Implementation Plan for E980

servers

At

Maruti Suzuki India Ltd

© 2016 International Business Machines Corporation 1


POWER9 processor
1st chip

~1TB/s
with PCIe4
4GHZ
7TB/s
BW into chip PEAK
FREQUENCY

on chip
BW 8
BILLION

>15 TRANSISTORS
>24B
MILES OF VIAS
WIRE
17 Innovation that makes a
LEVELS OF
METAL difference for mission
critical applications
Key Differences between POWER9 and POWER 8

POWER9 POWER8
5U Server (Single CEC) + 2U control Unit, 920 GB/s
Form Factor (For Enterprise total System bandwidth per drawer
5U Server (Single CEC) + 2U control Unit
Servers)
Rack & Tower Rack & Tower

Transistor Count 8 Billion 4.2 Billion

CPU Lithography 14nm 22nm

74 GB/s - Fabric BW 38.4 GB/s - Fabric BW


64TB 32TB
Memory IS RDIMMs Scale out/ CDIMMS Scale-Up CDIMMs

PCIe – GEN3/4 Directly Integrates PCI Leadership PCIe GEN3 (48 lanes) Directly Integrates PCI
Lane Count Full Cache Integration Improves latency/bandwidth CAPI 1.0 Support

I/O 80 GB/s peak BW 48GB/s peak BW


4 internal NVMe U.2 boot devices Not available
6Gb SAS, Four 25Gb ports per drawer to attach
6Gb SAS
accelerators

CAPI CAPI 2.0 CAPI 1.0

2U – Single & Dual RAID Write Cache 2U - Dual RAID Write Cache
RAS
4U and Above – Dual Raid Write Cache 4U and Above – Dual Raid Write Cache

© 2018 International Business Machines Corporation 3


The E980 Enterprise Server features

© 2018 International Business Machines Corporation 4


Current Infrastructure in DC
P8 - E870 - T/M 9119-MME S.No. 84D7067 P7 - P750 - T/M 8233-E8B S.No. 06B9D8R
Hostname Core Memory (GB) Host Core Memory (GB)
Total = 80 Total = 1.5 TB Total = 32 Total = 512
VIOS-1 1 16 VIOS-1 1 16
VIOS-2 1 16 VIOS-2 1 16
CL01 2 16 CL01_FO 1 16
CL02 2 16 CL02_FO 1 16
CL03 2 20 CL03_FO 1 20
SR1_PR 11 128 SR1_FO 5 128
SR2_PR 6 48 SR2_DR 3 48
SR3 8 112 SR3_FO 7 112
KDPROD 0.5 16 KDPROD_FO 0.5 16
SR11_PR 4 32 SR11_FO 1 32
DEV01 2 60 MIG05 1 48
TEST01 2 60 Reserved memory -- 15
MIG01 1 32 Free 9.5 29
MIG03 1 48
MIG04 1 16
P8NIM 2 16
SR10 2 64
SR16 2 32
DV16 1 16
Reserved Memory -- 39
Free 28.5 733
Two New Enterprise E980 servers with 96 cores each
• Solution Highlights
– The new E980 servers are with 96 cores, 1536 GB RAM.
– Dual VIOS will be installed on the servers
– 4* (2 ports 10Gbps+ 2 Ports 1 Gbps) provisioned for Ethernet
– 4*4-port 16 Gbps FC HBA provisioned for SAN connectivity
– All Applications are to be SAN Boot
Proposed LPAR Distribution at DC

