You are on page 1of 69

CPA CONSTRUCTION

INDUSTRY FORECAST
JANUARY 2019

Modest market growth possible


BESA is pleased to be able to offer members exclusive access to While the M&E sector is not heavily reliant on EU migrant labour other
valuable market information provided by the Construction Products’ trades are so this will affect everyone working on supply chain projects.
Association (CPA). These forecasts have been very accurate in the The government will require Regulated Qualifications Framework (RQF)
past and are regularly referred to by the Treasury. Level 3 and above for anyone wishing to enter the UK, which rules out
many working in construction trades.
Of course, forecasting anything business-related at the moment is
a tricky exercise thanks to the ongoing Parliamentary chaos around The CPA says there is clear evidence that Brexit is depressing construction
Brexit, but the CPA has assumed that there will be a ‘deal’ of some kind demand with anything requiring high upfront cost in search of long-
before we leave the EU on March 29th term return under real pressure. This is leading to delays in investment
decisions and project cancellations with the full impact likely to feed
Construction has remained surprisingly resilient despite the political through to m&e projects in 2020.
upheaval around Brexit and our rather sluggish economy. However, the
rest of this year is looking tough with the CPA predicting construction All of these predictions also depend on us not having a disorderly
output rising by a very modest 0.3%. It was originally forecasting better departure from the EU and it would only be right to consider the ‘worst-
growth until the latest parliamentary shenanigans. case scenario’ painted by the Bank of England.
However, it does still believe we are on track for a more health recovery BESA is happy to pass on this information to members to keep you
of 1.6% in 2020. informed, but we fervently hope this won’t come to pass and please
‘don’t shoot the messenger’.
Office construction is under real pressure and the CPA expects that
sector to slump by 20% this year and remain flat in 2020 as a direct A no deal exit from the EU would lead to an 8% drop in GDP with the
result of Brexit uncertainty. On the plus side, infrastructure could see impact being felt in the second and third quarters of this year before the
a rise of almost 9% this year and 8% next, but only if the government economy starts to recover from the initial shock, according to the Bank.
improves its record on delivering major projects.
To put this in perspective, the 2008 financial crash led to a 5% fall in
Housing will also continue to grow, but not at the rate hoped for by the GDP and a consequent drop in construction activity of 17%. Therefore,
government to meet its targets. avoiding this scenario would be a major bonus.
CPA economics director Noble Francis also explained that its forecasts Finally a comment on the political situation: Donald Trump may well
were conditional on the government getting a new Brexit deal or have instigated a US government shut down, but the UK finds itself in
delaying Article 50. a similar position because there is no bandwidth within government
for anything that is not related to Brexit at the moment.
“However, even if this occurs, the uncertainty surrounding Brexit is
clearly affecting the construction industry in areas that require high With no clear consensus on the way forward, this impasse is hitting
investment up front for a long-term rate of return such as commercial investment and means we are not dealing with the other major challenges
offices,” he said. facing us, such as climate change, air quality, social care and the housing
crisis.
KEY STATS
The decision to suspend the project to build a new nuclear power station
• Construction output UP by 0.3% in 2019 and 1.6% in 2020 in Anglesey demonstrates this point. The government has taken its eye
off the ball on energy policy and this vital infrastructure development,
• Private housing starts UP by 2.0% in 2019 and 1.0% in 2020 which has already cost £2bn, is now in serious doubt.
• Office construction DOWN by 20.0% in 2019 and 2.0% in 2020 In the words of Joseph de Maistre:
• Retail construction DOWN 4.0% in 2019 and remaining flat in 2020 “Every country gets the government it deserves”
• Infrastructure work UP by 8.8% in 2019 and 7.7% in 2020
So some growth, but profit margins remain a serious concern with David Frise
main contractors still showing negative returns – the current average CEO BESA
for the Top 10 is -0.9%. This is likely to increase pressure on supply
chains to keep prices low and increases the risk of further insolvencies.
Construction output inflation is expected to rise to 2.8% with material
prices going up by 5.1% – putting further pressure on margins. Wages
too will go up by a significant 4.3%, according to the CPA, and the
government’s plans for restricting EU immigration could further reduce
the pool of available skills, which may drive up labour costs again.

contact@thebesa.com 0207 313 4919 thebesa.com @theBESAGroup BESAGroup


Construction Industry
Forecasts 2019-2020
Winter 2018/19 Edition - £210
2
Contents
Overview 4

Economy 12

Private Housing 16

Private Housing RM&I 22

Public Housing 26

Public Housing RM&I 32

Public Non-housing 32

Public Non-housing R&M 38

Commercial 40

Private Non-housing R&M 50

Industrial 52

Infrastructure 56

Infrastructure R&M 64

© 2019 Construction Products Association. All rights reserved.


This document is licensed for the exclusive use of
Members of the CPA and purchasers of its economic
forecasts (£210, including 20% VAT).
Please do not publicly distribute this document.
Additions to the distribution list can be made by
contacting the CPA at 020 7323 3770.

DISCLAIMER

All construction figures (starts, completions, orders and output)


refer to Great Britain.

All output figures are in 2016 constant prices using the historic
figures from the Office for National Statistics (ONS).

All new orders figures are in 2005 constant prices using the
historic figures from the Office for National Statistics (ONS).

The information in this booklet has been prepared by


Construction Products Association and represents the views of
Construction Products Association without liability on the part
of the Construction Products Association and its officers.

3
Overview
Construction output is forecast to remain broadly flat in 2019 before growth of 1.6% in
2020 (assuming a revised Brexit Withdrawal Agreement that enables the UK to enter an
implementation period or a delay to Article 50 to allow a renegotiation with the EU).

Construction output has remained resilient this first three quarters of 2018 was 0.7% higher than
year in spite of the rising political uncertainty a year earlier, this was primarily driven by 7.7%
that the UK is currently experiencing. Output growth in private house building output, with
in the first three quarters of 2018 was 0.7% increases outside the capital offsetting falls in
higher than in the same period one year earlier London, the 7.8% growth in the industrial sector
despite unseasonably bad weather during the as double-digit increases in the warehouses
first quarter of 2018, which suffered from sub-sector offset falls in activity in the
factories sub-sector, as well as 4.5% growth in
substantial rain in January in addition to snow
infrastructure in spite of continued delays and
in February and March. However, the growth
cost overruns on major infrastructure projects.
in construction activity between January and
Growth in these sectors during the first three
September varied considerably by region and by
quarters of 2018 was enough to offset a 15.0% fall
construction sector. In the North West, Midlands in public non-housing and a 5.1% fall in commercial,
and Yorkshire, construction output continued to the second largest construction sector.
enjoy growth, not just during the long Summer
but also into the Autumn and Winter. Conversely, Uncertainty regarding the UK’s withdrawal from
the EU has increased considerably since the
Construction activity to rise by only CPA’s Autumn forecasts and there is less time
available for a Brexit Withdrawal Agreement

0.3% &
1.6% with the EU that also passes through the UK
parliament. The CPA forecasts assume that either
in 2019 in 2020 a revised agreement will be made with the EU
that passes through UK Parliament in spite of
the failure of the initial Parliamentary vote on 15
January or, more likely at the time of writing given
the lack of time between the vote and the UK
whilst construction activity in London still remains leaving the EU on 29 March 2019, an extension
at a relatively high level, output peaked in 2017 to Article 50. Either of these would ensure that
and fell throughout 2018. Across the different trading conditions would remain similar in the
sectors, although construction output during the near-term although neither provides a solution
to the long-term relationship with the EU. The
extent of the loss in January suggests that minor
revisions to the draft agreement will not be
• Construction output to rise by 0.3% in enough to ensure it passes through Parliament
Key Points

2019 and 1.6% in 2020 and major revisions would require renegotiation
and agreement with the EU. Given the lack of
• Private housing starts to rise 2.0% in
agreement in UK Parliament, the probability of a
2019 and 1.0% in 2020
second referendum has increased although there
• Offices construction to decline is little to suggest what the question would be
20.0% in 2019 and 2.0% in 2020 and whether it be able to would settle such a
divisive issue. The prospect of ‘No Deal’ remains
• Retail construction to fall 4.0% in 2019
high and is rising. Given the lack of preparation
and remain flat (0.0%) in 2020
by government, businesses, especially small
• Infrastructure work to rise by 8.8% in businesses, and households for ‘No Deal’, it is
2019 and 7.7% in 2020 unlikely to arise by design. If ‘No Deal’ does arise,
it is still only likely to arise due to the failure to
agree on any other option. An extension to

4
Article 50 is more likely than No Deal and that Private housing starts to rise by
would, at the very least, provide a degree of
certainty and little disruption in the next three
months but the essential problems would remain
2.0% in 2019
unsolved and the uncertainty would remain.
The issues of ‘No Deal’ and UK construction are 1.0% in 2020
explored in the CPA Brexit Presentation. as Help to Buy sustains
Whilst construction output has remained robust growth outside London
in spite of the political uncertainty over Brexit,
this does not mean it has had no impacts on
The CPA’s private housing output forecast
the construction industry, particularly since the
remains unchanged from the past three and six
uncertainty increased considerably after the
months. Clearly, there has been a slowdown
Summer. Activity on site is largely determined
in the general housing market, which is only
by projects signed up to in previous months and
expected to deteriorate further until there is
years. The primary impact of Brexit uncertainty more clarity over Brexit and UK macroeconomic
has been on signing up to new major projects, fortunes. UK mortgage approvals in the year
particularly in construction sectors that are to November 2018 were 2.5% lower than a
dependent upon high investment up front for year earlier and property transactions in the
a long-term rate of return, especially when the same period were 3.1% lower than a year
funding is from international investors. This, in earlier. However, whilst mortgage approvals
particular, impacts upon construction sectors and property transactions have fallen, house
such as prime residential apartments in London, prices have continued to rise in most regions,
commercial offices towers and industrial clearly indicating that whilst demand has fallen
factories. Conversely, construction sectors that in the general market, supply has also fallen as
so far appear to have been immune from Brexit potential sellers adjust to uncertain conditions
uncertainty include private housing outside the by taking their properties off the market. ONS/
capital, and private housing repair, maintenance Land Registry average UK house prices in the
and improvement, a sector in which an older, year to October 2018 by region were highest in
wealthier demographic with housing and pension the North West and Yorkshire and the Humber,
wealth has generated growth since the pension where prices rose by 4.9% and 4.4%. The lowest
freedoms were introduced in April 2015. house price growth in the year to October

Construction Output
180,000
7.2% 0.3% 1.6%
160,000 4.1%
4.4% -0.2%
2.2% 8.8%
140,000
£ million - 2016 Constant Prices

1.5%

120,000
-6.9%
100,000

80,000

60,000

40,000

20,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p

Source: ONS, Construction Products Association

5
to adapt to market conditions should there be a
sudden deterioration in UK economic conditions
in 2019.

The CPA continues to have serious concerns


regarding the ONS infrastructure data, which
is used as the historic data to forecast from.
These are highlighted in the disclaimers at the end
of the overview. As a result, estimated figures
for 2018 and forecasts reflect activity on the
ground measured by survey evidence as well as
sales and orders data rather than the ONS data.
Infrastructure activity is still expected to be the
key driver of growth over the next two years
and the forecast remains broadly unchanged
since the Autumn forecasts. Infrastructure
output is forecast to rise by 8.8% in 2019 and
7.7% in 2020. There remain concerns regarding
persistent and increasing delays and cost overruns
to major projects such as Crossrail and HS2 in
addition to increasing concerns regarding the
Thames Tideway Tunnel, in which there are
reports that a substantial proportion of the
contingency has already been used only a few
weeks into the tunnelling work on a project that
is set to continue until 2023. However, given
historical delivery issues in the sector, delays
and cost overruns have already been built into
CPA forecasts on major infrastructure projects.
Main work at Hinkley Point C is expected to
get going early in 2019 and should boost output
in the electricity sub-sector each year into the
middle of the next decade. However, the second
of the planned new nuclear power stations,
2018 was in London, where prices fell by 1.7% Wylfa Newydd, was suspended by Hitachi in
but survey and anecdotal indications are that January. Water & sewerage output is expected
there have been double-digit falls in demand in to continue next year at its highest level since
London but these have yet to translate to prices 2012 due to work under five-year spending
as anyone who does not need to sell has taken plans from water companies in addition to the
their property off the market or not put it on Thames Tideway Tunnel. Activity in the roads
the market in the first place. In areas where sub-sector appears to be split between smart
house price growth continues apace, such as the motorways and traditional roads construction. In
North West, Yorkshire and the Humber and smart motorways, projects are feeding through
the Midlands, house builders have continued from Highways England and boosting activity for
to increase building activity and increase starts electrics, signage, IT and groundworks. However,
as Help to Buy is sustaining demand for new there is little in the way of new major projects
build and growth in these areas is still expected on traditional roads construction, particularly
to offset falls in house building in London. on local roads given that local authorities
A 2.0% growth in private housing starts is remain highly financially-constrained despite the
expected in 2019 and 1.0% growth is expected government’s claims of an end to austerity. This
in 2020 although it should be noted that major is reflected in surveys from the Civil Engineering
housebuilder business models are flexible enough Contractors Association (CECA), which note falls

6
in construction activity over the last six months
on motorways, trunk roads and also local roads.
The harbours sub-sector, dominated by work on
ports, is expected to grow by 12.0% in 2019 and
10.0% in 2020 due to growth in world trade and
an improvement in facilities on site such as offices
and warehousing. In addition, an increase in
Brexit uncertainty would boost demand for ports
expansions even further.

The commercial sector is expected to endure


the sharpest falls in volume of activity over
the forecast period due to declines in offices
construction and retail construction. Falls in the
sector have also been adversely affected by the accounted for 21.5% of total UK retail sales, the
two former Carillion PFI hospital projects in first time that online spending has accounted
Liverpool and Sandwell moving to public funding for over one-fifth of total retail sales as Black
due to a lack of interest from private sector Friday exacerbated the shift of spending further
investors. Overall, commercial output is expected towards online given that the greatest reductions
to fall by 8.0% in 2019 and 1.5% in 2020. Offices are often not in-store. The start of 2018 saw
construction in London, which accounts for many traditional retailers, which had struggled
over one-quarter of the UK offices construction with changing business models to match high
market, peaked at the start of 2017 and output street and online retail spending patterns, go into
is expected to fall from this high level throughout administration or liquidation and the start of 2019
the forecast period. Small and medium-sized is expected to see further bankruptcies. It is not
projects continue, particularly in cities outside the all bad news for retail construction but activity
capital. In addition, speculative demand continues is likely to be focused on interiors and fit-out of
from the Technology, Media and Telecoms (TMT) existing properties for reuse by new retailers
sector but speculative demand from the financial rather than construction of new out-of-town
sector for new high-end offices projects has fallen facilities. Overall, retail construction is expected
away the most and is expected to offset growth to fall 4.0% in 2019 and remain flat in 2020 as
in the other areas. Retail construction continues large projects such as the £1.4 billion Brent Cross
to be adversely affected by the shift to spending Extension and Croydon Partnership offset further
online and, in November 2018, online spending falls in the sub-sector.

Public & Private Sector Construction Output


£ million 2016 2017 2018 2019 2020

Change on previous year Actual Actual Estimate Forecast Projection

37,505 38,994 37,275 37,788 38,370


Public Sector inc. PFI
-3.4% 4.0% -4.4% 1.4% 1.5%

114,266 123,707 125,101 125,083 127,100


Private Sector
6.8% 8.3% 1.1% 0.0% 1.6%

151,771 162,701 162,376 162,871 165,470


Total Construction
4.1% 7.2% -0.2% 0.3% 1.6%

Source: ONS, Construction Products Association

7
from an increase in construction activity related
to storage and stockpiling requirements.
Construction Output (% Growth)
7.2% Key Risks
Brexit
4.1% The CPA has assumed that a broad agreement is
made between the UK and EU that can be taken
to the UK Parliament and be ratified by the 27
1.6%
EU parliaments prior to Brexit on 29 March, thus
-0.2% 0.3% enabling the implementation period. If this were
not to be the case then the UK would be in a
2016 2017 2018e 2019f 2020p
‘No Deal’ scenario. Issues around Brexit and the
Source: ONS, Construction Products Association
construction industry are explored further in the
CPA’s Brexit presentation.

Margins
Industrial sector output is expected to rise In 2017/18, the average pre-tax margin of the
by 2.5% in 2019 and a further 4.4% in 2020 but top 10 UK contractors was -0.9%. In the year
there are clearly contrasting fortunes between to October 2018, construction output inflation
the industrial factories and warehouses sub- averaged 2.1% compared with a year earlier
sectors. The main factories activity currently whilst construction wage inflation was 3.6% and
on site is based on projects for which the construction materials inflation was 5.4%, the
investment decision was made prior to the EU
latter primarily due to the impacts of fuel input
Referendum in June 2016. It is doubtful whether
prices in the energy-intensive manufacturing of
these major investments would have gone
products. Margins for the main contractors are
ahead given the uncertainty over long-term
unlikely to be substantially better in 2018/19
returns had these decisions been made later.
and issues are likely to be pushed throughout
The lack of a pipeline of projects outside of
the supply chain to sub-contractors and
these projects suggests that output in the sub-
manufacturers.
sector will fall 5.0% in 2019 and 2.0% in 2020.
Conversely, whilst the shift to online spending Housing
adversely impacts retail construction, it boosts
the demand for warehouse construction, which Private house building is expected to rise
is not only increasing in terms of the number of throughout the forecast period as increases
units but also in value as warehousing projects in housing demand, sustained by Help to Buy,
become larger and incorporate more technology. ensure growth in the North West, Midlands and
The increase in demand from retailers has also Yorkshire and the Humber that offsets falls in
drawn in speculative demand from investors the London and the South East housing markets.
and the uncertainty regarding Brexit and need The confirmed extension of the equity loan
for space to stockpile has also raised demand through to March 2023, albeit with narrower
for warehousing space. Both of these factors eligibility conditions from March 2021, has
have also led to a sharp rise in warehouse space allayed some medium-term concerns from house
prices over the past year. After growth of 20.0% builders. However, if market uncertainty spreads
in 2018, warehouses construction is forecast beyond London and the South East, a fall in
to rise by 10.0% in 2019 and a further 10.0% in house building activity is likely to follow quickly
2020. As with the infrastructure harbours sub- as house builders reduce starts and build out
sector, if there are major issues around Brexit, rates, despite government pressure to increase
warehousing will be a sub-sector that benefits house building volumes to 300,000 per year.

