Excavation Units

Total Scope 50000


Duration (Months) 3
Disposal 1 km lead
Avg Excavation per Day (cu m) 641.0256410256 cu m
Accounting for Peak Excavation
(25% more) (cu m) 801.2820512821 cu m

Type of Plant and Equipment Excavator, 50 cu m/h, 10 hours working


Tipper 6 cu m capacity
No. of Excavators 2
Computation of no. of Tippers
Loading Time for Excavator (7
buckets*1.2 min) 8.4
Travel Time to Cover 1 km * 2 at 15
k/h 8
Tipping Time (min) 1
Turning Time (min) 3
Total Time Reqd per Cycle (min) 20.4
No. of Tippers Reqd. for 1
Excavator 2.4285714286
No. of Tippers Reqd. for 2
Excavator 4.8571428571

Equipment Owning Cost


Hire Charges
Description No. (Rs./Month) Months
Excavator 2 125000 5
Tippers 5 50000 5

Operating Fuel and Power for Equipment


Description No. Months Days
Excavator 2 3 26
Tippers 5 3 26
Total
1250000
1250000

Hours Fuel/Power Cost O&L Amount


10 131 38 1.3 10095384
10 51 38 1.3 9825660