New Power E980 configuration


New Power E980 Configuration
Model VM Workload Cores RAM OS Model VM Workload Cores RAM OS
VIO 1 1.00 16 VIO 1 1 16
VIO 2 1.00 16 VIO 2 1 16
LPAR 1 CL01_PR_FO 2 37 AIX 7.1 LPAR 1 CL01_PR 2 37 AIX 7.1
LPAR 2 CL02_PR_FO 2 37 AIX 7.1 LPAR 2 CL02_PR 2 37 AIX 7.1
LPAR 3 CL03_PR 2 37 AIX 7.1 LPAR 3 CL03 _PR_FO 2 37 AIX 7.1
LPAR 4 SR1_PR_FO 13 206 AIX 7.1 LPAR 4 SR1_PR 13 206 AIX 7.1
LPAR 5 SR2_PR_FO 7 112 AIX 7.1 LPAR 5 SR2_PR 7 112 AIX 7.1
LPAR 6 SR3_PR 11 168 AIX 7.1 LPAR 6 SR3_PR_FO 11 168 AIX 7.1
LPAR 7 KDPROD_PR 1 16 AIX 7.1 LPAR 7 KDPROD_PR_FO 1 19 AIX 7.1
LPAR 8 SR11_PR 2 37 AIX 7.1 LPAR 8 SR11_PR_FO 2 37 AIX 7.1
PS-1 LPAR 9 SR10_PR 2 37 AIX 7.1 PS-2 LPAR 9 SR10_PR_FO 2 37 AIX 7.1
LPAR 10 SR16_PR 2 37 AIX 7.1 LPAR 10 SR16_PR_FO 2 37 AIX 7.1
LPAR 12 SR09_PR_FO 6 96 AIX 7.1 LPAR 12 SR09_PR 6 96 AIX 7.1
LPAR 13 SR07_PR 3 44 AIX 7.1 LPAR 13 SR07_PR_FO 3 44 AIX 7.1
LPAR 15 DEV01 2 32 AIX 7.1 LPAR 15 MIG01 1 16 AIX 7.1
LPAR 16 DV16 3 48 AIX 7.1 LPAR 16 MIG03 1 16 AIX 7.1
LPAR 17 MIG04 1 16 AIX 7.1 LPAR 17 TEST01 2 32 AIX 7.1
LPAR 18 MIG05 1 16 AIX 7.1 LPAR 18 P8NIM 2 32 AIX 7.1

Summary 63 1011 Summary 62 998


Buffer 33 525 Buffer 34 538
Current Infrastructure in DR
P6-570 - T/M 9117-MMA S.No. 068C604 P6-570 - T/M 9117-MMA S.No. 068D2D4
Host Name Core Memory (GB) Host Name Core Memory (GB)
Total = 16 Total = 128 Total = 16 Total = 128
VIOS1 1 16 VIOS1 1 16
VIOS2 1 16 VIOS2 1 16
SR2_DR_BN 1 24 SR1_DR_BN 4 32
SR3_DR_BN 3 25 CL02_DR_BN 1 10
CL01_DR_BN 1 10 CL03_DR_BN 1 15
NIM_DR_BN 1 10 Reserved memory -- 4
Reserved memory -- 7 Free 8 35
Free 8 20
One New Enterprise Server E950 with 48 cores

• Solution Highlights
– Both servers used are existing servers to be moved from DC
– DR capacity is at 80% of Prod DC
Proposed LPAR Distribution at DR
Existing P870 Configuration
Exisitng P750 Configuration
Model VM Workload Cores RAM OS Model VM Workload Cores RAM OS