8
9
Infrastructure by the ONS earlier than it actually occurs. An
illustration of this is in the water & sewerage
Due to persistent poor procurement, delays and sub-sector. General activity in the sector occurs
cost overruns on major infrastructure projects, under frameworks and often takes relatively
in addition to projects in five-year spending plans little time to feed through from new orders to
frequently being pushed back into the next five- output as a part of general works under the
year spending plan, the CPA has been cautious five-year plan. However, the ONS has assigned
regarding infrastructure growth in 2019 and work on the £4.2 billion Thames Tideway
2020. However, if government is able to improve Tunnel shortly after the new orders in 2016. As
its delivery of infrastructure projects then a consequence, the CPA is forecasting actual
sector output would be expected to increase by activity growth in the infrastructure sector and
double-digit growth rates each year. sub-sectors rather than forecasting distortions in
the ONS data.
DISCLAIMER 1: The Office for National
Statistics (ONS) made major revisions to the DISCLAIMER 3: The ONS has substantially
construction output data in October 2015. The revised upward all historic data going back to
result of this was to add an extra £150-200 2016 Q2. Construction output between January
million per month from March 2015 into the and July 2017 was initially 1.3% higher than a
infrastructure sector. As a result, there is now year earlier. However, the ONS has revised this
a structural break in the ONS infrastructure up to 5.1% higher than a year earlier with the
sector and sub-sector output data and 2015 significant step up in construction output at the
ONS infrastructure data cannot be compared end of 2016 whilst simultaneously construction
with data from previous years. employment remained broadly flat.
DISCLAIMER 2: The ONS determines sub-
sector output by utilising the new orders data
and an average length of time between orders
and output. However, this means that major
one-off projects may be assigned to output

ONS Construction Output (September & October 2017 Data Releases)


126
October Release September Release
124

122
Construction Output (2013=100)

120

118

116

114

112

110

108

106

104
2015 2016 2017

Source: ONS

10
Construction Industry Forecasts - Winter 2018/19
£ million 2016
2016 2017 2018 2019 2020
constant prices

% annual change Actual Actual Estimate Forecast Projection

Housing

Private 31,189 34,334 36,051 36,772 37,139

14.9% 10.1% 5.0% 2.0% 1.0%

Public 5,102 6,205 6,081 6,142 6,142

-2.2% 21.6% -2.0% 1.0% 0.0%

Total 36,291 40,539 42,132 42,913 43,281

12.2% 11.7% 3.9% 1.9% 0.9%

Other New Work

Public Non-Housing 11,055 10,771 9,311 9,251 9,283

3.8% -2.6% -13.6% -0.6% 0.3%

Infrastructure 18,521 19,659 19,843 21,583 23,238

-3.4% 6.1% 0.9% 8.8% 7.7%

Industrial 4,572 4,710 5,134 5,261 5,492

-5.4% 3.0% 9.0% 2.5% 4.4%

Commercial 28,768 30,999 29,359 26,997 26,601

7.6% 7.8% -5.3% -8.0% -1.5%

Total other new work 62,916 66,139 63,647 63,092 64,614

2.5% 5.1% -3.8% -0.9% 2.4%

Total new work 99,207 106,678 105,778 106,005 107,895

5.8% 7.5% -0.8% 0.2% 1.8%

Repair and Maintenance

Private Housing RM&I 19,630 21,530 21,530 21,530 21,961

5.6% 9.7% 0.0% 0.0% 2.0%

Public Housing RM&I 7,581 7,391 7,391 7,391 7,391

-7.4% -2.5% 0.0% 0.0% 0.0%

Private Other R&M 12,063 13,003 13,653 13,926 14,205

5.1% 7.8% 5.0% 2.0% 2.0%

Public Other R&M 5,001 5,102 4,847 4,750 4,750

-0.8% 2.0% -5.0% -2.0% 0.0%

8,289 8,997 9,177 9,269 9,269


Infrastructure R&M
-5.8% 8.5% 2.0% 1.0% 0.0%

Total R&M 52,564 56,023 56,598 56,866 57,575

0.9% 6.6% 1.0% 0.5% 1.2%

TOTAL ALL WORK 151,771 162,701 162,376 162,871 165,470

4.1% 7.2% -0.2% 0.3% 1.6%

Source: ONS, Construction Products Association

11
Economy
After estimated growth of 1.3% in 2018, UK GDP is expected to grow by 1.4% in 2019
(assuming a revised Brexit Withdrawal Agreement that enables the UK to enter an
implementation period or a delay to Article 50 to allow a renegotiation with the EU).

UK GDP rose by 0.6% in 2018 Q3 following Growth in services output slowed to 0.5% yet,
growth of 0.4% in Q2 due to a continued catch- as it dominates UK economic activity, services
up from the loss of activity during the weather- remained the largest contributor to UK GDP
affected first quarter. In addition, growth in growth in the third quarter.
the third quarter of 2018 was also buoyed by
In terms of more recent data, the Markit/CIPS
PMI for manufacturing was 53.6 in November and
reached a six-month high of 54.2 in December.
Although the reading was above 50, the threshold
UK GDP set to grow by for expansion, the average reading during Q4
was the weakest in two years, indicating that

1.4% in 2019 activity in the manufacturing sector remained


subdued. Output and new orders both picked
up in December. Growth in new orders was
primarily driven by new product launches and
client stock-building in the domestic and overseas
increases in consumer spending. Across the markets. The December survey also showed that
different sectors, construction output growth optimism among manufacturers remained near
rose after a weak start to the year whilst the 27-month low recorded in November, due to
manufacturing output increased for the first time concerns over Brexit uncertainty, exchange rates
in 2018 after two consecutive quarters of falls. and a slowing economy.

Economic Indicators
2016 2017 2018 2019 2020

Actual Actual Estimate Forecast Projection


GDP 1.8% 1.8% 1.3% 1.4% 1.9%
Fixed Investment 2.3% 3.5% 2.0% 3.0% 2.0%
Household Consumption 3.2% 2.2% 1.6% 1.8% 2.0%
Real Household Disposable Income -0.2% 0.5% 1.0% 1.2% 1.7%
Government Consumption 0.8% -0.2% 0.5% 0.4% 0.3%
CPI Inflation 0.7% 2.7% 2.5% 2.0% 2.0%
RPI Inflation 1.8% 3.6% 3.0% 2.7% 2.7%
Bank Base Rates - June 0.50% 0.25% 0.50% 0.75% 1.00%
Bank Base Rates - December 0.25% 0.50% 0.75% 1.00% 1.00%

Source: ONS, Construction Products Association

12
Interest Rates and Inflation
Bank of England Base Rate
4.5%
CPI
RPI
4.0%

3.5%

3.0%

2.5%

2.0%

1.5%

1.0%

0.5%

0.0%

-0.5%
2013 2014 2015 2016 2017 2018
Source: Bank of England, ONS

The Markit/CIPS PMI for construction fell to work to replace projects that are completing. In
52.8 in December from 53.4 in November but addition, softer demand and cost-cutting measures
remained above the no-change mark of 50 that led to hiring activity at its lowest for 29 months.
separates growth from contraction. December’s Looking at the year ahead, optimism among
data pointed to an expansion led by civil services producers fell to the second-lowest since
engineering work. Slower growth was recorded March 2009, owing to Brexit-related uncertainty,
for housing and commercial, the latter of which concerns about the outlook for business
fell to the lowest since May. The prospect of large investment and the availability of skilled staff.
transport and energy infrastructure projects
GDP growth in 2018 Q4 is expected to slow
boosting growth in 2019 led to an uptick in
to between 0.3% and 0.4% and GDP growth
business confidence for the year ahead for the
overall for 2018 is estimated to be 1.3%. Looking
civil engineering sector, but political uncertainty
forward, almost all macroeconomic forecasters
delaying spending decisions dented confidence for anticipate a deal between the UK and EU that
the commercial construction sector. Construction enables the implementation period and the
employment continued to increase in December, average of the forecasters expects GDP growth
but the survey also showed that rising labour costs of 1.5% in 2019.
mean firms are not replacing voluntary leavers.

The Markit/CIPS PMI for services was 51.2 in


December, up from the 28-month low of 50.4 in
November but still marking one of the weakest One interest
expansions in the services sector since mid-2016.
The slowdown in business activity reflected
rate rise
subdued business and consumer spending, with expected in 2019
survey respondents attributing this to heightened
Brexit uncertainty. New business growth also
picked up marginally from a two and a half year low The Bank of England raised interest rates from
in November, but remained subdued compared to 0.5% to 0.75% in August 2018. The continued
earlier readings. Respondents noted a lack of new uncertainty regarding Brexit and UK economic

13
to Brexit. Traders have, in general, factored in
an eventual deal between the UK and EU. If this
occurs then a slight appreciation in Sterling and
slower import price inflation would be expected.
Conversely, No Deal would suggest a sharp
depreciation in Sterling, as occurred post-EU
Referendum, which would lead to sharp rises in
import inflation in addition to supply issues initially.
The former is assumed in the CPA forecast. The
issues around the latter are highlighted in the CPA
Brexit Presentation.

The Bank of England Agents’ Summary for 2018


Q4 highlights some key points about how the
Bank’s contacts see key areas of interest for the
construction industry. It reported that, overall,
construction output growth remained modest,
split by varying performance across sectors.
growth prospects in 2019 indicates that further
Growth in house building slowed in some regions,
rises would only occur once data are available
reflecting caution over weaker markets in London
illustrating that UK economic activity continued
and the southern regions by major house builders,
to grow in the first half of 2019, which would only but activity in the private rental sector and rm&i
become clear in Autumn 2019. The CPA forecast was firm. In terms of housing market conditions,
anticipates a further rate rise in the second half although intense competition among lenders has
of 2019. increased the availability of higher loan-to-value
CPI inflation slowed to 2.3% in November, mortgages, buyers were reported to be taking
slightly lower than the 2.4% in October and it is longer to commit to purchases and economic and
edging closer to the Bank of England’s target of political uncertainty had led to an increase in the
2.0%. The key driver of the slowdown in inflation number of purchases falling through. Activity in
the commercial and public non-housing sectors
during November was a fall in petrol prices, a
was reported to have slowed, particularly in
consequence of falls in the oil price since the
retail and offices, whilst growth in infrastructure
Summer. The Bank of England expects a further
is balanced by concern over delays and projects
slowdown in inflation in January and for it to
being scaled back.
remain below target in subsequent months.
Forecasting oil prices is challenging at the best of UK business investment continued to experience
times but determining the impacts of oil prices small rises following the EU Referendum in June
on UK CPI inflation is likely to be extremely 2016 and by the final quarter of 2017 it was 2.9%
challenging over the next 12-18 months given higher than in 2016 Q2, illustrating that whilst
the various uncertain factors at play. OPEC and major investments were affected by the rise
Russia’s decision to cut oil production at the end in uncertainty, the majority of smaller business
of November 2018 in addition to continual falls in investments such as IT and equipment continued
Venezuelan oil production would suggest a rise in broadly in line with UK economic activity.
oil prices during early 2019, providing an upward However, business investment fell by 1.1% in 2018
contribution to CPI inflation that would suggest it Q3 compared with the previous quarter and was
is likely to stay above the Bank’s target in the first 1.8% lower than a year ago. This was the third
half of 2019. However, global uncertainty regarding consecutive quarterly fall and business investment
demand and continual increases in US shale oil is expected to have fallen further during the final
production may offset this. The larger impact of quarter of 2018 and in the first quarter of 2019
oil, as well as other imported commodities and at the very least. The last time that business
components, on UK CPI inflation is likely to be investment fell for more than two consecutive
what occurs with the Sterling exchange rate due quarters was during the financial crisis during

14
2008 and 2009. The implication of this is that the
heightened uncertainty during 2018 and upcoming
deadline for withdrawing from the EU is not only
Unemployment 1.5 Million
2019
impacting upon the largest investments but is also
hindering general expansions, improvements and
capital investments.

The UK labour market remains buoyant in terms


of the number of people in employment. There
were 32.48 million people in work in the UK 1.38 Million
between August and October 2018, slightly above October 2018
the 32.40 million in May to July 2018 and 396,000
higher than a year earlier. The employment
rate was 75.7% between August and October
2018, matching the rate between May and July
2018 but higher than a year earlier (75.1%). The
unemployment rate was 4.1% between August
and October 2018. Between May and July, the
unemployment rate was 4.0%, which was the
lowest since 1975. Source: ONS, Construction Products Association

Although employment has continued to be


buoyant in recent years, a great concern has been
the lack of wage growth. However, in October Uncertainty regarding ‘No Deal’ is assumed
2018, average weekly earnings including bonuses to dissipate but, if it continues closer to the 29
rose by 3.3%, which combined with CPI inflation March 2019 deadline, even if a deal is eventually
slowing to 2.3% in November, implies real wage concluded, then firms would be more cautious
growth of 1.0%, which continues the real wage regarding business investment and hiring whilst
growth since December 2017, albeit still low by focusing on cost reduction and stockpiling. This
historic standards. Given increasing real wage would be expected to impact adversely on
growth, it would be expected that retail sales investment, unemployment and wage growth
would be relatively buoyant yet retail sales in the whilst slowing economic activity, rising uncertainty
three months to November rose by only 0.4% and interest rate rises may also impact on
in spite of, or perhaps because of, Black Friday in consumer confidence and spending.
November. In addition, Black Friday is likely to have
exacerbated the trend away from the high street Upside Risks:
towards online shopping, where the best deals
• UK economic growth rates accelerate
have tended to be available and, in November, UK
online retail sales reached their highest ever level • Unemployment continues to be subdued
and were 21.5% of all retail sales.
• Real wages rise significantly during 2019
Downside Risks:
If UK economic activity grows at rates of above
• Economic activity slows due to continued 0.5% per quarter or above, the unemployment
uncertainty rate would be anticipated to fall even further and
nominal wages may start to rise significantly. If
• Unemployment rises due to subdued
the lower oil prices continue and feed through
economic activity
into slower inflation, this could consequently
• Real wages growth continues to be poor ensure stronger real wage growth, which boosts
in 2019 consumer confidence and spending. In addition, a
final agreement on the UK’s withdrawal from the
• Interest rate rises impact on consumer EU would provide a boost to Sterling, lowering
confidence imports inflation.

15
Private Housing
Growth in housing starts is expected to slow from an average growth rate of 10.4% between
2013 and 2017, to 2.0% in 2019 and 1.0% in 2020.

Private sector house building is closely linked to 65,000 per month. UK property transactions
the performance of the overall housing market, have followed a similar trend to mortgage
driven by mortgage lending, property transactions lending, decreasing 0.8% in 2017, and were 3.1%
and house prices. Bank of England data show lower in January to November 2018 than in the
that after declining 1.6% in 2017, the number corresponding period of the previous year. Annual
of mortgage approvals fell 2.5% year-on-year property transactions volumes have remained
in January-November 2018, to an average of at around 1.2 million per year since 2014 and

Private Housing Starts and Completions Great Britain


2016 2017 2018 2019 2020

Actual Actual Estimate Forecast Projection

147,916 155,343 158,449 161,618 163,235


Starts
5.4% 5.0% 2.0% 2.0% 1.0%

133,561 153,552 155,088 156,638 158,205


Completions
3.1% 15.0% 1.0% 1.0% 1.0%

31,189 34,334 36,051 36,772 37,139


Output (£m)
14.9% 10.1% 5.0% 2.0% 1.0%

19,630 21,530 21,530 21,530 21,961


RM&I Output (£m)
5.6% 9.7% 0.0% 0.0% 2.0%

Source: MHCLG, ONS, Construction Products Association

16
Lending to Individuals Total Mortgage Approvals for House Purchase (number)
Remortgaging (value)
140 Total Mortgage Approvals (value) 50%

120 40%

Lending – 3 month change on a year earlier


Secured Lending - Total Approvals (000s)

100 30%

80 20%

60 10%

40 0%

20 -10%

0 -20%
Jan 15 Jul 15 Jan 16 Jul 16 Jan 17 Jul 17 Jan 18 Jul 18

Source: Bank of England

the latest data to November imply the same


level for the whole of 2018. By market segment,
in 2017 the number of purchases by first-time
buyers reached its highest level since 2007, and 2018
90.9%
UK Finance data show that lending to first-time
of new mortgage lending
buyers continued to increase throughout 2018. at fixed interest rates
In contrast, mortgage lending to home movers
and buy-to-let lending has decreased, with the
latter affected by changes to stamp duty and the

49.7%
reduction in tax relief for residential landlords.
2008
In terms of house prices, there is a varying
performance by region. According to the ONS/ of new mortgage lending
Land Registry, UK house prices rose 2.7% in
October, the slowest national growth rate since
at fixed interest rates
July 2013. Price growth was led by the North
West (4.9%), Yorkshire and the Humber (4.4%), Royal Institution of Chartered Surveyors (RICS)
the East Midlands (4.3%) and the West Midlands and the Bank of England suggest that housing
(3.8%). House prices in London have fallen
market weakness will remain concentrated in
since June and fell 1.7% in October. In inner
the capital, the South East and East of England
London, an increase in the supply of higher-end
and that appears to be a view shared by major
residential units, as well as stamp duty changes in
2014 that raised tax on higher-value properties, house builders. Barratt, Crest Nicholson and
has led to a slowdown in annual house price Berkeley have all announced a reduction in
growth in these boroughs since July 2016, with operations in London. Outside of London,
falls recorded throughout 2018. This weakening pent-up demand and a reported reduction in
appears to have spread to outer London, where the supply of existing properties for sale has
house price growth has slowed to below 1.0% contributed to the continued house price growth
each month since February, from an average of and whilst this inflation continues, there would be
12.6% in 2016 and 3.5% in 2017. Surveys from the expected to be an associated increase in house

