You are on page 1of 5

Originally appeared in: Plant safety

February 2011, pgs 85-89.


Used with permission.

Circumvent design issues when


adding new hydrotreating units
Follow these guidelines for substantial capital cost savings
with existing flare systems
M. H. Marchetti, A-Evangelista, S.A., Buenos Aires, Argentina

D
ue to higher global demand for gasoil a column with a cooling failure, power fail- ance (V1), the relief load is calculated as
and gasoline along with strict envi- ure or reflux failure, the energy balance is: L = 2,923 kg/hr.
ronmental regulations, refineries are •  As an approximation, using (Q1 +
F  hF + QR = B  hB + P  hP + V  hV +
incorporating new hydrotreating units into QA)/reboiler, the relief load is L = 3,035kg/hr.
QA + Q1 + L  hL  (1)
their existing facilities. Just in the southern Once the preliminary relief loads are
cone of Latin America (Argentina, Chile where: calculated, the new pressure-relief valves
and Uruguay) at least five hydrotreating F = Feed flow are sized, and the new flare system lines
units have been projected and/or built in hF = Feed enthalpy are designed and routed into a new unit
the last five years. These hydrotreating units QR = Reboiler duty subheader. While calculating the concur-
aim to lower the sulfur content to 20 ppm– B = Bottom liquid flow rent PSV contingency loads, most coming
50 ppm on final products. hB = Bottom liquid enthalpy from columns, towers or pressure separa-
Project attention focuses on these new P = Product flow tors, other process engineers can work on
hydrotreating units, while utilities and hP = Product enthalpy calculating all the single-contingency PSV
other services are evaluated later in the V = Vapor flow loads, such as blocked outlet loads, control
project cycle. Verifying the existing refinery hV = Vapor enthalpy valve full-open cases, etc.
flare systems has to be performed as early L = Relief load
as possible during the detail engineering hL = Relief load enthalpy HAZOP analyses and relief sce-
project phase to answer key questions, such QA = Air cooler (condenser) duty narios. A hazardous operation (HAZOP)
as: Would the existing crude distillation Q1 = Trim cooler (condenser) duty analysis of the new process enables assess-
unit pressure-relief valve (PSV) open with reboiler = Latent heat of vaporization or, ment of the number of PSVs that might
the new backpressure introduced from the for multicomponent systems, the differ- be triggered to open in various scenarios.
new hydrotreating unit’s PSV? Is the exist- ence between the vapor and liquid specific In a new gasoline hydrotreating unit, the
ing flare tall enough that it doesn’t exceed enthalpies. number of PSVs involved in a multivalve
the radiation limits at ground level? Are the The reboiler duty is recalculated for opening contingency, other than fire, that
emission contaminants changing compared relieving conditions. For an air-cooler con- could impact the existing flare design rating
to the previous refinery operations? tingency (or power loss), QA in relieving are shown in Table 1.
conditions would be 20% of operating QA. Out of 30 PSVs, only two were involved
Method description and best For cooling water loss, Q1 would be 0. To in concurrent PSV discharge scenarios—a
practice tips. The proposed method- evaluate a reflux failure, the top tray vapor cooling water and general power failure—
ology is used as a multi-tier approach to less the operating vapor to the condenser is
compress project schedules, determine a good approximation to calculate L.1–4,7 L
V1
PSV requirements earlier in the project V

and purchase those PSVs early, if it’s eco- Example. With a new gasoline stabilizer QA CW Q1

nomical; assess alternatives to improve column without an air-cooler condenser P

design and save on capital costs without (QA = 0), the following quick calculations
compromising safety. were considered to estimate the relief load B
To quickly identify possible problems, for a loss of cooling in the condenser:
relief loads are first calculated using a •  A steady-state simulation model was QR
simple approach. The different concurrent used (Fig. 2), setting the column pressure as
B
contingency loads can be calculated with the opening valve pressure and Q1 = 0. The
the basic material and energy balance engi- relief load is calculated as L = 3,732 kg/hr.
neering data. A conservative enthalpy bal- •  For normal vapor flow to the con- Fig. 1 Material and energy balance in a
ance approach can be used. For example, in denser from the material and energy bal- column.

