Professional Documents
Culture Documents
Rab Kosan
Rab Kosan
Jumlah 4,470,940,472.00
DIBULATKAN 4,470,900,000.00
A. PEKERJAAN PERSIAPAN
1 Pembersihan lapangan Sebelum dan sesudah proyek M² 800.00 150,000 120,000,000.00
2 Papan nama proyek Identitas Blok dan Nama unit 1.00 450,000 450,000.00
3 Direksi keet dan gudang Uk. 4x8 m' M² 32.00 367,650 11,764,800.00
4 Air kerja Pompa tangan Ls 1.00 3,500,000 3,500,000.00
5 Listrik kerja 1300 watt Ls 1.00 3,000,000 3,000,000.00
6 Bauwplank Keliling lahan M' 124.00 25,070 3,108,680.00
TOTAL 141,823,480.00
B. PEKERJAAN TANAH
1 Galian Pondasi M³ 181.44 89,028 16,153,240.32
2 Urugan tanah pondasi Urug kembali dari sisa galian M³ 46.80 20,680 967,824.00
3 Urugan pasir bawah pondasi tebal = 5 cm M³ 3.80 66,000 250,800.00
4 Urugan pasir bawah lantai tebal = 5 cm M³ 31.96 66,000 2,109,360.00
5 Pemadatan tanah Pondasi M² 64.20 15,000 963,000.00
6 Pemadatan tanah lantai M² 667.50 15,000 10,012,500.00
TOTAL 30,456,724.32
C. PEKERJAAN PONDASI
1 Cerucuk Gelam Ttk 560.00 10,000 5,600,000.00
2 Pondasi Tapak Uk.150/150, 80 x 80 M³ 26.20 2,544,946 66,677,588.96
3 Balok Sloof Uk.20/30, 15/25 cm M³ 38.80 4,842,484 187,888,363.35
4 Lantai kerja bawah pondasi T = 5 cm M³ 7.80 721,312 5,626,233.60
5 Pondasi rollag bata M² 626.00 90,900 56,903,274.80
TOTAL 322,695,460.71
G. Pekerjaan Plafond
1 Plafond Gypsum + Rangka Metal Elephant Rangka Metal Furing Aplus M² 1,720.20 150,010 258,047,202.00
2 Man hole M² 45.00 25,000 1,125,000.00
TOTAL 259,172,202.00
K. Pekerjaan Pengecatan
1 Cat dinding dalam M² 2,970.20 71,060 211,062,412.00
2 Cat dinding luar M² 1,727.00 81,060 139,990,620.00
3 Cat listplank M' 20.60 81,060 1,669,836.00
TOTAL 352,722,868.00
L. Pekerjaan listrik
1 Instalasi titik lampu Kabel Praba Ttk 400.00 125,000 50,000,000.00
Fitting lampu downlight Ttk 300.00 35,000 10,500,000.00
2 Instalasi Stop kontak Kabel Praba Ttk 200.00 125,000 25,000,000.00
Stop kontak Gracio 4151-55 white Ex. Broco Ttk 200.00 14,410 2,882,000.00
3 Saklar tunggal Gracio 4161-55 white Ex. Broco Bh 60.00 13,580 814,800.00
4 Saklar double Gracio 4162-55 white Ex. Broco Bh 180.00 19,580 3,524,400.00
5 Saklar hotel Gracio 4163-55 white Ex. Broco Bh 40.00 19,430 777,200.00
6 Panel box/Sekering 2 group MG Domae Unit 50.00 42,500 2,125,000.00
7 Panel box/Sekering 12 group MG Domae Unit 20.00 85,000 1,700,000.00
8 Instalasi TV Ttk 45.00 175,000 7,875,000.00
Outlet TV Gracio 4183-55 white Ex.Broco Ttk 45.00 41,450 1,865,250.00
9 Instalasi Telepon Ttk 45.00 155,000 6,975,000.00
Outlet Telpon Gracio 4171-55 white Ex. Broco Ttk 45.00 57,310 2,578,950.00
10 Instalasi lampu dinding Bh 40.00 125,000 5,000,000.00
11 Sparing SR Bh 40.00 20,000 800,000.00