17
Affordability House Price/Earnings Ratio
First Time Buyers’ Affordability
6.00 55

5.50
50
5.00

Mortgage Payment as a % of Income


4.50
45
Ratio

4.00

40
3.50

3.00
35
2.50

2.00 30
2009 Q1

2009 Q3

2010 Q1

2010 Q3

2011 Q1

2011 Q3

2012 Q1

2012 Q3

2013 Q1

2013 Q3

2014 Q1

2014 Q3

2015 Q1

2015 Q3

2016 Q1

2016 Q3

2017 Q1

2017 Q3

2018 Q1

2018 Q3
Source: Nationwide

building. Forecasts for UK house price inflation in from 8.8% to 13.0% and for the first half of 2018,
the HM Treasury’s comparison of independent rose to 13.7%. In Wales and Scotland, the equity
economic forecasts in December averaged 2.3% loan scheme will be in operation until March
for the year to 2019 Q4 and reflecting general 2021. In the Budget in October, the Chancellor
macroeconomic uncertainty for the year ahead, announced that in England the scheme would
projections range between 0.8% and 3.7%. be extended for a further two years to March
2023. From April 2021, however, the eligibility
A regional variance in demand for house criteria will be narrowed to first-time buyers and
purchases, and particularly new build, has been regional caps will be set for purchase prices. It will
underpinned by Help to Buy. The equity loan remain at £600,000 for homes in London, but
was introduced in April 2013, and between its be set at 1.5 times the current forecast regional
introduction and June 2018, the equity loan average first-time buyer price elsewhere, ranging
was used on 183,947 transactions in England. from £186,100 in the North East to £437,600 in
Although this accounts for only 3.4% of property the South East. This will have an impact on SME
transactions over the period, it represents 31.4% builders offering higher-end and higher-value
of new build completions. Furthermore, in the properties in the East and South East. In addition,
most recent four-quarter period, this proportion the proportion of first-time buyers using Help to
rose to 37.2%. Among the top 20 volume house Buy is lower than the national average of 80.9%
builders, the proportion of sales supported by in seven of the top ten local authorities with the
Help to Buy reaches as high as two-thirds. The largest equity loan uptake, particularly among
counterpart schemes in Scotland and Wales those in the South East and East.
have accounted for a similar proportion of
transactions and building activity. Given that Macroeconomic uncertainty provides the largest
property transactions volumes have remained risk to near-term demand and developments in
relatively unchanged during Help to Buy’s period the labour market, particularly with regards to
of operation, the equity loan is likely to be unemployment and job security, will be a key
skewing demand towards new build. In England, determinant of how house building moves in line
between 2014 and 2017, new build completions with the forecast. In addition, the Bank of England
as a proportion of property transactions rose raised interest rates by 0.25 percentage points

18
at its August 2018 meeting, marking the second of de-risking projects to attract other investment.
increase in nine months. The bank rate of 0.75% The funding is yet to be allocated, which suggests
remains at a low level by historical standards and that the house building activity from these
these increases alone are unlikely to have a material measures will occur beyond the forecast period.
impact on demand. Interest rates on new fixed- For the same reason, long-running reform to the
rate mortgages during 2018 remained below the National Planning Policy Framework (NPPF), the
interest rates available in 2016. However, combined Mayor of London’s housing strategy and long-
with constrained real incomes, hawkish statements term devolved regional housing deals have not
from policymakers may set expectations for higher been factored into the forecast at this point.
future interest rates and a worsening in mortgage
repayment affordability. The government is keen to develop the
Build to Rent sector, which covers new build
The government’s focus on increasing net supply developments for private rent that aim to
to 300,000 homes per year by the mid-2020s generate a long-term return on investment.
has resulted in a raft of policy measures since the According to the British Property Federation
Housing White Paper was published in February in 2018 Q3, there had been a cumulative
2017. These include the £5.5 billion Housing 25,665 units completed and there were 64,320
Infrastructure Fund (topped up with a further units of this tenure with planning permission,
£500 million at Budget 2018), a £1.3 billion Land concentrated mainly in London, Manchester and
Assembly Fund to acquire and prepare land Birmingham. This has potential to provide some
for development, a £630 million Small Sites uplift to house building activity, but accounts for a
Fund, the £4.5 billion Home Building Fund of very small proportion of the 5.3 million privately-
loans for SMEs, and the £1.0 billion SME loan rented housing stock in Great Britain.
finance package provided through a partnership
between Homes England and Barclays. £866 In England, statistics from the Ministry of Housing,
million was allocated to 133 projects in February Communities and Local Government showed
under the marginal viability arm of the Housing that on a seasonally adjusted basis, private
Infrastructure Fund, which aims to unblock housing starts in 2018 Q3 rose 13.9% from Q2
sites held up by infrastructure funding gaps. and were 16.7% higher year-on-year. For the first
The second tranche covers larger, strategic three quarters of 2018, starts increased 3.9%.
infrastructure projects, with up to £250 million New orders in Q3 fell 8.3% year-on-year but for
in early finance available for each bid, and an aim the year to date, were 2.9% higher due to the

Private housing completions by type (England)


100 Houses
Flats
90

80
Property Completions by Type %

70

60

50

40

30

20

10

0
2008/09 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18

Source: MHCLG

19
18.7% increase registered in Q1. Unlike starts reduce appetite for borrowing and, notably, big-
and completions, private housing output includes ticket purchases. Consumer confidence would be
change of use, such as offices to residential, and worsened further if the Bank of England raises
conversions, commonly changing a house into interest rates more than once in 2019, particularly
flats. The former accounted for 13.4% of net in the case of a No Deal Brexit to support
housing supply in 2017/18 (29,720 units), whilst Sterling. House builders would reduce starts
conversions, added 4,550 units. Net additions relatively quickly in response to any deterioration
through change of use appear to have peaked in in the general housing market but output and
2016/17 and, therefore, are expected to provide completions would be expected to hold up
less of an impetus to output growth than was initially as house builders destock, but fall from
seen between 2015 and 2018, partly due to the second half of 2019.
the diminishing stock of desirable commercial
premises for this purpose. Following an estimated Upside Risks:
2.0% rise in private housing starts and 5.0%
• UK economic activity avoids marked slowdown
increase in output in 2018, the forecasts for
growth starts and output are expected to align at • Consumer confidence maintained in line with
2.0% in 2019 and 1.0% in 2020. economic growth and a rise in real wages
Upside Risks: • Pick up in mortgage lending and property
transactions
• Renewed falls in real wages deter Help to Buy
purchases • House price growth continues at current rates
• House price weakness extends to UK regions If economic uncertainty lifts and GDP growth
and demand for home ownership increase, then
• The Bank of England raises interest rates more
mortgage lending, property transactions and
than once in 2019
house prices would be expected to pick up in
Mild growth in real wages returned in 2018, but 2019. This is especially the case given reported
an upswing in inflation due to a rise in commodity reductions in the supply of pre-owned properties
prices or further Sterling depreciation could on the market. There is also the potential for
elicit further declines in real wages. Any large government policy measures on garden cities
deterioration in consumer confidence, particularly such as Ebbsfleet to provide an earlier-than-
around job security and unemployment, would expected boost to house building in 2019.

Private Housing Output


40,000 2.0% 1.0%
5.0%
10.1%
35,000
14.9%

30,000
£ million - 2016 Constant Prices

11.5%
25.4%
25,000
9.4%
9.0%
20,000

15,000 -2.4%

10,000

5,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p

Source: ONS, Construction Products Association

20
21
Private Housing RM&I
Private housing rm&i activity is forecast to remain flat in 2019 as home improvements
spending by demographics with pension and housing wealth fails to offset the overall weakness
in household confidence, particularly for large, discretionary purchases.

Planning permission approvals The key factors that drive activity in the sector,
particularly for improvements, are property
for large householder developments transactions and consumer spending on big-ticket
items. In addition, housing wealth, pension wealth
and household savings enable activity in the
Increased 6.3% in 2015 sector as they are used as sources of finance for
rm&i activity.
Increased 5.8% in 2016
Property transactions are a key determinant of
Increased 0.9% in 2017 activity in the sector because improvements to
an existing property tend to be made with a
typical lag of 6-9 months after purchase. Property
Fell 1.4% in 2018 H1 transactions have remained around 1.2 million
per year since 2014, but due to the popularity of
the Help to Buy equity loan, new build accounts
for an increasing proportion of transactions

22
Private Housing RM&I Output
28,000

24,000 0.0% 2.0%


9.7% 0.0%
£ million - 2016 Constant Prices

5.6%
20,000 9.2% 1.6%
0.8%
2.3%
16,000
-4.9%

12,000

8,000

4,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p

Source: ONS, Construction Products Association

and is likely to have weakened the link between of moving. More significantly, retired, outright
property transactions and rm&i. In terms of homeowners who are unaffected by real wage
funding streams for rm&i work, the household falls and have benefited from long-term rises in
savings ratio has steadily declined from 10.7 in housing wealth and pensions freedom and do
2009 to 3.9 in 2017, which was the lowest on not wish to downsize are also driving activity.
record and remained at this level, on average, Since pension freedoms were introduced in
in the first three quarters of 2018. Real wage April 2015, flexible payments to over-55s have
growth returned in 2018, albeit at a low rate, but totalled £21.7 billion and according to the ONS’s
an acceleration in inflation due to higher global Family Spending survey, households headed by
commodity prices or renewed Brexit-related 50-64 year olds have the largest expenditure on
uncertainty causing a depreciation in Sterling, alterations and improvements to dwellings. For
are a key risk to consumer confidence in 2019, larger householder developments that require
especially for purchases of big-ticket items. In planning permission, figures from the Ministry of
addition, record-low interest rates between 2009 Housing, Communities and Local Government
and 2017 enabled homeowners to repay equity (MHCLG) showed that momentum in larger
back into their homes, rather than withdrawing improvements spending is easing, however. After
it as a means of funding home improvements. approvals increased 5.8% in 2016 and 0.9% in
The Bank of England raised interest rates by 0.25 2017, they fell 2.5% in the first nine months of
percentage points in November 2017 and August 2018.
2018. The impact of a cumulative 0.5 percentage
point interest rate rise is expected to be limited, In terms of energy-efficient retrofitting work, the
but the Bank has indicated that a ‘smooth’ Brexit next phase of the Energy Company Obligation
transition would elicit a further tightening in programme, ECO3, began in October, running
monetary policy over the next couple of years, to March 2022. The programme is valued at
which may have a further negative impact on around £640 million per year and focuses on
consumer confidence and appetite for credit. fuel poverty. This is lower than the £870 million
spent under ECO previously and shifts focus
Conversely, there are other drivers of sector from energy efficiency. Given its smaller scope,
activity that have been performing more strongly. activity under the scheme is likely to be lower
The Royal Institution of Chartered Surveyors than its predecessor. During the transition period,
(RICS) has been reporting a low supply of existing under ECO: Help to Heat between April 2017
properties for sale, which is providing impetus for and September 2018, the number of measures
property extensions or improvements instead installed averaged 18,287 per month, compared

23
covering costs in the case of Blenheim Centre in
Hounslow. Questions over future regulations and
policy recommendations mean work has been
slow to start, however, as evidenced by delays to
remedial work on Greenwich Square (Mace).

Output from the sector grew strongly in 2016


and 2017 but momentum weakened in 2018,
reflecting the lagged effect of falls in real wages
hindering big-ticket spending. In Q3, output fell
1.9% compared to a year earlier and was 0.6%
lower for the year to date. Output is estimated to
remain flat for the full year. No change in output
is also forecast for 2019, followed by growth
of 2.0% in 2020 as improvements in real wage
growth and consumer confidence lead to an
to a monthly average of 41,382 measures over the increase in property transactions.
previous four-year ECO programme.
Downside Risks:
From April 2018, the Minimum Energy Efficiency
Standards Regulations will require a minimum • Consumers retrench spending in response
EPC rating of E to apply to new tenancies for to higher interest rates and a low household
properties rented out in the private sector savings ratio
and will apply to all tenancies from April 2020.
• House prices fall across the UK
According to the English Housing Survey,
320,000 private rental properties have an A sharp deterioration in consumer confidence
EPC rating of F or G, representing 6.6% of the due to a UK-wide fall in house prices, constrained
housing stock of that tenure. This suggests a growth in real incomes or a rise in economic
stream of potential work in the sector, but little uncertainty could result in households taking a
has been evident so far and questions remain precautionary savings stance and cutting non-
over how effectively the regulations can be essential spending. This may also be the case if the
monitored and enforced by local authorities. Bank of England raises interest rates more than
once in 2019. Whilst these factors are unlikely to
In December, MHCLG reported that there
affect basic repairs and maintenance, they could
were 183 private sector residential buildings
have a large impact on refurbishment work,
with cladding systems unlikely to meet current
especially in the near-term.
Building Regulations. Of these, 73 had plans for
remediation. Work has started on nine and Upside Risks:
completed on five. The Housing Secretary, James
Brokenshire, has warned of enforcement action • Real wage growth accelerates
for owners and developers if no action is taken. • House price inflation increases from current
However, high-profile examples such as New rates
Capital Quay in Greenwich and Citiscape in
Croydon have highlighted the issues and delays Inflation peaked during 2017 and this may continue
regarding liability for financing and undertaking driving the higher wage settlements seen in 2018.
remedial works on privately-owned residential Combined with national house price growth at
towers. There has been no standard response, 3.0%-4.0%, this would see the prospects for rm&i
with the NHBC agreeing to pay for remediation remain positive. Whilst UK economic growth is still
on New Capital Quay, whereas the original expected to be below the long-term trend in 2018,
developers are covering the cost of work on rm&i activity could accelerate as rises in incomes
Citiscape (Barratt) and Glasgow Harbour drive an increase in property refurbishment and
(Taylor Wimpey), and the freeholder (L&G) is improvements spending.

24
25
Public Housing
Public housing starts were weak in 2018, in spite of certainty over grant funding. A growing
dependence on market-linked housing sales leaves the sector vulnerable to a deterioration in
the wider housing market.

The main driver of house building activity In light of these policy interruptions, public
by housing associations and local authorities housing starts declined 2.7% in 2015 and rose
is funding through the Affordable Homes 1.4% in 2016 and 4.8% in 2017. In 2017 output
Programme. Since 2015, government policy for rose 21.6% and completions increased 9.7%.
funding has been amended several times. This suggests that policy changes have led to the
build out of previously-approved developments,
rather than a rapid response to new funding
Housing associations and local programmes, reflecting the time taken to adjust
authorities accounted for business plans. Homes England and Greater

18.3% of
London Authority (GLA) affordable housing
completions data show that in 2016/17, three-
quarters of completed units in that period
starts and completions were for affordable rent, funded under the
in 2017, the lowest original Affordable Homes Programme. Of the
affordable housing starts that received Homes
proportion in 10 years England or GLA funding in 2017/18, typically
housing associations or local authorities, 37.9%
were for shared ownership. This was the highest
A 1.0% annual cut in social rents is in place until
proportion on record, signalling that activity is
March 2020, the Affordable Homes Programme
now beginning on the SOAHP.
2015-18 that prioritised homes for affordable
rent was switched to the Shared Ownership The change in focus to shared ownership links
and Affordable Homes Programme 2016-21 the public housing sector more closely to
(SOAHP), under which 88% of homes were to the general housing market, however. This is
be for shared ownership tenures (announced in particularly the case in London, where 57.8%
April 2016), followed by an allowance for greater of affordable starts in the first half of 2018/19
flexibility to include affordable rent in July 2017. were reported as affordable home ownership

Public Housing Starts and Completions Great Britain


2016 2017 2018 2019 2020

Actual Actual Estimate Forecast Projection

33,313 34,910 33,863 35,556 35,556


Starts
1.4% 4.8% -3.0% 5.0% 0.0%

31,355 34,383 34,383 34,727 35,074


Completions
-15.4% 9.7% 0.0% 1.0% 1.0%

5,102 6,205 6,081 6,142 6,142


Output (£m)
-2.2% 21.6% -2.0% 1.0% 0.0%

7,581 7,391 7,391 7,391 7,391


RM&I Output (£m)
-7.4% -2.5% 0.0% 0.0% 0.0%

Source: MHCLG, ONS, Construction Products Association

26
27
Public Housing Output
7,000
32.0% 21.6% 1.0% 0.0%
6,000
2.2% -2.0%
£ million - 2016 Constant Prices

6.6%
5,000
-15.3% -2.2%

4,000 -16.3%

3,000

2,000

1,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p
Source: ONS, Construction Products Association

tenures. In 2018 Q3, Homes England’s survey of for social house building, expected to be for
registered providers showed that the stock of affordable rent as announced at the Conservative
unsold shared ownership units has risen in every Party Conference in 2017. This is yet to be
quarter since 2016 Q3. The number of units that allocated, however. The paper also announced
remained unsold for more than six months also the government was abandoning plans for local
increased to the highest in three years in Q3 and authorities to sell their highest-value properties
providers noted that units were taking longer to to fund the extension of Right to Buy to housing
sell. In addition, strong house price growth has association tenants. A £200 million pilot scheme
encouraged housing associations to increase open for the extended policy began in the Midlands in
market operations to cross-subsidise affordable mid-August and following concern from the Local
operations. In the first half of 2018/19, 32.8% Government Association that local authority
of starts by registered providers in England building capacity is constrained by returning
(including London) were for open market sale and receipts from Right to Buy sales to the Treasury, a
the Homes England survey for Q3 showed that consultation was launched, proposing an easing of
providers planned to double the number of units the restrictions on combining receipts with other
for open market sale in the next 18 months. In funding streams. Barclays and Homes England
addition, in 2017/18, 47.5% of affordable homes announced a £1.0 billion SME development
were provided through Section 106 agreements, finance fund in September and it was
likely built by private sector developers and subsequently confirmed that housing associations
acquired by housing associations after completion. would also be able to apply for these loans, in
This means that as well as exposure to the cyclical combination with grant funding for mixed-tenure
open market, a proportion of housing that ends schemes. Of greater significance for the sector,
up as a social tenure may not be included in constraints on local authority borrowing for
public housing data collection. housing delivery have been loosened significantly.
Initially, an additional £1.0 billion in housing
Government housing policy has already started to revenue account borrowing was opened for
increase the role of social and affordable tenures bidding in areas of high affordability pressure in
in overall house building. In June, £1.67 billion of July, followed by the complete removal of the
outstanding SOAHP funding was allocated for housing borrowing cap in England and Wales
23,000 homes in England, excluding London, of in October. The government expects this to
which half are intended to be for social rent in increase local authority house building to 10,000
low-affordability areas. The government published units per year. In the last ten years, housing
its green paper on social housing in August 2018, completions by local authorities have averaged
confirming £2.0 billion in additional funding 1,300 per year in England, whilst local planning

28
and development departments have seen severe
budget cuts since 2010. The government’s most
recent announcement of £2.0 billion funding for
social housing from 2022 falls beyond the current
forecast period.

