the machines has been much greater overseas with the
Germans, in particular, performing extensive application studies and
machine development.
Overall use within the United States has been very limited.
Excavators
2
Hydraulic Shovels
Specifications
Surface Mine Design
3
Excavator Specifications
Surface Mine Design
4
Digging Envelopes
Front Shovels
Surface Mine Design
5
Curl and Crowd Forces
Front Shovels
Surface Mine Design
6
Digging Envelopes
Excavators
Surface Mine Design
7
Surface Mine Design
Excavators Bucket
8
Surface Mine Design
Loaders
9
Breakout Force
Loaders
Surface Mine Design
10
Breakout Force from Rackback
Loaders
Surface Mine Design
11
Carry Position
Loaders
Surface Mine Design
12
900 Series II – Dimensions
Loaders
Surface Mine Design
13
900 Series II – Dimensions
Loaders
Surface Mine Design
14
Specifications
Loaders
Surface Mine Design
15
Specifications
Loaders
Surface Mine Design
16
Travel Time – Loaded
Loaders
Surface Mine Design
17
Travel Time – Empty
Loaders
Surface Mine Design
18
Excavator Production
Calculations
O = B x BF x D x HS x J x A x 3,600 seconds
(1+S) C hour
Bucket Load Buckets/Period
19
Bucket Load
20
Bucket Load
21
Wheel Loader Bucket Fill
Factors
Surface Mine Design
(CAT)
22
Weight of Materials
Surface Mine Design
(CAT)
23
Bucket Load
a measured number
• Loose density (D/(1 + S)) important and
should be a measures number
24
Buckets/Period
• Material fragmentation
• Material size distribution
• Pile configuration
25
Buckets/Period
26
Wheel Loader Cycle Time
1.7-4.5 .45-.50
5.0-7.5 .50-.55
7.5-11 .55-.60
15-21 .60-.70
27
Cycle Time
28
Cycle Time
29
Cycle Time
• Age of machine
• Schedule
30
Loading Methods
31
Surface Mine Design
Loading Methods
32
Loading Methods
Surface Mine Design
(Mining Magazine)
33
Shovels:
Double Back-Up
Options include
• Double back-up
• Single back-up
Surface Mine Design
• Drive-by
• Modified drive-by
34
Shovels:
Double Back-Up
• Trucks loaded on both sides
• Average swing angle reduces
• Clean-up allowed on one side while loading
Surface Mine Design
continues
• Moves required as shovel penetrates bank
35
Shovels:
Double Back-Up
Surface Mine Design
36
Shovels:
Double Back-Up
Requires
balance of
Surface Mine Design
move time
versus
cycle time
37
Shovels:
Single Back-Up
• Truck loaded on one side
• Larger swing angle
• Potential clean-up delays
Surface Mine Design
38
Shovels:
Single Back-Up
Surface Mine Design
39
Shovels:
Drive-By
• Used with tractor trailers
• Large swing angles
• Potential clean-up delays
Surface Mine Design
40
Surface Mine Design
Shovels:
Drive-By
41
Shovels:
Modified Drive-By
• Truck backs in to reduce swing angle
• Potential clean-up delays
• Minimal amount of shovel moves
Surface Mine Design
• Blending problems
• Depth of cut effects cycle time and move
time
42
Shovels:
Modified Drive-By
Surface Mine Design
43
Modified Drive-By:
Optimum Width
Surface Mine Design
44
Production Estimating of Material
Movement With Earth Moving Equipment
The factors affecting these components will determine the time each
component will require.
Load Factors
• Size and type of loading machine
• Type & condition of material to be loaded
• Capacity of unit
• Skill of the loading operator
Haul/Push Factors
• Performance ability of unit
• Hauling distance
• Haul road condition
• Grades
• Miscellaneous factors affecting haul speed
Dump Factors
• Destination of material -Hopper, Over Bank, Fill, Stockpile, etc.
• Condition of dump area
• Type & maneuverability of hauling unit
• Type & condition of material
Return Factors
• Performance ability of unit
• Return distance
• Haul road condition
• Grades
• Miscellaneous factors affecting return speed
Spot Factors
• Maneuverability of unit
• Maneuver area available
• Type of loading machine
• Location of loading equipment
Delay Factors
• Time spent waiting on loading unit or pusher
• Time spent waiting to dump –at crusher
2. Job Efficiency Factors
An estimate must indicate sustained, or average earthmoving production
over a long period of time.
For example, the percent swell of shale is 33% indicating that one
bank cubic yard of shale will swell to 1.33 cubic yards in the loose
state.
Shale weighs 2800 pounds per bank cubic yard. At a swell factor of
0.75 (inverse of 1.33) the weight of one loose cubic yard of shale is
2100 pounds (2800 pounds * 0.75).
For haulers the SAE heaped capacity is for a load at a 2: 1 slope. For
scrapers the SAE heaped capacity is for a load at a 1: 1 slope.
The final decision will, of course, depend on which method offers the
lowest cost per yard or ton.
In some cases, methods such as draglines, belt conveyors, etc. will also
be considered.
Example
Rock density: 11 cubic feet per short ton
Swell factor: 1.6
Shovel
Bucket capacity: 18.8 cubic yards
Digging cycle time: 30 seconds per pass
Bucket fill factor: 0.92
Truck
Load capacity: 62 cubic yards struck
88 cubic yards at 2:1 SAE
140 tons payload capacity
2
Truck Selection
4
Truck Selection
• Loading
• Space and ground conditions at loading point
• Type and size of loading equipment
• Total availability of loading equipment
Surface Mine Design
• Dumping
• Dumping arrangements: rear dump into hopper, drive
over hopper, edge of spoil, windrow, etc.
• Space and ground condition at dump point
• Total availability of down stream equipment
5
Truck Selection:
Rear Dump
• High horsepower to weight ratio
• Deep pits, high grades, maneuverability required
high impact and rough in pit conditions.
Surface Mine Design
6
Truck Selection:
Bottom Dump
• Low HP/weight ratio
• Free flowing material
• Dumping over hopper or in windrow
Surface Mine Design
7
Production Calculations
8
Production Calculations
9
Rimpull vs. Velocity
Surface Mine Design
10
Rolling Resistance
flexing).
