UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO

FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA

Escuela de INGENIERÍA CIVIL

TRABAJO GRUPAL

DISEÑO DE ZAPATA COMBINADA

CURSO:

CONCRETO ARMADO II

DOCENTE:

ING. SERRANO ZELADA, OVIDIO

CICLO:

CICLO ORDINARIO 2019 - I

ALUMNOS:

AGAPITO VELASQUEZ JERSON


BUSTAMANTE VÉLIZ JOSÉ ALEXANDER
CONDOR LEON LUIS ANGEL
CASAS FLORES DUBER
FERNANDEZ COLMENARES JESÚS ALBERTO
HERNANDEZ CABALLERO MIGUEL ANGEL

LAMBAYEQUE - JULIO DEL 2019

CONCRETO ARMADO II ING. SERRANO ZELADA, OVIDIO


CONCRETO ARMADO II ING. SERRANO ZELADA, OVIDIO
UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

CARGA MUERTA EN ETABS

Unique Load C. Station P V2 V3 T M2 M3


Story Column Name /Comb. m tonf tonf tonf tonf-m tonf-m tonf-m
piso 1 C1 47 Dead 0 -49.3507 0.4825 0.0531 0.0017 0.0384 0.382
piso 1 C1 47 Dead 1.175 -49.0053 0.4825 0.0531 0.0017 -0.024 -0.1849
piso 1 C1 47 Dead 2.35 -48.6598 0.4825 0.0531 0.0017 -0.0864 -0.7518
piso 1 C4 50 Dead 0 -52.8216 0.6057 0.0508 0.0017 0.0363 0.5119
piso 1 C4 50 Dead 1.175 -52.4762 0.6057 0.0508 0.0017 -0.0233 -0.1997
piso 1 C4 50 Dead 2.35 -52.1307 0.6057 0.0508 0.0017 -0.083 -0.9114
piso 1 C6 55 Dead 0 -9.9513 0.0433 0.0938 0.0004 0.083 0.0257
piso 1 C6 55 Dead 1.175 -9.7751 0.0433 0.0938 0.0004 -0.0272 -0.0252
piso 1 C6 55 Dead 2.35 -9.5988 0.0433 0.0938 0.0004 -0.1374 -0.0762
piso 1 C8 57 Dead 0 -17.7215 -0.3689 -0.1803 0.0004 -0.1655 -0.3329
piso 1 C8 57 Dead 1.175 -17.5453 -0.3689 -0.1803 0.0004 0.0463 0.1006
piso 1 C8 57 Dead 2.35 -17.369 -0.3689 -0.1803 0.0004 0.2581 0.534
piso 1 C9 58 Dead 0 -26.9483 0.2015 0.293 0.0009 0.2554 0.1518
piso 1 C9 58 Dead 1.175 -26.6945 0.2015 0.293 0.0009 -0.0889 -0.085
piso 1 C9 58 Dead 2.35 -26.4407 0.2015 0.293 0.0009 -0.4331 -0.3217
piso 1 C10 59 Dead 0 -20.6327 -0.5094 0.1187 0.0009 0.101 -0.4992
piso 1 C10 59 Dead 1.425 -20.3249 -0.5094 0.1187 0.0009 -0.0681 0.2267
piso 1 C10 59 Dead 2.85 -20.0171 -0.5094 0.1187 0.0009 -0.2372 0.9527
piso 1 C11 63 Dead 0 -19.0404 0.1909 0.028 0.0009 0.0238 0.1457
piso 1 C11 63 Dead 1.175 -18.7866 0.1909 0.028 0.0009 -0.0091 -0.0786
piso 1 C11 63 Dead 2.35 -18.5328 0.1909 0.028 0.0009 -0.042 -0.3029
piso 1 C13 64 Dead 0 -10.9605 0.2389 0.1773 0.0009 0.1493 0.186
piso 1 C13 64 Dead 1.0808 -10.727 0.2389 0.1773 0.0009 -0.0423 -0.0722
piso 1 C13 64 Dead 2.1617 -10.4936 0.2389 0.1773 0.0009 -0.2338 -0.3304
piso 1 C14 65 Dead 0 -17.0761 -0.2785 -0.2712 0.0009 -0.2509 -0.2668
piso 1 C14 65 Dead 1.175 -16.8223 -0.2785 -0.2712 0.0009 0.0678 0.0604
piso 1 C14 65 Dead 2.35 -16.5685 -0.2785 -0.2712 0.0009 0.3864 0.3877
piso 1 C15 66 Dead 0 -17.1186 -0.2702 0.2333 0.0009 0.1968 -0.256
piso 1 C15 66 Dead 1.175 -16.8648 -0.2702 0.2333 0.0009 -0.0773 0.0614
piso 1 C15 66 Dead 2.35 -16.611 -0.2702 0.2333 0.0009 -0.3515 0.3789
piso 1 C16 67 Dead 0 -32.5561 -0.915 -0.0015 0.0009 -0.0116 -0.8242
piso 1 C16 67 Dead 1.175 -32.3023 -0.915 -0.0015 0.0009 -0.0098 0.2509
piso 1 C16 67 Dead 2.35 -32.0485 -0.915 -0.0015 0.0009 -0.008 1.3261
piso 1 C17 68 Dead 0 -16.2146 0.237 -0.1416 0.0009 -0.1267 0.198
piso 1 C17 68 Dead 1.175 -15.9608 0.237 -0.1416 0.0009 0.0397 -0.0804
piso 1 C17 68 Dead 2.35 -15.707 0.237 -0.1416 0.0009 0.2061 -0.3589
piso 1 C18 72 Dead 0 -29.6473 0.3141 -0.4314 0.0009 -0.3874 0.2704
piso 1 C18 72 Dead 1.175 -29.3935 0.3141 -0.4314 0.0009 0.1195 -0.0987
piso 1 C18 72 Dead 2.35 -29.1397 0.3141 -0.4314 0.0009 0.6265 -0.4678

