DESAGREGADO DE PROPUEST

"SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA - QUEROBA

PUENTE 01 PUENTE 02 PUENTE 03

ITEM DESCRIPCION DE ACTIVIDADES UNIDAD CHANQUIL VISCACHAYOC CHALCO

15+266 18+242 28+000

01.00.00 PLAN DE TRABAJO GLB 4,580.00 4,580.00 4,580.00

02.00.00 TRABAJOS PRELIMINARES GLB 6,250.00 6,250.00 6,250.00

03.00.00 DEMOLICION DE ESTRUCTURA EXISTEN GLB 3,150.00 3,150.00 3,150.00

04.00.00 SUBESTRUCTURA GLB 15,800.00 15,800.00 15,800.00

05.00.00 TRANSPORTE DE ESTRUCTURA METALI GLB 8,500.00 8,500.00 8,500.00

06.00.00 MONTAJE DE ESTRUCTURA DE PUENTES GLB 8,020.00 8,020.00 8,020.00

07.00.00 ACCESOS GLB 8,010.34 5,447.13 10,412.05

08.00.00 SEÑALIZACION Y SEGURIDAD VIAL GLB 21,450.00 21,450.00 21,450.00

09.00.00 VARIOS GLB 10,053.11 10,053.11 10,053.11

10.00.00 DESMOVILIZACION GLB 1,830.50 1,830.50 1,830.50

11.00.00 INFORME FINAL GLB 1,418.62 1,418.62 1,418.62

TOTAL COSTO DIRECTO 89,062.57 86,499.36 91,464.28


GASTOS GENERALES 31% 27,923.36 27,119.73 28,676.36

UTILIDAD 5% 4,141.41 4,022.22 4,253.09

SUBTOTAL 121,127.34 117,641.31 124,393.73

IGV 18% 21,802.92 21,175.44 22,390.87

COSTO TOTAL DEL PROYECTO ### ### ###


DO DE PROPUESTA ECONOMICA
ANDAMARCA - QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO I"

PUENTE 04 PUENTE 05 PUENTE 06 PUENTE 07 PUENTE 08 PUENTE 09 PUENTE 10

CHACAMAYO MACRO PAMPAS CHECCOSNO VIZCAS PUMAHUASI PACHAYA

31+080 49+515 54+000 292+475 297+200 326+125 324+360

4,580.00 4,580.00 4,580.00 4,580.00 4,580.00 4,580.00 4,580.00

6,250.00 6,250.00 6,250.00 6,250.00 6,250.00 6,250.00 6,250.00

3,150.00 3,150.00 32,500.00 3,150.00 3,150.00 3,150.00 3,150.00

15,800.00 15,800.00 152,000.00 105,000.00 105,000.00 105,000.00 105,000.00

8,500.00 8,500.00 222,000.00 8,500.00 8,500.00 8,500.00 8,500.00

8,020.00 8,020.00 241,101.00 8,020.00 8,020.00 8,020.00 8,020.00

4,277.97 1,170.40 1,170.40 15,000.00 28,000.00 24,000.00 24,000.00

21,450.00 21,450.00 21,450.00 21,450.00 21,450.00 21,450.00 21,450.00

10,053.11 10,053.11 13,823.81 10,053.11 10,053.11 10,053.11 10,053.11

1,830.50 11,297.24 11,297.24 1,830.50 1,830.50 1,830.50 1,830.50

1,418.62 1,418.62 1,418.62 1,418.62 1,418.62 1,418.62 1,418.62

85,330.20 91,689.37 707,591.07 185,252.23 198,252.23 194,252.23 194,252.23


26,753.17 28,746.93 221,847.66 58,081.25 62,157.08 60,902.98 60,902.98

3,967.85 4,263.56 32,902.98 8,614.23 9,218.73 9,032.73 9,032.73

116,051.23 124,699.86 962,341.72 251,947.71 269,628.04 264,187.94 264,187.94

20,889.22 22,445.97 173,221.51 45,350.59 48,533.05 47,553.83 47,553.83

### ### ### ### ### ### ###


UCHO I"