• Expressed in terms of lb/ton vehicle weight or %
vehicle weight
• Haul Road Resistance can be estimated by:
RR = 2%+1.5% per inch of tire penetration
11
Rolling Resistance Factors
TYPICAL ROLLING RESISTANCE FACTORS
Various tire sizes and inflation pressures will greatly reduce or increase the rolling resistance. The
values in this table are approximate, particularly for the track and track+ tire machines. These values
can be used for estimating purposes when specific performance information on particular equipment
and given soil conditions is not available See Mining and Earthmoving Section for more detail:
ROLLING RESISTANCE, PERCENT`
Tires Track Track
UNDERFOOTING Bias Radial ** +Tires
A very hard, smooth roadway, concrete, cold asphalt
or dirt surface, no penetration or flexing 1.5%* 1.2% 0% 1.0%
A hard; smooth, stabilized surfaced roadway
without penetration under load; watered; maintained 2.0% 1.7% 0% 1.2%
Surface Mine Design
12
Grade Resistance
• Force required to overcome gravity when moving
vehicle uphill. Expressed in % vehicle weight (adds
power to vehicle downhill).
• Percent Grade = Vertical rise or drop (ft) x 100
Surface Mine Design
13
Weights and Traction
• Weights: determines the force required to propel
vehicle.
• Function of vehicle weight, rated capacity (CY), and
density of material hauled, number of passes of
Surface Mine Design
excavator
• Traction: force deliverable can be limited by
traction conditions
• Usable rimpull is a function of road surface and weight
on the drive wheels
Usable Rimpull =
Coefficient of Traction x Weight on Drive Wheels
14
Coefficient of Traction Factors
Surface Mine Design
(CAT)
15
Altitude Deration
Surface Mine Design
(CAT)
16
Speed Limits
17
Acceleration, Deceleration,
Operator
• Speeds obtained from performance curves indicate
maximum velocity under optimum conditions on a
given profile.
•
Surface Mine Design
18
Tires
Average Tire Load = Empty Tire Load + Loaded Tire Load (tons)
2
Surface Mine Design
20
Ton-MPH Data
Surface Mine Design
(CAT)
21
Estimating Cycle Time
22
Estimating Cycle Time
24
Unit Production
25
Match Factor and System
to the excavator
26
Match Factor and System
Allocations based on at least two approaches:
• Number of trucks = Truck cycle time / Load time
(excluding first pass)
Surface Mine Design
27
Match Factor Approach
N o . T ru c k s ( 1 7 . 0 1 / 3 . 0 0 ) 5.67
N o . T ru c k s ( 1 7 . 0 1 / ( 3 . 0 0 + 1 . 3 0 ) ) 3.96
28
System Production
29
Surface Mine Design
The End
30
TRUCK SELECTION AND
PRODUCTION CALCULATIONS
Surface Mine Design
• Example:
Calculate the output in tons/hr of a 990 Wheel
Loader with a 11cy bucket with .55 min. cycle time
Surface Mine Design
2
Wheel Loader Production
Calculations (Cont.)
• Equation to estimate the production per hour:
O = BC*BF*D*MA*JF*3,600sec
(1+SF)*CT hour
Where,
Surface Mine Design
O =Production, tons/hr
BC =Bucket Size, CY (Usually heaped at 2:1)
BF =Bucket Fill Factor, %
D =In Place Density, tons/CY
MA=Mechanical Availability, %
JF =Job Factor, %
SF =Material Swell, %100
CT =Average cycle time, seconds
3
Wheel Loader Production
Calculations (Cont.)
• Solution:
O = 11*0.95*1.55*0.85*0.833*3,600sec
Surface Mine Design
33sec
= 1252 tons/hr
4
Loader-Truck Production
Calculations
• Example:
CAT775 truck (65ton) is loaded with a 11.0CY 990
loader with 0.55min cycle time with 95% fill factor.
For truck cycle time, use the following table.
Surface Mine Design
= 4 cycles
6
Loader-Truck Production
Calculations (Cont.)
Cycle time
Load 1.7min
Haul 3.8min
Surface Mine Design
Dump 1.0min
Return 1.8min
Spot 0.6min
7
Loader-Truck Production
Calculations (Cont.)
8
Loader-Truck Production
Calculations (Cont.)
• Total Production
Assume – 50 min / hour, and 85% availability
65T/cycle*1cycle/8.9min*50min/hr*0.85/unit = 312T/hr
Surface Mine Design
9
Loader-Truck Production
Calculations
• Example:
A quarry works with CAT769D flat floor trucks (Max
payload 41T, Engine+-450hp) that is loaded by 8cy loader.
Surface Mine Design
10
Loader-Truck Production
Calculations (Cont.)
• Example (Cont.):
Loader data:
Capacity: 8cy
Surface Mine Design
11
Loader-Truck Production
Calculations (Cont.)
• Example (Cont.):
Truck cycle time data:
Spot time: 0.8 min
Surface Mine Design
Dump time:1.5min
12
Loader-Truck Production
Calculations (Cont.)
• Example (Cont.):
Road profile:
2 762 20 8 2
3 152 45 0 4
13
Loader-Truck Production
Calculations (Cont.)
Tons / cycle = 8CY/cycle * 0.8*2800lb/cy / 2000lb
= 9T/cycle
Surface Mine Design
14
Loader-Truck Production
Calculations (Cont.)
Haul Speed:
Segment1
Surface Mine Design
Total Resistance = 4%
Max speed = 42km/h
< Speed limit (45km/hr)
42
15
Loader-Truck Production
Calculations (Cont.)
Conversion of Max Speed to Average Speed
Weights to HP ratio:
Surface Mine Design
75050kg = 165456lb
165456lb / 450hp = 368lb/hp
Haul load length:
122m = 401ft
Conversion factor = 0.51
16
Loader-Truck Production
Calculations (Cont.)
Haul Speed :
Segment2
Conversion factor = 1
Avg speed = 16km/hr
16
17
Loader-Truck Production
Calculations (Cont.)
Haul Speed :
Segment3
Total Resistance = 4%
Max speed = 42km/h
Surface Mine Design
42
18
Loader-Truck Production
Calculations (Cont.)
Haul Time:
Segment1:
0.122km / 21.4km/hr * 60min = 0.34 min
Surface Mine Design
Segment2:
0.762km / 16km/hr * 60min = 2.86 min
Segment3:
0.152km / 28.6km/hr * 60min = 0.32 min
19
Loader-Truck Production
Calculations (Cont.)
Return Speed:
Segment1
Total Resistance = 4%
Surface Mine Design
Avg speed
= 45km/hr*0.68=30.6km/hr
73
20
Loader-Truck Production
Calculations (Cont.)