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

CARGA VIVAEN ETABS

Load Station P V2 V3 T M2 M3
Unique
Story Column C.
Name m tonf tonf tonf tonf-m tonf-m tonf-m
/Comb.
piso 1 C1 47 Live 0 -11.9315 0.2379 0.0484 0.0005 0.0426 0.2031
piso 1 C1 47 Live 1.175 -11.9315 0.2379 0.0484 0.0005 -0.0142 -0.0764
piso 1 C1 47 Live 2.35 -11.9315 0.2379 0.0484 0.0005 -0.0711 -0.356
piso 1 C4 50 Live 0 -12.8479 0.2822 0.0168 0.0005 0.0147 0.2486
piso 1 C4 50 Live 1.175 -12.8479 0.2822 0.0168 0.0005 -0.005 -0.083
piso 1 C4 50 Live 2.35 -12.8479 0.2822 0.0168 0.0005 -0.0248 -0.4145
piso 1 C6 55 Live 0 -1.5849 0.0153 0.0394 0.0001 0.0356 0.0114
piso 1 C6 55 Live 1.175 -1.5849 0.0153 0.0394 0.0001 -0.0107 -0.0066
piso 1 C6 55 Live 2.35 -1.5849 0.0153 0.0394 0.0001 -0.057 -0.0245
piso 1 C8 57 Live 0 -3.3666 -0.1376 -0.0816 0.0001 -0.0735 -0.1222
piso 1 C8 57 Live 1.175 -3.3666 -0.1376 -0.0816 0.0001 0.0223 0.0395
piso 1 C8 57 Live 2.35 -3.3666 -0.1376 -0.0816 0.0001 0.1181 0.2011
piso 1 C9 58 Live 0 -5.2778 0.0843 0.1374 0.0003 0.1219 0.0701
piso 1 C9 58 Live 1.175 -5.2778 0.0843 0.1374 0.0003 -0.0396 -0.029
piso 1 C9 58 Live 2.35 -5.2778 0.0843 0.1374 0.0003 -0.201 -0.1281
piso 1 C10 59 Live 0 -4.3069 -0.2188 0.0431 0.0003 0.0385 -0.2081
piso 1 C10 59 Live 1.425 -4.3069 -0.2188 0.0431 0.0003 -0.0228 0.1036
piso 1 C10 59 Live 2.85 -4.3069 -0.2188 0.0431 0.0003 -0.0842 0.4154
piso 1 C11 63 Live 0 -3.7412 0.0847 0.0162 0.0003 0.0154 0.0714
piso 1 C11 63 Live 1.175 -3.7412 0.0847 0.0162 0.0003 -0.0036 -0.0281
piso 1 C11 63 Live 2.35 -3.7412 0.0847 0.0162 0.0003 -0.0227 -0.1276
piso 1 C13 64 Live 0 -1.3402 0.0591 0.0614 0.0003 0.0532 0.0486
piso 1 C13 64 Live 1.0808 -1.3402 0.0591 0.0614 0.0003 -0.0132 -0.0152
piso 1 C13 64 Live 2.1617 -1.3402 0.0591 0.0614 0.0003 -0.0796 -0.0791
piso 1 C14 65 Live 0 -2.5197 -0.0975 -0.1271 0.0003 -0.1146 -0.089
piso 1 C14 65 Live 1.175 -2.5197 -0.0975 -0.1271 0.0003 0.0348 0.0255
piso 1 C14 65 Live 2.35 -2.5197 -0.0975 -0.1271 0.0003 0.1842 0.1401
piso 1 C15 66 Live 0 -2.5182 -0.0932 0.1154 0.0003 0.1006 -0.0841
piso 1 C15 66 Live 1.175 -2.5182 -0.0932 0.1154 0.0003 -0.035 0.0253
piso 1 C15 66 Live 2.35 -2.5182 -0.0932 0.1154 0.0003 -0.1706 0.1348
piso 1 C16 67 Live 0 -7.3307 -0.4087 0.003 0.0003 0.0009 -0.363
piso 1 C16 67 Live 1.175 -7.3307 -0.4087 0.003 0.0003 -0.0026 0.1173
piso 1 C16 67 Live 2.35 -7.3307 -0.4087 0.003 0.0003 -0.0061 0.5976
piso 1 C17 68 Live 0 -3.1755 0.0955 -0.0449 0.0003 -0.0388 0.0845
piso 1 C17 68 Live 1.175 -3.1755 0.0955 -0.0449 0.0003 0.0139 -0.0277
piso 1 C17 68 Live 2.35 -3.1755 0.0955 -0.0449 0.0003 0.0667 -0.1399
piso 1 C18 72 Live 0 -6.0194 0.1241 -0.2043 0.0003 -0.1813 0.1111
piso 1 C18 72 Live 1.175 -6.0194 0.1241 -0.2043 0.0003 0.0587 -0.0348
piso 1 C18 72 Live 2.35 -6.0194 0.1241 -0.2043 0.0003 0.2988 -0.1806