TOTAL

45,800.00

62,500.00

60,850.00

651,000.00

298,500.00

313,281.00

121,488.29

214,500.00

104,301.80

37,238.48

14,186.20

1,923,645.77
603,111.51

89,449.53

2,616,206.81

470,917.23

###
PROPUESTA ECONOMICA PARA LA INSTALACION DE PUENTES AYAC

P.U P1 P2
METRADO
ITEM ACTIVIDADES UND CHANQUIL VISCACHAYOC
TOTAL L - 12.19 L - 12.19
2 TRABAJOS PRELIMINARES 4,120.00 4,120.00
2.01 MOVILIZACION DE EQUIPO Y HERRAMIENTAS glb 0.60 10,000.00 0.10 1,000.00 0.10 1,000.00
2.02 DESBROCE Y LIMPIEZA DE LA ZONA DE TRABAJO ha 0.36 2,000.00 0.06 120.00 0.06 120.00
2.03 HABILITADO DE PASE PROVISIONAL ml 600.00 30.00 100.00 3,000.00 100.00 3,000.00
3 DEMOLICION DE ESTRUCTURAS EXISTENTE 1,260.00 1,260.00
3.01 DEMOLICION DE ESTRUCTURAS DE CONCRETO M3 361.65 80.00 15.75 1,260.00 15.75 1,260.00
3.02 DESMONTAJE DE BARANDAS METALICA ML 289.50 70.00 - - - -
4 SUBESTRUCTURA - 22,246.40 22,246.40
4.01 EXCAVACION EN MATERIAL SUELTO (bajo Agua) M3 - 10.00 - - - -
4.02 EXCAVACION EN MATERIAL SUELTO ( en seco) M3 179.56 15.00 37.80 567.00 37.80 567.00
4.03 DEMOLICION DE ESTRUCTURAS DE CONCRETO M3 22.40 90.00 - - - -
4.04 PERFORACION E INSTALACION DE DOWELS UND 195.00 20.00 - - - -
4.05 PUENTE DE ADHERENCIA M2 19.83 100.00 - - - -
ENCOFRADO Y DESENCOFRADO CARA NO VISTA (bajo
4.06 M2 - 45.00 - - - -
agua)
ENCOFRADO Y DESENCOFRADO CARA NO VISTA (En
4.07 M2 305.74 35.00 69.24 2,423.40 69.24 2,423.40
Seco)
4.08 ENCOFRADO Y DESENCOFRADO CARAVISTA (Seco) M2 141.36 50.00 22.64 1,132.00 22.64 1,132.00
4.09 ACERO fy= 4200 kg/cm2 GRADO 60 KG 11,645.60 4.50 389.60 1,753.20 389.60 1,753.20
4.1 CONCRETO fc= 100 Kg/cm2 (solado) M3 - 200.00 - - - -
4.11 CONCRETO fc= 140 Kg/cm2 + 30%PG M3 182.40 300.00 45.60 13,680.00 45.60 13,680.00
4.12 CONCRETO fc= 210 Kg/cm2 (bajo agua) M3 - 450.00 - - - -
4.13 CONCRETO fc= 210 Kg/cm2 M3 145.57 400.00 4.87 1,948.00 4.87 1,948.00
RELLENO COMPACTADO CON MATERIAL
4.14 M3 68.80 30.00 12.16 364.80 12.16 364.80
SELECCIONADO
ELIMINACION DE MATERIAL EXCEDENTE DE KM-
4.15 201.96 10.00 37.80 378.00 37.80 378.00
EXCAVACION m3
5 TRANSPORTE DE ESTRUCTURA METALICA 5,478.00 5,478.00
TRANSPORTE DE ESTRUCTURA METALICA, LIMA -
5.01 ton 584.63 240.00 19.41 4,658.40 19.41 4,658.40
OBRA
TRANSPORTE DE NARIZ DE LANZAMIENTO, LIMA -
5.02 ton 27.70 240.00 1.54 369.60 1.54 369.60
OBRA
5.03 TRANSPORTE DE NARIZ DE LANZAMIENTO EN OBRA ton 25.00 100.00 4.50 450.00 4.50 450.00
6 MONTAJE DE ESTRUCTURA DE PUENTE 7,664.00 7,664.00
6.01 MONTAJE LANZAMIENTO DE ESTRUCTURA METALICA ton 330.83 400.00 15.41 6,164.00 15.41 6,164.00
6.02 DISPOSITIVO DE APOYO glb 6.00 1,500.00 1.00 1,500.00 1.00 1,500.00
7 ACCESOS 4,368.00 3,513.00
7.01 COFORMACION DE TERRAPLENES m3 430.95 30.00 117.00 3,510.00 96.20 2,886.00
7.02 AFIRMADO (e=020m) m3 143.00 30.00 28.60 858.00 20.90 627.00
8 SEÑALIZACION Y SEGURIDAD VIAL 2,000.00 2,000.00
8.01 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL mes 12.00 1,000.00 2.00 2,000.00 2.00 2,000.00
9 VARIOS 11,937.33 11,187.33
9.01 LOSA DE APROXIMACION 8,548.33 8,548.33
9.01.01 CONCRETO f'c=100 kg/cm2 (Solado) M3 12.00 200.00 2.00 400.00 2.00 400.00
9.01.02 CONCRETO f'c=210 kg/cm2 M3 61.14 400.00 9.56 3,824.00 9.56 3,824.00
9.01.03 ENCOFRADO Y DESENCOFRADO M3 64.16 35.00 10.40 364.00 10.40 364.00
9.01.04 ACERO fy= 4200 kg/cm2 GRADO 60 KG 4,860.90 4.50 758.74 3,414.33 758.74 3,414.33
9.01.05 ANGULO DE PROTECCION DE PARAPETOS ML 56.40 65.00 8.40 546.00 8.40 546.00
9.02 MURO CONTRAIMPACTO 1,139.00 1,139.00
9.02.01 CONCRETO f'c=210 kg/cm2 M3 9.00 400.00 1.50 600.00 1.50 600.00
9.02.02 ENCOFRADO Y DESENCOFRADO M3 74.40 35.00 12.40 434.00 12.40 434.00
9.02.03 PINTURA KG 31.50 20.00 5.25 105.00 5.25 105.00
9.03 OTROS 2,250.00 1,500.00
9.03.01 TUBERIA DE DRENAJE DE 3" UND - 20.00 - - - -
9.03.02 ENCAUZAMIENTO M3 750.00 15.00 150.00 2,250.00 100.00 1,500.00
10 DESMOVILIZACION 1,169.60 1,169.60
10.01 DESMOVILIZACION DE EQUIPOS glb 0.60 8,000.00 0.10 800.00 0.10 800.00
10.02 TRANSPORTE DE ESTRUCTURA DESMONTADAS ton 13.50 240.00 - - - -
10.03 TRANSPORTE DE NARIZ DE LANZAMIENTO, OBRA-LIMA ton 27.70 240.00 1.54 369.60 1.54 369.60