Return Speed :
Segment2
21
Loader-Truck Production
Calculations (Cont.)
Return Speed :
Segment3
Total Resistance = 4%
Surface Mine Design
Avg speed
= 45km/hr*0.54=24.3km/hr
73
22
Loader-Truck Production
Calculations (Cont.)
Return Time:
Segment1:
0.122km / 30.6km/hr * 60min = 0.24 min
Surface Mine Design
Segment2:
0.762km / 19km/hr * 60min = 2.41 min
Segment3:
0.152km / 24.3km/hr * 60min = 0.38 min
23
Loader-Truck Production
Calculations (Cont.)
Haul and Return Time Summary:
Haul
Length Total Resistance Speed Limit Avg. Speed
Segment (m) Grade(%) RR (%) (%) (km/hr) (km/hr) Conversion (km/hr) time (min)
Return
Length Total Resistance Speed Limit Avg. Speed
Segment (m) Grade(%) RR (%) (%) (km/hr) (km/hr) Conversion (km/hr) time (min)
24
Loader-Truck Production
Calculations (Cont.)
Truck cycle time (min)
Haul 3.5min
Dump 1.5min
Return 3.0min
Spot 0.8min
Total 10.8min
25
Loader-Truck Production
Calculations (Cont.)
26
Loader-Truck Production
Calculations (Cont.)
Usable Rimpull
= Coefficient of Traction * Weight on Wheel
27
Loader-Truck Production
Calculations (Cont.)
28
Loader-Truck Production
Calculations (Cont.)
Weight of Wheel:
769D: Rear 66.7%, Front 33.3% Distribution
(by CAT Performance Book)
Weight on Rear Tire is
Surface Mine Design
29
Loader-Truck Production
Calculations (Cont.)
• CONDITION CHECK
Usable Rimpull > Available Rimpull
Surface Mine Design
30
Loader-Truck Production
Calculations (Cont.)
• Unit Production
Assuming 50min / hour
Surface Mine Design
Productivity:
41T/cycle*1cycle/10.8min*50min/hr*0.85 = 161T/hr
31
Loader-Truck Production
Calculations (Cont.)
(6trucks)
32
Fleet Size Determination Using
Binomial Distribution
by
Surface Mine Design
2
Example
3
Wrong Assumption
4
Binomial Distribution
n!
⋅ p x (1 − p) n− x
x! (n − x)!
Surface Mine Design
5
Binomial Distribution for
Trucks
Availability = 70%
6
Fleet Capacity
The fleet capacity can be stated as follows:
The loader operates 80% of the time and during this time,
34% will be at 9,000 tons per shift, 44% will be at 8,000
tons per shift, and 19% will be at only 4,000 tons per shift.
Surface Mine Design
7
Fleet Capacity
fleet.
8
Haul Truck Requirement
Determination
9
Haul Truck Requirement
Determination
It could be incorrectly assumed that 3 trucks would be
sufficient.
However, if the loading fleet contains only 1 loader , then
Surface Mine Design
20% of the time the haul fleet would be idle waiting for the
loader to be repaired.
It is also known that the loader could not keep up with three
trucks and production would be limited to 9,000 tons per shift,
not the 12,000 tons indicated by the haulage capacity.
10
Haul Truck Requirement
Determination
250 shifts x 0.80 x 0.34 x 9,000 tons = 612,000 tons
250 shifts x 0.80 x 0.44 x 8,000 tons = 704,000 tons
250 shifts x 0.80 x 0.19 x 4,000 tons = 152,000 tons
Surface Mine Design
11
Estimating Owning and Operating
Costs
by
Surface Mine Design
1 2
Machine Designation Track-type Tractor Wheel Loader
Estimated Ownership Period (Years) 7 5
Estimated Usage (Hours/Year) 1200 1500
Ownership Usage (Total Hours) 8400 7500
Surface Mine Design
Owning Costs
2
Hourly owning and operating
cost estimate
Operating Costs
3
9A. Lube Oils, Filters, Grease
Final Drives
Hydraulics
Grease
Filters
Total 0 Total 0
4
12A. Special Wear Items
5
Drilling
Surface Mine Design
• Rotary drilling
Drills for rotary crushing
Drills for rotary cutting
2
Surface Drilling Methods and
Applications
Surface Mine Design
3
Components of Surface Drilling
Methods
Surface Mine Design
4
Top Hammer Drilling
Feed
Rotation
Flushing
6
Relative Penetration Rate as a Function
of Percussion Pressure
Surface Mine Design
7
The Optimal Adjustment of Drilling
Parameters Means Maximum Penetration
Surface Mine Design
8
Surface Mine Design
Flushing
9
Surface Mine Design
Flushing
10
Penetration Rates Between Pneumatic
and Hydraulic Top Hammer Drilling
Surface Mine Design
11
Bench Drilling Rig
Surface Mine Design
12
Bench Drilling Rig
14
Application Range of Tube Drill Steels
Surface Mine Design
15
DTH Drilling
16
Principle of DTH Drilling
Surface Mine Design
17
A Typical DTH Hammer
Surface Mine Design
18
Features of DTH Hammer
Surface Mine Design
19
Truck Mounted DTH Drill
Surface Mine Design
20
Surface Mine Design
21
Rotary Drilling
22
Principle Rotary Drilling
Surface Mine Design
23
Surface Mine Design
Rotary Drills
24
Surface Mine Design
Rotary Drills
25
Principles of Rotation
Surface Mine Design
26
Rotary Power versus Hole Diameter
Surface Mine Design
27
Pull Down versus Hole Diameter
Surface Mine Design
28
Principles of Feed Systems
Surface Mine Design
29
Thrust and Pulldown Force
Surface Mine Design
30
Flushing Air Compressor Size
Surface Mine Design
31
Carrousel Type Pipe Changer
Surface Mine Design
32
Rotary Drilling Accessories
• Drill bits
• Drill pipes
Surface Mine Design
• Shock subs
• Stabilizers
• Saver subs
• Bit subs
33
Rotary Drill Bit Components
Surface Mine Design
34
Rotary Bit Selection Parameters
35
Bit Selection for Rotary Drilling
Surface Mine Design
36
Insert Shapes for Tricone Bits
Surface Mine Design
37
Penetration Rate versus Bit Load
Surface Mine Design
38
Principles of Rotary Cutting
Surface Mine Design
39
Drilling
Surface Mine Design
W rpm
P = (61 − 28 log10 Sc) ⋅ ⋅
φ 300
Surface Mine Design
Where:
P = penetration rate (ft/hr)
Sc = uniaxial compressive strength, in thousands of psi
W/F = Weight per inch of bit diameter, in thousands of pounds
rpm = revolutions of drill pipe per minute
hp = K ⋅ rpm ⋅ D 2.5
⋅W 1.5
Where:
Surface Mine Design
Um = 264 p 1/ 2
⋅d 1/ 2
Where:
Um =
Surface Mine Design
5
Bailing Velocities
Surface Mine Design
6
Air Requirements Chart