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

CARGA POR SISMO EN X EN ETABS

Load Station P V2 V3 T M2 M3
Unique
Story Column C.
Name m tonf tonf tonf tonf-m tonf-m tonf-m
/Comb.
piso 1 C1 47 EQX 1 0 2.1842 0.8187 0.028 0.0086 0.0427 1.1289
piso 1 C1 47 EQX 1 1.175 2.1842 0.8187 0.028 0.0086 0.0098 0.167
piso 1 C1 47 EQX 1 2.35 2.1842 0.8187 0.028 0.0086 -0.0231 -0.795
piso 1 C4 50 EQX 1 0 1.7523 1.0155 -0.0317 0.0086 -0.01 1.41
piso 1 C4 50 EQX 1 1.175 1.7523 1.0155 -0.0317 0.0086 0.0272 0.2168
piso 1 C4 50 EQX 1 2.35 1.7523 1.0155 -0.0317 0.0086 0.0645 -0.9764
piso 1 C6 55 EQX 1 0 -2.3507 0.247 0.0183 0.0022 0.0294 0.3181
piso 1 C6 55 EQX 1 1.175 -2.3507 0.247 0.0183 0.0022 0.0078 0.0279
piso 1 C6 55 EQX 1 2.35 -2.3507 0.247 0.0183 0.0022 -0.0137 -0.2623
piso 1 C8 57 EQX 1 0 1.6194 0.3157 -0.0222 0.0022 -0.0286 0.4242
piso 1 C8 57 EQX 1 1.175 1.6194 0.3157 -0.0222 0.0022 -0.0026 0.0533
piso 1 C8 57 EQX 1 2.35 1.6194 0.3157 -0.0222 0.0022 0.0235 -0.3176
piso 1 C9 58 EQX 1 0 0.7979 0.4821 0.0152 0.0046 0.0232 0.6303
piso 1 C9 58 EQX 1 1.175 0.7979 0.4821 0.0152 0.0046 0.0053 0.0638
piso 1 C9 58 EQX 1 2.35 0.7979 0.4821 0.0152 0.0046 -0.0125 -0.5027
piso 1 C10 59 EQX 1 0 0.5905 0.295 -0.0466 0.0046 -0.062 0.4883
piso 1 C10 59 EQX 1 1.425 0.5905 0.295 -0.0466 0.0046 0.0045 0.0679
piso 1 C10 59 EQX 1 2.85 0.5905 0.295 -0.0466 0.0046 0.0709 -0.3526
piso 1 C11 63 EQX 1 0 -4.402 0.4668 0.0918 0.0046 0.109 0.6335
piso 1 C11 63 EQX 1 1.175 -4.402 0.4668 0.0918 0.0046 0.0012 0.085
piso 1 C11 63 EQX 1 2.35 -4.402 0.4668 0.0918 0.0046 -0.1066 -0.4634
piso 1 C13 64 EQX 1 0 -9.1432 0.8769 -0.0534 0.0046 -0.0169 1.0085
piso 1 C13 64 EQX 1 1.0808 -9.1432 0.8769 -0.0534 0.0046 0.0408 0.0607
piso 1 C13 64 EQX 1 2.1617 -9.1432 0.8769 -0.0534 0.0046 0.0986 -0.8871
piso 1 C14 65 EQX 1 0 6.048 0.6179 -0.0361 0.0046 -0.0509 0.7879
piso 1 C14 65 EQX 1 1.175 6.048 0.6179 -0.0361 0.0046 -0.0086 0.0619
piso 1 C14 65 EQX 1 2.35 6.048 0.6179 -0.0361 0.0046 0.0338 -0.6642
piso 1 C15 66 EQX 1 0 6.0917 0.6438 -0.023 0.0046 -0.0394 0.8282
piso 1 C15 66 EQX 1 1.175 6.0917 0.6438 -0.023 0.0046 -0.0123 0.0717
piso 1 C15 66 EQX 1 2.35 6.0917 0.6438 -0.023 0.0046 0.0147 -0.6848
piso 1 C16 67 EQX 1 0 3.123 0.5224 -0.0174 0.0046 -0.0344 0.7408
piso 1 C16 67 EQX 1 1.175 3.123 0.5224 -0.0174 0.0046 -0.0139 0.1269
piso 1 C16 67 EQX 1 2.35 3.123 0.5224 -0.0174 0.0046 0.0065 -0.4869
piso 1 C17 68 EQX 1 0 -5.2565 0.5855 0.0443 0.0046 0.067 0.7968
piso 1 C17 68 EQX 1 1.175 -5.2565 0.5855 0.0443 0.0046 0.0149 0.1088
piso 1 C17 68 EQX 1 2.35 -5.2565 0.5855 0.0443 0.0046 -0.0373 -0.5792
piso 1 C18 72 EQX 1 0 2.0518 0.7194 0.0321 0.0046 0.0382 0.9352
piso 1 C18 72 EQX 1 1.175 2.0518 0.7194 0.0321 0.0046 0.0005 0.0899
piso 1 C18 72 EQX 1 2.35 2.0518 0.7194 0.0321 0.0046 -0.0373 -0.7554