12 Kabel tuvur NYY 4x10 mm +pipa PVC M' 40.00 47,500 1,900,000.00
13 Penagkal Petir Bc 35 mm + 2 bh split Ttk 2.00 4,500,000 9,000,000.00
14 Arde/pentanahan Maks 2 ohm, Kabel BC 6 mm+GIP ø1/2” Unit 2.00 2,500,000 5,000,000.00
RENCANA ANGGARAN BIAYA
JOHN KOS HARIAN & BULANAN
N. Pekerjaan Tambahan
1 Pek Foot plat Uk. 50x50x12 mm M³ 2.03 4,842,484 9,830,241.69
2 Pek Grountank Kap 1m3 + inst unit 8.00 3,500,000 28,000,000.00
3 Pek Cat plafond M² 1,720.20 71,060 122,237,412.00
TOTAL 160,067,653.69
SUBTOTAL 4,470,940,472.00
Dibulatkan 4,470,900,000.00
2 URUGAN TANAH m3
Tanah urug m3 1.200 45,000.00 54,000.00
Pekerja org 0.250 80,000.00 20,000.00
Mandor org 0.010 100,000.00 1,000.00
Alat bantu ls 1.000 1,200.00 1,200.00
Jumlah Harga 22,200.00 54,000.00
Total Harga 76,200.00
21 Plat beton t= 12 cm m3
Beton cor m3 1.000 696,500.00 696,500.00
Besi beton terpasang kg 124.952 9,120.00 1,139,558.70
Bekisting m2 8.333 75,388.19 628,234.95
Stutwerk m2 8.333 87,990.00
Upah cor m2 1.000 189,000.00 189,000.00
Upah pembesian kg 124.952 1,601.27 200,081.58
Upah Bekisting m2 8.333 30,600.00 255,000.00
Upah stutwerk m2 8.333 25,850.00 215,416.67
Jumlah Harga 859,498.25 2,464,293.65
Total Harga 3,323,791.90
TOTAL HARGA
NO URAIAN PEKERJAAN VOL. SAT HARGA SATUAN UPAH BAHAN TOTAL HARGA
( Rp) ( Rp)
22 Plat beton t= 10 cm m3
Beton cor m3 1.000 696,500.00 696,500.00
Besi beton terpasang kg 124.952 9,120.00 1,139,558.70
Bekisting m2 10.000 75,388.19 753,881.94
Stutwerk m2 10.000 87,990.00
Upah cor m2 10.000 189,000.00 1,890,000.00
Upah pembesian kg 124.952 1,601.27 200,081.58
Upah Bekisting m2 10.000 30,600.00 306,000.00
Upah stutwerk m2 10.000 25,850.00 258,500.00
Jumlah Harga 2,654,581.58 2,589,940.64
Total Harga 5,244,522.23
23 PASANGAN BATA 1 : 2 m2
Bata merah bh 50.000 500.00 25,000.00
PC (50 kg) zak 0.544 52,000.00 28,288.00
Pasir pasang m3 0.047 70,000.00 3,290.00
Pekerja org 0.429 80,000.00 34,320.00
Tukang org 0.214 90,000.00 19,260.00
Kepala tukang batu org 0.021 100,000.00 2,100.00
Mandor org 0.011 100,000.00 1,100.00
Jumlah Harga 56,780.00 56,578.00
Total Harga 113,358.00
24 PASANGAN BATA 1 : 5 m2
Bata merah bh 50.000 500.00 25,000.00
PC (50 kg) zak 0.335 52,000.00 17,440.80
Pasir pasang m3 0.058 70,000.00 4,060.00
Pekerja org 0.322 80,000.00 25,744.00
Tukang org 0.181 90,000.00 16,245.00
Kepala tukang batu org 0.016 100,000.00 1,580.00
Mandor org 0.008 100,000.00 830.00
Jumlah Harga 44,399.00 46,500.80
Total Harga 90,899.80
25 PLESTERAN 1 : 2 + ACIAN m2
PC (50 kg) zak 0.237 52,000.00 12,313.60
Pasir pasang m3 0.019 70,000.00 1,330.00
Pekerja org 0.286 80,000.00 22,880.00
Tukang org 0.214 90,000.00 19,260.00
Kepala tukang batu org 0.021 100,000.00 2,100.00
Mandor org 0.020 100,000.00 2,000.00