Surface Mine Design
7
Optimal Bit Load
C×D
OptimumBitLoad =
5
Where:
Surface Mine Design
8
Total Work
Where:
Surface Mine Design
4.95 × D × R × (W / 1000)1.6
Horse Power (hp) =
C
Where:
Surface Mine Design
hp = rotary horsepower
R = bit rotational speed
D = bit diameter (inches)
W = optimum bit load (lbs)
C = rock compressive strength
hp × C
Maximum Bit RPM ( R ) =
4.95 × D × (W / 1000)1.6
Where:
Surface Mine Design
hp = rotary horsepower
R = bit rotational speed
D = bit diameter (inches)
W = optimum bit load (lbs)
C = rock compressive strength
0.25πD 2 0.25πD 2
Volume CFM = P × × SF + P ×
144 144
Where:
Surface Mine Design
P = penetration rate
D = bit diameter (inches)
SF = swell factor (0.6 sedimentary or 0.4 Igneous/metamorphic)
12
Air Velocity
183× CFM
Air Velocity =
D2 − d 2
Where:
Surface Mine Design
13
Compressive Strength
2.18 × W × R
Compressive Strength (C ) =
0.2 × (1 / 10000) × P × D 0.9
Where:
Surface Mine Design
2.18 × W × R
Pure Penetratio n ( P ) =
0.2 × C × D 0.9 × (C / 10000)
Where:
Surface Mine Design
Definitions
Explosive -A chemical mixture that releases gasses and heat at
high velocity, causing very high pressures.
In the first stage, starting from the initiation point, the blasthole
expands by crushing the blasthole walls. This is due to the high
pressure upon detonation.
Compressiv
e Shock
Waves
Mechanics of Detonation
In the third stage, the released
gas volume "enters" the crack
formation under high pressure,
expanding the cracks.
(Atlas Copco)
History of Explosives Development
1000 -Black Powder
•Discovered in China around 1000 A.D.
•Mixture of potassium nitrate (saltpeter), sulfur and charcoal.
•The combustion of charcoal (C) and sulfur (S) is the fuel, and
oxygen is contained within the nitrate ion (NO3).
•Marco Polo brought it to Europe where it was originally used
for military purposes.
•The first blasting application was in Hungary in 1627 and by
the end of the 17th century most of the European miners used
black powder to loosen rock.
•The first black powder mills were established in America
around the year 1775.
History of Explosives Development
1831-Safety Fuse
•William Bickford, an Englishman, patented the “Miners Safety
Fuse”, in 1831.
1846 -Nitroglycerin
•In 1846, Ascanio Sobrero, an Italian, discovered nitroglycerin
(C3H5N3O9), but he considered it too unpredictable and
hazardous for anyone to use.
History of Explosives Development
1867 -Blasting Caps
1970’s -Emulsions
•1970's the development of emulsion explosives.
•Emulsion explosives are composed of separate, very small
drops of ammonium nitrate solution and other oxidizers,
densely dispersed in a continuous phase, which is composed of
oil and wax.
•The oil/wax mixture, which is the fuel, is in this way given a
very large contact surface to the oxidizer, the ammonium nitrate
solution .
Properties of Explosives
In the ideal conditions of dry blastholes a simple explosive can be
used, while under wet conditions, more sophisticated products are
called for .
The most important characteristics of an explosive are:
•velocity of detonation (VOD)
•strength
•detonation stability
•sensitiveness (propagation ability)
•density
•water resistance
•sensitivity
•safety in handling
•resistance to freezing
•oxygen balance
•shelf life
Classification of Explosives
The explosives used in civil engineering and mining can nowadays
be classified as:
•High explosives
•Blasting agents
Non-electric
•Safety Fuse and Blasting Cap
•Detonating Cord
•Nonel system
Electric
•Electronic Blasting Caps
Safety Fuse and Blasting Cap
The safety fuse consists of a black powder core that is tightly
wrapped with coverings of textile and waterproofing materials.
Resistance/series
R=
Number of series
Example
Assume a blast of 250 V A-detonators with a resistance of 3.6 Ohms each. (The
resistance is always 3.6 Ohms independent of legwire length.) The firing cable
has a resistance of 5 Ohms and a CID 330 V A blasting machine is used.
In accordance with the instructions on the blasting machine, the round may be
connected in 5 parallel series.
Infinite resistance:
* Interruption in series through incomplete connection.
* Faulty detonator (usually torn off legwire).
Electric Blasting Caps
Fuse
Element
Shell Crimps Ignition Priming Base
Plug Charge Fuse Charge
Powder Charge
Bridge
Closure
Wire
Electric Cap
Nonel system
A connector with a strength of 1/3 a #8 cap is used to connect and
initiate the detonators.
Nonel system
Fixed bottom
Free breakage
Bench Blasting
The tensile, compressive and shearing strengths of a rock mass vary with
different kinds of rock and may vary within the same blast.
Faults and dirt-seams may change the effect of the explosive in the blast.
Faulty rock containing voids, where the gases penetrate without giving
full effect, may be difficult to blast even though the rock may have a
relatively low tensile strength.
Bench Blasting
The requisite specific charge, (kg/m3 ) provides a first-rate measure of
the blastability of the rock.
Stemming -non-explosive
material that is placed in the bore
hole to confine the explosives
(usually placed near the collar of
the hole).
Before Blasting
After Blasting
Leaves Un-
fractured Toe
Partial
Reflected
Wave
Un-reflected
Compression
Wave
When hole depth equals the bench height masses of rock are often
left at the toe of the bench because of lack of reflected tension
energy from the free face. The solution for this is either sub-drilling
or inclined holes.
Blasting Theory
Total
Reflected
Tensile
Inclined holes cause total Waves
reflective tensile waves at
the toe of the bench. This
causes a flat lower bench
and is a more efficient use
of explosives.