VIO 1 1 16 VIO 1 1 16

VIO 2 1 16 VIO 2 1 16

LPAR 1 SR1_PR DR 30 480 LPAR 1 CL01 DR 2.61 41.76 AIX 7.1

LPAR 2 CL02 DR 2.61 41.76 AIX 7.1

LPAR 3 CL03 DR 2.61 41.76 AIX 7.1

LPAR 4 SR2_PR DR 7.94 127.0896 AIX 7.1

LPAR 5 SR3 DR 11.91 190.5648 AIX 7.1

LPAR 6 KDPROD DR 0.87 13.92 AIX 7.1


PS-1 PS-2
LPAR 7 SR11_PR DR 2.61 41.76 AIX 7.1

LPAR 8 SR16 DR 2.61 41.76 AIX 7.1

LPAR 9 SR09 DR 7.50 120 AIX 7.1

LPAR 10 SR07 DR 3.10 49.5552 AIX 7.1

LPAR 11 SR10 DR 2.61 41.76 AIX 7.1

Summary 32 512 Summary 48.98 783.69

Buffer 0 0 Buffer 31.02 752.31

PS-1 Existing P750 Server PS-2 Existing P870 Server

Note
The DR is provisioned at 80% of the capacity
- Power 9 sees a-least 30% technology upgrade over Power 8, Hence the number of cores required will be the same as
in current after considering 3 years 15 % growth
Implementation Activities
S/ Tentative Start Tentative End
Action Item Responsible Advisor Status Pre-Req's
N Date Date
Complete
1 Delivery of Hardware to DC IBM (TSS) Maruti 28-Feb-19 28-Feb-19
d
Complete
2 Inventory of Hardware IBM (TSS) Maruti 28-Feb-19 28-Feb-19
d
Complete
3 RACK Space & power allocation in stagging Maruti (Paramjeet) IBM (TSS) 28-Feb-19 28-Feb-19 Site Pre-Req's
d
Maruti
4 Asset creation IBM (TSS) Pending 28-Feb-19 12-Mar-19
(Paramjeet)
Maruti Complete
5 Power on the server in Staging IBM (TSS) 28-Feb-19 04-Mar-19
(Paramjeet) d
Complete
6 Download of latest VIOS/AIX/ image media IBM (TSS) Maruti 05-Mar-19 05-Mar-19
d
Complete
7 Allocation of 42000 BTU/Hrs Cooling (Maximum) Maruti (Paramjeet) IBM (TSS) 28-Feb-19 28-Feb-19
d
Complete
8 Space avaiability & allocation in DC for Rack1 Maruti (Paramjeet) IBM (TSS) 07-Mar-19 07-Mar-19
d
Complete
9 Allocation of 9KVA Power in a rack (Maximum) for Rack1 Maruti (Paramjeet) IBM (TSS) 28-Feb-19 12-Mar-19
d
Complete
10 Space avaiability & allocation in DC FOR Rack2 Maruti (Paramjeet) IBM (TSS) 28-Feb-19 12-Mar-19
d
11 Allocation of 9KVA Power in a rack (Maximum) for Rack2 Maruti (Paramjeet) IBM (TSS) Pending 28-Feb-19 20-Mar-19
Maruti (Manjit /
12 10G network cable feasibility & laying IBM (TSS) Pending 11-Mar-19 15-Mar-19 Network Connectivity
Deenbandhu)
Maruti Storage Team / Complete
13 16G FC SAN cable laying IBM (TSS) 11-Mar-19 12-Mar-19 SAN FC Connectivity
Manoj d
12 Management & client IP's IBM (TSS) Maruti Pending NA NA CR to Raise
13 Network switch installation in Server RACK for HMC network Network Team IBM (TSS) Pending 11-Mar-19 18-Mar-19 HMC network
RACK movement /Power ON/HMC connection/ Firmware
14 IBM (TSS) Maruti Pending 04-Mar-19 18-Mar-19 P9 Server Pre-Req's
Update
WWPN change of host on Power9, any storage host multipath
15 Maruti Storage Team IBM (TSS) Pending NA NA
change dependancy check
16 VIOS Servers installation/configuration IBM (TSS) Maruti Pending 13-Mar-19 15-Mar-19 LAB LLD, VIOS media images
a) VIOS profile creation & wwpn details IBM (TSS) Maruti Pending 13-Mar-19 15-Mar-19
Maruti Storage
b) 200GB LUN allocation from storage on each VIOS IBM (TSS) Pending 13-Mar-19 15-Mar-19 LLD from LAB team
Team
Maruti Storage
c) VIOS installation IBM (TSS) Pending 13-Mar-19 15-Mar-19
Team
17 Power LPARs profile creation & wwpn collection IBM (TSS) Maruti (Ravi) Pending 12-Mar-19 18-Mar-19