TOTAL COSTO DIRECTO 60,243.33 58,638.33


GASTOS GENERALES
SUB TOTAL
IGV
TOTAL PRESUPUESTO
TES AYACUCHO PAQUETE 01

P3 P4 P5 P6

CHALCO CHACAMAYO MACRO PAMPAS PARCIAL

L - 12.19 L - 12.19 L - 21.34 L - 140.21


4,120.00 4,120.00 4,120.00 4,120.00 24,720.00
0.10 1,000.00 0.10 1,000.00 0.10 1,000.00 0.10 1,000.00 6,000.00
0.06 120.00 0.06 120.00 0.06 120.00 0.06 120.00 720.00
100.00 3,000.00 100.00 3,000.00 100.00 3,000.00 100.00 3,000.00 18,000.00
1,260.00 1,260.00 2,205.00 41,952.00 49,197.00
15.75 1,260.00 15.75 1,260.00 15.75 1,260.00 282.90 22,632.00 28,932.00
- - - - 13.50 945.00 276.00 19,320.00 20,265.00
22,246.40 22,246.40 7,973.50 100,839.00 197,798.10
- - - - - - - - -
37.80 567.00 37.80 567.00 14.18 212.70 14.18 212.70 2,693.40
- - - - 4.20 378.00 18.20 1,638.00 2,016.00
- - - - 60.00 1,200.00 135.00 2,700.00 3,900.00
- - - - 4.56 456.00 15.27 1,527.00 1,983.00
- - - - - - - - -
69.24 2,423.40 69.24 2,423.40 11.64 407.40 17.14 599.90 10,700.90
22.64 1,132.00 22.64 1,132.00 22.64 1,132.00 28.16 1,408.00 7,068.00
389.60 1,753.20 389.60 1,753.20 389.60 1,753.20 9,697.60 43,639.20 52,405.20
- - - - - - - - -
45.60 13,680.00 45.60 13,680.00 - - - - 54,720.00
- - - - - - - - -
4.87 1,948.00 4.87 1,948.00 4.87 1,948.00 121.22 48,488.00 58,228.00
12.16 364.80 12.16 364.80 10.08 302.40 10.08 302.40 2,064.00
37.80 378.00 37.80 378.00 18.38 183.80 32.38 323.80 2,019.60
5,478.00 5,478.00 8,336.80 119,210.40 149,459.20
19.41 4,658.40 19.41 4,658.40 30.28 7,267.20 476.71 114,410.40 140,311.20
1.54 369.60 1.54 369.60 1.54 369.60 20.00 4,800.00 6,648.00
4.50 450.00 4.50 450.00 7.00 700.00 - - 2,500.00
7,664.00 7,664.00 13,612.00 97,064.00 141,332.00
15.41 6,164.00 15.41 6,164.00 30.28 12,112.00 238.91 95,564.00 132,332.00
1.00 1,500.00 1.00 1,500.00 1.00 1,500.00 1.00 1,500.00 9,000.00
5,668.50 2,349.00 660.00 660.00 17,218.50
159.25 4,777.50 58.50 1,755.00 - - - - 12,928.50
29.70 891.00 19.80 594.00 22.00 660.00 22.00 660.00 4,290.00
2,000.00 2,000.00 2,000.00 2,000.00 12,000.00
2.00 2,000.00 2.00 2,000.00 2.00 2,000.00 2.00 2,000.00 12,000.00
11,187.33 11,187.33 11,937.33 15,289.00 72,725.65
8,548.33 8,548.33 8,548.33 11,900.00 54,641.65
2.00 400.00 2.00 400.00 2.00 400.00 2.00 400.00 2,400.00
9.56 3,824.00 9.56 3,824.00 9.56 3,824.00 13.34 5,336.00 24,456.00
10.40 364.00 10.40 364.00 10.40 364.00 12.16 425.60 2,245.60
758.74 3,414.33 758.74 3,414.33 758.74 3,414.33 1,067.20 4,802.40 21,874.05
8.40 546.00 8.40 546.00 8.40 546.00 14.40 936.00 3,666.00
1,139.00 1,139.00 1,139.00 1,139.00 6,834.00
1.50 600.00 1.50 600.00 1.50 600.00 1.50 600.00 3,600.00
12.40 434.00 12.40 434.00 12.40 434.00 12.40 434.00 2,604.00
5.25 105.00 5.25 105.00 5.25 105.00 5.25 105.00 630.00
1,500.00 1,500.00 2,250.00 2,250.00 11,250.00
- - - - - - - - -
100.00 1,500.00 100.00 1,500.00 150.00 2,250.00 150.00 2,250.00 11,250.00
1,169.60 1,169.60 4,409.60 5,600.00 14,688.00
0.10 800.00 0.10 800.00 0.10 800.00 0.10 800.00 4,800.00
- - - - 13.50 3,240.00 - - 3,240.00
1.54 369.60 1.54 369.60 1.54 369.60 20.00 4,800.00 6,648.00

60,793.83 57,474.33 55,254.23 386,734.40 679,138.45


106,918.64
786,057.09
141,490.28
927,547.37
DETALLE DE LA ELABORACI
SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA - Q

A
A.1

A.2

A.3

A.4
B
B.1

B.2

C
C.1
C.2

D
DETALLE DE LA ELABORACION DE PL
ERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA - QUEROBAMBA

CONCEPTO

SUELDOS Y SALARIOS
PERSONAL PROFESIONAL
Ing.Especialista Estructural
Ing. Especialista en Geotecnia
PERSONAL TÉCNICO
Topografo
Asistente tecnico (CAD)
Tecnico en Laboratorio
PERSONAL AUXILIIAR DE SERVICIOS
Ayudante de Laboratorio (zona)
Ayudante de Topografía (zona)
BENEFICIOS SOCIALES
ALQUILERES Y SERVICIOS
ALQUILER DE OFICINAS / EQ. TOPOGRAFICOS / LABORATORIO
Alquiler y mantenimiento de Oficina equipada
Alquiler y mantenimiento de vivienda equipada
Equipo de Computación; incluye impresora
Equipo de Topografía (nivel, GPS,, Estación Total)
Servicio de Laboratorio (Mezclas Suelo, etc)
Camioneta 4*4 (Incluido Operador, Combustible y Seguros)
Camioneta (Tipo Van ) para transporte de personal (incluido Operador, Combustibl
OTROS
Comunicaciones
MOVILIZACIÓN Y APOYO LOGISTICO
MOVILIZACIÓN Y APOYO LOGISTICO
Pasaje Lima-Obra-Lima (Profesionales) (ida y Vuelta)
ALIMENTACIÓN
Profesionales
Técnicos
MATERIALES Y UTILES DE OFICINA
Materiales fungibles de oficina dibujo, etc.
Copias, reproducciones, anillados, etc.

TOTAL COSTO DIRECTO (A+B+C+D)


ACION DE PLAN DE TRABAJO
A - QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO

PLAZO DE EJECUCION 1 (MESES): 0.83 (MESES)


UNID # VECES CANT. P.U. S/ PARCIAL S/ TOTAL

S/ 35,245.95
14,525.00
Mes 1.000 0.830 ### 8,715.00
Mes 1.000 0.830 7,000.00 5,810.00
4,897.00
Mes 1.000 0.830 2,500.00 2,075.00
Mes 1.000 0.830 1,700.00 1,411.00
Mes 1.000 0.830 1,700.00 1,411.00
4,233.00
Mes 1.000 0.830 1,700.00 1,411.00
Mes 2.000 0.830 1,700.00 2,822.00
% 1.000 49.00% 23,655.00 11,590.95
S/ 8,673.50
8,424.50
Mes 1.000 0.830 550.00 456.50
Mes 1.000 0.830 550.00 456.50
Mes 2.000 0.830 450.00 747.00
Mes 1.000 0.830 500.00 415.00
Mes 1.000 0.830 450.00 373.50
Mes 1.000 0.830 3,600.00 2,988.00
Mes 1.000 0.830 3,600.00 2,988.00
249.00
Mes 1.000 0.830 300.00 249.00
S/ 700.51
102.91
Pasaj 1.00 1.000 102.91 102.91
597.60
Mes 3.00 0.830 80.00 199.20
Mes 6.00 0.830 80.00 398.40
S/ 1,180.04
Mes 1.00 0.830 885.00 734.55
Mes 1.00 0.830 536.74 445.49

S/ 45,800.00
DETALLE DE LOS GAST
RVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA - QUE

1.- GASTOS GENERALES FIJOS


A

2.- GASTOS GENERALES VARIABLES

A
A.1

A.2
A.3

A.4

A.5

B
B.1

B.2

C
C.1

C.2
D

TOTAL COSTO DIRECTO (1 + 2)


DETALLE DE LOS GASTOS GE
ENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA - QUEROBAMB

CONCEPTO

1.- GASTOS GENERALES FIJOS


OFICINA PRINCIPAL Y MATERIALES
Gerente
Coordinador de Obra
Asesoria Legal
Secretaria
Beneficios Sociales
Alquiler de Oficina
Mantenimiento, Copias, Comunicación
Utiles y Materiales Fungibles
GASTOS FINANCIEROS
Gastos de Fiel Cumplimiento
Garantía del Adelanto Directo
Garantía de los Beneficios Sociales de los Trabajadores
Seguro Conplementario de Trabajo de Riesgo
Seguro Vida Ley
Seguro Contra Todo Riesgo
Costo por emisión de Póliza
Gastos de Proceso de selección
Seguro por Transporte e instalación de estructura
Impuesto I.T.F.