Vertical Holes vs. Inclined Holes
Kadri Dagdelen
Fuat Bilgin
Mining Engineering Department
Colorado Shool of MInes
OUTLINE
INTRODUCTION
PREVIOS WORK
FUTURE WORK
CONCLUSIONS
10/29/2006 2
• Safety Issues
• Truck Proximity Warning
• Collision Avoidance
10/29/2006 3
• Trimble GPS
• Introduction to 802.11b
10/29/2006 5
10/29/2006 6
• Hardware Development
• Software Development
10/29/2006 7
10/29/2006 8
GPS
Data, DTM Wireless Communication
Transmitting Truck Position
GPS data Wireless Communication
Between Lafarge Quarry and CSM
GPS Differential
DTM
Control Base
10/29/2006 9
• Mobile Clients
• Haul Trucks
• Manager Trucks
• PDAs
• Central Points
• Repeaters
• Trailer
10/29/2006 10
10/29/2006 11
Omni Antenna
Lighting Arrestor
WRLA-1.2/1.8
N-Female N -Female
Barrel Adapter
N-Male N -Male
Wireless PCMCI Card
Cisco LMC 352
RS 232
10/29/2006 12
10/29/2006 13
10/29/2006 14
10/29/2006 15
10/29/2006 16
Coax Cable
LMR600
Directional Antennas N-Male N-Male
WRPA2400 11-AM Coax Cable
V Pol N-Male LMR600
N-Male N-Male
Coax Cable
LMR600
N-Male N-Male
Lighting Arrestor
WRLA-1.2/1.8
N-Female N-Female
Power Supplies
Solar Panels
Barrel Adapter
N-Male N-Male
10/29/2006 17
Server
10/29/2006 18
10/29/2006 19
Cisco
AP 350
RPTNC-male
DC Injector Barrel Adapter
N-Male N-Male
N-Female
N-Female
10/29/2006 20
10/29/2006 21
• Radar Implementation
10/29/2006 22
GPS
Data, DTM
DTM
Control Base
10/29/2006 23
Existing Protocols
• Flooding
• Adaptive-SBA
• AHBP-EX
OptiTrack Protocols
• Naive Bayes
• Adaptive Boosting (AdaBoost)
10/29/2006 24
10/29/2006 25
Classification
Rebroadcast
Incoming
Packet
Discard
10/29/2006 26
10/29/2006 27
Number of Trials 10
Confidence Interval 95 %
Trial 1 2 3 4 5
Number of Nodes 40 50 60 70 90
10/29/2006 28
Delivery Ratio
100
95
90
85
Adaptive SBA
Delivery Ratio
AHBP-EX
80 Flooding
AdaBoost
Naive Bayes
75
70
65
60
1 2 3 4 5
Trial
10/29/2006 29
60
50
NumberofRetransmittingNodes
40
Adaptive SBA
AHBP-EX
30 Flooding
AdaBoost
Naive Bayes
20
10
0
1 2 3 4 5
Trial
10/29/2006 30
End-to-End Delay
2,5
2
End-to-EndDelay
Adaptive SBA
AHBP-EX
1,5 Flooding
AdaBoost
Naive Bayes
0,5
0
1 2 3 4 5
Trial
10/29/2006 31
Infrastructure
ADHOC
10/29/2006 32
10/29/2006 33
by
Antonio Peralta
• A concept of needs;
• Idea of limitations; SUSTAINABLE
DEVELOPMENT
• Future oriented paradigm, and;
SOCIAL ECOLOGICAL
• A process of change.
PHASE IN MINE
PRINCIPAL ENVIRONMENTAL
PROJECT PRINCIPAL MINE PLANNING ACTION
MANAGEMENT ACTION
DEVELOPMENT
Exploration road construction
Rock core drilling Environmental assessment
Exploration Geochemical analysis Rehabilitation plan
Geostatistical analysis Exploration permit application
Orebody evaluation
Facilities decommissioning
Dismantling Implementation of closure plan
Decontamination Site cleanup
Closure Burial Final reclamation
Removal Final impact assessment
Asset recovery Post closure planning
Recycling
Treatment
Maintenance
Post closure
Monitoring
Final bond release
By considering:
Ø Capital costs
Ø Operating costs
Ø Closure costs
Ø Potential costs for retrofits associated with
regulatory compliance
Ø Potential cost for remediation
Ø Life-cycle environmental costs
South pit is backfilled & west dump is almost covered Waste dumps encapsulation is finished
by
Antonio Peralta
Contributing Factors
q Impact on mine water quality.
Rock Classification
q AMD waste materials includes overburden, waste
rock, pit walls, pit floor and tailings.
Block Modeling
q Ore grades.
q Contaminants.
q Metallurgical recoveries.
q Economic parameters.
q Environmental parameters.
q Development phasing
éPeriod of development
éAreas of extraction
by phase
2035 2050
Maps for different time periods
q Clearing / Vegetation removal
q Topsoil management
q Grading principles
q Erosion control
q Revegetation
Isolation Strategy
q AMD waste is selectively handled and surrounded
with non-acid producing materials to limit flow of air
and water into waste and AMD flow out.
Waste Encapsulation
q Similar in concept to encapsulation. Method is
useful where a mined out pit of sufficient size is
available.
In -Pit Disposal
q Involves the blending/mixing and co-disposal of
AMD wastes with benign non-acid producing
materials or even acid neutralizing materials.
Covers
q Option for marginal acid producing wastes where
subsequent acid drainage is recovered and treated
downstream.
Conclusions
Questions and comments???????
Summitville, Colorado
According to the United States Environmental Protection Agency
(US EPA), mining generates twice as much waste as all other
American industries put together.
So-called "hard rock" mining wastes are acidic and contaminated
with toxic heavy metals which have poisoned more than 12,000
miles of streams and rivers and 180,000 acres of lakes.
EPA estimates the public cost to clean up the more than 550,000
abandoned mines in America at between $32-72 billion.
The very scale of today's massive open-pit mining operations
means that sometimes cleanup costs will outstrip the value of the
metals pulled out of the ground, as happened with the $232 million
cleanup of the Summitville mine in southern Colorado.
Summitville, Colorado
At Eagle mine, a zinc, copper and silver operation, ten million tons
of mine waste and mine tailings were left along the banks of the
Eagle River in Gilman Colorado.
Cleanup costs exceeded $55 million which totaled more than $5.50
per ton of mine waste.
A zinc, lead and silver mine at Smuggler Mountain in Pitkin
Colorado. The estimated cost for environmental recovery is $7.2
million. This equals $2.40 per ton of waste.