© 2018 International Business Machines Corporation 11


S/ Tentative Start Tentative End
Action Item Responsible Advisor Status Pre-Req's
N Date Date
18 UAT envoirnment for CL01 IBM (TSS) Maruti Pending 19-Mar-19 15-Apr-09
a) IP address for UAT environment IBM (TSS) Maruti Pending 11-Mar-19 18-Mar-19 CR to Raise
b) Storage disk allocation for Alt_clone on CL01 Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
c) Alt_clone rootvg of CL01 IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
d)shutdown MIG01 & remove network adapter in profile IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
e) Note & unassign disks from MIG01 LPARs Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
f) Map alt_clone disk from CL01 and assign to MIG01 for AIX
Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
upgrade.
g) Upgrade AIX 5.3 to 7.1 on MIG01 LPAR IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
h) Unassign cloned CL01 disk from MIG01 LPARs and assign to
Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
CL01 on power9
i) Create UAT LPARs for CL01 on Power 9 server IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
j) Power on CL01 UAT LPAR & health check IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
k) Assign Storage disk for datavg IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
BACKUP TEAM/ AIX
l) Restore datavg from backup or rsync Maruti Pending 19-Mar-19 20-Mar-19
Team
m) Test UAT environment Maruti IBM (TSS) Pending 20-Mar-19 15-Apr-19
n) Upon UAT test acceptance, shutdown production Maruti IBM (TSS) Pending 20-Mar-19 15-Apr-19
o) Change IP of UAT environment to production IBM (TSS) Maruti Pending 20-Mar-19 15-Apr-19
19 PowerHA Cluster for CL01 IBM (TSS) Maruti Pending 20-Apr-19 20-Apr-19 5 Hrs downtime for cluster configuration & testing
a) Take all kind of consistent backups Maruti Backup Team IBM (TSS) Pending NA NA
b) Install powerHA filesets IBM (TSS) MARUTI Pending NA NA
c)Take mksysb from CL01_PR & restore to CL01_PR_FO IBM (TSS) MARUTI Pending NA NA
d) Assign LPAR new hostname & IP address for CL01_PR &
CL01_PR_FO
IBM (TSS) MARUTI Pending NA NA CR TO RAISE
Note : CL01 with current IP would become flotting IP in
cluster
e) assign 10G cluster repository disk Maruti Storage Team MARUTI Pending NA NA
f) cluster configuration & testing IBM (TSS) MARUTI Pending NA NA
AIX image media/ storage team dependancy /
20 UAT envoirnment for SR1 IBM (TSS) Maruti (Ravi) Pending 21-Apr-19 28-Apr-19
downtime dependancy
a) IP address for SR1 UAT environment
IBM (TSS) Maruti Pending 11-Mar-19 18-Mar-19 CR to Raise
( SR1_PR , SR1_PR_FO & SR1 service IP)
b) Storage disk allocation for rootvg on SR1_PR , SR1_PR_FO
Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
LPARs
c) Take mksysb of SR1_PR & SR1_PR_FO IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
d) Restore mksysb through NIM on power9 for SR1_PR &
IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
SR1_PR_FO LPARs
e) Take storage level ReadWritable Business copy of data
volumes & map to SR1_PR & SR1_PR_FO on power9
f) configure cluster & health check