2.- GASTOS GENERALES VARIABLES

SUELDOS Y SALARIOS
PERSONAL PROFESIONAL
Ing. Civil Jefe de Servicio
Ing. Asistente *
PERSONAL TÉCNICO
Técnico Montajista en Puentes
Técnico en Laboratorio
Topográfo
Prevencionista Seguridad y Medio Ambiente
PERSONAL AUXILIIAR DE SERVICIOS
Guardian (zona)
Ayudante de Topografía (zona)
Ayudante de Laboratorio (zona)
Ayudante de Prevencionista
ADMINISTRACIÓN
Administrador
Almacenero
Secretaria (zona)
BENEFICIOS SOCIALES

ALQUILERES Y SERVICIOS
ALQUILER DE OFICINAS / EQ. TOPOGRAFICOS / LABORATORIO
Alquiler y mant de Oficina + Vivienda + Grupo Electrógeno 150 Kw (incl. Combustible
Equipo de Computación; incluye impresora
Equipo de Topografía (nivel, GPS,, Estación Total)
Equipo de Protección Personal (EPP)
Servicio de Laboratorio (Mezclas Suelo, etc)
Camioneta 4*4 (Incluido Operador, Combustible y Seguros)
Camioneta (Tipo Custer) para transporte de personal (incluido Operador, Combustible
OTROS
Comunicaciones
MOVILIZACIÓN Y APOYO LOGISTICO
MOVILIZACIÓN Y APOYO LOGISTICO
Transporte Terreste - Personal Profesional (ida y vuelta)
Transporte Terrestre - Personal Técnico-adm. (ida y vuelta)
ALIMENTACIÓN
Profesional
Técnico Administrativo
Ayudantes (zona)
MATERIALES Y UTILES DE OFICINA
Materiales fungibles de oficina dibujo, etc.
Fotografías, filmación
Copias, reproducciones, anillados, etc.
COSTO SOCIO AMBIENTAL
Materiales fungibles de información
Fotografías, filmación
Difusión Impresa/Sonora
OTROS
Examenes médicos ocupacionales

TOTAL COSTO DIRECTO (1 + 2)


GASTOS GENERALES
A - QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO

TIEMPO
UND CANT. P.U. S/ PARCIAL S/ TOTAL S/
(MESES)
###
S/ 20,753.48
Mes 0.200 4.67 5,000.00 4,670.00
Mes 0.200 4.67 4,000.00 3,736.00
Mes 0.200 4.67 3,000.00 2,802.00
Mes 0.200 4.67 1,000.00 934.00
% 1.000 0.49 12,142.00 5,949.58
Mes 0.200 4.67 1,200.00 1,120.80
Mes 0.200 4.67 1,000.00 934.00
Mes 0.200 4.67 650.00 607.10
S/ 88,385.02
Global 1.000 1.00 4,745.10 4,745.10
Global 1.000 1.00 14,235.30 14,235.30
Global 1.000 1.00 1,186.28 1,186.28
Global 1.000 1.00 7,550.00 7,550.00
Global 1.000 1.00 9,648.04 9,648.04
Global 1.000 1.00 20,544.38 20,544.38
Global 1.000 1.00 4,025.81 4,025.81
Global 1.000 1.00 3,000.00 3,000.00
Global 1.000 1.00 23,141.40 23,141.40
% 2.000 0.005% 3,087,124.04 308.71

###

###
74,720.00
Mes 1.000 4.67 10,000.00 46,700.00
Mes 1.000 4.67 6,000.00 28,020.00
78,750.00
Mes 4.000 3.50 4,000.00 56,000.00
Mes 0.500 3.50 2,000.00 3,500.00
Mes 1.000 3.50 3,500.00 12,250.00
Mes 1.000 3.50 2,000.00 7,000.00
48,145.00
Mes 4.000 4.67 1,500.00 28,020.00
Mes 2.000 3.50 850.00 5,950.00
Mes 1.000 3.50 1,500.00 5,250.00
Mes 3.000 3.50 850.00 8,925.00
42,030.00
Mes 1.000 4.67 5,500.00 25,685.00
Mes 1.000 4.67 2,000.00 9,340.00
Mes 1.000 4.67 1,500.00 7,005.00
% 1.000 0.49 243,645.00 119,386.05

S/ 84,783.33
84,081.24
Mes 1.000 3.50 2,500.00 8,750.00
Mes 2.000 3.50 350.00 2,450.00
Mes 1.000 3.50 350.00 1,225.00
Glb 1.000 1.00 3,406.24 3,406.24
Mes 1.000 3.50 1,500.00 5,250.00
Mes 2.000 3.50 5,000.00 35,000.00
Mes 2.000 3.50 4,000.00 28,000.00
702.09
Mes 1.000 4.67 150.34 702.09
S/ 23,617.46
6,000.00
Glb 1.000 1.00 3,000.00 3,000.00
Glb 1.000 1.00 3,000.00 3,000.00
17,617.46
Glb 1.000 1.00 8,406.00 8,406.00
Glb 1.000 1.00 8,406.00 8,406.00
Glb 1.000 1.00 805.46 805.46
S/ 6,317.50
Mes 1.000 3.50 455.00 1,592.50
Mes 1.000 3.50 500.00 1,750.00
Mes 1.000 3.50 850.00 2,975.00
S/ 10,500.00
Mes 1.000 3.50 1,000.00 3,500.00
Mes 1.000 3.50 1,000.00 3,500.00
Mes 1.000 3.50 1,000.00 3,500.00
S/ 5,723.67
Glb 1.000 1.00 5,723.67 5,723.67

###
DETALLE DE LA ELABORACION DE INFORME FINA
ICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA - QUEROBAMBA - HUANCAPI - CAN