Examples, Colorado
Feasibility Studies
The formal feasibility study includes an economic analysis of the rate of
return that can be expected from the mine at a certain rate of production.
The most serious risks in any mining project are those associated
with:
Among other uses of the cash flow generated by the mine, these
funds must finance:
•continuing exploration elsewhere,
•pay for past failures, and
•contribute to the mine's portion of main office and general
overhead.
Time Value of Money
Money has a time value. The future value of an investment can be
calculated by:
F = P(1 + i) N
where:
P = Present value of investment
F = Future value of investment
i = interest rate
N = number of years
For example $100 invested at 10% interest for 1, 2, and 3 years would
yield:
F = 100(1 + .10) 1 = $110.00
F = 100(1 + .10) 2 = $121.00
F = 100(1 + .10) 3 = $133.10
Time Value of Money
Conversely money received in the future is not as valuable as money
received today. If money is received in the future:
P = F / (1 + i) N
The term is a special version of the more generic term, internal rate
of return (IRR).
N
CFn (4)
∑
n = 0 (1 + i)
n
=0
where:
CFn = Amount of cash in or out in a given year
n = Year
N = Project life
i = DCF-ROR
Once the cash flows for a project have been determined, the
interest rate i can be solved for using an iterative process, i.e. guess
at an initial value for i and then solve Equation 4 until a result of 0
is obtained.
Steps Involved in Cash Flow Analysis
The evaluation of a mining project is usually an iterative process
using the following steps:
Change steps 4, 2, and 1 and select the alternative that gives the
highest return.
Steps Involved in Cash Flow Analysis
In a feasibility study, attempt to quantify all geologic, technical,
marketing, environmental, political, etc. factors. Many of these
variables are dependent on each other. A feasibility study are
usually divided into the pre-production, production, and post-
production phases:
1. Preproduction Period
Exploration
Water and land acquisition
Mine and mill capital
Working capital, etc
2. Production Period
Revenue less costs
Calculation Of Annual Cash Flow
3. Postproduction Period
Equipment salvage
Working capital liquidation
Steps Involved in Cash Flow Analysis
Depletion
One of the features that distinguish a mining enterprise from many
other businesses is that during production, the company’s assets,
i.e. the ore, is consumed.
Having recaptured the initial asset cost from the annual tax deductions, the
owner can, in theory, replace the worn-out piece of equipment with a new
one and keep himself in business.
Case Study
The calculation of the cash flow and DCF-ROR is illustrated using a
bedded zinc deposit, producing 6000 tons per day, with total reserves of
22.5 MM Tons @ 14% zinc.
Lead: No payment.
Price Adjustment:
Increase by $3.00 per ton for each $.01 that the zinc
quotation exceeds $.40 per pound. Fractions in
proportion.
Decrease by $2.00 per ton for each $.01 that the zinc
quotation decreases below $.40 per pound. Fractions
in proportion.
Smelter Schedule Calculations
Concentrate Grade = 55%
zinc Price = $0.47/lb
Payments:
2,000 lb/ton * 0.55 * 0.85 * $(0.47- 0.015)/lb = $425.43/ton
Deductions:
Base Charge 170.00
Price Adjustment
(47- 40)c * $3.00/c = 21.00
Total Deductions: (191.00)
Freight:
Truck 5.00
Rail 15.00
Total Freight: (20.00)
Depletion ($1,000):
By Linear Interpolation
40000
30000
20000
10000
$ *1000
0
11
13
15
17
19
21
-10000
-20000
-30000
-40000
-50000
Year
10,000
5,000
0
$ *1000
11
13
15
17
19
21
(5,000)
(10,000)
(15,000)
(20,000)
Year
Definitions of troy ounce on the Web:
ounce: a unit of apothecary weight equal to 480 grains or one twelfth of a pound
Although the metric system is used increasingly in mining and the gold
business, the troy ounce remains the basic unit in which the price of 995
gold is quoted.
K. Dagdelen
Professor
Mining Engineering Department
Colorado School of Mines
Golden, Colorado 80401
OPEN PIT OPTIMIZATION
Physical Capacities
Production Extraction
Costs Scheduling
Design Of Cuts
technique
OPEN PIT OPTIMIZATION
ULTIMATE PIT LIMITS
Physical Capacities
Production Extraction
Costs Scheduling
Design Of Cuts
PHASE 1
PHASE 2
PHASE 3
OPEN PIT OPTIMIZATION
DESIGN OF PUSHBACKS
Physical Capacities
Production Extraction
Costs Scheduling
Design Of Cuts
Pit
Stockpiles
Autoclave Mill
Round Mountain Gold Mine
Oxide Waste
Low grade
stockpiles Waste
Ore
dumps
2005 SME Annual Meeting
Sulfide
Crusher
Stockpiles
CIP Mill
Leach Pads
Breakeven Mill Cutoff Grade
Milling Cost
Breakeven cutoff grade =
(Price – Refining Cost - Sales Cost) * Recovery
$19/ton
Breakeven cutoff grade =
($600/oz - $5.0/oz) * 0.90
= 0.035 oz/ton
Oxide Waste
Low grade
stockpiles Waste
Ore
Sulfide
dumps
Crusher
Stockpiles
CIP Mill
APCOM 2005
Leach Pads
COMPLICATED PROCESSES AND
CAPACITIES limited by
10M crusher
ROM
tons/yr
Dump Leach
Cr
1 Leach
roc
P 2
roc
P
Phase
Proc 3
1 Cr Autoclave
Phase2
Pr
oc
1.05M
Mine 4
20% tons/yr
5M
APCOM 2005
tons/yr Flot.
80%
Mining Capacity: 12M tons/yr
2M
Refining Capacity: 350 koz/yr tons/yr
Tailings
Stockpile available
OPEN PIT OPTIMIZATION
CUTOFF GRADES
operating environments.
CUTOFF GRADE FORMULATION
Index d
Dump
Cutoff Mill
Grade
Tons
McLaughlin mine Grade intervals
l Decision variables:
APCOM 2005
Mine
t
X igd
Index g
• Defines ore tons and its quality for different time periods.
1
Push Backs or Phases Example
MNGN 433 Mine Systems Analysis
Phase 1 Phase 2
2
Push Backs or Phases Example
(Cont.)
MNGN 433 Mine Systems Analysis
Phase 3 Phase 4
3
Push Backs or Phases Example
(Cont.)