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

CARGA POR SISMO EN Y EN ETABS

Load Station P V2 V3 T M2 M3
Unique
Story Column C.
Name m tonf tonf tonf tonf-m tonf-m tonf-m
/Comb.
piso 1 C1 47 EQY 2 0 1.0662 0.5005 1.0775 -0.0441 1.5394 0.6975
piso 1 C1 47 EQY 2 1.175 1.0662 0.5005 1.0775 -0.0441 0.2733 0.1094
piso 1 C1 47 EQY 2 2.35 1.0662 0.5005 1.0775 -0.0441 -0.9928 -0.4787
piso 1 C4 50 EQY 2 0 -1.0643 -0.6871 1.0315 -0.0441 1.4988 -0.9011
piso 1 C4 50 EQY 2 1.175 -1.0643 -0.6871 1.0315 -0.0441 0.2867 -0.0938
piso 1 C4 50 EQY 2 2.35 -1.0643 -0.6871 1.0315 -0.0441 -0.9253 0.7136
piso 1 C6 55 EQY 2 0 -3.7937 0.271 0.2015 -0.0115 0.2899 0.348
piso 1 C6 55 EQY 2 1.175 -3.7937 0.271 0.2015 -0.0115 0.0532 0.0297
piso 1 C6 55 EQY 2 2.35 -3.7937 0.271 0.2015 -0.0115 -0.1835 -0.2887
piso 1 C8 57 EQY 2 0 1.8185 -0.2886 0.4364 -0.0115 0.6115 -0.381
piso 1 C8 57 EQY 2 1.175 1.8185 -0.2886 0.4364 -0.0115 0.0987 -0.0419
piso 1 C8 57 EQY 2 2.35 1.8185 -0.2886 0.4364 -0.0115 -0.4141 0.2972
piso 1 C9 58 EQY 2 0 -3.9428 0.5868 0.5103 -0.0238 0.7704 0.7447
piso 1 C9 58 EQY 2 1.175 -3.9428 0.5868 0.5103 -0.0238 0.1707 0.0552
piso 1 C9 58 EQY 2 2.35 -3.9428 0.5868 0.5103 -0.0238 -0.4289 -0.6343
piso 1 C10 59 EQY 2 0 14.0468 0.1601 0.9414 -0.0238 1.3302 0.2836
piso 1 C10 59 EQY 2 1.425 14.0468 0.1601 0.9414 -0.0238 -0.0113 0.0555
piso 1 C10 59 EQY 2 2.85 14.0468 0.1601 0.9414 -0.0238 -1.3528 -0.1725
piso 1 C11 63 EQY 2 0 -2.8774 0.3043 0.5123 -0.0238 0.6803 0.4081
piso 1 C11 63 EQY 2 1.175 -2.8774 0.3043 0.5123 -0.0238 0.0783 0.0505
piso 1 C11 63 EQY 2 2.35 -2.8774 0.3043 0.5123 -0.0238 -0.5236 -0.3071
piso 1 C13 64 EQY 2 0 19.9696 -0.1292 0.8551 -0.0238 0.9578 -0.1659
piso 1 C13 64 EQY 2 1.0808 19.9696 -0.1292 0.8551 -0.0238 0.0337 -0.0263
piso 1 C13 64 EQY 2 2.1617 19.9696 -0.1292 0.8551 -0.0238 -0.8905 0.1134
piso 1 C14 65 EQY 2 0 -0.2513 0.0709 0.7983 -0.0238 1.1728 0.0966
piso 1 C14 65 EQY 2 1.175 -0.2513 0.0709 0.7983 -0.0238 0.2348 0.0133
piso 1 C14 65 EQY 2 2.35 -0.2513 0.0709 0.7983 -0.0238 -0.7032 -0.07
piso 1 C15 66 EQY 2 0 0.2274 -0.134 0.8535 -0.0238 1.2218 -0.1736
piso 1 C15 66 EQY 2 1.175 0.2274 -0.134 0.8535 -0.0238 0.2189 -0.0161
piso 1 C15 66 EQY 2 2.35 0.2274 -0.134 0.8535 -0.0238 -0.784 0.1414
piso 1 C16 67 EQY 2 0 -0.5684 -0.2869 0.9282 -0.0238 1.2881 -0.4136
piso 1 C16 67 EQY 2 1.175 -0.5684 -0.2869 0.9282 -0.0238 0.1974 -0.0765
piso 1 C16 67 EQY 2 2.35 -0.5684 -0.2869 0.9282 -0.0238 -0.8933 0.2606
piso 1 C17 68 EQY 2 0 -3.23 -0.36 0.6011 -0.0238 0.759 -0.4785
piso 1 C17 68 EQY 2 1.175 -3.23 -0.36 0.6011 -0.0238 0.0528 -0.0555
piso 1 C17 68 EQY 2 2.35 -3.23 -0.36 0.6011 -0.0238 -0.6535 0.3676
piso 1 C18 72 EQY 2 0 3.2842 -0.6016 0.4709 -0.0238 0.7354 -0.7935
piso 1 C18 72 EQY 2 1.175 3.2842 -0.6016 0.4709 -0.0238 0.1821 -0.0866
piso 1 C18 72 EQY 2 2.35 3.2842 -0.6016 0.4709 -0.0238 -0.3712 0.6202