© 2018 International Business Machines Corporation 12


S/ Tentative Start Tentative End
Action Item Responsible Advisor Status Pre-Req's
N Date Date
21 UAT envoirnment for CL02 IBM (TSS) Maruti Pending 19-Mar-19 15-Apr-09
a) IP address for UAT environment IBM (TSS) Maruti Pending 11-Mar-19 18-Mar-19 CR to Raise
b) Storage disk allocation for Alt_clone on CL02 Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
c) Alt_clone rootvg of CL02 IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
d)shutdown MIG01 & remove network adapter in profile IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
e) Note & unassign disks from MIG01 LPARs Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
f) Map alt_clone disk from CL02 and assign to MIG01 for AIX
Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
upgrade.
g) Upgrade AIX 5.3 to 7.1 on MIG01 LPAR IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
h) Unassign cloned CL02 disk from MIG01 LPARs and assign to
Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
CL02 on power9
i) Create UAT LPARs for CL02 on Power 9 server IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
j) Power on CL02 UAT LPAR & health check IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
k) Assign Storage disk for datavg IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
l) Restore datavg from backup or rsync BACKUP TEAM/ AIX Team Maruti Pending 19-Mar-19 20-Mar-19
m) Test UAT environment Maruti IBM (TSS) Pending 20-Mar-19 15-Apr-19
n) Upon UAT test acceptance, shutdown production Maruti IBM (TSS) Pending 20-Mar-19 15-Apr-19
o) Change IP of UAT environment to production IBM (TSS) Maruti Pending 20-Mar-19 15-Apr-19
AIX image media/ storage team dependancy / downtime
22 UAT envoirnment for SR2 IBM (TSS) Maruti (Ravi) Pending 21-Apr-19 28-Apr-19
dependancy
a) IP address for SR2 UAT environment
IBM (TSS) Maruti Pending 11-Mar-19 18-Mar-19 CR to Raise
( SR2_PR , SR2_PR_FO & SR2 service IP)
b) Storage disk allocation for rootvg on SR2_PR , SR2_PR_FO
Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
LPARs
c) Take mksysb of SR2_PR & SR2_PR_FO IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
d) Restore mksysb through NIM on power9 for SR2_PR &
IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
SR2_PR_FO LPARs
e) Take storage level ReadWritable Business copy of data
volumes & map to SR2_PR & SR2_PR_FO on power9
f) configure cluster & health check
23 UAT envoirnment for CL03 IBM (TSS) Maruti Pending 19-Mar-19 15-Apr-09
a) IP address for UAT environment IBM (TSS) Maruti Pending 11-Mar-19 18-Mar-19 CR to Raise
b) Storage disk allocation for Alt_clone on CL03 Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
c) Alt_clone rootvg of CL03 IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
d)shutdown MIG01 & remove network adapter in profile IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
e) Note & unassign disks from MIG01 LPARs Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
f) Map alt_clone disk from CL03 and assign to MIG01 for AIX
Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
upgrade.
g) Upgrade AIX 5.3 to 7.1 on MIG01 LPAR IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
h) Unassign cloned CL03 disk from MIG01 LPARs and assign to
Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
CL03 on power9
i) Create UAT LPARs for CL03 on Power 9 server IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
j) Power on CL03 UAT LPAR & health check IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
k) Assign Storage disk for datavg IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19

© 2018 International Business Machines Corporation 13


S/ Tentative Start Tentative End
Action Item Responsible Advisor Status Pre-Req's
N Date Date
BACKUP TEAM/ AIX
23 l) Restore datavg from backup or rsync Maruti Pending 19-Mar-19 20-Mar-19
Team
m) Test UAT environment Maruti IBM (TSS) Pending 20-Mar-19 15-Apr-19
n) Upon UAT test acceptance, shutdown production Maruti IBM (TSS) Pending 20-Mar-19 15-Apr-19
o) Change IP of UAT environment to production IBM (TSS) Maruti Pending 20-Mar-19 15-Apr-19
AIX image media/ storage team dependancy /
24 UAT envoirnment for SR3 IBM (TSS) Maruti (Ravi) Pending 21-Apr-19 28-Apr-19
downtime dependancy
a) IP address for SR3 UAT environment
IBM (TSS) Maruti Pending 11-Mar-19 18-Mar-19 CR to Raise
( SR3_PR , SR3_PR_FO & SR3 service IP)
b) Storage disk allocation for rootvg on SR3_PR ,
Maruti Storage Team IBM (TSS) Pending 19-Mar-19 20-Mar-19
SR3_PR_FO LPARs
c) Take mksysb of SR3_PR & SR3_PR_FO IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
d) Restore mksysb through NIM on power9 for SR3_PR &
IBM (TSS) Maruti Pending 19-Mar-19 20-Mar-19
SR3_PR_FO LPARs
e) Take storage level ReadWritable Business copy of data
volumes & map to SR3_PR & SR3_PR_FO on power9
f) configure cluster & health check
25 PowerHA Cluster for CL02 IBM (TSS) Maruti Pending 27-Apr-19 27-Apr-19 5 Hrs downtime for cluster configuration & testing
a) Take all kind of consistent backups Maruti Backup Team IBM (TSS) Pending NA NA
b) Install powerHA filesets IBM (TSS) MARUTI Pending NA NA
c)Take mksysb from CL02_PR & restore to CL02_PR_FO IBM (TSS) MARUTI NA NA
D) Assign LPAR new hostname & IP address for CL02_PR &
CL02_PR_FO
IBM (TSS) MARUTI Pending NA NA CR TO RAISE
Note : CL02 with current IP would become flotting IP in
cluster
e) assign 10G cluster repository disk Maruti Storage Team MARUTI Pending NA NA
f) cluster configuration & testing IBM (TSS) MARUTI Pending NA NA
26 PowerHA Cluster for CL03 IBM (TSS) Maruti Pending 04-May-19 04-May-19 5 Hrs downtime for cluster configuration & testing
a) Take all kind of consistent backups Maruti Backup Team IBM (TSS) Pending NA NA
b) Install powerHA filesets IBM (TSS) MARUTI Pending NA NA
c)Take mksysb from CL02_PR & restore to CL02_PR_FO IBM (TSS) MARUTI NA NA
d) Assign LPAR new hostname & IP address for CL03_PR &
CL03_PR_FO
IBM (TSS) MARUTI Pending NA NA CR TO RAISE
Note : CL03 with current IP would become flotting IP in
cluster
e) assign 10G cluster repository disk Maruti Storage Team MARUTI Pending NA NA
f) cluster configuration & testing IBM (TSS) MARUTI Pending NA NA