HYDROCARBON PROCESSING February 2011


Plant safety

Engineering workflow and guide-


lines. Fig. 3 represents the workflow of
the flare-system rating method. The vari-
ous steps are described as follows:
•  Workflow starts with a parallel evalu-
ation of multiple PSV load contingencies
and single or unit-wide contingencies,
using a flare-system analyzer model.
•  New flare network is designed. At this
stage in the detailed engineering project,
the new units’ isometrics are not available.
To complete the flare header design and
rating, basic routing of PSV exits are made
over the plot plan of the plant or layout of
new and existing units. Choosing the tie-in
point and knockout drum verification will
be discussed in detail later.
•  The network is designed and rated to
project-specific values of ∙v2 and Mach
Fig. 2 A steady-state simulation model. number. Good engineering practice uses
∙v2 for gases of less than 150,000 Pa
and Mach numbers of 0.3 to 0.7. If these
parameters are not met in the existing main
Single-contingency loads Multiple-PSV load scenarios header, then a better understanding of the
existing relief loads can be achieved through
dynamic simulation. Once the hydraulic
calculations comply with the design param-
Design new flare PSVs, depressurization valves, eters, the PSV orifice calculations for the
exit lines, sub headers and headers (ISBL) multi-PSV opening cases are reviewed. Dis-
persion and radiation studies are performed
Verify knockout drum (KOD) with new vapor and liquid loads and, if all studies comply with international
Perform dynamic and local regulations, the flare-system rat-
simulation of columns,
or HIPPS analysis ing is completed.
Unfortunately, flare-system analysis
Add new KOD tie-in Tie-in point upstream does not always follow a straight path.
downstream existing KOD existing KOD, check
Mach. number Sometimes a more detailed analysis and
additional problem-solving solutions are
required, and these will be discussed further.
Verify v 2 and Mach number on existing header
downstream the tie-in point Tie-in point and final disposal
design. The tie-in location choice is gen-
erally made as close to the flare stack as pos-
Review PSV orifice calculation with calculated back pressure
sible, taking into consideration whether the
existing knockout drum can handle the worst
Perform dispersion and radiation studies case vapor and liquid loads. When a PSV has
a high setpoint and the volumetric flow for
the design case is high, the Mach number at
Fig. 3 Flare system rating method workflow. the tie-in point tends to be high as well. In
these cases, having a higher backpressure at
the tie-in point can reduce the Mach num-
Table 1. Gasoline hydrotreating unit relief scenarios ber. For example, moving the tie-in point
Contingency Fire Concurrent other than fire Single contingency only upstream in the existing flare header helps
Number of PSVs involved 25 2 4
reduce the Mach number; the consequence
is a slight increase in the backpressure.
and these potentially affect the existing flare dispersion was reduced to two. Only these Fig. 4 illustrates an example of a flare
header performance. All other contingen- two scenarios had to be studied further at a system analyzer simulation with a stabilizer
cies, including fire, were unit-wide sce- plant-wide level. All other new-unit scenar- PSV that has a high set pressure with its
narios but not plant- or refinery-wide sce- ios were studied separately to size the new tie-in point in the unit’s 16 in. subheader
narios. The number of plant-wide scenarios unit main header, which in this example and in a 30-in. main header. The 30-in. tie-
that might affect existing flare backpres- was determined to be governed by one of in point resulted in high Mach numbers
sure, radiation intensity and contaminant the fire cases. while the resulting Mach numbers using the