Jumlah Harga 46,240.00 13,643.60
Total Harga 59,883.60
26 PLESTERAN 1 : 5 + ACIAN m2
PC (50 kg) zak 0.140 52,000.00 7,300.80
Pasir pasang m3 0.019 70,000.00 1,330.00
Pekerja org 0.286 80,000.00 22,880.00
Tukang org 0.214 90,000.00 19,260.00
Kepala tukang batu org 0.021 100,000.00 2,100.00
Mandor org 0.020 100,000.00 2,000.00
Jumlah Harga 46,240.00 8,630.80
Total Harga 54,870.80
36 CAT PLAFOND m2
Cat tembok m2 1.000 11,500.00 11,500.00
Rol cat bh 0.010 70,000.00 700.00
Amplas lbr 0.500 3,500.00 1,750.00
Steger ls 1.000 25,000.00 25,000.00
Pekerja org 0.104 80,000.00 8,320.00
Tukang org 0.182 90,000.00 16,380.00
Mandor org 0.065 50,000.00 3,250.00
Jumlah Harga 27,950.00 38,950.00
Total Harga 66,900.00
37 CAT BESI m2
Meni besi kg 0.167 17,500.00 2,922.50
Cat besi/kayu Sive kg 0.200 66,500.00 13,300.00
Amplas kg 0.400 3,500.00 1,400.00
Thiner A kg 0.150 40,000.00 6,000.00
Kuas kg 0.050 4,000.00 200.00
Pekerja org 0.200 80,000.00 16,000.00
Tukang org 0.300 90,000.00 27,000.00
Mandor org 0.010 50,000.00 500.00
Jumlah Harga 43,500.00 23,822.50
Total Harga 67,322.50
38 CAT KAYU m2
Meni kayu kg 0.167 22,000.00 3,674.00
Dempul kayu kg 0.083 22,000.00 1,826.00
Cat besi/kayu Sive kg 0.200 66,500.00 13,300.00
Amplas kayu kg 0.400 3,500.00 1,400.00
Thiner A kg 0.150 40,000.00 6,000.00
Kuas kg 0.050 4,000.00 200.00
Pekerja org 0.200 80,000.00 16,000.00
Tukang org 0.300 90,000.00 27,000.00
Mandor org 0.010 50,000.00 500.00
Jumlah Harga 43,500.00 26,400.00
Total Harga 69,900.00
I TENAGA KERJA
1 Pekerja orang/hari 80,000.00
2 Tukang orang/hari 90,000.00
3 Kepala tukang orang/hari 100,000.00
4 Tukang bongkar orang/hari 50,000.00
5 Mandor orang/hari 100,000.00
II MATERIAL
1 Bata merah bh 500.00 500.00
2 Batu koral & kerikil m3 320,000.00 320,000.00
3 Pasir beton m3 55,000.00 55,000.00
4 Pasir pasang m3 70,000.00 70,000.00
5 Pasir urug m3 37,500.00 37,500.00
6 Tanah urug m3 45,000.00 45,000.00
7 Beton Readymix K. 225 m3 620,000.00 620,000.00
8 Concret Pump m3 26,500.00 26,500.00
9 PC (50 kg) zak 52,000.00 52,000.00
10 Semen warna kg 2,850.00 2,850.00
11 Kayu kls III m3 1,950,000.00 1,950,000.00
12 Pintu Fibre galss MORIKO unit 244,750.00 244,750.00
13 Alluminium Foil m2 21,000.00 21,000.00
14 Bak air Fibre bh 210,000.00 210,000.00
15 Triplek 3 mm kpg 40,000.00 40,000.00
16 Multiplek 9 mm lbr 98,750.00 98,750.00
17 Seng BJLS 7 kk lbr 42,000.00 42,000.00
18 Atap Genteng Flat stone ex CP m2 4,100.00 2,000.00 6,100.00
19 Nok Genteng Plat stone ex CP bh 5,250.00 2,000.00 7,250.00
20 Nok Ujung Plat stone ex CP bh 24,350.00 2,000.00 26,350.00
21 Nok Segitiga Plat stone ex CP bh 24,350.00 2,000.00 26,350.00
22 Gypsum board 9 mm m2 77,500.00 77,500.00
23 GRC 6 mm lbr 82,500.00 82,500.00