MNGN 433 Mine Systems Analysis
Cross Section
4
Cutoff Grade
• Minimum grade of the material for processing.
MNGN 433 Mine Systems Analysis
5
Breakeven Cutoff Grade
• The lowest economic grade where mining, milling, and
MNGN 433 Mine Systems Analysis
• Cutoff grades in the pit are normally much higher than the
breakeven cutoff grade.
6
Hypothetical Case Study
• Consider a hypothetical case study where an epithermal gold
MNGN 433 Mine Systems Analysis
8
Traditional Cutoff Grades
• Traditionally, a cutoff grade is used to determine if a block
MNGN 433 Mine Systems Analysis
9
Ultimate Pit Cutoff Grade
• Ultimate pit cutoff grade is defined as the breakeven grade
MNGN 433 Mine Systems Analysis
$19/ton + $1.2/ton
Ultimate pit cutoff grade =
($600/oz - $5.0/oz) * 0.90
= 0.038 oz/ton
10
Milling Cutoff Grade
• Milling cutoff grade is defined as the breakeven grade that
MNGN 433 Mine Systems Analysis
$19/ton
Milling cutoff grade =
($600/oz - $5.0/oz) * 0.90
= 0.035 oz/ton
11
Milling Cutoff Grade (Cont.)
• In the milling cutoff grade, no mining cost is included since
MNGN 433 Mine Systems Analysis
•
MNGN 433 Mine Systems Analysis
• They are constant unless the commodity price and the costs
change during the life of the mine.
14
Yearly Tons and Grades Schedules by
Constant Cutoff Grades
• Define:
MNGN 433 Mine Systems Analysis
Profits ($M) = (P - s) * Qr – Qc * c – Qm * m
15
Yearly Tons and Grade Schedules by
Constant Cutoff Grades
33.0 33.0 …
+ +
(1 + 0.15)4 (1 + 0.15)5
33.0 31.4
+ +
(1 + 0.15)34 (1 + 0.15)35
= $218.5M
17
Summary of Constant Cutoff
Grade
• Total 28.44M tons is mined (Avg. grade 0.102 oz/ton)
MNGN 433 Mine Systems Analysis
• NPV: $218.5M
18
Declining Cutoff Grade
• Traditional cutoff grade (constant cutoff grade) does not
MNGN 433 Mine Systems Analysis
19
Heuristic Cutoff Grade
• The traditional cutoff grade is modified so that they include
MNGN 433 Mine Systems Analysis
20
Concept of Heuristic Cutoff
Grade
• The concept is demonstrated pictorially as follows:
MNGN 433 Mine Systems Analysis
21
Capital Cost
• Assume:
MNGN 433 Mine Systems Analysis
22
Minimum Profit
MNGN 433 Mine Systems Analysis
• Assume:
23
Heuristic Cutoff Grade
Calculation
• The milling cutoff grades will be:
MNGN 433 Mine Systems Analysis
Yr 1 to 5
= 0.060 oz/ton
24
Heuristic Cutoff Grade
Calculation (Cont.)
MNGN 433 Mine Systems Analysis
Yr 6 to 10
$19/ton + $10/ton
Ultimate pit cutoff grade =
($600/oz - $5.0/oz) * 0.90
= 0.054 oz/ton
25
Heuristic Cutoff Grade
Calculation (Cont.)
MNGN 433 Mine Systems Analysis
Yr 11 to Depletion
Milling Cost
g milling =
(Price – Refining Cost - Sales Cost) * Recovery
$19/ton
Ultimate pit cutoff grade =
($600/oz - $5.0/oz) * 0.90
= 0.035 oz/ton
26
Yearly Tons and Grade
Schedules
• The year by year tons and grade schedule obtained modified
MNGN 433 Mine Systems Analysis
28
Heuristic Cutoff Grade
(Including G & A)
• In the previous calculations, the G & A costs were not
MNGN 433 Mine Systems Analysis
• Assume:
Fixed Costs per year: $8.35M / year
Fixed Costs per ton: ($8.35M/year) / (1.05Mtons/year)
= $7.95 / ton
29
Heuristic Cutoff Grade Calculation
(With G & A)
Yr 1 to 5
= 0.075 oz/ton
30
Heuristic Cutoff Grade Calculation
(With G & A) (Cont.)
MNGN 433 Mine Systems Analysis
Yr 6 to 10
= 0.069 oz/ton
31
Heuristic Cutoff Grade Calculation
(With G & A) (Cont.)
MNGN 433 Mine Systems Analysis
Yr 11 to Depletion
$19/ton + $7.95/ton
Ultimate pit cutoff grade =
($600/oz - $5.0/oz) * 0.90
= 0.050 oz/ton
32
Yearly Tons and Grades
Schedules
• The year by year tons and grade schedule obtained modified
MNGN 433 Mine Systems Analysis
•
MNGN 433 Mine Systems Analysis
34
Lane’s Approach
• Declining cutoff grades throughout the mine life gives
MNGN 433 Mine Systems Analysis
higher NPV.
35
Lane’s Approach (Cont.)
•
MNGN 433 Mine Systems Analysis
37
Cutoff Grade Equation for
Lane’s Approach (Cont.)
•
MNGN 433 Mine Systems Analysis
Where
d is the discount rate;
NPVi is the NPV of the future cash flows of the years (i) to the end
of mine life;
fa is the annual fixed costs
38
Yearly Tons and Grades
Schedules
• The year by year tons and grade schedule resulted from
MNGN 433 Mine Systems Analysis
39
Steps to Obtain Table 6 (1st Iteration)
Year (i) NPVi Cog Ore Grade (Mtons) (Mtons) (Mtons) (Mtons) (ktons) ($M) ($M)
1 0 0.050 0.133 101.5 24.0 4.2 5.5 1.05 125.7 39.9 $255.0
2 0 0.050 0.133 97.1 23.0 4.2 5.5 1.05 125.7 39.9 $253.4
3 0 0.050 0.133 92.6 21.9 4.2 5.5 1.05 125.7 39.9 $251.5
4 0 0.050 0.133 88.2 20.9 4.2 5.5 1.05 125.7 39.9 $249.3
5 0 0.050 0.133 83.7 19.8 4.2 5.5 1.05 125.7 39.9 $246.8
6 0 0.050 0.133 79.3 18.8 4.2 5.5 1.05 125.7 39.9 $243.9
7 0 0.050 0.133 74.9 17.7 4.2 5.5 1.05 125.7 39.9 $240.6
…
21 0 0.050 0.133 12.7 3.0 4.2 5.5 1.05 125.7 39.9 $86.6
22 0 0.050 0.133 8.3 2.0 4.2 5.5 1.05 125.7 39.9 $59.7
23 0 0.050 0.133 3.8 0.9 4.2 5.1 0.91 108.9 33.1 $28.7
Total 125.8 24.0 2,874.0 910.8
(NPV@15%)
$255.0
40
Steps to Obtain Table 6 (2nd Iteration)
2nd iteration
MNGN 433 Mine Systems Analysis
41
Steps to Obtain Table 6 (3rd Iteration)
3rd iteration
MNGN 433 Mine Systems Analysis
42
Steps to Obtain Table 6 (4th Iteration)
4th iteration
MNGN 433 Mine Systems Analysis
43
Table 6
Table 6
MNGN 433 Mine Systems Analysis
44
Summary of Lane’s Approach
constraints: N
Maximize NPV = ∑ profit(i ) * (1+1d ) i
i =1
3
Derivation of Opportunity Costs of
Mining Low Grades (Cont.)