HYDROCARBON PROCESSING February 2011


Plant safety

16 in. subheader were lower without exces-


sively elevating the PSV’s exit backpressure. Quemador 601-L
The resulting hydraulic performance for
both situations is shown in Fig. 4. 601-L
1101-16-in. C 100-RV-0001-30-in. A 1.11894/1.10724
The existing knock-out drum rating Nodo 5 Nodo 6 16 in. x 30 ft 0.109/0.110
can be performed in parallel with the flare-
header rating and later checked by the final 1101-16-in.–B Nodo 7 100-RV-0001-
simulation model. The various flare-header 30-in. AB2A
1.13374/1.12803
scenarios are loaded into the simulation 0.108/0.108
tool, and the PSV sizing and flare calcula- 610-F
tions are performed. The flare-tip pressure 1311-2-in. Tie-in 30-in. header
3400-RV-1122-14-AB2A
drop can be simulated, using the old design 2.03759/1.36906 mach 0.8
PSV BP = 2.03 bara
data and extrapolated to new loads, using a 0.445/0.808
Bernoulli Equation approximation: PSV-34026/27 PSV-34022
14.00500/ 11.53.000/2.03759
v ×ρ
2
0.445
+ P + ρ × g ×z = K
2 1101-16-in.–D
The process engineer can consider the 1.31911/1.22139
1101-16-in. C 0.360/0.394
backpressure problems that might arise Nodo 5 Nodo 6 16-in. x 30 ft
from these calculations on existing PSVs,
especially on the crude unit PSVs that have 1101-16-in.–B Nodo 7 100-RV-0001-
low pressure settings. For the new units, 30-in. AB2A
1.13373/1.12802
the project team can select the PSV types, 0.108/0.108
conventional or balanced, and purchase
these early if there are cost savings. 1311-2-in. 3400-RV-1122-14-AB2A
2.09626/1.58825 Tie-in 16-in. sub-header
The radiation intensity methods 0.430/0.624 Mach 0.6
described in API 521, a simple radiation PSV BP=2.09 bara
PSV-34026/27 PSV-34022
method, and Brzustowski and Sommer, can 14.00500/ 11.53.000/2.9626
be used to determine the radiation intensity 0.445
based on the worst case heat of combustion Fig. 4 Tie-in point diagram.10
calculations.1 Finally, the contaminant dis-
persion into the atmosphere can be calcu-
lated using the US EPA Screen 3 models.9 Table 2. Gasoline hydrotreating unit PSV changes between revisions
When to use dynamic simulation Rev. A Rev. 0
and relief considerations. The relief Project’s Month 5 Project’s Month 11
Number of PSVs API orifice Number of PSVs API orifice
load calculation is a difficult task when rat-
12 D 13 D
ing or designing a flare system. The API
521 standard gives general guidelines on 0 E 2 E
estimating relief loads but leaves the cal- 2 F 0 F
culation details to the process engineer’s 3 G 3 G
judgment. 1 This is due to the different 1 H 1 H
approaches a process engineer can take to 1 K 1 K
perform relief-load calculations.
1 P 0 P
As previously discussed, typical scenar-
ios to consider for a column are related to 1 Q 0 Q
reflux, cooling or power loss. A dynamic 0 R 2 R
modeling approach has been used and Total 21 22
documented, and it helped the engineers
gain additional insight on what happened performed for the new gasoline stabilizer, does not impact the whole flare system,
during a relief event.5 Often, this confirms resulting in a relief load of L = 2,200 Kg/ and if the pressure drop does not increase
that traditional methods are conservative, hr. This load represented a 24% reduction substantially, and there are no radiation or
allowing engineers to use reduced relief of the lowest load estimation using steady dispersion problems, then dynamic calcula-
loads while still focusing on safety. How- state calculations. tions can be avoided.
ever, dynamic simulation takes time and One way to decide when to use dynamic
tight project schedules may make it diffi- simulation and when to apply the stan- Guidelines for hydrotreating
cult to use this approach. Dynamic simula- dard steady-state calculations is to analyze unit flare analysis. Specifically for
tion benefits are clear and project teams are if the contingency being studied impacts hydrotreating units, the guidelines to rate
encouraged to consider it when the situa- the whole flare system, involving multiple and design a flare system comprise the fol-
tion requires it. units across the plant or refinery. If this lowing load calculations and possible solu-
A dynamic simulation (Fig. 5) was contingency is limited to a single unit and tions, including dynamic simulation, to

HYDROCARBON PROCESSING February 2011


Plant safety

hydrotreating unit. Dispersion constraints


are key in designing this system with con-
centration limits for SO2 that are defined
by the World Health Organization and
other local regulatory authorities.