PLAZO DE EJE
N° CONCEPTO
UND # VECES
A SUELDOS Y SALARIOS
A.2 PERSONAL TÉCNICO
Topografo Mes 1.00
Asistente Tecnico Mes 1.00
A.3 PERSONAL AUXILIIAR DE SERVICIOS
Ayudante de Topografía Mes 1.00
A.4 BENEFICIOS SOCIALES % 1.00
B ALQUILERES Y SERVICIOS
B.1 ALQUILER DE OFICINAS / EQ. TOPOGRAFICOS / LABORATORIO
Alquiler y mantenimiento de Oficina equipada Mes 1.00
Alquiler y mantenimiento de vivienda equipada Mes 1.00
Equipo de Computacion (Incluye impresora) Mes 2.00
Equipo de Topografia (Nivel, GPS, Estacion Total) Und 1.00
Camioneta 4*4 (Incluido Operador, Combustible y Seguros) Mes 1.00
B.2 OTROS
Comunicaciones Mes 1.00
C MOVILIZACIÓN Y APOYO LOGISTICO
C.1 MOVILIZACIÓN Y APOYO LOGISTICO
Pasaje Lima-Obra-Lima (Profesionales) (ida y Vuelta) Pasaj 1.00
C.2 ALIMENTACIÓN
Profesionales Mes 3.00
Técnicos Mes 3.00
D MATERIALES Y UTILES DE OFICINA
Materiales fungibles de oficina dibujo, etc. Mes 1.00
Fotografías, filmación Mes 1.00
Copias, reproducciones, anillados, etc. Mes 1.00

TOTAL COSTO DIRECTO (A+B+C+D)


E FINAL
PI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO I"

O DE EJECUCION 1 (MESES): 0.33 (meses)


CANT. P.U. S/ PARCIAL TOTAL S/
S/ 7,867.20
4,620.00
0.330 9,000.00 2,970.00
0.330 5,000.00 1,650.00
660.00
0.330 2,000.00 660.00
49.00 % 5,280.00 2,587.20 2,587.20
S/ 5,062.20
4,913.70
0.330 1,650.00 544.50
0.330 1,650.00 544.50
0.330 530.00 349.80
0.330 530.00 174.90
0.330 ### 3,300.00
148.50
0.330 450.00 148.50
S/ 651.88
156.88
1.000 156.88 156.88
495.00
0.330 250.00 247.50
0.330 250.00 247.50
S/ 604.92
0.330 600.00 198.00
0.330 600.00 198.00
0.330 633.10 208.92

S/ 14,186.20
MINISTERIO DE TRANSPORTES Y COMUNICACIONES - PROVIAS NACIONAL

Servicio : SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA - QUEROBAMBA - HU


PAQUETE AYACUCHO I

Contrato : N° 033-2018-MTC/20
Contratista : CONSTRUCTORA DURAN S.A.
Sistema : SUMA ALZADA
SIN IGV

MONTO DEL CONTRATO 2,616,206.81

ADELANTO DIRECTO - (30%) 784,862.04

RESUMEN VALORIZACION Nª 01 - DEL CONTRATISTA


CORRESPONDIENTE AL MES DE JUNIO DEL 2018

MINISTERIO DE TRANSPORTES Y COMUNICACIONES - PROVIAS NACIONAL


Servicio
: SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA -
QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO I
Contrato : N° 033-2018-MTC/20
Contratista : CONSTRUCTORA DURAN S.A.
Sistema : SUMA ALZADA

VALORIZACION Y REAJUSTES

CONCEPTO

Monto Valorizado en el presente mes:

Valorización Bruta Mensual del Servicio

Reajuste de las Valorizaciones:

Reajuste de la Valorización

Amortización de los adelantos: Adelanto Directo SIN/IGV = S/. 784,862.04

Por adelanto directo en efectivo

Deducción del reajuste que no corresponde:

Por adelanto directo

1.- MONTO FACTURABLE (Sin IGV)


2.- IGV (18%)

3.- MONTO TOTAL A FACTURAR (1 + 2)

RESUMEN VALORIZACION Nª 02 - DEL CONTRATISTA


CORRESPONDIENTE AL MES DE JULIO DEL 2018

MINISTERIO DE TRANSPORTES Y COMUNICACIONES - PROVIAS NACIONAL


Servicio
: SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA -
QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO I
Contrato : N° 033-2018-MTC/20
Contratista : CONSTRUCTORA DURAN S.A.
Sistema : SUMA ALZADA

VALORIZACION Y REAJUSTES

CONCEPTO

Monto Valorizado en el presente mes:

Valorización Bruta Mensual del Servicio

Reajuste de las Valorizaciones:

Reajuste de la Valorización

Amortización de los adelantos: Adelanto Directo SIN/IGV = S/. 784,862.04

Por adelanto directo en efectivo

Deducción del reajuste que no corresponde:

Por adelanto directo

1.- MONTO FACTURABLE (Sin IGV)

2.- IGV (18%)

3.- MONTO TOTAL A FACTURAR (1 + 2)


RESUMEN VALORIZACION Nª 03 - DEL CONTRATISTA
CORRESPONDIENTE AL MES DE AGOSTO DEL 2018

MINISTERIO DE TRANSPORTES Y COMUNICACIONES - PROVIAS NACIONAL


Servicio
: SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA -
QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO I
Contrato : N° 033-2018-MTC/20
Contratista : CONSTRUCTORA DURAN S.A.
Sistema : SUMA ALZADA

VALORIZACION Y REAJUSTES

CONCEPTO

Monto Valorizado en el presente mes:

Valorización Bruta Mensual del Servicio

Reajuste de las Valorizaciones:

Reajuste de la Valorización

Amortización de los adelantos: Adelanto Directo SIN/IGV = S/. 784,862.04

Por adelanto directo en efectivo

Deducción del reajuste que no corresponde:

Por adelanto directo

1.- MONTO FACTURABLE (Sin IGV)

2.- IGV (18%)

3.- MONTO TOTAL A FACTURAR (1 + 2)

RESUMEN VALORIZACION Nª 04 - DEL CONTRATISTA


CORRESPONDIENTE AL MES DE SETIEMBRE DEL 2018

MINISTERIO DE TRANSPORTES Y COMUNICACIONES - PROVIAS NACIONAL


Servicio
: SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA -
QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO I
Contrato : N° 033-2018-MTC/20
Contratista : CONSTRUCTORA DURAN S.A.
Sistema : SUMA ALZADA
VALORIZACION Y REAJUSTES

CONCEPTO

Monto Valorizado en el presente mes:

Valorización Bruta Mensual del Servicio

Reajuste de las Valorizaciones:

Reajuste de la Valorización

Amortización de los adelantos: Adelanto Directo SIN/IGV = S/. 784,862.04

Por adelanto directo en efectivo

Deducción del reajuste que no corresponde:

Por adelanto directo

1.- MONTO FACTURABLE (Sin IGV)

2.- IGV (18%)

3.- MONTO TOTAL A FACTURAR (1 + 2)