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

DISEÑO DE ZAPATA COMBINADA EJE B-6 , B-5 (COLUMNA EXTERIOR e INTERIOR)


Columna 01: EJE B-6 C9 Columna 02: EJE B-5 C1
b= 0.30 m b= 0.35 m
h= 0.30 m h= 0.35 m

PD= 26.9483 Tn PD= 49.3507 Tn


PL= 5.2778 Tn PL= 11.9315 Tn
Dirección Longitudinal.- Dirección Transversal.- Dirección Longitudinal.- Dirección Transversal.-
MD= 0.26 Tn-m MD= 0.15 Tn-m MD= 0.04 Tn-m MD= 0.38 Tn-m
ML= 0.12 Tn-m ML= 0.07 Tn-m ML= 0.04 Tn-m ML= 0.20 Tn-m
MS= 0.77 Tn-m MS= 0.63 Tn-m MS= 1.54 Tn-m MS= 1.13 Tn-m
Ps= 3.94 Tn Ps= 0.80 Tn Ps= 1.07 Tn Ps= 2.18 Tn
Distancia entre col 3.36 m
σt= 1.00 Kg/cm2
K30= 4500 Tn/m3 3--3 TRANS
f'c= 210 Kg/cm2 2--2 LONG.
s/c= 200 Kg/m2
NPT= 0.15 m
NFZ= -1.40 m

Solución.-
1.-Esfuerzo Neto del Suelo.-
σn= 6.70 Tn/m2 Sin Sismo
σns= 9.70 Tn/m2 Con Sismo

2.-Dimensionamiento en Planta - Cargas de Servicio.-


A.- Cargas de Gravedad.-
P1= 32.2261 Tn P2= 61.2822 Tn
ML1= 0.38 Tn-m ML2= 0.08 Tn-m
MT1= 0.22 Tn-m MT2= 0.59 Tn-m
L1= 3.685 m
R= 93.5083 Tn
XR= 2.57 m
L= 5.140 m L= 5.20 m
σn= 6.70 Tn/m2 B= 2.80 m 2.684
Az= 13.95646 m2
B= 2.684 m
Esfuerzos en el suelo.-
R= 93.5083 Tn
e= -0.03
ML= -2.81213 Tn-m
MT= 0.81 Tn-m

σ1= 6.42 + -0.22 + 0.12 = 6.32 Tn/m2


σ2= 6.42 - -0.22 + 0.12 = 6.76 Tn/m2
σ3= 6.42 + -0.22 - 0.12 = 6.08 Tn/m2
σ4= 6.42 - -0.22 - 0.12 = 6.53 Tn/m2

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

B.- Cargas de Gravedad + Sismo Longitudinal Horario


P1= 35.38034 Tn P2= 62.1352 Tn
ML1= 0.99 Tn-m ML2= 1.31 Tn-m
MT1= 0.22 Tn-m MT2= 0.59 Tn-m
L1= 3.685 m
R= 97.5155 Tn
XR= 2.52 m
L= 5.20 m
σn= 9.70 Tn/m2 B= 2.80 m

