Professional Documents
Culture Documents
D
ue to higher global demand for gasoil a column with a cooling failure, power fail- ance (V1), the relief load is calculated as
and gasoline along with strict envi- ure or reflux failure, the energy balance is: L = 2,923 kg/hr.
ronmental regulations, refineries are • As an approximation, using (Q1 +
F hF + QR = B hB + P hP + V hV +
incorporating new hydrotreating units into QA)/reboiler, the relief load is L = 3,035kg/hr.
QA + Q1 + L hL (1)
their existing facilities. Just in the southern Once the preliminary relief loads are
cone of Latin America (Argentina, Chile where: calculated, the new pressure-relief valves
and Uruguay) at least five hydrotreating F = Feed flow are sized, and the new flare system lines
units have been projected and/or built in hF = Feed enthalpy are designed and routed into a new unit
the last five years. These hydrotreating units QR = Reboiler duty subheader. While calculating the concur-
aim to lower the sulfur content to 20 ppm– B = Bottom liquid flow rent PSV contingency loads, most coming
50 ppm on final products. hB = Bottom liquid enthalpy from columns, towers or pressure separa-
Project attention focuses on these new P = Product flow tors, other process engineers can work on
hydrotreating units, while utilities and hP = Product enthalpy calculating all the single-contingency PSV
other services are evaluated later in the V = Vapor flow loads, such as blocked outlet loads, control
project cycle. Verifying the existing refinery hV = Vapor enthalpy valve full-open cases, etc.
flare systems has to be performed as early L = Relief load
as possible during the detail engineering hL = Relief load enthalpy HAZOP analyses and relief sce-
project phase to answer key questions, such QA = Air cooler (condenser) duty narios. A hazardous operation (HAZOP)
as: Would the existing crude distillation Q1 = Trim cooler (condenser) duty analysis of the new process enables assess-
unit pressure-relief valve (PSV) open with reboiler = Latent heat of vaporization or, ment of the number of PSVs that might
the new backpressure introduced from the for multicomponent systems, the differ- be triggered to open in various scenarios.
new hydrotreating unit’s PSV? Is the exist- ence between the vapor and liquid specific In a new gasoline hydrotreating unit, the
ing flare tall enough that it doesn’t exceed enthalpies. number of PSVs involved in a multivalve
the radiation limits at ground level? Are the The reboiler duty is recalculated for opening contingency, other than fire, that
emission contaminants changing compared relieving conditions. For an air-cooler con- could impact the existing flare design rating
to the previous refinery operations? tingency (or power loss), QA in relieving are shown in Table 1.
conditions would be 20% of operating QA. Out of 30 PSVs, only two were involved
Method description and best For cooling water loss, Q1 would be 0. To in concurrent PSV discharge scenarios—a
practice tips. The proposed method- evaluate a reflux failure, the top tray vapor cooling water and general power failure—
ology is used as a multi-tier approach to less the operating vapor to the condenser is
compress project schedules, determine a good approximation to calculate L.1–4,7 L
V1
PSV requirements earlier in the project V
and purchase those PSVs early, if it’s eco- Example. With a new gasoline stabilizer QA CW Q1
design and save on capital costs without (QA = 0), the following quick calculations
compromising safety. were considered to estimate the relief load B
To quickly identify possible problems, for a loss of cooling in the condenser:
relief loads are first calculated using a • A steady-state simulation model was QR
simple approach. The different concurrent used (Fig. 2), setting the column pressure as
B
contingency loads can be calculated with the opening valve pressure and Q1 = 0. The
the basic material and energy balance engi- relief load is calculated as L = 3,732 kg/hr.
neering data. A conservative enthalpy bal- • For normal vapor flow to the con- Fig. 1 Material and energy balance in a
ance approach can be used. For example, in denser from the material and energy bal- column.
three possible discrete integrity levels (SIL hydrotreating units to an existing refinery • Material capital cost savings in accu-
1, SIL 2 and SIL 3) of safety instrumented are discussed below. rate header sizing.