RESUMEN VALORIZACION N° 05 DEL CONTRATISTA


CORRESPONDIENTE AL MES DE OCTUBRE DEL 2018

MINISTERIO DE TRANSPORTES Y COMUNICACIONES - PROVIAS NACIONAL


Servicio
: SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA -
QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO I
Contrato : N° 033-2018-MTC/20
Contratista : CONSTRUCTORA DURAN S.A.
Sistema : SUMA ALZADA

VALORIZACION Y REAJUSTES

CONCEPTO

Monto Valorizado en el presente mes:

Valorización Bruta Mensual del Servicio


Reajuste de las Valorizaciones:

Reajuste de la Valorización

Amortización de los adelantos: Adelanto Directo SIN/IGV = S/. 784,862.04

Por adelanto directo en efectivo

Deducción del reajuste que no corresponde:

Por adelanto directo

1.- MONTO FACTURABLE (Sin IGV)

2.- IGV (18% d 18%

3.- MONTO TOTAL A FACTURAR (1 + 2)


IAS NACIONAL

ARES CARRETERA ANDAMARCA - QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO)

CON IGV

###

###

ONTRATISTA
EL 2018

IAS NACIONAL
ARES CARRETERA ANDAMARCA -
A TOCTO) PAQUETE AYACUCHO I

S/.

439,186.15

439,186.15

9,751.38

9,751.38

131,755.85

131,755.85

440.14

440.14

316,741.54
57,013.48

373,755.02

ONTRATISTA
EL 2018

IAS NACIONAL
ARES CARRETERA ANDAMARCA -
A TOCTO) PAQUETE AYACUCHO I

S/.

285,823.45

285,823.45

7,464.61

7,464.61

85,747.03

85,747.03

615.77

615.77

206,925.26

37,246.55

244,171.81
ONTRATISTA
DEL 2018

IAS NACIONAL
ARES CARRETERA ANDAMARCA -
A TOCTO) PAQUETE AYACUCHO I

S/.

725,355.86

725,355.86

19,712.20

19,712.20

217,606.75

217,606.75

1,789.03

1,789.03

525,672.28

94,621.01

620,293.29

ONTRATISTA
DEL 2018

IAS NACIONAL
ARES CARRETERA ANDAMARCA -
A TOCTO) PAQUETE AYACUCHO I
S/.

266,225.94

266,225.94

7,641.79

7,641.79

79,867.78

79,867.78

776.43

776.43

193,223.51

34,780.23

228,003.74

ONTRATISTA
DEL 2018

IAS NACIONAL
ARES CARRETERA ANDAMARCA -
A TOCTO) PAQUETE AYACUCHO I

S/.

880,321.82

880,321.82
25,475.89

25,475.89

264,096.54

264,096.54

2,628.36

2,628.36

639,072.80

115,033.10

754,105.90
SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA - QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO I

RESUMEN DE VALORIZACIONES PAGADAS


CONTRATO : N° 033-2018-MTC/20
SISTEMA : A SUMA ALZADA
SERVICIO SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA - QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S
8ABRA TOCTO) PAQUETE AYACUCHO I
CONTRATISTA : CONSTRUCTORA DURAN S.A

Sin IGV Con IGV


ADELANTO DIRECTO 784,862.04 926,137.21
MONTO DEL CONTRATO 2,616,206.81 ###

N°. DE VALORIZACION AMORTIZACION


MES POR ADELANTO REAJUSTE DEDUCCION NETO I.G.V. TOTAL
VALORIZ BRUTA DIRECTO

ADELANTO 784,862.04 141,275.17 926,137.21


Junio 2018 1 439,186.15 131,755.85 944.33 440.14 307,934.49 55,428.21 363,362.70
Junio 2018 2 285,823.45 85,747.03 1,711.02 615.77 201,171.67 36,210.90 237,382.57
Agosto 2018 3 725,355.86 217,606.75 5,095.81 1,789.03 511,055.89 91,990.06 603,045.95
Setiembre 2018 4 266,225.93 79,867.78 2,269.18 776.43 187,850.90 33,813.16 221,664.06
Octubre 2018 5 880,321.82 269,884.63 7,706.37 2,685.97 615,457.59 110,782.37 726,239.96

TOTAL ACUMULADO 2,596,913.21 784,862.04 17,726.71 6,307.34 2,608,332.58 469,499.87 3,077,832.45


RECALCULO DEL REAJUSTE, DEDUCCION Y AMORTIZACION DEL ADELANTO OTORGADO

Contrato : N° 033-2018-MTC/20
Sistema : A SUMA ALZADA
Servicio : SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA - QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO I

Contratista : CONSTRUCTORA DURAN S.A

Sin IGV Con IGV


ADELANTO 784,862.04 926,137.21
MONTO DEL CONTRATO 2,616,206.81 3,087,124.04
MONTO REAL DEL SERVICIO 2,680,953.05 3,163,524.60