Esfuerzos en el suelo.-
R= 97.5155 Tn
e= -0.08 m
ML= -7.63877 Tn-m
MT= 0.81 Tn-m

σ1= 6.70 + -0.61 + 0.12 = 6.21 Tn/m2


σ2= 6.70 - -0.61 + 0.12 = 7.42 Tn/m2
σ3= 6.70 + -0.61 - 0.12 = 5.97 Tn/m2
σ4= 6.70 - -0.61 - 0.12 = 7.18 Tn/m2

C.- Cargas de Gravedad + Sismo Longitudinal AntiHorario


P1= 29.07186 Tn P2= 60.4292 Tn
ML1= -0.24 Tn-m ML2= -1.15 Tn-m
MT1= 0.22 Tn-m MT2= 0.59 Tn-m
L1= 3.685 m
R= 89.5011 Tn
XR= 2.62 m
L= 5.20 m
σn= 9.70 Tn/m2 B= 2.80 m

Esfuerzos en el suelo.-
R= 89.5011 Tn
e= 0.02 m
ML= 2.014514 Tn-m
MT= 0.81 Tn-m

σ1= 6.15 + 0.16 + 0.12 = 6.43 Tn/m2


σ2= 6.15 - 0.16 + 0.12 = 6.11 Tn/m2
σ3= 6.15 + 0.16 - 0.12 = 6.19 Tn/m2
σ4= 6.15 - 0.16 - 0.12 = 5.87 Tn/m2

D.- Cargas de Gravedad + Sismo Transversal Horario.-


P1= 32.86442 Tn P2= 63.0296 Tn
ML1= 0.38 Tn-m ML2= 0.08 Tn-m

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

MT1= 0.73 Tn-m MT2= 1.49 Tn-m


L1= 3.685 m
R= 95.89398 Tn
XR= 2.58 m

L= 5.20 m
σn= 9.70 Tn/m2 B= 2.80 m

Esfuerzos en el suelo.-
R= 95.89398 Tn
e= -0.02 m
ML= -2.21802 Tn-m
MT= 2.21 Tn-m

σ1= 6.59 + -0.18 + 0.33 = 6.74 Tn/m2


σ2= 6.59 - -0.18 + 0.33 = 7.09 Tn/m2
σ3= 6.59 + -0.18 - 0.33 = 6.08 Tn/m2
σ4= 6.59 - -0.18 - 0.33 = 6.44 Tn/m2

E.- Cargas de Gravedad + Sismo Transversal AntiHorario.-


P1= 31.58778 Tn P2= 59.5348 Tn
ML1= 0.38 Tn-m ML2= 0.08 Tn-m
MT1= -0.28 Tn-m MT2= -0.32 Tn-m
L1= 3.685 m
R= 91.12262 Tn
XR= 2.56 m
L= 5.20 m
σn= 9.70 Tn/m2 B= 2.80 m

Esfuerzos en el suelo.-
R= 91.12262 Tn
e= -0.04 m
ML= -3.40623 Tn-m
MT= -0.60 Tn-m

σ1= 6.26 + -0.27 + -0.09 = 5.90 Tn/m2


σ2= 6.26 - -0.27 + -0.09 = 6.44 Tn/m2
σ3= 6.26 + -0.27 - -0.09 = 6.08 Tn/m2
σ4= 6.26 - -0.27 - -0.09 = 6.62 Tn/m2

3.- Esfuerzos Ultimos en el Suelo.-


A.- Cargas de Gravedad.-
P1= 46.69988 Tn P2= 89.3745 Tn
ML1= 0.56 Tn-m ML2= 0.13 Tn-m
MT1= 0.33 Tn-m MT2= 0.88 Tn-m
L1= 3.685 m
R= 136.0744 Tn

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

XR= 2.58 m
L= 5.151 m L= 5.20 m
σn= 6.70 Tn/m2 B= 2.80 m
Az= 20.30961 m2
B= 3.906 m

Esfuerzos en el suelo.-
R= 136.0744 Tn
e= -0.02
ML= -3.34619 Tn-m
MT= 1.21 Tn-m

σ1= 9.35 + -0.27 + 0.18 = 9.26 Tn/m2


σ2= 9.35 - -0.27 + 0.18 = 9.79 Tn/m2
σ3= 9.35 + -0.27 - 0.18 = 8.90 Tn/m2
σ4= 9.35 - -0.27 - 0.18 = 9.43 Tn/m2

B.- Cargas de Gravedad + Sismo Longitudinal Horario


P1= 44.22543 Tn P2= 77.669 Tn
ML1= 1.24 Tn-m ML2= 1.64 Tn-m
MT1= 0.28 Tn-m MT2= 0.73 Tn-m
L1= 3.685 m
R= 121.8944 Tn
XR= 2.52 m
L= 5.20 m
σn= 9.70 Tn/m2 B= 2.80 m

Esfuerzos en el suelo.-
R= 121.8944 Tn
e= -0.08 m
ML= -9.54846 Tn-m
MT= 1.01 Tn-m