£3.15 billion in funding was allocated to the Mayor


of London in 2016 to provide 90,000 affordable
housing starts by 2021. This implies 22,500 per
year, which compares to 12,555 affordable starts
in 2017/18 and a five-year annual average of 9,217
starts. In the first half of 2018/19, affordable starts
in London were only 2,400. £1.7 billion of the
funding pot was allocated in July 2017, for 49,398
homes for social rent, London living rent and rents and ratings agencies have warned that
shared ownership. A further £1.67 billion funding this, alongside lower levels of grant funding and
was announced in the Spring Statement 2018, a greater reliance on market-linked housing, will
which aims for an additional 27,000 starts by the worsen housing association creditworthiness. In
end of parliament in 2021/22. This will be used to the event of a marked slowdown in the general
increase grant for social rent homes to £100,000 housing market, any changes to the planned
per home, and raise the grant rate for schemes tenure mix of development away from market-
that increase the proportion of affordable homes linked products is likely to delay start dates as
to £70,000 per unit instead of £60,000. Work on housing association business plans are changed.
the ground would be expected to start towards There is also still uncertainty over the ability to
the end of the forecast period. access finance from the European Investment
In the near-term, the increased exposure to a Bank once the UK leaves the EU. Housing
slowing general housing market is balanced with associations have £1.2 billion of borrowing lined
a clearer profile of funding for affordable housing up for upcoming projects, concentrated among
provision. Starts in Great Britain in the first half the G15 largest providers. With loan appraisal
of 2018 were weak, falling 4.1% compared to periods of around two years, this raises questions
the same period of 2017 and in Q3, starts in of whether new applications for EIB funding will
England rose 2.1% from Q2 but fell 7.3% from be pursued by the sector given uncertainties over
a year earlier. However, public housing output access once the UK leaves the EU.
increased 3.0% year-on-year in Q3 and reached
Upside Risks:
a record high level, which suggests that activity is
now beginning to accelerate in line with increased • Open market demand for housing remains
funding and AHP certainty and the recovery from buoyant
poor weather in Q1. However, given the fall in
starts in Q1 to Q3, a full-year decline of 3.0% is • Flexibility to increase housing built for
estimated for 2018, followed by a 5.0% increase affordable rent
forecast for 2019. Starts are then expected to
remain flat at around 35,000 per year in 2020. With around one-third of housing association
starts for the open market, if underlying demand
Downside Risks: remains buoyant for market sales, market rentals
and shared ownership products, this could
• Difficulties in raising finance for housing cushion the fall in social housing construction
associations activity by housing associations. If, in contrast,
• A further weakening in the housing market market conditions deteriorate and housing
undermines focus on market-linked products associations can quickly adjust business plans to
accommodate a larger proportion of affordable
Housing associations’ borrowing capacity has rental tenures instead of sales, this will help avoid
been reduced by the annual 1.0% cut to social a hiatus in activity.

29
Public Housing RM&I
Urgent remediation work on social housing towers is likely to bring work forward and displace routine
repairs and maintenance work originally planned by housing associations and local authorities.

Sector output has been on a long-term downtrend that some work may not be captured in the ONS
and fell 16.2% between 2010 and 2017 as capital output data, as it is based on a survey of contractors.
investment by the Ministry of Housing, Communities
and Local Government (MHCLG) was cut as part of Following the Grenfell Tower disaster in June 2017,
the government’s austerity drive. In addition, publicly- the typical drivers of rm&i work in the sector will
funded schemes for energy-efficiency improvements be replaced by a shift in focus towards internal
on the public housing stock have either been and external fire safety, structural investigations
and a review of the housing stock of 2.0 million
local authority dwellings and 2.8 million housing
In England association dwellings in Great Britain. The response
of local authorities to the disaster suggests that
13.6% & 11.9% public sector rm&i resources will be redirected
to prioritise fire safety measures for high-rise
of local of housing social housing towers, yet with the results of fire
investigations and a public inquiry pending, the
authority association full scale of the issue and, therefore, future works
properties properties required is unknown and extends beyond the
scope of the forecasts. The forecasts assume that
do not meet the Decent Homes Standard emergency measures will need to be carried out
as a priority on the public housing stock but are
assumed to displace other planned repairs and
heavily revised (CERT), cancelled (the Green Deal) non-essential maintenance activity given financial
or narrowed in coverage (ECO, to ECO: Help to constraints. The government has assigned £400
Heat and ECO3), whilst the 1.0% annual cut to million to fund the removal and replacement of
social rents until March 2020 will also reduce the cladding by housing associations and local authorities
revenues received by housing associations who are in England, which has been diverted from the
likely to prioritise new build and urgent remediation existing Shared Ownership and Affordable Homes
over routine rm&i. Housing associations are also Programme (SOAHP) funding pot. By December,
increasingly carrying out r&m in-house, which means £248 million had been assigned, split by £132

Public Housing RM&I Output


10,000

9,000 2.2% 2.5% 0.6%


8,000 0.0% 0.0% 0.0%
-8.1%
7,000 -4.1%
-7.4%
£ million - 2016 Constant Prices

-2.5%
6,000

5,000

4,000

3,000

2,000

1,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p

Source: ONS, Construction Products Association

30
million to local authorities and £116 million to a 1:1 replacement of homes sold through the Right
housing associations. The MHCLG’s Building Safety to Buy has not been met, as between the second
Programme statistics indicated in December that quarter of 2012 and the third quarter of 2018, there
there are 160 social housing buildings taller than 18 were 72,929 Right to Buy sales in England, but only
metres that have cladding unlikely to meet current 18,834 direct replacements started over the same
Building Regulations, split between 46 owned period, a ratio of one replacement for every four sold.
by local authorities and 114 owned by housing Alongside the social housing green paper in August
associations. Remediation work has completed on 2018, the government also launched a consultation
34 of these and has begun on a further 82 buildings, on reforming the commitment to 1:1 replacement
whilst 41 have a remediation plan in place and three and expanding the definition of a replacement to all
are still developing a plan. affordable homes, regardless of funding source.
According to the Regulator of Social Housing, in
Any uptick in urgent repair work in 2018 is unlikely
2017/18, housing associations’ spending on major
to offset the decline in output that has occurred
repairs increased 3.0% in terms of cost per unit.
in consecutive quarters since 2015 Q4. Output
Total spend on major repairs was reported at £486
is estimated to have remained flat in 2018 and
million (£466 million in 2016/17), £846 million was
spent on planned maintenance (£831 million in given limited financial capacity and remediation
2016/17) and £1.9 billion on routine maintenance work taking precedence, output is also expected
(also £1.9 billion in 2016/17). Rm&i on social housing to remain flat during 2019 and 2020. This does
has been affected by a reduction in the number of not take into account the potential for large-scale
measures installed under the Energy Companies improvement work that may result from a longer-
Obligation (ECO) and the cancellation of the Green running inquiry.
Deal in July 2015. The original ECO programme
ended in March 2017 and its successor, ECO:
Downside Risks:
Help to Heat, began in April 2017, as an 18-month • Housing association revenues reduced by a
transition before the full programme began in weaker than expected housing market
October. Under the ECO3 programme, which runs
until March 2022, the focus will shift from improving The risk of further reductions in funding, through
energy efficiency to reducing fuel poverty and the local authorities adjusting local spending priorities
annual funding for the scheme will be cut from or a weaker housing market performance affecting
£870 million to £640 million. Between April 2017 housing associations’ open market sales revenues,
and September 2018, which formed the 18-month pose a downside risk to rm&i spending. Public
transition, Help to Heat, the number of measures housing providers may also decide to delay rm&i
averaged 18,287 per month, compared to a monthly spending until the full scale of wider fire safety
average of 41,382 measures over the previous remedial work required is known.
four-year ECO programme. The government’s
social housing green paper released in August, Upside Risks:
will consult on proposals in the Clean Growth
Strategy to improve social housing properties to a • Housing associations focus on maintenance
minimum EPC rating of C. Currently, 49.4% of the
• Housing market performs stronger than expected
English social housing stock is below a C rating. If
implemented, this is unlikely to take full effect during If building homes for market sale or shared
the forecast period, however. ownership becomes less financially viable due to a
The public housing stock is likely to be diminished weaker housing market throughout 2019, housing
through the increased uptake of Right to Buy. The associations may instead focus on maintaining their
policy is expected to be extended to housing existing, revenue-earning housing stock. Conversely,
association tenants, subject to the results of a two- if the housing market remains more buoyant than
year £200 million pilot scheme in the Midlands that expected, this would raise the revenues housing
began in August. The government’s proposals for associations receive from sales of shared ownership
local authorities to sell off their high-value housing and units sold on the open market, offering
assets as a means of funding the policy have been additional funding for rm&i work. This would help to
abandoned, however. The government’s pledge for offset constrained local authority rm&i spending.

31
Public Non-housing
Following two years of falling output, public non-housing activity is forecast to remain broadly
flat across 2019 and 2020.

Sector output is largely determined by capital


funding allocated to departmental budgets by
Public Non-housing Output by Sub-sector central government and, therefore, is less affected
2017 (%) by uncertainty than other sectors that depend
on business and investor confidence. However,
Education Health recent data has shown declines in output in
50% 18% the three largest sub-sectors: education, health
and other, which includes defence and prisons.
Entertainment
Work on the second phase of the Priority School
7% Building Programme (PSBP) has been slow to
move through the pipeline, whilst work on the
Midland Metropolitan Hospital and the Royal
Liverpool Hospital is yet to restart. Both hospitals
Other
projects were switched to public funding, rather
25%
than PFI, after the liquidation of Carillion, the
Source: ONS main contractor for both projects. Public non-
housing construction output is expected to have

32
Public Non-housing Output
18,000

16,000

14,000
£ million - 2016 Constant Prices

-7.6%
12,000 0.7%
3.8%
-21.0% 0.3%
10,000
-9.6% -0.7% -2.6%
8,000 -13.6% -0.6%

6,000

4,000

2,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p

Source: ONS, Construction Products Association

decreased 13.6% in 2018, followed by a forecast lower than the previous Building Schools for the
fall of 0.6% in 2019. An uptick in activity on the Future programme. The £2.0 billion second phase
second phase of the Priority School Building (PSBP2) focuses on rebuilding individual blocks at
Programme and the two former Carillion 277 schools by 2021/22. Like the first phase, rising
hospitals is forecast to see mild growth of 0.3% cost pressures for contractors were highlighted
in 2020, along with some uplift from work by the National Audit Office as a threat to
around the Commonwealth Games to be held in achieving time and budget targets for the PSBP2.
Birmingham in 2022. According to the Education and Skills Funding
Agency’s (ESFA) annual report, five schools have
already completed under the PSBP2 framework
Education output has fallen and 30 contracts have been signed. Feasibility

40.1% since 2010


studies have been approved on approximately
120 others but are yet to award contracts.
According to the National Infrastructure and
2010

Construction Pipeline (NICP) for 2017, £400


21.2% since 2016 million of capital expenditure on the PSBP2 was
2016

expected in 2017/18, but the 2018 update to the


Q1 NICP showed only £95 million actually occurred.
If work continues in line with the projected
funding profile, activity is set to peak in 2019/20.
An additional £100 million of government funding,
In the publicly-funded education sub-sector, the
generated by the soft drinks industry levy will
primary driver of activity continues to be the
be provided for the Healthy Pupils Capital Fund
Priority School Building Programme (PSBP). In in 2018/19, to be spent on improving outdoor,
the first phase of the programme 260 schools kitchen and medical facilities in schools.
will have been rebuilt, 214 of which are publicly
funded. Work on 23 of these is yet to complete, In addition, a programme of new free schools,
running beyond the original completion schedule which are publicly-funded but operate outside
due to site difficulties or planning issues. In of local authority control, has been favoured
addition, the National Audit Office assessed there by government since 2010. The Free Schools
was a budget overrun of £286 million for the Programme has a budget of £1.4 billion per
programme, although the average cost per square year between 2016/17 and 2020/21 to open
metre of the completed schools was one-third 500 new schools by the end of the period

33
Output in the sub-sector has fallen in every
quarter since 2016 Q1 as work ends on the first
phase of the PSBP and takes time to enter the
pipeline on the PSBP2. In Q3, output fell 9.6%
on an annual basis and for Q1 to Q3 was 18.5%
lower than the corresponding period of 2017.
New orders have declined since 2018 Q1 but
on a four-quarter total basis increased 0.7%.
An 18.0% fall in output is estimated for 2018
and output is forecast to fall a further 2.0% in
and the government allocated £320 million in 2019, before an acceleration of work on new
additional funding for 140 new free schools in programmes drives growth of 1.0% in 2020.
the March 2017 Budget, although the majority is
not expected to be used until 2020. In 2017/18, Downside Risks:
55 free schools were opened. Whilst some of • Cost increases and a lack of contractor
the premises for free schools are conversions interest delay start dates on the second phase of
or refurbishments of existing buildings, the government programmes
National Audit Office has highlighted that the
low availability of sites is a key constraint on the If contractors are reluctant to sign contracts for
new build element. According to the National work due to cost inflation, the start and end
Audit Office, the Department for Education will dates for PSBP2 work could be pushed further
need to spend £2.5 billion to purchase land for beyond the forecast horizon, whilst start dates for
the free schools in the current pipeline to 2022, future schools construction programmes in Wales
but the Public Accounts Committee found that may also be delayed. In addition, high bids for
on average, land purchases to date have cost land may also push up costs for the Free Schools
19.0% above official valuations. Despite the slow Programme. It is unlikely that the government will
start to the PSBP2, work is expected to ramp up increase funding as a result, leading to a delay in
alongside the Free Schools Programme and would the start of construction.
be expected to provide output growth in 2020. Upside Risks:
Budget 2018 raised the Department for • Capital funding is brought forward
Education’s capital spending limit for 2018/19 by
£0.4 billion to £5.6 billion. Planned spending was Additional financial support for school building is
left unchanged at £5.1 billion for 2019/20 and £4.5 only likely to arise if government brings forward
billion for 2020/21. The Welsh Government’s £1.4 funding from later years of the departmental
billion 21st Century Schools programme ends in budget, as a means of covering higher cost
March 2019 but a second phase backed by £2.3 pressures in the near-term and providing
billion funding is scheduled to follow immediately confidence over start dates for new building
in 2019/20. The funding will be split between programmes.
capital allocations and the mutual investment Output in the health sub-sector has experienced
model, a new form of public-private partnership. sharp falls in output since 2017 Q2. Work in
In Scotland, work continues on the £1.8 billion this sub-sector includes publicly-funded work
Schools for the Future programme, which aims on hospitals, health centres and clinics. Among
to build or refurbish over 117 schools by March projects currently underway are the £136 million
2020. It is entirely publicly-funded, with the proton beam treatment centre in London (in
Scottish government contributing £1.13 billion in service in 2020) and the £480 million Royal
funding, and the remainder from local authorities. Sussex County Hospital, where work is expected
So far, 75 have been completed and a further to peak in 2019, prior to its 2020 completion.
25 are underway. In November, the Scottish In addition, the £160 million redevelopment
Government assigned £1.0 billion for school of Springfield Hospital, on two sites in south
rebuilding and refurbishment from 2021. London, saw contracts awarded at the end of