VALORIZACION Indice de Precios al Consumidor (IPC-INEI) Base 2009 = 100.0 Amortizacion del Monto de la MONTO A
VALORIZ. BRUTA VALORIZACION
REAJUSTE DEDUCCION Adelanto Valorizacion IGV FACTURAR
A MES DE REAJUSTADA
N° MES FECHA BASE ENE-2017 FECHA ADELANTO MAY-2018 FECHA VALORIZAR DIRECTO Reajustada Vr (CON IGV)
SERVICIOS
Vo Io Ia Ir
1 JUNIO 2018 439,186.15 448,970.12 9,783.97 449.74 131,755.85 316,764.53 57,017.62 373,782.15
Indice Junio 430,856.00 126.014256 128.383312 128.812187 440,422.42 9,566.42 431.79 129,256.80 310,733.83 55,932.09 366,665.92
Indice Julio 8,330.15 126.014256 128.383312 129.305262 8,547.70 217.55 17.95 2,499.05 6,030.70 1,085.53 7,116.23
2 JULIO 2018 285,823.45 293,687.15 7,863.70 733.28 85,747.03 207,206.83 37,297.23 244,504.06
Indice Junio 0.00 126.014256 128.383312 128.812187 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Indice Julio 59,773.11 126.014256 128.383312 129.305262 61,334.15 1,561.04 128.77 17,931.93 43,273.45 7,789.22 51,062.67
Indice Agosto 179,278.53 126.014256 128.383312 129.475644 184,202.99 4,924.46 457.61 53,783.56 129,961.82 23,393.13 153,354.95
Indice Setiembre 45,180.04 126.014256 128.383312 129.723825 46,510.04 1,330.00 141.52 13,554.01 32,814.50 5,906.61 38,721.11
Indice Octubre 1,591.77 126.014256 128.383312 129.829788 1,639.97 48.20 5.38 477.53 1,157.06 208.27 1,365.33
3 AGOSTO 2018 725,355.86 745,243.31 19,887.43 1,840.64 217,606.75 525,795.91 94,643.26 620,439.17
Indice Junio 22,610.42 126.014256 128.383312 128.812187 23,112.45 502.03 22.66 6,783.13 16,306.66 2,935.20 19,241.86
Indice Julio 68,783.28 126.014256 128.383312 129.305262 70,579.63 1,796.35 148.18 20,634.98 49,796.47 8,963.36 58,759.83
Indice Agosto 549,137.40 126.014256 128.383312 129.475644 564,221.23 15,083.83 1,401.68 164,741.22 398,078.33 71,654.10 469,732.43
Indice Setiembre 75,093.80 126.014256 128.383312 129.723825 77,304.39 2,210.59 235.23 22,528.14 54,541.02 9,817.38 64,358.40
Indice Octubre 9,730.98 126.014256 128.383312 129.829788 10,025.62 294.64 32.89 2,919.29 7,073.44 1,273.22 8,346.66
4 SETIEMBRE 2018 266,225.93 273,871.89 7,645.96 777.67 79,867.78 193,226.45 34,780.76 228,007.21
Indice Junio 3,230.06 126.014256 128.383312 128.812187 3,301.78 71.72 3.24 969.02 2,329.52 419.31 2,748.83
Indice Julio 0.00 126.014256 128.383312 129.305262 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Indice Agosto 87,293.86 126.014256 128.383312 129.475644 89,691.67 2,397.81 222.82 26,188.16 63,280.69 11,390.52 74,671.21
Indice Setiembre 170,741.32 126.014256 128.383312 129.723825 175,767.55 5,026.23 534.84 51,222.40 124,010.32 22,321.86 146,332.18
Indice Octubre 4,960.69 126.014256 128.383312 129.829788 5,110.89 150.20 16.77 1,488.21 3,605.92 649.07 4,254.99
4 OCTUBRE 2018 880,321.82 905,797.71 25,475.89 2,628.36 264,096.55 639,072.80 115,033.10 754,105.90
Indice Junio 0.00 126.014256 128.383312 128.812187 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Indice Julio 0.00 126.014256 128.383312 129.305262 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Indice Agosto 269,479.93 126.014256 128.383312 129.475644 276,882.07 7,402.14 687.85 80,843.98 195,350.24 35,163.04 230,513.28
Indice Setiembre 501,461.42 126.014256 128.383312 129.723825 516,223.29 14,761.87 1,570.80 150,438.43 364,214.06 65,558.53 429,772.59
Indice Octubre 109,380.47 126.014256 128.383312 129.829788 112,692.35 3,311.88 369.71 32,814.14 79,508.50 14,311.53 93,820.03
5 SALDO OCTUBRE 19,293.59 19,877.77 584.18 65.21 5,788.08 14,024.49 2,524.41 16,548.90
Indice Octubre 19,293.59 126.014256 128.383312 129.829788 19,877.77 584.18 65.21 5,788.08 14,024.49 2,524.41 16,548.90

TOTAL ACUMULADO 2,616,206.80 2,687,447.95 71,241.13 6,494.90 784,862.04 1,896,091.01 341,296.38 2,237,387.39
: SERVICIO GENERAL DE INSTALACION DE PUENTES MODULARES CARRETERA ANDAMARCA -
Servicio
QUEROBAMBA - HUANCAPI - CANGALLO - EMP.PE-3S 8ABRA TOCTO) PAQUETE AYACUCHO I

Contratista : CONSTRUCTORA DURAN S.A


Contrato : N° 033-2018-MTC/20

LIQUIDACION FINAL DEL SERVICIO

COSTO FINAL DEL


MONTOS PAGADOS SALDO POR PAGAR
CONCEPTO SERVICIO
S/. S/. S/.

1. MONTO DE VALORIZACIÓN BRUTA 2,616,206.80 2,596,913.21 19,293.59


POR CONTRATO PRINCIPAL 2,616,206.80 2,596,913.21 19,293.59
Valorizacion N° 01 439,186.15 439,186.15 -
Valorizacion N° 02 285,823.45 285,823.45 -
Valorizacion N° 03 725,355.86 725,355.86 -
Valorizacion N° 04 266,225.93 266,225.93 -
Valorizacion N° 05 880,321.82 880,321.82 -
Valorizacion N° 06 (Final) 19,293.59 - 19,293.59
POR ADICIONALES : - - -
OTROS - - -
2. REAJUSTE DE LA VALORIZACION 71,241.13 17,726.71 53,514.42
POR CONTRATO PRINCIPAL 71,241.13 17,726.71 53,514.42
Valorizacion N° 01 9,783.97 944.33 8,839.64
Valorizacion N° 02 7,863.70 1,711.02 6,152.68
Valorizacion N° 03 19,887.43 5,095.81 14,791.62
Valorizacion N° 04 7,645.96 2,269.18 5,376.78
Valorizacion N° 05 25,475.89 7,706.37 17,769.52
Valorizacion N° 06 (Final) 584.18 - 584.18
POR ADICIONALES
3. MONTO BRUTO VALORIZ. REAJUSTADO 2,687,447.93 2,614,639.92 72,808.01

4. DEDUCCION DEL REAJUSTE 6,494.90 6,307.34 187.56


POR ADELANTO DIRECTO 6,494.90 6,307.34 187.56
Valorizacion N° 01 449.74 440.14 9.60
Valorizacion N° 02 733.28 615.77 117.51
Valorizacion N° 03 1,840.64 1,789.03 51.61
Valorizacion N° 04 777.67 776.43 1.24
Valorizacion N° 05 2,628.36 2,685.97 (57.61)
Valorizacion N° 06 (Final) 65.21 - 65.21

5. MONTO NETO VALORIZ. REAJUSTADO 2,680,953.03 2,608,332.58 72,620.44


6. ADELANTOS -
6.a Adelanto Otorgados 926,137.21 926,137.21

6.b Amortizaciones de Adelanto 784,862.04 784,862.04 -

Valorizacion N° 01 131,755.85 131,755.85 -


Valorizacion N° 02 85,747.03 85,747.03 -
Valorizacion N° 03 217,606.75 217,606.75 -
Valorizacion N° 04 79,867.78 79,867.78 -
Valorizacion N° 05 264,096.55 269,884.63 (5,788.08)
Valorizacion N° 06 (Final) 5,788.08 - 5,788.08
7. OTROS
MAYORES Gastos Generales Ampl. de Plazo - - -
Otros - - -