σ1= 8.37 + -0.76 + 0.15 = 7.76 Tn/m2


σ2= 8.37 - -0.76 + 0.15 = 9.28 Tn/m2 MAS CRITICO
σ3= 8.37 + -0.76 - 0.15 = 7.47 Tn/m2
σ4= 8.37 - -0.76 - 0.15 = 8.98 Tn/m2

C.- Cargas de Gravedad + Sismo Longitudinal AntiHorario


P1= 36.33983 Tn P2= 75.5366 Tn
ML1= -0.30 Tn-m ML2= -1.44 Tn-m
MT1= 0.28 Tn-m MT2= 0.73 Tn-m
L1= 3.685 m
R= 111.8764 Tn
XR= 2.62 m
L= 5.20 m
σn= 9.70 Tn/m2 B= 2.80 m

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

Esfuerzos en el suelo.-
R= 111.8764 Tn
e= 0.02 m
ML= 2.518143 Tn-m
MT= 1.01 Tn-m

σ1= 7.68 + 0.20 + 0.15 = 8.03 Tn/m2


σ2= 7.68 - 0.20 + 0.15 = 7.63 Tn/m2
σ3= 7.68 + 0.20 - 0.15 = 7.73 Tn/m2
σ4= 7.68 - 0.20 - 0.15 = 7.34 Tn/m2

D.- Cargas de Gravedad + Sismo Transversal Horario.-


P1= 41.08053 Tn P2= 78.787 Tn
ML1= 0.47 Tn-m ML2= 0.10 Tn-m
MT1= 0.91 Tn-m MT2= 1.86 Tn-m
L1= 3.685 m
R= 119.8675 Tn
XR= 2.58 m
L= 5.20 m
σn= 9.70 Tn/m2 B= 2.80 m

Verificación de Esfuerzos en el suelo.-


R= 119.8675 Tn
e= -0.02 m
ML= -2.77253 Tn-m
MT= 2.77 Tn-m

σ1= 8.23 + -0.22 + 0.41 = 8.42 Tn/m2


σ2= 8.23 - -0.22 + 0.41 = 8.86 Tn/m2
σ3= 8.23 + -0.22 - 0.41 = 7.61 Tn/m2
σ4= 8.23 - -0.22 - 0.41 = 8.05 Tn/m2

E.- Cargas de Gravedad + Sismo Transversal AntiHorario.-


P1= 39.48473 Tn P2= 74.4186 Tn
ML1= 0.47 Tn-m ML2= 0.10 Tn-m
MT1= -0.35 Tn-m MT2= -0.40 Tn-m
L1= 3.685 m
R= 113.9033 Tn
XR= 2.56 m
L= 5.20 m
σn= 9.70 Tn/m2 B= 2.80 m

Verificación de Esfuerzos en el suelo.-

R= 113.9033 Tn
e= -0.04 m

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

ML= -4.25779 Tn-m


MT= -0.8 Tn-m

σ1= 7.82 + -0.34 + -0.11 = 7.38 Tn/m2


σ2= 7.82 - -0.34 + -0.11 = 8.05 Tn/m2
σ3= 7.82 + -0.34 - -0.11 = 7.60 Tn/m2
σ4= 7.82 - -0.34 - -0.11 = 8.27 Tn/m2

Esfuerzos Ultimos en el Suelo.- Cargas de Gravedad + Sismo Longitudinal Horario.-


Pu1= 41.08053 Tn Pu2= 77.669 Tn
ML1= 1.24 Tn-m ML2= 1.64 Tn-m
MT1= 0.28 Tn-m MT2= 0.73 Tn-m
L1= 3.685 m
R= 121.8944 Tn
XR= 2.52 m
L= 5.20 m
σn= 9.70 m B= 2.80 m

Esfuerzos en el suelo.-
R= 121.8944 Tn
e= -0.08 m
ML= -9.54846 Tn-m
MT= 1.01 Tn-m

σ1= 8.37 + -0.76 + 0.15 = 7.76 Tn/m2


σ2= 8.37 - -0.76 + 0.15 = 9.28 Tn/m2 MAS CRITICO
σ3= 8.37 + -0.76 - 0.15 = 7.47 Tn/m2
σ4= 8.37 - -0.76 - 0.15 = 8.98 Tn/m2

Esfuerzo Ultimo de Diseño, Gud= 9.28 Tn/m2


Combinación de Diseño = 1.25D + 1.25L + 1SLH

4. Altura de la Zapata.-
A.- Por Rigidez.-
Lm= 3.36 m
L= 5.20 m
B= 2.80 m
n= 1.857
s= 0.846154 3.36 1.9279
Ks= 3808 Tn/m3
Ec= 2173707 Tn/m2 0.6033 0.2776
hz= 0.65 m

B.- Por Longitud de Desarrollo.-


Ld= 42.01 cm
hz= 52.83 cm
hz= 0.65 m

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

C.- Verificación por Fuerza Cortante por Flexión.-

Pu1= 41.08 Pu2= 77.67

0.15 3.66 1.39

ơ = 9.28 Tn/m2
carga ultima por metro lineal 5.20
wu= 25.97566 tn/m
Pu1= Pu1= 41.08 tn
Pu2= Pu2= 77.67 tn

