Date : Bill Of Quantities
MATERIAL LABOR
ITEM NO. SCOPE OF WORKS QTY UNIT TOTAL COST
3.2 Concrete
3.2.1 Portland Cement 15,650.00 bags 250.00 3,912,500.00 1,565,000.00 5,477,500.00
3.2.1 Coarsand 750.00 cu.m 750.00 562,500.00 225,000.00 787,500.00
3.2.1 Gravel Y-Y 1,650.00 cu.m 1,000.00 1,650,000.00 660,000.00 2,310,000.00
3.3 Miscillanous
3.3.1 No. 16 tie wire 50.00 rolls 1,950.00 97,500.00 39,000.00 136,500.00
3.3.2 Common nails 50.00 kl 1,625.00 81,250.00 32,500.00 113,750.00
3.3 Masonry
3.3.2 6" CHB 15,756.00 pcs 35.00 551,460.00 220,584.00 772,044.00