TEST PROCEDURE :

Preparation

Before connecting the PC to the equipment, ensure that the equipment power supply is turned on.

1- Referring to FIG-1, connect the personal computer to the IDU LCT PORT using the USB cable.
2- Run the WEB browser and connect to LCT system.
3- Enter the specified Login name then press ‘ENTER’.

4- Enter the specified password then press ‘Login’. Then, LCT main menu will be appeared.

5- Select the Metering from the left side flame Then following display is appeared.

7- Check the each Values and record the results on Test Data Sheet
4. At each station, remove the cap from the RX LEV MON connector on the ODU
5. At each station, Connect cables to RX LEV MON connector using F-type plug And either
end of cable connect to digital voltmeter.
6. Measured the Voltage on the digital voltmeter.
7. Check the voltage depending on the indication of receiving level on LCT.
8. Remove the cable from the RX LEV MON connector on ODU and set the cap for this
connector.
9. Repeat above steps for Channel 2
6. Confirm the value field and succeeding the process.
7. Select the main loopback (Far End) as ‘Off’ after confirming