34
2017. Main work is expected to begin in 2019 Q2.
The largest change in the sub-sector has been
the announcement that the Midland Metropolitan
Hospital in Sandwell, and the Royal Liverpool
ProCure22
Hospital, where work was stalled by the demise pipeline: £4.0bn out of
of Carillion, will both be completed with public
funding, rather than a replacement private finance
deal. On the Midland Metropolitan, originally a
£2.7bn £4.0bn
£350 million project, it is estimated that £205
total
million of work was carried out by Carillion. now allocated
Rising costs due to site deterioration mean that
the new contract for remediation and build
completion is capped at £320 million, but the of £442 million. However, new orders rose each
work required could be as high as £400 million quarter in 2018, which reflects the award of
to include improvements that enable the current contracts for the Public Health England’s £400
hospital to continue operating in the interim. The million science campus and a new headquarters
contract for initial remedial works was awarded in Harlow, taking place in four phases between
in October, with work occurring in the first half 2019 and 2021, the new £350 million Llanfrechra
of 2019. The contract for main works is expected Grange Hospital in Gwent and an increase in
to be awarded in 2019 Q1, with completion low-value departmental refurbishments. In a small
set for 2022. The Royal Liverpool Hospital was sub-sector, orders can be volatile on a quarterly
nearer completion when it had its PFI contract basis, and were 70.4% higher on a four-quarter
terminated in September. The remainder of basis in Q3. As work completes on large hospital
the project’s fit-out and remediation work for projects already underway and the drop in new
structural and cladding issues is expected to be orders in 2016 and 2017 means the pipeline is not
completed in 2020. Further delays caused by cost replenished at the same rate, output is expected
rises or further site remediation cannot be ruled to have fallen 25.0% in 2018. Reflecting a lag
out on either project, however. between contract awards on new projects and
the start of work, output is forecast to increase
In October’s Budget, the Department of Health’s 2.0% per year in 2019 and 2020.
capital spending allocation for 2018/19 was
reduced from £6.4 billion to £5.9 billion, but was
Downside Risks:
left unchanged from Budget 2017 for subsequent • Cost rises delay projects
years at £6.7 billion in 2019/20 and £6.8 billion
in 2020/21. These levels are an increase from Rising costs, particularly for the now publicly-
£5.2 billion capital expenditure in 2017/18, but funded completion of the Midland Metropolitan
it is unclear how much of the capital budget will Hospital and Royal Liverpool Hospital, may cause
be assigned to new building work, rather than IT delays if contracts need to be renegotiated before
upgrades and equipment. In 2017/18, over £1.5 the start of works, or if further site issues arise
billion was spent on IT, plant and equipment. once work begins.
Furthermore, the department typically
Upside Risks:
underspends due to a degree of contingency.
• Capital funding is brought forward
The latest NHS smaller works framework, the
£4.0 billion ProCure22, started in October 2016 A sharp rise in costs that leads to contractors
and will provide a stream of work over the next pausing activity could also prompt the
few years. Between its start date and December government to change the existing capital funding
2018, 62 major works schemes and 21 small profile, bringing forward spending from later
works packages have started under ProCure22, years.
at a capital value of £2.7 billion.
Public non-housing other covers construction
New orders fell 55.7% in 2017 to a record low work on publicly-funded facilities such as prisons

35
and defence projects. Output growth accelerated but so far, only one (Full Sutton in Yorkshire)
between 2016 Q3 and 2017 Q4 as two large has received outline planning permission for
defence projects entered the pipeline: the £500 a £100 million development. Furthermore,
million, ten-year upgrade to the Faslane naval base the temporary closures of the current prisons
in Scotland, which began in early 2017, and the in Rochester and Wigan that would allow
£135 million works at RAF Marham in Norfolk, redevelopment of these sites, have been deferred
including a new aircraft hangar and runway and beyond the current parliament. In June 2018,
taxiway resurfacing works, which completed in the government abandoned plans to build five
mid-2018. In addition, despite the compulsory community prisons for women and whilst these
liquidation of Carillion as one of the joint venture represent small volumes of work, it signals a
partners, the Ministry of Defence’s £1.1 billion direction of policy that may weaken sector
new accommodation and facilities scheme for prospects in the longer-term. In terms of public
the Army Basing Programme on Salisbury Plain office buildings, the first £500 million tranche of
is set to provide activity throughout 2019, ahead work under the £1.0 billion Government Hubs
of the project’s completion in mid-2020. The programme, which seeks to reorganise public
programme includes 1,000 homes on Salisbury sector offices into regional hubs, mainly through
Plain and the £60 million upgrade of Catterick fit-out work, was awarded in June 2017 and is
Garrison. Two other defence contracts were expected to continue providing work through
awarded in Q4 for air base improvements at 2019. New orders in the sub-sector are volatile,
RAF Northolt (£23 million runway resurfacing) and in Q3 declined 16.2% on a four-quarter total
and £160 million of hangars and storage facilities basis. This follows a 32.9% fall in 2017. Despite
construction at RAF Lakenheath. In addition, ongoing work on the Army Basing Programme
the £149 million expansion of RAF Lossiemouth and naval and RAF facilities in England and
in Scotland is also in the early stages of Scotland, lower volumes of work after large
procurement, with contract awards scheduled for projects completed are estimated to have driven
Spring 2019. a decline in output of 5.0% in 2018. Activity is
expected to remain flat in 2019 and 2020.
Budget 2018 confirmed the Ministry of Defence’s
capital budget allocation at £9.4 billion in 2018/19
Downside Risks:
(£8.7 billion in Autumn Budget 2017), £9.8 billion • Delays to projects
in 2019/20 (£9.0 billion in the previous Budget)
and was maintained at £9.6 billion for 2020/21. Questions over contractor appetite may arise
In terms of prisons projects, there is little in the if prolonged financial and economic uncertainty
near-term Ministry of Justice construction pipeline act as a drag on confidence and activity. In
aside from the expansion of Rye Hill (£25 million) addition, contractors may pause to renegotiate
and Stocken (£24 million) prisons, which are both contracts to take account of rising costs, forming
underway. In Scotland, a £66 million new prison the main downside risks to sub-sector activity.
in Inverness gained planning approval in October Government and public opposition to the
2017 and is expected to start construction this construction of the new prison facilities in Port
year. The new £150 million HMP Wellingborough Talbot and Yorkshire would delay the entire
was approved in November and demolition English prison redevelopment programme
work on the existing prison has begun. Work is indefinitely.
expected to peak in late-2019 and 2020, ahead
of the planned 2021 completion. The Glen Upside Risks:
Parva prison in Leicestershire was closed in • Further detail and contracts for new prisons
June 2017 and final plans for a £170 million new
build replacement are expected to be approved Full planning approval for the four new prisons
imminently, with work starting in late 2019. Back announced in March 2017 would increase
in early 2017, the government announced that certainty for the sub-sector. However,
four new prisons would be built in Yorkshire, construction activity would not be expected to
Wigan, Rochester and Port Talbot as part of begin until late-2019 at the earliest, to allow for
its £1.3 billion investment in the prison estate, design and tendering.

36
37
Public Non-housing R&M
Output in the public non-housing repair and maintenance (r&m) sector consists of basic repairs
and maintenance carried out on schools, hospitals and other public buildings.

Public Non-housing R&M Output


7,000

6,000 6.0% 1.4%


£ million - 2016 Constant Prices

2.0%
0.0%
5,000 -1.4%
-2.7%
-12.8% -0.8%
-5.0% -2.0%
4,000

3,000

2,000

1,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p
Source: ONS, Construction Products Association

Basic repairs and maintenance cannot be Similarly, the Ministry of Housing, Communities
cancelled or postponed significantly, which has and Local Government (MHCLG) has identified
helped keep output less volatile than in public nine publicly-owned high-rise buildings (over 18
non-housing new build, in spite of cuts to metres) that have failed large-scale wall system
departmental funding since 2010. tests in England. This is broken down into one
school and eight hospitals. Data from December
For school buildings, a £1.4 billion investment
confirmed that remediation has started on two, is
has been allocated for 2018/19 to help improve
planned for five, with two awaiting further advice.
and maintain the condition of schools, which
matches the funding assigned each year between Pauses in activity over cladding liability issues on
2015 and 2018. However, the condition of the the Papworth Hospital in Cambridge and the
school estate is expected to deteriorate further Royal Liverpool Hospital, although PFI-funded
despite this planned investment. According to the (or originally PFI-funded) projects, highlight the
Department for Education’s own estimates, the potential issues for public non-housing buildings.
cost to return schools to satisfactory conditions For the overall NHS estate, the 2017/18 Estates
is likely to have doubled between 2015/16 and Return Information Collection found that the
2020/21. The methodology for school condition backlog of general building maintenance was £6.0
capital funding allocations for 2019/20 was billion, £1.0 billion of which was classified as high
unchanged and will match the £1.4 million annual risk and requiring immediate attention.
allocation. The results of the survey of the
condition of the schools estate, the Condition
Data Collection, will be published in Autumn
and are likely to determine if future condition
funding allocations will increase. Following the
identification and remediation of structural
63% of the NHS estate was
defects in public buildings including schools, built before 1985
leisure centres and care homes in Edinburgh
during 2018, the Accounts Commission in
Scotland has recommended that checks and
maintenance on publicly-owned buildings be
carried out across local authorities.

38
The Government Hubs Programme aims to
reduce the government estate from around
800 buildings to 200 by 2023 by creating
shared regional hubs across government
departments. The programme is expected to
save approximately £2.5 billion over 10 years.
Since 2010, the government estate has been
reduced by 28.0% with 94% of this resulting
from the disposal of public sector office space.
Further reductions in the size of the government
estate are expected to exert a downward impact
on r&m activity in the sector over the longer
term. £2.9 billion of contracts on the Defence
Infrastructure Organisation’s seven-year facilities
management framework were launched for bids
in September, to follow on from the Ministry of
Defence’s contract with Amey (formerly a joint
venture with Carillion), which ends in March 2019.

Against a backdrop of reduced grant funding


from central government, and financially-
constrained councils, output in the sector is
estimated to have declined 5.0% in 2018. On the
basis of no further increases in funding, output is
forecast to decrease 2.0% in 2019 and remain at
that level in 2020.

Downside Risks:
• Local authorities cut spending plans

• Direct funding from central government is cut


to focus on new build

A further reduction in local authority spending


power, due to budget tightening by councils or
central government shifting funding profiles to
focus on new build would reduce sector output
further in 2019 and 2020.

Upside Risks:
• Work on framework contracts limits falls in
discretionary activity

Existing long-term contracts for maintenance on


prisons and hospitals are less likely to be affected
by economic uncertainty and will provide a steady
stream of public non-housing r&m activity. Public
sector organisations may also focus on maintaining
existing buildings, rather than new build.

39
Commercial
After an estimated 5.3% fall in 2018, commercial output is forecast to fall 8.0% in 2019 and
1.5% in 2020.

In addition, ongoing work on the new delayed


Spurs stadium continues to sustain activity in the
Commercial Output by Sub-sector sub-sector longer than was initially anticipated.
2017 (%)
Entertainment
Commercial sector output rose by 7.6% during
23% 2016 and a further 7.8% in 2017. In contrast to
rising output, new orders fell by 11.3% during the
second half of 2016, post-EU referendum and
Retail
Education 17% fell by a further 8.2% during 2017. New orders
16%
Other continued to fall in the first three quarters of
25% 2018, to be 14.6% lower than the same period of
Health 3% 2017.
Garages & Misc 5%
The high volumes of activity are demonstrated
Offices
by the cranes for towers projects visible across
36% Source: ONS the country on student accommodation projects
or high-profile mixed-use schemes. Small and
medium-sized offices construction continues
apace, including refitting of space for co-working
or fit-out of existing retail space for new value
As anticipated in previous CPA forecasts, the falls supermarkets.
in commercial new orders since the second half
of 2016 are now beginning to result in weaker Looking to 2019, however, sector output will feel
activity on the ground. Activity still remains at the lagged impact of the sustained fall in new
relatively high levels, particularly in the offices orders since the end of 2016. The CPA forecasts
sub-sector, due to projects on site that were that output will fall 8.0% during 2019 before
signed up to between 2015 and the second contracting a further 1.5% during 2020. These
quarter of 2016, prior to the EU Referendum. have been revised downwards from forecasts
The lag between new orders and output in the of -7.1% in 2019 and -0.3% in 2020 in Autumn.
commercial sector has historically tended to be An increasing number of retailers experiencing
around 12-18 months, and it is only during 2018 difficulties signals a deteriorating outlook for
that we have seen the fall in new orders translate new retail construction, whilst work that is set
into declining output. to restart on the originally PFI-funded Midland
Metropolitan and Royal Liverpool hospitals will
The uncertainty following the EU Referendum now be switched to the public sector.
regarding long-term economic prospects
and returns on investment mean that major In the offices sub-sector, demand for space has
new investments in office and retail space been demonstrated by large transactions for
have become increasingly difficult to justify. existing towers in London by overseas investors
Accompanying the declines in offices and retail, from Asia and Europe. During 2018, there were
activity in commercial PFI hospitals has been hit several transactions valued over £1.0 billion,
by the liquidation of Carillion, which halted work including Plumtree Court (£1.2 billion) and 5
on the two largest projects in the sub-sector, Broadgate (£1.0 billion). However, highlighting
before the remaining works were switched to the balance between currency-related discounts
public funding. However, one bright part of after Sterling’s depreciation and heightened risk
the sector has been work in the commercial aversion, all transactions over £500 million in
entertainment sub-sector, reflecting increased London were for towers fully occupied with
activity on hotels, in spite of the growth of tenants. Take-up of offices space in Central
Airbnb, as tourist numbers continue to rise. London, also remains robust. In 2018 Q3, Knight

40
Commercial Output
35,000
7.8%
7.6%
30,000 2.4%
6.3% 2.6%
-5.3%
£ million - 2016 Constant Prices

0.0%
25,000 -8.0% -1.5%
-9.8%
20,000

15,000

10,000

5,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p
Source: ONS, Construction Products Association

Frank reported that take-up reached 3.74 million Despite strong levels of transactions for existing
sq. ft., a 12.0% increase from Q2 and 17.0% space and the Deloitte Crane Survey’s findings
above the long-term average. Three of the largest that central London office completions reached
transactions during Q3 were for Facebook’s new a record high in the second half of 2018, the
offices and firms in the Technology, Media and
Telecoms sector (TMT) accounted for 42.0% of
take-up during the quarter, overtaking the public The Deloitte London Office Crane
sector and flexible offices space. In addition, Knight
Frank reported that supply has peaked, particularly Survey found the average size
for speculative completions, which for the whole of new schemes
of 2018, are expected to be 28.0% lower than in
2017. Outside of London, Savills expects take-up
in London has
of grade A space in Manchester to have been fallen by
the highest on record in 2018, with supply at the
lowest level since 2005 and pent-up demand
a third
exerting upward pressure on rents. since Summer

41
environment of uncertainty has held back
decisions for new major construction investments
that target a long-term rate of return. Therefore,
as current projects finish, they are unlikely to
be replaced by new projects in the short-term.
It also suggests that we are likely to see further
falls in new orders until the current uncertainty
dissipates. As highlighted in previous forecasts,
the concerns regarding long-term returns on
commercial real estate have occurred since
the first half of 2016, when the UK had its
referendum on membership of the EU. The
forecast assumes that either a revised draft Brexit
Agreement passes through the UK Parliament
or, more likely, there is a delay to Article 50 to
allow time for renegotiation with the EU on a
significantly revised Brexit withdrawal agreement
that also passes through the UK Parliament. Either
of these would provide a degree of certainty in
the near-term but uncertainty would still remain
over the UK’s relationship with the EU in the
medium-term.

IPF forecasts
capital values
for offices 2.3%
falling in 2019
1.8%
in 2020

Offices new orders reached a peak in 2016


Q1, the quarter immediately preceding the
referendum, at £1.6 billion. In the second half
of 2016, new orders for offices were 20.6%
lower than one year earlier and in 2017 orders
fell a further 25.2%. New orders continued
to fall in the first half of 2018 and were 25.5%
lower than the same period one year earlier.
Furthermore, in 2018 Q1 orders were only £0.8
billion, which was half the levels recorded before
the EU Referendum. New orders rose 33.7%
in Q3, however, driven by the £300 million,
50-storey tower for the Mitsubishi Estate at
6-8 Bishopsgate. Given that the eight quarters

42
of falling new orders between 2016 Q3 and In November, it was announced that the
2018 Q2 are likely to be driven by the current £500 million second phase of the Paradise
uncertainty, it is expected to have affected the development in Birmingham city centre was
largest projects, where the expected rate of unable to commence as the £50 million required
return is over a longer period and, consequently for infrastructure and enabling works had been
riskier. It also means that it affects the part of the spent as contingency on the first phase, which
offices sector where the lag between orders and experienced cost increases and was affected by
output is longer. A CPA analysis of new orders the collapse of Carillion. A request for funding
and output indicates a lag of around 12-18 months has been submitted to the local enterprise
with the larger projects at the upper end. The partnership, but approval is yet to be confirmed.
largest falls in new orders since 2017 Q1 started
Overall, new offices construction output is
to filter through into lower activity from 2018
estimated to have fallen 10.0% in 2018. Further
Q1, but would be expected to be felt more
declines of 20.0% and 2.0% are forecast for 2019
acutely throughout 2019. Furthermore, it suggests
and 2020, respectively. Despite these falls, output
that even when the uncertainty dissipates, any
in the sub-sector in 2020 is likely to still be above
subsequent substantial rise in new orders, from a
levels in 2014 due to the rapid growth in activity
low base, will still take around 18 months to feed
in recent years.
through to substantial rises in output.

The majority of the major offices projects


Downside Risks:
entering the pipeline remain in London, which • Prolonged Brexit negotiation uncertainty
accounts for more than one quarter of the UK’s
offices construction market. Since the Autumn • Business investment is constrained by subdued
forecasts, contracts have been awarded for economic activity
Facebook’s £200 million new headquarters
Continued uncertainty in the lead-up to the
in Kings Cross, comprising 415,000 sq. ft. of
Brexit deal and throughout the transition period
offices space for completion in 2021, as well
would be expected to lead to further falls in
as the £300 million Mitsubishi/Bishopsgate
investment and a pause in taking contract awards
tower and the £100 million, 36-storey mixed-
already in the system through to work on site.
use development at 1 Leadenhall. The largest
Prolonged uncertainty is likely to mean firms
project in the pipeline remains the £650
rapidly focus on contingency and risk rather than
million contract to start the refurbishment
expansion.
of Parliament’s Northern Estate buildings in
preparation for MPs to use when the Palace of Upside Risks:
Westminster undergoes a multi-year programme
of restoration. Transport for London (TfL) is • Stronger economic growth despite rising
likely to be a driver of investment in mixed-use inflation
offices projects, with 12 major developments
• Clarity over post-Brexit implementation period
‘planned above Elizabeth line (Crossrail) stations,
raises business confidence
covering over 3.0 million sq. ft. of development
space. The first agreement was signed in August, If the economy returns to robust GDP growth of
to build a 138,000 sq. ft. nine-storey mixed-use rates of 0.5% per quarter or above, then business
project at Farringdon station, which is expected confidence and investment may also improve
to be completed in 2020. Outside of London, markedly. Additionally, confidence regarding a
the top three projects entering the pipeline in comprehensive deal between the UK and the EU
2018 were the £100 million offices and industrial after the UK leaves the EU and at the end of the
mixed-use development at Geddington Road implementation period would also be expected
in Corby, the £90 million Tunbridge Wells to boost business confidence and business
civic development and the £70 million new investment. In turn, this could incentivise new
headquarters for TK Maxx in Watford. long-term major investment in commercial offices.