systems defined in terms of probability of Tables 2 and 3 show the number of • New flare cost savings in performing
failure on demand (PFD). SIL 3 has the PSVs that changed from one type to a dif- more accurate dynamic-load calculations
highest reliability, SIL1 has the lowest. API ferent type as the project progressed. This when needed. HP
521 Fifth Edition allows you to take load resulted from the simulation model being
literature cited
credits for the use of HIPPS.1 The benefit improved as various engineering tasks 1 ANSI/API Standard 521 (ISO 23251), “Pressure-
of this approach is the avoidance of having were completed, and as the overall design relieving and Depressuring Systems,” Fifth
to build a complete new flare. The down- evolved and improved. Edition, January 2007.
side is the operational constraints on the Even though many load calculations 2 ANSI/API Standard 520, “Sizing, Selection
degree of turndown or the possibility even changed and PSV sizes were revised during and Installation of Pressure-Relieving Devices
in Refineries. Part I: Sizing and Selection,” Seventh
having to shutdown a unit to avoid over- the project, the unit’s main header diame- Edition, January 2000.
loading the flare system, and the capital ter, the tie-in point and the knockout-drum 3 K. Banjee, N. P. Cheremisinoff and P. N.
investment needed to enhance the control calculations remained unchanged between Cheremisinoff, Flare Gas Systems Pocket
systems of existing units. design revisions. Handbook, Gulf Publishing Company, 1985.
4 Kister, H. Z., “Distillation Operation,”
2. Increase existing flare height. The This experience demonstrates that some MacGraw-Hill, Inc, Chapter 9.
radiation intensity and dispersion con- tasks can be performed in parallel. Later 5 Gruber, D., D.-U. Leipnitz, P. Seturaman,
centration at ground level will improve in the project cycle all pieces of the flare M. Alos, J. M. Nougues and M. Brodcorb,
but the support structures may have to be system can be quickly recalculated using “Are there alternatives to an expensive overhaul of
a bottlenecked flare system?, Petroleum Technology
revamped or new structures added. process simulator and flare system analysis Quarterly, Q1 2010.
3. Change the existing main flare software. 6 Marshall, B., “Improve Flare System Design
header. Sometimes backpressure prob- to Reduce Cost and Enhance Safety,” AspenTech
lems persist in existing PSVs and the only Benefits of using this method. Webinar, November 2009.
7 Crosby, T. Pressure Relief Valve Engineering
option is to replace portions of the existing Many benefits can be obtained using the Handbook, Technical Document, May 1997.
network. Obviously, this will require addi- approach presented in this article, as vali- 8 Ouderkirk, R., “Rigorously Size Relief Valves
tional capital investment. dated by experience on several projects: for Supercritical Fluids,” CEP Magazine, August
4. Add a gas-recovery facility. When • Compressed project schedules by per- 2002.
9 US Environmental Protection Agency, “Guía
a dispersion analysis results in high con- forming PSV calculations and flare system del usuario del Modelo SCREEN3,” EPA454/
taminant concentration, this approach calculations in parallel. For the example B95-004, September 2000.
could partially solve the problem, but it cited previously, these calculations resulted 10 Simulation performed with Aspen Flare System
also might increase the backpressure on the in achieving a three-month reduction in Analyzer V7.1, Aspen Technology, 2009.
PSVs and increase capital cost. the project schedule.
5. Change the flare tip. Sometimes, • Project man-hour savings by perform-
high Mach numbers at the flare tip can be ing the appropriate level of modeling as Mayra Marchetti is a process
engineer at A. Evangelista S.A. She has
avoided by simply changing the flare tip. required by the project-specific design. The 10 years´ work experience in process
example cited represented saving 160 engi- simulation and industrial projects, with
Results obtained by applying neering man-hours of modeling time. a special focus in relief system design
and evaluation studies, revamps and new designs. She
this method. The results of applying • Early definition of header sizing and
graduated as a chemical engineer from Buenos Aires
this approach to flare-system analysis in a the PSVs required. There may be cost sav- University and holds an MS degree in engineering man-
project involving the addition of two new ings in procuring these supplies early. agement from Florida International University.
Article copyright ©2011 by Gulf Publishing Company. All rights reserved. Printed in U.S.A.
Not to be distributed in electronic or printed form, or posted on a website, without express written permission of copyright holder.