New sweet-loads evaluation:


Hydrotreating unit reactors usually work
at high temperatures and when the system
is evaluated at opening pressure for a fire
relief, the hydrocarbon/H2 mixture usu-
ally enters in a critical flow regime. In these
cases API 521 recommends using depres-
suring systems and dry fire calculations.
The loads calculated using API dry formu-
las are very conservative. A more accurate
approach is presented by Ouderkirk.8
The new flare-header design for
hydrotreating units is often governed by
Fig. 5 Dynamic relief load calculations using a simulation model. one of these cases:
•  Depressurization loads
•  Fire loads
Table 3. Gasoil hydrotreating unit PSV changes between revisions •  Electrical failure loads (considering
that most condensers are air coolers and
Rev. A Rev. 0
Project’s Month 5 Project’s Month 11
relief loads for cooling-water failure is mini-
Number of PSVs API orifice Number of PSVs API orifice mal compared to an electrical failure).
9 D 7 D If the multiple concurrent PSV design
scenarios do not comply with the conserva-
3 E 4 E
tive API 521 radiation limits or environ-
3 F 4 F
mental regulations, it is worth calculating
4 G 4 G the relief loads using dynamic simulation.
4 H 4 H Most column relief loads can be calcu-
1 J 1 J lated with a more rigorous model, and the
0 K 0 K revised loads are used to rate the overall
1 M 1 M
flare system including recalculating the
flare main header, the radiation intensity
0 P 0 P
and the dispersion levels.
0 Q 0 Q While the rigorous models are being
0 R 0 R developed, the piping engineers might have
Total 25 25 also completed the isometrics using the first
non-rigorous simulation diameters. By the
problems that may be encountered. These tional PSVs to a balanced (bellow or pilot) time the more rigorous load calculations
guidelines include the usual analysis of type. If the existing PSVs are a balanced are being done, these final flare simulations
relief loads, but also additional consider- type, then it is advisable to perform a can be performed, putting all the pieces
ation of new acid loads, etc. dynamic analysis of the PSVs that partici- of the puzzle together (isometrics, revised
pate in that design contingency. This would multiple-contingencey loads, existing PSV
Evaluate existing loads. Determine typically involve PSVs with greater volu- pressures, etc.). This provides the most
if, for a plant-wide concurrent contingency metric loads and usually concurrent scenar- complete, accurate and rigorous analysis.
(cooling or power loss, etc.), the new relief ios involving topping columns, absorbers, If radiation intensity, back pressure or
loads added to existing loads resulted in stabilizers and FCC’s safety valves. contaminant dispersion issues cannot be
any of the following effects or conditions resolved using the methodology presented,
being violated: New acid loads. The new other alternatives may be considered:
•  Substantial backpressure changes on hydrotreating units concentrate H 2S in 1.  Perform a high-integrity pressure
existing PSVs the top vapor streams of unit operations. protection system (HIPPS) project to iden-
•  Radiation intensity at ground level Most of the H2S is extracted in an amine tify which units control the relief loads,
corresponding to API 521 radiation limits contactor and then sent to the amine and and perform a permutation analysis of the
•  Air contaminant dispersion comply- sour-water unit strippers, which then have individual relief loads by their probability
ing with EPA and local environmental the flare loads rich in H2S and NH3. If the of occurrence and determine the applicable
regulations. refinery doesn’t already have a sour-flare safety integrity level (SIL). SIL is a measure
If any of the verification steps fail, the system, then the company should con- of the reliability of a safety instrumented
solution is to change the existing conven- sider building one when adding the new system to function as designed. There are