43
Online sales as a proportion The ONS reported that in November the value of
retail sales was 1.5% higher than in October and
of total of UK retailing 5.0% higher than a year earlier. In volume terms,
retail sales in November were 1.4% higher than in
October and 3.6% higher than a year earlier. For
4.9% 17.8% the first eleven months of the year, sales volumes
increased by 2.7%. Internet sales increased by
in 2008 in 2018 13.1% in value terms in November 2018 compared
with November 2017, with all sectors showing
strong year-on-year growth. The British Retail
Consortium reported that in November total
The retail sub-sector has struggled in recent retail sales were 0.5% higher than a year earlier but
years. Despite poor real wage growth since the like-for-like were 0.5% lower, despite Black Friday
financial crisis and, in particular, the falls in real discounting. Non-food online sales were reported
wages during 2017, consumer spending continued to have risen 2.9% in November.
to hold up in 2018. The sector’s fortunes
According to the ONS, online sales accounted
have been more impacted by the longer-term
for 21.5% of total retailing in November, the first
structural trend of rising e-commerce shifting
time the proportion has exceeded 20.0% and the
demand for retail premises from high street highest on record, although this is likely to have
stores to industrial space for storage, logistics and been boosted by Black Friday discounting. For the
distribution. The increase in traditional high street previous ten months of 2018, online sales were
retailers entering administration and Company 17.3% of total retail, on average. In the Budget
Voluntary Arrangements (CVAs) suggests issues in October, the Chancellor announced a digital
for those that are struggling to come to terms services tax from April 2020 for online firms with
with the long-term trend away from the high global revenues above £500 million. However,
street and towards internet shopping as well as this is narrower in scope than anticipated and will
how to provide a balanced offering that meets only apply to online marketplaces, rather than
the needs of changing consumer preferences. direct sales.

44
The retail sector has been keen to highlight the Supermarket chains such as Aldi and Lidl, with a
recent revaluation of business rates and rising staff focus on a value offering, continue with expansion
costs due to the increase in the living wage but the plans, in spite of the challenging retail conditions
bigger issue appears to be the large oversupply of and, potentially, because of it. Seven of the top
retail units given the structural change away from 20 retail projects that signed contracts in 2018
the high street towards online shopping without were by Aldi and Lidl. Aldi, the UK’s fifth largest
a subsequent sharp fall in retail rents, which have supermarket by market share in 2018, operates
been broadly flat since mid-2016. 827 stores in the UK and opened a further 70
new UK stores in 2018 as part of its plans to
reach 1,200 stores by 2025. Lidl, the seventh
largest retailer, is currently in its £1.45 billion UK
Retail new orders investment plan, opened 50 stores and revamped
30 others in 2018 and is actively advertising for 60
fell to new sites per year. However, as stated in previous
forecasts, the value chains have refocused from
a record low in 2018 Q3 initial out-of-town stores and are increasingly

The troubles on the high street during 2018


have been highlighted clearly by the liquidations,
administrations and CVAs of traditional retailers.
In 2018, high-profile high street names such as
House of Fraser, Mothercare, Marks & Spencer
and Debenhams all announced financial difficulties
and store closures, which follows on from the
administrations of the UK arm of Toys R Us and
Maplin Electronics during the first quarter of 2018.
Retail vacancy rates at the national level were 12.6%
in 2018 Q3 according to Knight Frank, marginally
higher than the 12.4% in the first half of 2018.
Whilst retail vacancy rates are not rising rapidly
as yet, Knight Frank also stated in September that
retailers are reluctant to commit to new sites and
leases until they have greater clarity as to whether
others are vacating or remaining on compromised
terms. In addition, they highlight that uncertainty
in occupier markets is extending to investment
markets and most investors are adopting a “wait
and see” attitude. This is in line with Investment
Property Forum (IPF) forecasts for retail values
to fall 3.3% in 2019 and 1.9% in 2020 for standard
retail, and values for shopping centres to decrease
5.4% in 2019 and 3.2% in 2020. Knight Frank has
also noted limited transactions in retail units and
centres with large floor space. Shopping centre
management firm, Intu, announced in November
that it was cutting dividends to shareholders to
protect its capital investment programme. Its plan is
to diversify its centres, by reducing retail floor space
and increasing residential, leisure and hotel space.

45
looking at taking over smaller existing urban retail 1.5 million sq. ft. building that is expected to be
units aimed at the convenience market. These completed in 2022. In September 2018, Croydon
smaller stores of around 8,000 sq. ft. open their Council issued notices to landowners and other
opportunities in cities, particularly in London, affected parties around the proposed site that
where the margins are higher and where they the Compulsory Purchase Order (CPO) process
can potentially take over sites from distressed was to begin and the Croydon Partnership, a joint
retailers. Similarly, Poundstretcher announced a venture between Unibail-Rodamco-Westfield
plan to double the number of retail outlets to 433 and Hammerson, will take possession of the site
stores by 2022, prioritising vacated high street in 2019.
stores, rather than new build premises.
Initial works on the £1.4 billion Brent Cross
In response to the growth of value chains, which extension started early in 2018 but it was
now account for 13.1% of supermarket sales, announced in June 2018 that main construction
Tesco has launched a value offering, Jack’s, in two work on the shopping centre redevelopment
locations in Chatteris, Cambridgeshire, and at has been delayed by six months and will only
Immingham, Lincolnshire. It is anticipating opening now start in January 2019. This will also push the
between 10 and 15 stores in 2019 although many completion date back from September 2022
of these will either be next to existing stores or to March 2023 but the key concern must be
in converted Tesco stores. Further stores beyond that in a declining retail sub-sector, especially in
next year will be dependent upon the success the shopping centre category, in 2019, investing
of the two existing stores but the concern must £1.4 billion in a shopping centre extension
be that it will merely take market share from may become increasingly difficult to justify. In
its existing Tesco stores rather than offset the October, Hammerson, the developer, announced
growth of value chains. that it was considering shifting the weighting of
units away from retail, potentially to offices and
Apart from value chains, the key driver of activity residential.
in the retail sector from 2019 is still expected to
be the £1.4 billion Croydon Partnership project, After several delays, the £1.6 billion takeover of
which the Mayor of London gave final approval the commercial phase of Battersea Power Station
in January 2018 and will see the current Whitgift by a Malaysian investment management firm was
and Centrale shopping centres replaced by a finalised in December. The development will

46
include 540,000 sq. ft. of office space, of which University applications
500,000 sq. ft. has already been let to Apple, and
700,000 sq. ft. of retail space. However, at the for 2018 by domicile:
time of the deal, 420,000 sq. ft. remained unlet. Non-EU:
UK: EU:
As in previous CPA forecasts, the headwinds
+3.4% +11.1%
facing the UK retail sector are primarily due to -2.6%
structural changes, although a slowdown in retail (Source: UCAS)
sales at the end of 2018 will worsen the near-
term financial woes of high street retail. New
PFI education output doubled between 2012
orders in the retail sector fell by 9.3% in 2017 and
and 2017, primarily driven by major investments
fell to a record low in 2018 Q3. For the first three
by universities attempting to compete at a
quarters of 2018, new orders were 33.3% lower
global level by improving accommodation and
than a year earlier. The decrease in orders is likely
infrastructure facilities. The most high profile of
to take around 9-12 months to feed through into
these remain the ten-year plans valued at £1.0
output, during 2019. The decline in orders in 2017
billion each by the University of Cambridge
has seen output fall in the first nine months of
(including a £250 million physics laboratory
2018 and a contraction of 10.0% is estimated for
and facilities hub to start in early 2019), the
the whole year. A further 4.0% fall is forecast for
University of Manchester, University College
2019, a revision down from the previous forecast
of -2.0%. Output is then forecast to remain flat
in 2020 due to concern over progress on the
Croydon and Brent Cross projects.

Downside Risks:
• Stubborn inflation and subdued real wage
growth

• Rising unemployment

If exchange rate weakness means inflation


accelerates in 2019 and real wages fall again in
2019 then this would be expected to impact
on consumer confidence and spending. Any
significant rise in unemployment, albeit from
historic lows, would also be expected to
adversely affect consumer confidence and
spending. Both of these would also be likely to
shift spending further towards cheaper online
offerings.

Upside Risks:
• Stronger than anticipated UK economic growth

• Real wage growth

• Unemployment falls

Stronger UK economic growth at rates above


0.5% per quarter, real wage growth and further
falls in unemployment would be expected to
boost consumer confidence and spending.

47
London (in which the £200 million East Campus a 12.0% fall in output is estimated for 2018 before
Building will start in 2019 and undergo a phased a further decline of 3.0% in 2019 as activity on
opening from September 2022), the University major university programmes eases. Activity is
of Glasgow and a joint programme between the then expected to remain flat in 2020.
University of Warwick and Coventry University.
However, over the past year, there have been Downside Risks:
increasing concerns about the sustainability
• R ising construction costs hinder viability of
of these investments given their reliance on
university projects
increasing student numbers and increasing
student fee income. For 2018 entry, university Cost overruns on the initial phases of major
applications fell 0.9% on an annual basis, with a fall investment programmes at the University of
in applications from UK students outweighing a Cambridge due to lack of project management
rise in applications from EU and non-EU students. experience may occur at other universities that
In addition, there have also been concerns about have major investment programmes. If so, this
the ability of universities to contract out and may reduce activity on further phases.
manage large investment plans. The University of
Cambridge’s audit committee highlighted some Upside Risks:
of the problems facing an academic institution
that is attempting to get involved in real estate • Increased funding from non-EU students
development on an unprecedented scale for the Further rises in student fees and rises in non-
first time and PwC reported that construction EU students could incentivise further university
costs for phase 1 of the Cambridge investment campus and accommodation investment,
programme rose from £259 million in July 2013 to especially given the increased competitive
£378 million in July 2015. environment for universities seeking to attract
More recent contract awards in the sub-sector students.
have focused on smaller universities projects such
The prospects for the PFI Health sub-sector
as the £56 million Royal College of Art campus in
have weakened from previous CPA forecasts
Battersea for completion in Summer 2020, a £55
during 2018. After the liquidation of Carillion in
million student accommodation village at Exeter
January 2018, work had been paused on the two
University, with two phases of completion in 2020
largest projects in the sub-sector, the £450 million
and 2021, a £54 million accommodation project
Royal Liverpool Hospital redevelopment and the
for the new University Campus of Football
£350 million Midland Metropolitan Hospital. The
Business in Wembley and a £55 million redesign
Royal Liverpool Hospital redevelopment was over
and refurbishment of student accommodation at
70% complete at the point of Carillion’s demise
Kingston University. Larger projects return in the
and was originally expected to finish in May 2018.
longer-term pipeline, subject to planning approval,
Failure to secure private funding for remediation
and include plans for a new university in Milton
Keynes and a £100 million project to rebuild the and remaining works on both hospitals saw the
Glasgow School of Art’s Mackintosh Building
following a fire in June 2018. PFI Health
PFI education output has risen for six consecutive new orders
years on the back of university investment plans.
Output in the sub-sector rose by 12.7% in 2015,
8.6% in 2016 and a further 9.7% in 2017. However,
output has been falling steadily since its peak in
2017 Q1 and was 21.1% lower than this peak in
2018 Q3. New orders in PFI education in 2017
were 7.5% lower than in 2016 and new orders
during the first three quarters of 2018 were 17.1% 11.4% lower
lower than one year earlier. Based on new orders, in 2018 (Q1-Q3)
48
government agree to take over responsibility for in every year except 2014 and have reached
completing the projects. As a result, this activity such low levels that one or two small projects
will now occur in the public non-housing health is enough to lead to a significant rise in orders,
sub-sector. although the construction activity from these
projects would be spread over two or three years
Private healthcare providers’ appetite for
and so would contribute little to output. New
expansion has been reduced in recent years,
orders during the first three quarters of 2018
due to a fall in referrals from the NHS and lower
numbers of overseas patients coming to the were 11.4% lower than a year earlier. Output in
UK for private treatment. This resulted in the the sub-sector in 2016 was 13.7% higher than in
cancellation of two planned £70 million private 2015 but output fell by 26.3% in 2017. Overall,
hospitals in Milton Keynes and Manchester. There output is estimated to have fallen 4.0% in 2018.
are still some lower-value private healthcare A further decline of 5.0% is forecast for 2019,
projects entering the pipeline, however, including reflecting the removal of two major PFI projects
the £50 million Pirbright Institute research from the sub-sector, before output remains at
laboratory in Surrey, which reached the stage of this level in 2020. The cancellation of PFI and PF2
contract awards in December. Construction is for new projects in Budget 2018 also constrains
scheduled to start in Q1, until the 2021 opening. sub-sector growth in the longer-term beyond the
In addition, the first large project on the £500 forecast period.
million four-year Private Investment Construction
Framework for healthcare was awarded in Downside Risks:
April, for a £65 million acute care hospital in
• Rising construction costs hinder project viability
Birmingham, due to be completed in Winter
2020. Designs for two research facilities at the Continued construction cost inflation may
Harwell Campus in Oxfordshire were submitted increase risk aversion of private healthcare
in September, with an estimated £100 million providers who have already consolidated
cost to build, and approval was granted in July expansion plans due to fewer patients from the
for Nuffield Health’s £60 million private cardiac UK and abroad.
and general surgery units at St Bartholomew’s
Hospital in London. Construction work is set Upside Risks:
to occur over the next three years. The £25
million Sight and Sound Centre project at Great • The number of private sector hospital projects
Ormond Street Hospital began in Autumn and is increases
expected to be completed in 18 months with the
Private healthcare providers have increased
centre due to open in 2020.
development in recent years and a small number
New orders in the sector peaked in 2006, of medium-sized projects would be enough to
when PFI was the preferred method of financing drive growth in the sub-sector during both 2019
hospital builds. Orders have subsequently fallen and 2020.

49
Private Non-housing R&M
Output in the private non-housing repair and maintenance (r&m) includes basic repairs and
maintenance of offices, shops, warehouses, factories and other privately-owned properties and is
dominated by work on offices and retail units.

Household consumption growth the government’s expansionary fiscal policy. By


contrast, household spending increased 0.5%
is set to reach £ £ £ £
£ £
£
£
£ £ ££ £
£ £
quarter-on-quarter in Q3, unchanged from
Q2, driven by warmer than usual weather.
a seven-year low of £ £ However, looking ahead, growth is expected to

1.2% in 2019 £ £ £ be constrained by weak real wage growth and


low savings and according to the OBR, consumer
£
(Source: OBR) spending is forecast to rise at its slowest pace
since 2009 in both 2019 and 2020.

Overall, output in the private non-housing r&m


The two key determinants of activity in the sector tends to be less volatile than new build,
sector, business investment and consumer given the reliance on facilities management
spending, continued to paint a mixed picture in contracts. Carillion was the UK’s second
the third quarter of 2018. Business investment largest construction, facilities and property
declined 1.1% on a quarterly basis in Q3, management company and, despite its liquidation
following a 0.4% fall in the previous quarter and in January 2018, government and key private
marked the sharpest decline since 2016 Q1 (see sector clients remain committed to sustaining
Economy). This was also the third consecutive facilities management services. The impact of its
quarterly fall, the first time this has occurred collapse on activity has, therefore, been limited.
since the global financial crisis, which can be Furthermore, remedial work to replace some
attributed to the impact of ongoing Brexit-related of the insulation materials on the public-private
uncertainty on business confidence and decision- partnership (PPP) Papworth hospital project in
making. Although such effects are expected Cambridge is currently underway and is expected
to persist in the near-term, the Office for to support activity in the near-term. As a result,
Budget Responsibility (OBR) forecasts business following an estimated increase of 5.0% in 2018,
investment growth to pick up from an estimated output growth is forecast to rise by 2.0% in both
0.5% in 2018 to 2.3% in 2019, supported by 2019 and 2020.

Private Non-housing R&M Output


16,000
5.0% 2.0% 2.0%
14,000 7.8%
5.1%
2.9%
£ million - 2016 Constant Prices

12,000 7.1%
2.3% 3.6%
7.1%
10,000

8,000

6,000

4,000

2,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p

Source: ONS, Construction Products Association

50
Downside risks: Upside risks:
• Weaker than expected growth in business • Stronger than expected growth in business
investment and household spending investment and consumer spending

A prolonged period of heightened uncertainty Greater clarity over the future UK-EU relationship
over the UK’s future relationship with the EU and in the short-term, alongside stronger global
slower economic and real wage growth is likely economic conditions that strengthen business
to weigh on business and consumer confidence confidence and investment intentions is likely to
in the near-term. In this case, consumers and pose an upside risk to the sector. This, coupled
businesses are expected to rein back spending with a marked improvement in consumer spending
and investment plans respectively, restraining amid lower inflation and rising real wages, is likely
activity in offices and retail. to boost activity in the sector further.

51
Industrial
The outlook for the industrial sector remains bright, with output projected to increase 16.6% by
2020, as growth in warehouses, driven by e-commerce, offsets declines in factories.