Esfuerzos cortantes y momentos flectores


1= 3.896349
2= 37.1837
3= 36.1062
4= 41.56383
5= 0.292226
6= 25.09379
7= 30.80194

d= 56.73 42.5475
x= 1.72821 cm 85.095

Vu= 18.5 Tn 46.6999


φVc= 77.8 Tn

D.- Verificación por Fuerza Cortante por Punzonamiento.-


Columna Exterior.- Columna Exterior.-
s= 30.00 cm s= 35 cm
t= 30.00 cm t= 35 cm
dL= 56.73 cm dL= 56.73 cm
dT= 54.82 cm dT= 54.82 cm
m= 58.365 cm m= 91.73 cm
n= 84.82 cm n= 89.82 cm
b0= 201.55 cm b0= 363.1 cm
A0= 4950.519 cm2 A0= 8239.19 cm2
Pu= 41.08053 Tn Pu= 77.669 Tn
σu= 9.28 Tn/m2 σu= 9.28 Tn/m2
Vup= 36.5 Tn Vup= 70.0 Tn
Beta= 1 Beta= 1
φVcp1= 221.8391 Tn φVcp1= 399.652 Tn
φVcp2= 149.7073 Tn φVcp2= 269.703 Tn
φVc= 149.7073 Tn φVc= 269.703 Tn

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

5. Diseño del Refuerzo.-


Acero Mínimo.-
b= 280.0 cm
h= 65 cm
As,min= 32.76 cm2
barras de 5/8" 1.98 cm2
S= 16.92 cm
Usar 1 de 5/8" @ 0.15
Apoyo Izquierdo
Usar 1 de 5/8" @ 0.15
Apoyo Derecho.-
Mu= 25.09 Tn-m
b= 280.0 cm
d= 56.73 cm
a= 5.673 cm
As= 12.32 cm2
a= 1.04 cm
As= 11.81 cm2
a= 0.99 cm
As= 11.8 cm2 -20.95
a= 0.99 cm
S= -16.9699 cm -9.4871
Usar 1 de 1/2"@0.30

Tramo Central.- 0.4997


Mu= 30.80194 Tn-m 8.58282 22.2191
b= 280.0 cm b= 280.0 b= 280.0
d= 56.73 cm d= 56.73 d= 56.73
a= 5.673 cm (asumido) a= 5.673 a= 5.673
As= 15.96 cm2 As= 4.21 As= 11.51
a= 5.67 cm a= 0.35 a= 5.67
As= 15.12 cm2 As= 4.01 As= 10.91
a= 1.27 cm a= 0.34 a= 0.92
As= 14.53 cm2 As= 4.01 As= 10.45
a= 1.22 cm a= 0.34 a= 0.88
As= 14.5 cm2 As= 4.01 As= 10.4
a= 1.22 cm a= 0.34 a= 0.88
barra 1/2" 1.27 cm2 barra 1/2 1.27 barra 1/2 1.27
S= 24.49 cm S= 88.58 S= 34.05
Usar 1 de 1/2" @ 0.20 Usar 1 de 1/2" @ 0.30 Usar 1 de 1/2" @ 0.30

Refuerzo Transversal.-
Bajo Columna Exterior.- Bajo Columna Exterior.-
Lv= 1.25 m Lv= 1.25 m
b= 74.05 cm b= 93.7 cm
Gud= 9.28 Tn/m Gud= 9.28 Tn/m
Wu= 6.87 Tn/m Wu= 8.70 Tn/m

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

Mu= 5.37 Tn-m Mu= 6.79 Tn-m


d= 30 cm d= 54.19 cm
a= 3 cm (asumido) a= 5.419 cm (asumido)
As= 5.26 cm2 As= 3.68 cm2
a= 1.67 cm a= 0.93 cm
As= 4.87 cm2 As= 3.34 cm2
a= 1.55 cm a= 0.84 cm
As= 4.86 cm2 As= 3.34 cm2
a= 1.54 cm a= 0.84 cm
As= 4.86 cm2 As= 3.34 cm2
a= 1.54 cm a= 0.84 cm
As,min= 8.66 cm2 As,min= 11.0 cm2
barras de 1.98 cm2 barras de 1.98 cm2
Nro barra 5.0 Nro barra 6.0
Usar 5 Φ 5/8" Usar 6 Φ 5/8"

Acero mínimo
b= 100 cm
d= 54.19 cm
As = 9.9 cm2
Barras de 1.98 cm2
Espaciami 20
Usar 1 Φ 5/8" @ 0.20 m

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO


UNIVERSIDAD NACIONAL PEDRO RUIZ GALLO
FACULTAD DE INGENIERÍA CIVIL, SISTEMAS Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

n Transversal.-

CONCRETO ARMADO II ING. SERRANO ZELADA OVIDIO