HYDROCARBON PROCESSING February 2011


Plant safety

three possible discrete integrity levels (SIL hydrotreating units to an existing refinery •  Material capital cost savings in accu-
1, SIL 2 and SIL 3) of safety instrumented are discussed below. rate header sizing.
systems defined in terms of probability of Tables 2 and 3 show the number of •  New flare cost savings in performing
failure on demand (PFD). SIL 3 has the PSVs that changed from one type to a dif- more accurate dynamic-load calculations
highest reliability, SIL1 has the lowest. API ferent type as the project progressed. This when needed. HP
521 Fifth Edition allows you to take load resulted from the simulation model being
literature cited
credits for the use of HIPPS.1 The benefit improved as various engineering tasks 1 ANSI/API Standard 521 (ISO 23251), “Pressure-
of this approach is the avoidance of having were completed, and as the overall design relieving and Depressuring Systems,” Fifth
to build a complete new flare. The down- evolved and improved. Edition, January 2007.
side is the operational constraints on the Even though many load calculations 2 ANSI/API Standard 520, “Sizing, Selection

degree of turndown or the possibility even changed and PSV sizes were revised during and Installation of Pressure-Relieving Devices
in Refineries. Part I: Sizing and Selection,” Seventh
having to shutdown a unit to avoid over- the project, the unit’s main header diame- Edition, January 2000.
loading the flare system, and the capital ter, the tie-in point and the knockout-drum 3 K. Banjee, N. P. Cheremisinoff and P. N.

investment needed to enhance the control calculations remained unchanged between Cheremisinoff, Flare Gas Systems Pocket
systems of existing units. design revisions. Handbook, Gulf Publishing Company, 1985.
4 Kister, H. Z., “Distillation Operation,”
2.  Increase existing flare height. The This experience demonstrates that some MacGraw-Hill, Inc, Chapter 9.
radiation intensity and dispersion con- tasks can be performed in parallel. Later 5 Gruber, D., D.-U. Leipnitz, P. Seturaman,

centration at ground level will improve in the project cycle all pieces of the flare M. Alos, J. M. Nougues and M. Brodcorb,
but the support structures may have to be system can be quickly recalculated using “Are there alternatives to an expensive overhaul of
a bottlenecked flare system?, Petroleum Technology
revamped or new structures added. process simulator and flare system analysis Quarterly, Q1 2010.
3.  Change the existing main flare software. 6 Marshall, B., “Improve Flare System Design

header. Sometimes backpressure prob- to Reduce Cost and Enhance Safety,” AspenTech
lems persist in existing PSVs and the only Benefits of using this method. Webinar, November 2009.
7 Crosby, T. Pressure Relief Valve Engineering
option is to replace portions of the existing Many benefits can be obtained using the Handbook, Technical Document, May 1997.
network. Obviously, this will require addi- approach presented in this article, as vali- 8 Ouderkirk, R., “Rigorously Size Relief Valves

tional capital investment. dated by experience on several projects: for Supercritical Fluids,” CEP Magazine, August
4.  Add a gas-recovery facility. When •  Compressed project schedules by per- 2002.
9 US Environmental Protection Agency, “Guía
a dispersion analysis results in high con- forming PSV calculations and flare system del usuario del Modelo SCREEN3,” EPA454/
taminant concentration, this approach calculations in parallel. For the example B95-004, September 2000.
could partially solve the problem, but it cited previously, these calculations resulted 10 Simulation performed with Aspen Flare System

also might increase the backpressure on the in achieving a three-month reduction in Analyzer V7.1, Aspen Technology, 2009.
PSVs and increase capital cost. the project schedule.
5.  Change the flare tip. Sometimes, •  Project man-hour savings by perform-
high Mach numbers at the flare tip can be ing the appropriate level of modeling as Mayra Marchetti is a process
engineer at A. Evangelista S.A. She has
avoided by simply changing the flare tip. required by the project-specific design. The 10 years´ work experience in process
example cited represented saving 160 engi- simulation and industrial projects, with
Results obtained by applying neering man-hours of modeling time. a special focus in relief system design
and evaluation studies, revamps and new designs. She
this method. The results of applying •  Early definition of header sizing and
graduated as a chemical engineer from Buenos Aires
this approach to flare-system analysis in a the PSVs required. There may be cost sav- University and holds an MS degree in engineering man-
project involving the addition of two new ings in procuring these supplies early. agement from Florida International University.

Article copyright ©2011 by Gulf Publishing Company. All rights reserved. Printed in U.S.A.
Not to be distributed in electronic or printed form, or posted on a website, without express written permission of copyright holder.

You might also like