Output in the industrial sector is forecast to Industrial Output by Sub-sector


increase 2.5% in 2019, an upward revision from 2017 (%)
0.4% predicted in the Autumn forecasts due to
stronger growth expectations for warehouses,
Warehouses
before accelerating to 4.4% in 2020. Growth will
45%
primarily be driven by the warehouses sub-
sector, which is expected to enjoy double-digit
growth over the forecast period driven by a
strong pipeline of projects, as the ongoing shift
towards e-commerce continues to fuel demand
for warehousing and distribution space. This is Factories
Oil, Steel
expected to offset the weakness in factories, 54% & Coal

where construction output is predicted to fall 1%


due to a limited pipeline of new work and slower
global economic growth. By the end of the Source: ONS

forecast period, industrial output is projected to


total £5.5 billion, 16.6% higher than in 2017, but Growth forecasts for factories have been
22.1% lower than its peak in 2006. downgraded since the Autumn forecasts, with
output now expected to contract 5.0% in 2019
Industrial output growth to slow from and 2.0% in 2020 due to a lack of projects with
contracts signed in the pipeline. New orders
in factories have declined in each quarter since
2017 Q3, which is expected to filter through
to lower activity on the ground. The primary
determinants of sub-sector activity are industrial
9.0% 2.5% production and manufacturing output and,
while both increased in Q3 following a decline
in 2018 in 2019 in Q2, the longer-term picture remains one
of a slowdown. In Q3, manufacturing output
rose 1.3% in annual terms, down from 2.0%
in Q2 and marked the weakest growth since

52
2016 Q3, reflecting the underlying weakness in Factories new orders fell
domestic demand, as well as weaker growth
in the Eurozone, the UK’s largest trading
partner. This is consistent with industry surveys,
34.3% year-on-year to
notably, IHS Markit/CIPS, which reported
weaker manufacturing activity in July and
£300m
August 2018. Furthermore, the latest survey in Q3, the lowest
for December showed that the average PMI in seven years
reading for Q4 was the weakest since 2016
Q3, whilst optimism among manufacturers was
at a 27-month low. Despite slower Eurozone an SMMT Brexit impact survey carried out in
economic conditions and the fading effect of November 2018, nearly one-third of businesses
the past Sterling depreciation, UK exports of reported that they had postponed or cancelled
goods increased 3.2% in annual terms to a investments decisions in the UK due to Brexit,
record high of £88.9 billion in Q3, which is likely with one in five having already lost business as a
to be attributed to robust demand from non- direct consequence.
EU countries such as the US. However, looking
ahead, slower global economic growth and rising Downside risks:
global trade tensions are expected to dampen
export growth and, according to the EEF/BDO • Manufacturers delay or cancel investment
manufacturing outlook survey for Q4, growth in plans
the manufacturing sector output is forecast to • Weaker domestic and global demand
slow from 1.1% in 2018 to 0.3% in 2019.
If manufacturers continue to delay or cancel
In terms of the project pipeline, works at major long-term investment plans and possibly
Aston Martin’s £200 million manufacturing shift production outside the UK in the near-term
facility in South Wales, JCB’s new 350,000 sq. amid heightened Brexit-related uncertainty, this
ft. factory worth £50.0 million in Staffordshire poses a downside risk. Furthermore, a marked
and Berkeley Group’s 150,000 sq. ft. modular slowdown in domestic demand and weaker
home manufacturing facility in Kent are currently external demand due to slower global economic
underway and due for completion in 2019. growth and escalating trade tensions are likely to
Looking ahead, activity will be supported by weigh on manufacturing activity.
plans to build a new £80.0 million UK Battery
Industrialisation Centre in Coventry (UKBIC), Upside risks:
which forms part of the government’s £246
million Faraday Battery Challenge. After • Stockpiling activity boosts manufacturing
receiving planning approval in November 2018, output
works are expected to commence this year and • A fall in Sterling and stronger global growth
be completed by 2020. Other notable projects boosts exports
in the pipeline include Siemens’s £200 million rail
factory in Hull and Forterra’s plan to build a new Recent industry surveys (IHS/Markit, EEF and the
factory in Leicestershire that has an expected SMMT) revealed that some UK manufacturers
cost of between £90 and £95 million. However, are currently stockpiling in order to avoid any
there are no indicative start dates for both potential supply chain disruptions in the event of
projects and, as a result, there is little in the way a No Deal Brexit. If manufacturers continue to
of new work. Furthermore, over the past 12-18 undertake such precautionary measures in the
months, ongoing Brexit-related uncertainty short-term amid heightened Brexit uncertainty,
has continued to dampen business confidence this is likely to provide a temporary boost to
and investment in the UK’s automotive and manufacturing activity. A Sterling depreciation
aerospace industry, with several manufacturers and stronger global economic growth that
holding back major long-term investment supports UK export activity in the near-term
decisions awaiting further clarity. According to presents another upside risk.

53
The outlook for the warehouses sub-sector nearly two years in Q3, due to the temporary
remains bright, with double-digit growth rates effect from the unusually warm weather. This
forecast for both 2019 and 2020 even though was mirrored in the volume of retail sales, which
economic and consumer spending growth is set increased 3.5% year-on-year in Q3, up from 2.8%
to remain modest. Official figures show that both in Q2. This also marked the strongest growth
these drivers recorded the strongest growth in in two years driven primarily by online sales,
which accounted for 18.0% of all retail sales

The £350m in Q3, the highest proportion since quarterly


records began in 2008. Although more recent
data from the British Retail Consortium show
distribution centre near that retail sales growth slowed in November,
Magna Park will provide: the online penetration rate rose to an all-time

3.6m sq. ft. of


high of 33.8%, reflecting the ongoing structural
change within the retail industry. This, in turn, has
continued to underpin demand for warehouses
warehousing space, and distribution space and, according to BNP
and 3,000 car parking spaces Paribas, total take-up for distribution warehouses

Industrial Output
6,000 4.4%
9.0% 2.5%
11.6%
5,000 3.0%
-5.4%
16.0%
£ million - 2016 Constant Prices

9.5%
4,000

-9.5% -9.2%
3,000

2,000

1,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p
Source: ONS, Construction Products Association

54
of more than 100,000 sq. ft. reached 22.2 million A major downside risk to sub-sector growth
sq. ft. in Q3, a 13.2% increase compared with a emerges if consumers rein back their spending
year earlier. By region, the Midlands recorded sharply in the face of a renewed rise in inflation
the highest take-up, accounting for 35.4% of and falling real wages. Faced with lower retail
total take-up, followed by the South East (19.4%) sales, retailers may cut back on expansion plans,
and the North West (16.6%). Furthermore, denting demand for warehousing and distribution
Q3’s report from BNP Paribas revealed that 9.1 space. This, alongside a fall in speculative
million sq. ft. of speculatively developed units are development activity due to heightened Brexit-
expected to be completed by the end of 2018, related uncertainty would result in lower activity
slightly surpassing its peak in 2016. Looking ahead, over the forecast period.
it stated that major port expansions planned at
Tilbury 2 and Felixstowe should support activity. Upside risks:
New orders in warehouses increased 9.5% year-
• Stronger than anticipated consumer spending
on-year in Q3 however, quarterly orders tend to
growth and a lower Sterling boosts online
be volatile, and on a four-quarter basis, were still
retailers and manufacturers demand
13.0% higher than a year earlier, largely due to
respectively
the contract award for Amazon’s 500,000 sq. ft.
distribution centre project at the East Midlands • Higher demand for warehousing facilities linked
Gateway in Leicestershire. This growth in new to port expansions as a result of Brexit
orders is expected to filter through to activity on
the ground and, as a result, warehouses output is Stronger-than-expected growth in real incomes
forecast to increase 10.0% in both 2019 and 2020, that boosts consumer spending, alongside
which also reflects work occurring on the £350 stronger export growth supported by a lower
million distribution centre project near Magna Sterling exchange rate and healthy global growth
Park in Leicestershire. should buoy retailers’ and manufacturers’ demand
for warehousing and distribution space. Demand
Downside risks: may increase further if requirements for industrial
• A sharp slowdown in consumer spending warehousing and logistics facilities, including
bonded warehouses and cold storages close to
• Speculative development declines due to all UK exit and entry points such as ports and
heightened economic uncertainty airports, surges ahead of Brexit.

55
Infrastructure
The outlook for the infrastructure sector remains unchanged since the Autumn forecasts, but
there are ongoing concerns over the delivery of major infrastructure projects.

Please note that the ONS has issues with its Infrastructure Output by Sub-sector
measurement of the sub-sectors in infrastructure. 2017 (%)
Firstly, the ONS’s methodology means that although
the level and growth of total infrastructure overall Harbours
Electricity
may be fine, sub-sector output is determined by 3%
45%
the relationship between new orders and output Water &
Sewerage
in the medium-term, often determined by projects
12%
within five-year spending plans in regulated sectors.
However, if a new order for a major project in the
sub-sector is placed, this may underestimate the
Gas, Air &
time taken for it to provide activity on the ground Communications
and overestimate the amount of activity in one 4%
Roads
quarter or year. An example of this may potentially
Rail 15% 21%
be the extent of recent growth in water & sewerage
due to the Thames Tideway Tunnel project. Secondly, Source: ONS
the ONS only surveys firms that are officially
classified as contractors so if the activity is done
by an engineering firm then it will not be covered.
This applies to all construction sectors and firms
Infrastructure that do construction work but are not technically
output contractors. However, this issue impacts most upon
infrastructure. Therefore, given concerns regarding
forecast
8.8% 7.7%
the ONS’s data on infrastructure output, especially
to rise at sub-sector level, the forecasts are not purely
& based on the ONS output data but take into account
in 2019 in 2020 recent industry surveys and pipeline evidence. This is
particularly the case for the roads sub-sector.

56
Output in the infrastructure sector is forecast to
increase 8.8% in 2019 and 7.7% in 2020¸ driven
by construction works occurring on large-
scale infrastructure projects in the rail, water
& sewerage and electricity sub-sectors such as
HS2, the Thames Tideway Tunnel and Hinkley
Point C. However, as highlighted in previous CPA
forecasts, there remain concerns over delivery
to time and budget. In the October Budget, the
government increased the size of the National
Productivity Investment Fund (NPIF) from £31
billion to £37 billion and extended it by one year
to 2023/24. However, the annual NPIF spend
is expected to be broadly flat over the next
four years. Furthermore, as part of the NPIF,
the government also extended the £1.7 billion
Transforming Cities Fund by a year to 2022/23. published its final determination on Network
In November 2018, the government updated the Rail’s spending plans for CP6, which showed
National Infrastructure and Construction Pipeline, that the total expenditure is expected to be
setting out £413 billion worth of planned private £1.8 billion higher than its funding envelope.
and public investment over this Parliament, with Nevertheless, the ORR approved Network Rail’s
£188 billion worth of projects from 2018/19 to £34.7 billion spending plans, allocating £31.0
2020/21, which is £6.0 billion higher than the £182 billion for England and Wales and £3.7 billion for
billion previously estimated in December 2017. Scotland. Although the focus of CP6 will remain
However, it is the delivery of these infrastructure on maintenance and renewals, it is also expected
announcements that will be key. By the end of the to see the delivery of projects deferred from
forecast period, infrastructure output is projected CP5, including the Great Western electrification
to total £23.2 billion, £3.6 billion (18.2%) higher and Phase 2 of the East West Rail project.
than in 2017 and the highest level on record. Furthermore, a £2.9 billion upgrade to the
TransPennine Route between Manchester and
Rail construction output is forecast to increase
10.0% in 2019, driven by ongoing works on the Leeds is expected to occur from 2019 to 2024.
£655 million Bank station capacity upgrade Activity will also be underpinned by electrification
project and the £1.2 billion Northern Line of cross-country routes, including the Great
extension to Battersea. The latter project was Western Main Line between London and Cardiff,
due to open in 2020, but it is now thought to be which is due to be completed this year, and the
running at least 12 months behind scheduled and Midland Main Line between London and Bedford,
over budget due to design changes to the tube which is scheduled to be completed in 2020.
station. As a result, the project is expected to However, given that three electrification schemes
open in 2021 at the earliest. Furthermore, main on the MML, GWML in South Wales and the
construction works on the £263 million London Lakes Line (LL) from Oxenholme to Windermere
Overground extension to Barking Riverside were all cancelled in July 2017, owing to cost
and major upgrading work on the East Coast overruns, further delays or cancellations on major
Main Line are expected to commence this year. electrification projects cannot be ruled out.
Growth will also be supported by works under
the next five-year Control Period 6 (CP6), which Construction
will run from April 2019 to 2024 and has a total
budget of £47.9 billion, compared to £38.3 billion
allocated for the current control period, CP5
of the 4.5km
(2014-2019), of which £34.7 billion will come
Barking
directly from government grant. However, in Riverside extension
October 2018, the Office of Rail and Road to start this year
57
Infrastructure Output
30,000

25,000 7.7%
8.8%
£ million - 2016 Constant Prices

6.1% 0.9%
22.6%
20,000 8.4%
2.3%
-3.4%
15,000
-10.6% -2.1%

10,000

5,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p
Source: ONS, Construction Products Association

Work on the Crossrail project (also known as November 2018, the tender process for the
the Elizabeth line) is now 95% complete and is Birmingham Curzon Street station commenced,
in its final stages of testing and commissioning with bidders expected to be shortlisted in
and station building. In December 2018, the Spring before contract award in 2020. However,
government and Transport for London (TfL) anecdotal evidence suggests that main works on
confirmed a new financing package to deliver the HS2 are expected to be delayed by more than
final stages, which marked the third financial rescue a year and the costs for the main works civil
plan in six months. This comes after previous contracts are expected to exceed the budget of
funding announcements of £590 million in July £6.6 billion. Reflecting this, as well as the poor
2018 and £350 million in October 2018, as well track record of delivering major infrastructure
as the announcement in August 2018 that the projects to time and budget suggests that further
opening of the central section of the Elizabeth delays cannot be ruled out.
line has been delayed until at least Autumn 2019.
According to a review by KPMG, additional capital Downside risks:
funding in the region between £1.3 billion and £1.7
• Main works on HS2 delayed further
billion would be required due to this delay and, as
a result, a total of £2.15 billion additional funding • Work slows under CP5 as the programme
was committed. This includes a £1.3 billion loan comes to an end
from DfT, a £100 million cash contribution from
the GLA and a £750 contingency loan facility from • Additional funding requirements for the
the DfT. Overall, this suggests that the total cost of Crossrail project impacts delivery of other
the project is now £17.6 billion, up from the £14.8 London projects
billion estimated in 2009. With the revised Autumn
A main downside risk to rail growth emerges if
2019 opening date yet to be confirmed, further
main construction works on Phase 1 of the HS2
delays and cost overruns into 2020 are expected.
project are pushed back further. Moreover, higher
Consequently, the Association expects the project
to be completed by the second half of 2020. construction costs fuelled by inflationary pressures
could also exacerbate the project’s budget issues,
Looking ahead, output growth is forecast to pushing the total cost of HS2 above the estimated
accelerate to 20.0% in 2020, driven by main £55.7 billion. Also, a potential hiatus between the
works occurring on the £55.7 billion High end of CP5 and the start of CP6 could slow the
Speed 2 (HS2) rail project. Phase 1 of the delivery of projects. The extra capital funding
scheme (London to Birmingham) includes committed to Crossrail in December 2018 will be
the construction of four new stations and in partly funded through tax revenues earmarked

58
for Crossrail 2, leaving that project with a funding Hornsea Project One
shortfall. Any further capital funding requirements
in the near-term that may require tapping into
once completed in 2020
sources reserved for other rail projects in London
presents another downside risk. In this case, will provide
projects in the capital are likely to be put on hold
or delayed whilst new funding sources are agreed.
power to more
than 1 million homes
Upside risks:
• Main civil works on Phase 1 of HS2 starts Pre-construction works on the 2.7 GW Wylfa
this year Newydd nuclear project were expected to occur
from 2020, but in January, Hitachi announced
If main civil engineering works on Phase 1 of
that it was suspending the project due to
HS2 commences in the second half of this year,
rising costs and a failure to agree final financing
boosting activity on the ground, this presents an
arrangements. Highlighting uncertainty over such
upside risk to the sub-sector.
projects, this follows Toshiba abandoning its plans
Growth forecasts for the electricity sub-sector to build a nuclear power station at Moorside in
remain unchanged, with output set to increase Cumbria in November. Moreover, at the peak of
14.0% in 2019 and 7.0% in 2020. Alongside construction, Hinkley Point C is expected to see
ongoing nuclear decommissioning, which includes 5,600 workers onsite, which raises concerns over
Sellafield, the UK’s largest nuclear site, and work skills availability in the medium to long-term given
around the National Grid power connections, that other major infrastructure projects in roads
activity will be supported by a pipeline of projects and rail are also expected to occur at the same
in the offshore wind farm sector. Construction time.
is currently underway at the £2.6 billion Beatrice
Offshore Wind Farm, located in the Outer Firth Downside risks:
of Moray, as well as projects under the Round 3 • Investment on key energy projects stalls
Offshore Wind Programme, including Hornsea
Project One, the world’s largest offshore wind • Major nuclear projects delayed further
farm, and East Anglia ONE. The former is
scheduled for completion this year, whilst the A potential loss of access to European Investment
latter two are expected to be fully operational in Bank (EIB) funding post-Brexit or reduced
2020. Meanwhile, construction works on the £2.6 investor confidence amid heightened Brexit
billion Moray Offshore Wind farm (East), which uncertainty, which in turn, hinders decision-
is located off the coast of Scotland, and the 860 making on key energy infrastructure projects
MW Triton Knoll offshore wind farm, located off pose a downside risk to the sub-sector. This is
the Lincolnshire coast are expected to start this alongside the risk of further delays on major
year, whilst works on the 784 MW Inch Cape and nuclear projects, notably, Hinkley Point C.
448 MW Neart na Gaoithe offshore wind farm
Upside risks:
projects in Scotland are due to start in 2020. Main
works on Hornsea Project Two are also expected • Investor confidence improves leaving large-scale
to commence in 2020 and once operational projects unaffected
in 2022, it will overtake Hornsea Project One
to become the world’s largest offshore wind Improved investor confidence amid greater
farm. Besides offshore wind farms, activity will clarity regarding the future UK-EU relationship
be underpinned by the £19.6 billion Hinkley and stronger than expected economic conditions
Point C project, with main construction works presents an upside risk to the sub-sector. This
expected to occur from 2019. Approximately would, in turn, allow large-scale projects, including
80% of procurement on the project is now work previously paused under the Round 3
complete, with 30 contracts yet to be signed. Offshore Wind Programme to get off the ground.