8. MONTO NETO FACTURABLE, SIN IGV 2,680,953.03 2,608,332.58 72,620.44


9. MONTO RETENIDO
VARIOS - - -

10. IMPUESTO GENERAL A LAS VENTAS (IGV) 482,571.54 469,499.86 13,071.68


- Del Monto Neto Facturable 18%
MONTO NETO 482,571.54 469,499.86 13,071.68

10. SUB TOTAL 3,163,524.57 3,077,832.45 85,692.12

11. MULTAS Y OBLIGACIONES VARIAS 132,892.65 132,892.65 -


MULTAS 132,892.65 132,892.65 -
VARIOS - - -

12. MONTO A CANCELAR FACTURABLE 3,030,631.92 2,944,939.80 85,692.12


PROYECCIO
(

DATOS ADD

VALORIZACIONES DEL MES

INGRESOS

- COBRANZA BRUTA DE VALORIZACION


- DETRACCION - (4%)
- COBRANZA NETA DE VALORIZ
- NOTA DE CREDITO ( SANCION )
- DEVOLUCION DE FONDO DE GARANTIA

TOTAL INGRESOS

EGRESOS MULTA = 62,577.31


CONTRATO
- PAGOS AL CONTRATISTA - " ADONIS " 927,547.37
- PAGOS DE DETRACCION - " ADONIS " MULTA = 33,907.10
- PAGOS AL CONTRATISTA - " JM " 863,706.45
- PAGOS DE DETRACCION - " JM "
- PAGO DE SUELDOS
- PAGO R.H (NETO) - INGENIERO
- PAGO R.H (NETO) - ASISTENTE
- PAGO DE POLIZAS "EAR"
- PAGO DE POLIZAS "TRANSPORTE"
- PAGO DE POLIZAS "RESPONSABILIDAD CIVIL"
- PAGO DE FONDO DE GARANTIA
- COMPRA DE ACEROS - MATERIAL
- PAGO DE PINTADO DE ESTRUC METALICAS 115,620.50
- PAGO DE DETRACCION - 4% MULTA = 10,000.00
- PAGO DE SEÑALIZACIONES DE PUENTES 77,545.20
- PAGO DE DETRACCION - 4%
- PAGO DE FAB. DE PLACAS PARA LOS PUENTES
- PAGO DE ALQUILER DE OFICINA

TOTAL EGRESOS

FLUJO DE CAJA ECONÓMICO -


COK
VAN
TIR
PROYECCION DE FLUJO DE CAJA
(EXPRESADO EN SOLES)

MAYO JUNIO JULIO AGOSTO SETIEMBRE

926,137.21 363,362.70 237,382.57 603,045.95 221,664.06

- 926,137.21 363,362.70 237,382.57 603,045.95


- 37,045.00 14,535.00 9,495.00 24,122.00
- 889,092.21 348,827.70 227,887.57 578,923.95

- 889,092.21 348,827.70 227,887.57 578,923.95

MULTA = 62,577.31

384,000.00 67,200.00 48,000.00


MULTA = 33,907.10 16,000.00 2,800.00
336,000.00 48,000.00 45,312.00
14,000.00 2,000.00 1,888.00
39,600.00 39,600.00 39,600.00 39,600.00 39,600.00
5,000.00 5,000.00 5,000.00 5,000.00 5,000.00
2,000.00 2,000.00 2,000.00 2,000.00 2,000.00
17,509.60 17,509.60
7,287.83 7,287.83
1,582.57
121,752.30
22,544.44 22,544.44 22,544.44

MULTA = 10,000.00

3,000.00 3,000.00 3,000.00 3,000.00 3,000.00

49,600.00 891,352.30 151,727.01 211,453.87 149,629.87

-49,600.00 -2,260.09 ### 16,433.70 ###


8%
535,484.49
137%
LIQUIDACION FINAL DEL
SERVICIO

OCTUBRE NOVIEMBRE DICIEMBRE AÑO 2018

726,239.96 85,692.12 3,163,524.57


-
-
-
221,664.06 726,239.96 - 3,077,832.45
8,867.00 29,050.00 - 123,114.00
212,797.06 697,189.96 - 2,954,718.45
132,892.65 -132,892.65
32,051.20 89,701.10 121,752.30
-
244,848.26 564,297.31 89,701.10 2,943,578.10
-
-
-
96,000.00 48,000.00 643,200.00
2,000.00 4,000.00 2,000.00 26,800.00
113,280.00 96,000.00 638,592.00
4,720.00 4,000.00 26,608.00
39,600.00 27,900.00 27,900.00 293,400.00
5,000.00 5,000.00 5,000.00 40,000.00
2,000.00 2,000.00 2,000.00 16,000.00
17,509.60 17,509.60 70,038.40
14,575.66
1,582.57
121,752.30
22,544.44 90,177.76
77,697.35 33,299.15 110,996.50
3,237.00 3,237.00
29,777.08 44,666.12 74,443.20
1,241.00 1,241.00
12,000.00 12,000.00
3,000.00 3,000.00 3,000.00 24,000.00
-
300,934.04 327,604.03 126,343.27 2,208,644.39
-
-56,085.78 ### -36,642.17 734,933.71
AÑO 2019 AÑO 2020 AÑO 2021 AÑO 2022

727,610.65 2,182,831.95 4,802,230.30 5,762,676.36


- - - -
- - - -
- - - -
707,901.46 2,123,704.39 4,672,149.66 5,606,579.59
28,316.22 84,948.66 186,887.05 224,264.46
679,585.24 2,038,755.73 4,485,262.61 5,382,315.13
- - - -
28,003.03 84,009.09 184,819.99 221,783.99

707,588.27 2,122,764.82 4,670,082.60 5,604,099.12


- - - -
- - - -
- - - -
147,936.00 443,808.00 976,377.60 1,171,653.12
6,164.00 18,492.00 40,682.40 48,818.88
146,876.16 440,628.48 969,382.66 1,163,259.19
6,119.84 18,359.52 40,390.94 48,469.13
67,482.00 202,446.00 445,381.20 534,457.44
9,200.00 27,600.00 60,720.00 72,864.00
3,680.00 11,040.00 24,288.00 29,145.60
16,108.83 48,326.50 106,318.29 127,581.95
3,352.40 10,057.21 22,125.85 26,551.02
363.99 1,091.97 2,402.34 2,882.81
28,003.03 84,009.09 184,819.99 221,783.99
20,740.88 62,222.65 136,889.84 164,267.81
25,529.20 76,587.59 168,492.69 202,191.22
744.51 2,233.53 4,913.77 5,896.52
17,121.94 51,365.81 113,004.78 135,605.73
285.43 856.29 1,883.84 2,260.61
2,760.00 8,280.00 18,216.00 21,859.20
5,520.00 16,560.00 36,432.00 43,718.40
- - - -
507,988.21 1,523,964.63 3,352,722.18 4,023,266.62

169,034.75 507,104.26 1,115,629.37 1,338,755.25