24 Metal furing Aplus m2 9,500.00 9,500.00
25 Keramik Lantai 40 x 40 ex Roman dos 63,000.00 7,200.00 70,200.00
26 Keramik Lantai 30 x 30 ex Roman dos 58,800.00 6,400.00 65,200.00
27 Keramik Lantai 20 x 20 ex Roman dos 53,900.00 6,000.00 59,900.00
28 Keramik Dinding 20 x 20 ex Roman dos 48,000.00 6,000.00 54,000.00
29 Step nosing keramik bh 8,300.00 8,300.00
30 Besi beton kg 7,000.00 7,000.00
31 Kawat beton kg 10,800.00 10,800.00
32 Paku 2" kg 15,000.00 15,000.00
33 Paku 5" kg 15,000.00 15,000.00
34 Paku beton 3/4" kg 13,000.00 13,000.00
35 Septictank Biofil unit 2,500,000.00 200,000.00 2,700,000.00
36 Amplas lbr 3,500.00 3,500.00
37 Amplas kayu lbr 2,500.00 2,500.00
38 Cat lisplank Ex Prima shield m2 21,500.00 21,500.00
39 Cat tembok dalam Ex Rumalux m2 11,500.00 11,500.00
40 Cat tembok luar Ex Prima shield m2 21,500.00 21,500.00
41 Waterprofing m2 23,500.00 23,500.00
42 Dempul kayu kg 16,000.00 16,000.00
43 Kuas bh 4,000.00 4,000.00
44 Meni besi kg 17,500.00 17,500.00
SATUAN HARGA SAT. ONGKOS TOTAL HRG
NO URAIAN
(Rp.) KIRIM BAHAN ( Rp. )
45 Minyak cat kg 11,500.00 11,500.00
46 Plamur dinding / plafond kg 26,000.00 26,000.00
47 Rol cat ltr 70,000.00 70,000.00
48 Sincromat kg 25,000.00 25,000.00
49 Meni kayu kg 22,000.00 22,000.00
50 Thiner A ltr 40,000.00 40,000.00
51 Pas. closet duduk Granada 3000 CCST unit 1,563,000.00 1,563,000.00
52 Kran air tembok IN 361A Ex Am Sat unit 113,000.00 113,000.00
53 Floor drain IR 23 N Ex American standar unit 175,000.00 175,000.00
54 Roof drain Steinlees unit 75,000.00 75,000.00
55 Tempat sabun AAR 3A6 Ex Amstand unit 47,250.00 47,250.00
56 Pipa PVC dia. 1/2" Wavin AW + acc btg 15,000.00 15,000.00
57 Pipa PVC dia. 3/4" Wavin AW + acc btg 20,000.00 20,000.00
58 Pipa PVC dia. 1" Wavin AW +acc btg 30,000.00 30,000.00
59 Pipa PVC dia. 1 1/4" Wavin AW +acc btg 40,000.00 40,000.00
60 Pipa PVC dia. 1,5" Wavin D + acc btg 30,000.00 30,000.00
61 Pipa PVC dia. 2" Wavin D + acc btg 40,000.00 40,000.00
62 Pipa PVC dia. 2,5" Wavin D + acc btg 50,000.00 50,000.00
63 Pipa PVC dia. 3" Wavin D btg 72,500.00 72,500.00
64 Pipa PVC dia. 4" Wavin D btg 90,000.00 90,000.00
65 Instalasi titi lampu ttk 125,000.00 125,000.00
66 Instalasi TV ttk 175,000.00 175,000.00
67 Instalasi Telepon ttk 155,000.00 155,000.00
68 Saklar tunggal ex Broco bh 13,580.00 13,580.00
69 Saklar ganda ex Broco bh 19,580.00 19,580.00
70 Saklar hotel ex Broco bh 19,430.00 19,430.00
71 Stop Kontak ex Broco bh 14,410.00 14,410.00
72 Panel box seering 8 group MG Domae unit 42,500.00 42,500.00
73 Panel box seering 12 group MG Domae unit 85,000.00 85,000.00
74 Outlet TV bh 41,450.00 41,450.00
75 Outlet Telepon bh 57,310.00 57,310.00
76 Kabel tuvur NYY 4x10 + pipa sparing m' 47,500.00 47,500.00