59
Recent data show that in 2018 Q3, output in
the water & sewerage sub-sector increased
Tunnelling works on the 10.5% quarter-on-quarter to £628 million, the
25km Thames Tideway Tunnel highest level since 2012 Q3, which is likely to be
are currently underway attributed to preliminary works occurring on
the Thames Tideway Tunnel project. Preliminary
works, however, have been underway since 2016
and despite this, output has recorded quarterly
Following an estimated increase of 12.0% in declines since 2017 Q4. Contracts for the
2018, output in the water & sewerage sub- project were awarded in February 2015 and, as
sector is forecast to remain flat, but at this high result new orders increased 413.3% in that year.
level in both 2019 and 2020, driven by work Output rose 4.0% in 2015 and 26.8% in 2016,
on the largest project in the pipeline, the £4.2 before accelerating to 61.6% in 2017. This was the
billion Thames Tideway Tunnel. The project strongest annual growth on record even though
has £700 million of backing from the EIB and main tunnelling works on the project were yet to
following the EU referendum result, the Bank begin. This suggests that the ONS’s construction
has stated that its funding commitments to the output data is not accurately reflecting activity
sub-sector will remain unchanged. In November on the ground and is likely to have been
2018, tunnelling work on the 25km project incorporated too early in the data.
commenced and should be completed by 2021,
before being fully operational in 2023. However, Downside risks:
Bazalgette Holdings Group’s interim report • Thames Tideway Tunnel delayed
published in November 2018 revealed that
total spend on the project has reached £1.48 • Hiatus between AMP6 and AMP7
billion and contingency for the project has been
A downside risk to sub-sector growth arises if
substantially eroded even before tunnelling
work on the Thames Tideway Tunnel suffers from
started due to engineering complications and
delays due to cost overruns, slowing activity on
cost pressures across the programme. Although
the ground. However, in March 2017, a report
the holding company for the project indicated
by the National Audit Office revealed that the
that cost saving measures are underway, it
government has provided a contingent support
added that it was too early to conclude whether
package, which aims to mitigate any downside
such measures will mitigate the cost pressures.
risks, including providing financial support if cost
Activity in the sub-sector will also be supported
overruns exceed 30% or if economic and political
by work under the current five-year Asset
events make it difficult to access capital from debt
Management Plan (AMP6) running from 2015/16
capital markets. Moreover, a hiatus in work during
to 2019/20, but water companies will mainly
the transition from AMP6 to AMP7 may result
focus on efficiency, through maintenance of
in lower output growth in the final year of the
existing assets, rather than new build. With the
forecast period.
current regulatory period coming to an end, its
replacement AMP7, which will run from 2020 Upside risks:
to 2025 will support activity over the medium-
term. In September 2018, Water UK published • The focus shifts to new build under AMP6
a Manifesto for Water, which stated that water
Alongside construction activity on the Thames
companies plan to spend more than £50.0 Tideway Tunnel, increasing focus on new build
billion on improving services and upgrading the under the AMP6 will lead to stronger growth
network during AMP7, 13.0% higher than the rates over the forecast period.
£44.0 billion being spent in AMP6. Ofwat is
currently reviewing water companies’ business Forecasts for the roads sub-sector remain
plans, with the draft determination expected to unchanged, with modest growth anticipated over
be published in March/April. This will be followed the next two years despite ONS data for new
by a final determination at the end of this year. orders suggesting a stronger outlook. In 2018 Q3,

60
new orders increased 24.6% on an annual basis, Performance (April 2017-March 2018) published in
following growth of 172.3% in Q2, which was the July 2018, 85 major schemes are now expected to
strongest since 2015 Q1 driven by technology- start in Road Period 1 (2015/16 to 2019/20), down
focused smart motorway schemes. On a four- from 112 initially planned, owing to cost overruns.
quarter total basis, new orders increased 21.4% Furthermore, 39 road schemes are due to start
in Q3. This, however, contrasts with survey in the final year of Road Period 1, down from 69.
data from the Civil Engineering Contractors Despite these revisions, it still suggests that the
Association (CECA), which showed that both majority of work is heavily skewed towards the
workloads and order books in roads remained end of the Road Period 1 and, as a result, this will
weak in the first three quarters of 2018. In Q3, need to be matched by a significant increase in
13% and 21% of firms, on balance, reported an skills and capacity in order to ensure delivery of
annual fall in workloads in motorways/trunks these projects. The current RIS1 is due to end in
roads and local roads respectively. Both sectors 2019/20 however, this will be replaced by a second
also recorded an annual decline in orders in Q3, Road Investment Strategy (RIS2), which will run
with local roads reporting a negative balance from 2020/21 to 2024/25. In the Autumn Budget
(-26%) for a thirteenth consecutive quarter. 2018, the government announced a £28.8 billion
Furthermore, growth in asphalt sales, a key National Roads Fund, which includes £25.3 billion
indicator of activity in the sub-sector, was broadly funding for RIS2, 66.4% higher than the original
flat in the first nine months of the year, compared allocation for RIS1. Cost increases mean that the
to the same period in 2017. Despite this, official ORR forecasts total spend on RIS1 to be £2.9
data show that roads output in the year to Q3 billion above original plans.
was 26.3% higher than a year earlier even though
adverse weather conditions and the demise of In terms of projects in the pipeline, work is
Carillion in Q1 impacted activity on site. Overall, over halfway completed on the £1.5 billion A14
this suggests that the ONS’s construction output Cambridge to Huntingdon improvement scheme,
data is not fully reflecting activity on the ground. the UK’s largest road project, the A19/A1058
In addition, it could also reflect the increasing use Coast Road junction to relieve congestion and
of smart motorways, as opposed to traditional
roads construction. As a result, the Association
is forecasting actual activity growth in the sub-
sector rather than distortions in the ONS data.
The £1.5bn A14
Cambridge to
Output in the roads sub-sector is forecast to Huntington
increase 3.0% in 2019 and 5.0% in 2020, driven will include:
by a pick-up in activity in the final two years improvement
of Highways England’s £15.2 billion first Road scheme a new 12 mile
Investment Strategy (RIS). According to the southern bypass,
ORR’s Annual Assessment of Highways England’s widening the existing A14
61
the £745 million Aberdeen Western Peripheral projects. This, coupled with uncertainty regarding
Route (AWRP) project in Scotland. In terms European Investment Bank funding and whether
of the latter, a trading update published in the British Business Bank will act as a replacement,
November 2018 indicated that the final costs could see local government budgets stretched,
have risen by a further £20 million and the leaving projects unfunded. Furthermore, increasing
completion date of the project has been pushed focus on smart motorways, mainly technology-
back again from Autumn 2018 to this year, due to based, rather than new roads construction, as well
complexity and weather delays in implementing as higher construction costs due to a lack of plant
repairs to the bridge over the River Don. Main operators, could dampen activity in the sub-sector.
works on the project, however, are largely
completed and apart from this, there are very Upside risks:
few major projects in the pipeline in Scotland.
• Roads schemes receive go-ahead
Looking ahead, the £1.0 billion Silvertown Tunnel
project, which would involve the construction Several road schemes that are planned to start in
of a new twin-bore road tunnel under the River the final year of Road Period 1 are yet to receive
Thames in east London will support activity. final approval. If given go-ahead, this is likely to
Construction is expected to begin later this year boost activity on the ground. Moreover, financial
and be completed by 2024. Although works on incentives to local authorities mainly in the form
other major road projects are planned to start in of ring-fenced funding could provide more clarity
2019/20, many are still subject to final approval, on roads projects and, in turn, ensure delivery of
including the A63 Castle Street improvement them over the medium-term.
scheme. Even if given go-ahead, delays and
cost overruns cannot be disregarded given past Output in the gas, air and communications
delivery experiences. According to a report sub-sector is forecast to increase 4.0% in 2019
published by the Department for Transport in and 1.0% in 2020, driven by works under
August 2018, which evaluated 52 local major Manchester Airport’s £1.0 billion ten-year
transport schemes approved for construction investment programme, as well as Gatwick
between 2006 and 2010, only one-third of the Airport’s £1.1 billion and Heathrow Airport’s £3.3
schemes were delivered ahead of schedule or billion five-year capital investment programmes
on time, whilst the majority opened on average that will support activity throughout the forecast
six months later than forecast. It also reported period. Heathrow Airport’s regulatory period
that on average, schemes cost 9.0% more than Q6 (2014/15 to 2018/19) was extended by
initially predicted. Near-term activity will also be one year to the end of December 2019 by the
supported by smart motorway schemes, which Civil Aviation Authority (CAA) in 2016, and in
focus on the use of technology rather than new August 2018, a further two-year extension to
roads construction. According to Highways the end of December 2021 was confirmed. In
England, nine schemes are currently underway, addition to this, activity will be supported by
including the M4 Junctions 3 to 12. Construction work under London City Airport’s £480 million
on seven others is set to begin during the forecast expansion programme, which includes expanding
period, including the M25 Junctions 10 to 16. the existing terminal, constructing a three-story
passenger pier, building a new taxiway and other
Downside risks:
facilities, as well as Stansted Airport’s £600
• Further cuts to local authorities’ funding million five-year transformational programme.
In terms of the latter, construction of a new
• Focus shifts further to smart motorways £150 million arrivals terminal, which forms the
centrepiece of the programme, is expected
• Higher construction costs due to capacity
constraints to start this Spring and be completed in 2020.
Meanwhile, work on Luton Airport’s new £200
Government focus on austerity in the near-term million light rail system that will allow trains to run
could see funding to local authorities fall further, directly into the terminal is currently underway
constraining their ability to deliver on roads and due to be completed in 2021.

62
Sub-sector activity will additionally be driven improve connectivity on trains. Furthermore,
by work under BT’s £6.0 billion investment in the Autumn Budget 2018, the government
programme to extend its ultrafast fibre and allocated £200 million for full fibre broadband
mobile broadband network to at least 10 million connections in rural areas across the UK, with the
premises by mid-2020s, as well as Virgin Media’s first stage targeting primary schools.
£3.0 billion Project Lightning programme, which
aims to extend its fibre network to four million
Downside risks:
additional premises by 2019. According to • Further delays in expansion to superfast
Virgin Media’s preliminary results, 109,000 new broadband
connections were added in 2018 Q3, compared
to 118,000 in Q2, bringing the total to 1.4 million A downside risk to sub-sector growth emerges
premises since the project’s inception in February if work under major superfast broadband
2015. Other investments in full fibre networks programmes face delays. In this case, lower
include Vodafone UK and Cityfibre’s £2.5 billion activity would be anticipated in the near-term.
plan to roll out full fibre to five million premises Upside risks:
by 2025, Hyperoptic’s £500 million project to
extend its fibre network to five million homes • Substantial progress is made in expanding
by 2024 (revised from 2025 previously) and broadband across the UK
Gigaclear’s plans to expand its network to
• New gas storage investment occurs
150,000 rural properties by 2020. In Autumn
Statement 2016, the UK government allocated If progress is made on expanding broadband
£740 million from the National Productivity across the UK, including work under Virgin
Investment Fund (NPIF) to support the roll out Media’s £3.0 billion and BT’s £6.0 investment
of full fibre networks and 5G communications programmes, this presents an upside risk to sub-
by 2020/21. Of this, £190 million was allocated sector growth. This, as well as new investment
for a new Local Full Fibre Network (LFFN) in gas storage in response to utilising shale gas
challenge fund to stimulate investment in full fibre reserves and given the closure of Rough, which
networks across the UK, including rural and urban accounted for 70% of the UK’s total storage
locations, whilst £160 million has been earmarked capacity, would underpin stronger growth rates
to support 5G development and £35 million to over the next two years.

63
Infrastructure R&M
Infrastructure repair and maintenance (r&m) includes work on assets owned by utility companies,
publicly-funded assets such as roads and rail, airports and energy-generating facilities.

£10.8 billion estimated in the 2017 survey. For


London, the average maintenance backlog was
An extra£420m nine years (£465.9 million), which is marginally
down from the 10 years estimated in the previous
was announced to survey. The survey also reported that 40% of
the local road network is currently classified as
repair potholes amber (some deterioration apparent) or red
(poor overall condition). Of this, 24,496 miles of
and renew bridges road is identified as red, suggesting the urgent
& tunnels in 2018/19 need for maintenance in the next 12 months.
Reflecting this, in August 2018, the Transport
Select Committee launched an inquiry into the
funding and governance of local roads in England.
Highways England has a maintenance budget Evidence to the inquiry continues to highlight
of £1.3 billion over its first fixed five-year the lack of investment in local road maintenance
investment period, which began in 2015/16. and the Asphalt Industry Alliance estimates that
In 2018/19, expenditure on maintenance was highway authorities in England (except London)
£257 million and is expected to rise to £263 would need an additional £1.05 billion per year
million in 2019/20, the final year of the first road for 10 years for road maintenance.
period. However, local authorities manage 97%
of the roads network and remain financially- In the rail sub-sector, the current CP5
constrained. According to the Local Government (2014/15-2018/19) that largely focused on new
Association, local authorities will face an overall building activity is coming to an end and will
funding gap of £3.2 billion in 2019/20. As a result, be replaced by the next control period, CP6
basic repairs and maintenance are unlikely to be (2019/20-2023/24). In February 2018, Network
a key driver of work in the sector despite the Rail published its Strategic Business Plan for
urgent need for basic repairs to roads. In 2015, CP6, which stated that the focus will be on
the government announced a Pothole Action maintenance and renewals, with fewer new
Fund, which now totals £296 million between enhancements. CP6 has a budget of £47.9
2016/17 and 2020/21, to allow local authorities to billion, compared to £38.3 billion allocated for
repair potholes or stop them forming in the first CP5. In October 2018, the Office of Rail and
place. £50 million of this has been allocated for Road (ORR) set out its final determination on
2018/19. In March 2018, government announced Network Rail’s £34.7 billion five-year spending
a further £100 million to help repair two million plans. It approved £7.7 billion spending on
potholes and protect roads from future severe maintenance and £16.6 billion on renewing the
weather conditions. Furthermore, in the Autumn existing railway, with renewal work seeing a
Budget 2018, the government announced an 17.0% increase from the £14.2 billion in CP5.
additional £420 million to local authorities in The breakdown of the spending plans shows
2018/19 to repair potholes and renew bridges that expenditure on maintenance in England and
and tunnels. In addition to this, it allocated £150 Wales is set to rise from £1.2 billion in 2018/19
million of funding from the National Productivity to £1.4 billion in 2019/20, before remaining at
Investment Fund (NPIF) to local authorities for that level in 2020/21. For Scotland, spending on
small congestion-related improvement projects maintenance work is set to increase from £121
such as roundabouts. However, the Asphalt million in 2018/19 to £145 million in 2019/20
Industry Alliance’s 2018 ALARM survey reported and remain at that level in 2020/21. Renewals
that there was a 13-year backlog of local roads spending in England and Wales was £2.1 billion
maintenance in England, at a value of £8.2 billion. in 2018/19 and is set to rise to £2.7 billion in
This is lower than the one-time catch-up cost of 2019/20 and £3.1 billion in 2020/21. For Scotland,

64
Infrastructure R&M Output
12,000

10,000 7.0% 2.0% 1.0% 0.0%


3.6% 8.5%
12.3%
£ million - 2016 Constant Prices

8,000 -4.6%
-2.1% -5.8%

6,000

4,000

2,000

0
2010 2011 2012 2013 2014 2015 2016 2017 2018e 2019f 2020p

Source: ONS, Construction Products Association

spending on renewals work is expected to Upside risks:


increase from £343 million in 2018/19 to £377
million in 2019/20 and £510 million in 2020/21. • Central government increases infrastructure
r&m spending quickly
Overall, output in the infrastructure r&m sector
is forecast to increase 1.0% in 2019, driven by A large increase in ring-fenced funding to local
ongoing maintenance activity under the current authorities for transport projects that allows work
five-year Asset Management Programme, to get off the ground, in turn, providing a boost
(AMP6) in water & sewerage and maintenance to both infrastructure r&m output and the wider
and renewal work in the rail sub-sector. Although economy presents an upside risk.
expenditure on roads maintenance is expected
to be higher in the final two years of Road Period
1, 2018/19 and 2019/20, anecdotal evidence
suggests that this has not yet filtered through to
activity on the ground. Output growth is forecast
to remain flat in 2020.

Downside risks:
• Local authorities subject to further budget cuts

• R &m output is likely to be overshadowed


by new build activity rather than basic
maintenance

Further cuts to local authority funding amid


constrained spending by central government
under any further austerity programme pose a
downside risk to sub-sector activity. In the event
of this, local authorities may be forced to finance
new build from maintenance budgets in order to
ensure delivery. In addition, increased pressure
on government departmental budgets could lead
to schemes being cancelled or delayed.

65
The Construction Products Association represents
the UK’s manufacturers and distributors of
construction products and materials. The sector
directly provides jobs for 337,000 people across
24,000 companies, and has an annual turnover of
more than £60.2 billion. We act as the leading voice
to promote and campaign for this vital UK industry.

The CPA produces a range of economic reports


including quarterly Construction Industry
Forecasts, Construction Trade Surveys, State of
Trade Surveys and various bespoke research. 
These publications are available free to
members and via subscription to non-members. 
To learn more, please contact our
Economics team at 020 7323 3770
or visit www.constructionproducts.org.uk.

66
67
ISBN: 978-1-909415-31-7

February 2019

Construction Products Association


26 Store Street
London
WC1E 7BT
Tel: 020 7323 3770
www.constructionproducts.org.uk

You might also like