( profits ($M ) + Vq )
V=
MNGN 433 Mine Systems Analysis
(1 + d )T
V * (1 + d )T = ( profits ($ M ) + Vq)
V * (1 + d * T ) = profits ($ M ) + Vq
V + V * d * T = profits ($M ) + Vq
V − Vq = profits ($M ) − V * d * T
4
Derivation of Opportunity Costs of
Mining Low Grades (Cont.)
v = profits ($M ) − d * V * T
5
Basic Present Value Expression
• Annual profits can be calculated as follows:
MNGN 433 Mine Systems Analysis
v = ( P − r − s ) * Qr − c * Qc − m * Qm − f * T − d * V * T
Where
P: Metal price per ton of product
r: Marketing cost per ton of product
s: Sales cost per ton of product
c: Processing cost per ton of ore
m: Mining cost per ton of ore
f: Annual fixed administrative costs
T: Number of time periods that will take to mine, concentrate and
refine Qm amount of material from the pit (i.e. years)
6
Mine Limiting Case
Qm
T=
M
( f + d *V )
vm = ( P − r − s) * Qr − c * Qc − m + * Qm
M
vm
vm is a function of
cutoff grades
COG
7
COG of Mine Limiting Case
c
gm =
(P − r − s ) * y
where
y: Metallurgical recovery
8
Concentrator Limiting Case
Qc
T=
C
( f + d *V )
vc = ( P − r − s) * Qr − c + * Qc − m * Qm
C
( f + d *V )
c+
gc = C
( P − r − s) * y
9
Refinery Limiting Case
Qr
T=
R
( f + d *V )
vr = ( P − r − s − ) * Qr − c * Qc − m * Qm
R
C/M
g mc
11
Balancing Cutoff Grade (Cont.)
Mine - Refinery
MNGN 433 Mine Systems Analysis
R/M
g mr
12
Balancing Cutoff Grade (Cont.)
Mill - Refinery
MNGN 433 Mine Systems Analysis
R/C
g rc
13
Open Pit Copper Case Study
Deposit Reserves
MNGN 433 Mine Systems Analysis
(%Cu) (Mtons)
14
First Year Production Reserves
MNGN 433 Mine Systems Analysis
(%Cu) (Mtons)
15
Open Pit Copper Case Study
Unit of mining: ton
MNGN 433 Mine Systems Analysis
(V=0) (V=1174)
17
Concentrator Limited Case
MNGN 433 Mine Systems Analysis
(V=0) (V=1174)
18
Refinery Limited Case
MNGN 433 Mine Systems Analysis
(V=0) (V=1174)
19
Balancing Cutoff Grade
gm
gr
500 gc
400
300
200
vm
Profit
Gopt
100
vc
0 vr
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
-100
-200
-300
COG Feasible Region
20
Balancing Cutoff Grade
Balancing Cutoff Grades (V=1174)
MNGN 433 Mine Systems Analysis
300
250
200
150
100
vm
50
Profit
vc
0
vr
-50 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
-100
Gopt
-150
-200
-250
COG
21
Limiting Economic Cutoff Grades
c 2($ / ton) 2
gm = = = %Cu = 0.10%Cu
( P − s) * y ( 25 − 5)($ / 1%Cu *1ton) *1 ( 25 − 5) *1
22
Limiting Economic Cutoff Grades
(Cont.)
MNGN 433 Mine Systems Analysis
2
= %Cu = 0.16%Cu
300
25 − 5 − *1
40
23
MNGN 433 Mine Systems Analysis
24
MNGN 433 Mine Systems Analysis
25
MNGN 433 Mine Systems Analysis
26
MNGN 433 Mine Systems Analysis
27
MNGN 433 Mine Systems Analysis
28
Grade – Tonnage Relationship
MNGN 433 Mine Systems Analysis
Cutoff Quantity Tons Below Tons Above Avg Grade Cu Produced Ore to Product to Product to Ore to
(%Cu) (Mtons) Cutoff Cutoff Above Cutoff (%Cu of Material Material Ore Waste
(Mtons) (Mtons) (%Cu) 1ton of Material) Ratio Ratio Ratio Ratio
(C ) ( R) (C/M) (R/M) (R/C)
0.00 100 0 1000 0.500 500 1.0 0.500 0.500 0.00
0.10 100 100 900 0.550 495 0.9 0.495 0.550 0.11
0.20 100 200 800 0.600 480 0.8 0.480 0.600 0.25
0.30 100 300 700 0.650 455 0.7 0.455 0.650 0.43
0.40 100 400 600 0.700 420 0.6 0.420 0.700 0.67
0.50 100 500 500 0.750 375 0.5 0.375 0.750 1.00
0.60 100 600 400 0.800 320 0.4 0.320 0.800 1.50
0.70 100 700 300 0.850 255 0.3 0.255 0.850 2.33
0.80 100 800 200 0.900 180 0.2 0.180 0.900 4.00
0.90 100 900 100 0.950 95 0.1 0.095 0.950 9.00
29
Balancing Economic Cutoffs
MNGN 433 Mine Systems Analysis
30
Choosing Optimum Cutoff Grade
MNGN 433 Mine Systems Analysis
31
Choosing Optimum Cutoff Grade
MNGN 433 Mine Systems Analysis
Gmc = 0.40%Cu
Grc = 0.40%Cu
Gmr = 0.16%Cu
Then,
Gopt = 0.40%Cu
32