You are on page 1of 25
E = Frischmann Prabhu PLANNING + DESIGN « PROJECT MANAGEMENT (C4, Jawahar Nagar, Bharatpur, Rajasthan - 32100 fiscannbinfemal com: wa foidia.com FPI/BTP/O&M/IE/04/2016/106 Dated: 05” Oct, 2016 To, ‘The Project Director NHAI PIU, Dausa 87, Ganga Vihar Colony, Behind Rewat Palace Hotel, Dausa (Raj.) 303303. Phone: 01427-24918 Sub.: Independent Engineer Services for Operation & Maintenance Stage of 4/6 laning of Agra- Bharatpur BOT Project from Km 17.756 to Km 62.295 of NH-11 under NHDP Phase IIA in the state of Uttar Pradesh & Rajasthan — Standar Engineering Consultants (Independent Engineer) — MPR September.2016 in New Format Ref.: (i) Your email dated 19.08.2016 (ii) Your email dated 01.08.2016 Dear Sir, Monthly Progress Report for September 2016 in new format is submitted for your perusal and information please. Yours, Sincerely, For Frischmann Prabhu (1) Pvt. Ltd. dsl (Punil Pandey) Team Leader ‘Agra-Bharatpur Road Project Encl: Tee Copies of MPR in New Format ce 1. GM, FPL, Gurgaon 2. The Project Engineer, OPAPL, Korai Toll Plaza. CIN: Usszo0MH199SPTCORSS21 ORIENTAL PATHWAYS (AGRA) PVT. LTD. Independent Engineer Services during Operation & Maintenance stage of 4/6 laning of Agra - Bharatpur BOT project from Km. 17.756 to Km. 62.295 of NH-11 under NHDP Phase-lilA in the State of Uttar Pradesh & Rajasthan Independent Engineer FRISCHMANN PRABHU INDIA PVT. LTD. Executive Summary MONTHLY PROGRESS REPORT NO. 04 FOR THE MONTH OF: SEPTEMBER, 2016 1.1 Summary of Current Month's Progress: Expected Contents & Structure of Summary The Project is now in O&M Phase. Construction of road has already been completed in 2009. ‘Summary of Progress: Physical progress & length completed ~ Road is completed in 2009, Project is under Operation & Maintenance phase. Encroachment ~ Concessionaire makes effort for removing encroachments. Current Issues & Recommended Actions by IE: Not Applicable Issues related to progress made by concessionaire Issues with pending land acquisition, clearances & uility shifting. encumbrances etc. Status of change of scope proposals — lf applicable Action recommended by IE along with timelines Highlight potential risks due to the pending issues & pending issues from previous month Sample Summary — Illustrative, for reference Summary of Progress :- BOT The Project road starting from chainage 17+756 and ending at chainage 62+295 is under BOT. Total length of project is 44.539 km. The Project cost is 195 Cr. Appointment date of Concessionaire was (06.09.2006 and the date of completion of punch list items was 07.11.2009. The Commercial Operation Date was 09% July 2009, Concession Period is 20 years (including Construction period). Almost 10 years have elapsed in Operation and Maintenance. Korai Toll Plaza is situated at km 30+090. ETC lane for use of | FASTags is operational from either side. Weigh-In-Motion is operational.

You might also like