© 2018 International Business Machines Corporation 14


S/ Tentative Start Tentative End
Action Item Responsible Advisor Status Pre-Req's
N Date Date
AIX image media/ storage team dependancy /
27 LPAR pre Migration & Migration Activites for DEV01 IBM (TSS) Maruti (Ravi) Pending 27-Mar-19 27-Mar-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending NA NA
b) shutdown DB / APP Maruti IBM (TSS) Pending NA NA
c) LPAR shutdown IBM (TSS) Maruti Pending NA NA
d) Add power9 wwpn to storage host / unmap all disks
Maruti Storage Team IBM (TSS) Pending NA NA
at storage level
e) Remove power8 WWPN from storage host / map all
Maruti Storage Team IBM (TSS) Pending NA NA
disks to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending NA NA
AIX image media/ storage team dependancy /
28 LPAR pre Migration & Migration Activites for DV16 IBM (TSS) Maruti (Ravi) Pending 28-Mar-19 28-Mar-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending NA NA
b) shutdown DB / APP Maruti IBM (TSS) Pending NA NA
c) LPAR shutdown IBM (TSS) Maruti Pending NA NA
d) Add power9 wwpn to storage host / unmap all disks
Maruti Storage Team IBM (TSS) Pending NA NA
at storage level
e) Remove power8 WWPN from storage host / map all
Maruti Storage Team IBM (TSS) Pending NA NA
disks to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending NA NA
AIX image media/ storage team dependancy /
29 LPAR pre Migration & Migration Activites for MIG01 IBM (TSS) Maruti (Ravi) Pending 29-Mar-19 30-Mar-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks
Maruti Storage Team IBM (TSS) Pending
at storage level
e) Remove power8 WWPN from storage host / map all
Maruti Storage Team IBM (TSS) Pending
disks to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
AIX image media/ storage team dependancy /
30 LPAR pre Migration & Migration Activites for MIG03 IBM (TSS) Maruti (Ravi) Pending 29-Mar-19 30-Mar-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks
Maruti Storage Team IBM (TSS) Pending
at storage level
e) Remove power8 WWPN from storage host / map all
Maruti Storage Team IBM (TSS) Pending
disks to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending

© 2018 International Business Machines Corporation 15


S/ Tentative Start Tentative End
Action Item Responsible Advisor Status Pre-Req's
N Date Date
AIX image media/ storage team dependancy /
31 LPAR pre Migration & Migration Activites for MIG04 IBM (TSS) Maruti (Ravi) Pending 29-Mar-19 30-Mar-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks
Maruti Storage Team IBM (TSS) Pending
at storage level
e) Remove power8 WWPN from storage host / map all
Maruti Storage Team IBM (TSS) Pending
disks to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
AIX image media/ storage team dependancy /
32 LPAR pre Migration & Migration Activites for MIG05 IBM (TSS) Maruti (Ravi) Pending 29-Mar-19 30-Mar-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks
Maruti Storage Team IBM (TSS) Pending
at storage level
e) Remove power8 WWPN from storage host / map all
Maruti Storage Team IBM (TSS) Pending
disks to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
AIX image media/ storage team dependancy /
33 LPAR pre Migration & Migration Activites for TEST01 IBM (TSS) Maruti (Ravi) Pending 29-Mar-19 30-Mar-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks
Maruti Storage Team IBM (TSS) Pending
at storage level
e) Remove power8 WWPN from storage host / map all
Maruti Storage Team IBM (TSS) Pending
disks to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
AIX image media/ storage team dependancy /
34 LPAR pre Migration & Migration Activites for P8NIM IBM (TSS) Maruti (Ravi) Pending 29-Mar-19 30-Mar-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks
Maruti Storage Team IBM (TSS) Pending
at storage level
e) Remove power8 WWPN from storage host / map all
Maruti Storage Team IBM (TSS) Pending
disks to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending

© 2018 International Business Machines Corporation 16


S/ Tentative Start Tentative End
Action Item Responsible Advisor Status Pre-Req's
N Date Date
AIX image media/ storage team dependancy /
35 SR7 server LPAR for Migration IBM (TSS) Maruti (Ravi) Pending 04-Apr-19 07-Apr-19
downtime dependancy
a) LPAR creation IBM (TSS) Maruti Pending
b) Storage disk allocation Maruti Storage Team IBM (TSS) Pending
c) AIX installation IBM (TSS) Maruti Pending
d) Filesystems creation IBM (TSS) Maruti Pending
ACTUAL DOWNTIME CALCULATION FROM IBM LAB DB
e) Database migration IBM LABS IBM (TSS) Pending
TEAM
36 PowerHA Cluster for SR7 IBM (TSS) Maruti Pending 07-Apr-19 07-Apr-19
a) Take all kind of consistent backups Maruti Backup Team IBM (TSS) Pending
b) Install powerHA filesets IBM (TSS) Maruti Pending
c) Assign LPAR new hostname & IP address for SR7_PR &
SR7_PR_FO
IBM (TSS) Maruti Pending CR TO RAISE
Note : SR7 with current IP would become flotting IP in
cluster
d) assign 10G cluster repository disk Maruti Storage Team IBM (TSS) Pending
e) cluster configuration & testing IBM (TSS) Maruti Pending
37 ORACLE_ebs server Migration IBM (TSS) Maruti (Ravi) Pending 07-Apr-19 14-Apr-19
a) LPAR creation IBM (TSS) Maruti Pending
b) Storage disk allocation Maruti Storage Team IBM (TSS) Pending
c) AIX installation IBM (TSS) Maruti Pending
d) Filesystems creation IBM (TSS) Maruti Pending
ACTUAL DOWNTIME CALCULATION FROM IBM LAB DB
e) Database migration IBM LABS IBM (TSS) Pending
TEAM
38 PowerHA Cluster for ORACLE_ebs IBM (TSS) Maruti Pending
a) Take all kind of consistent backups Maruti Backup Team IBM (TSS) Pending
b) Install powerHA filesets IBM (TSS) Maruti Pending
c) Assign LPAR new hostname & IP address for
ORACLE_ebs_PR & ORACLE_ebs_PR_FO
IBM (TSS) Maruti Pending
Note : ORACLE_ebs with current IP would become flotting
IP in cluster
d) assign 10G cluster repository disk Maruti Storage Team IBM (TSS) Pending
e) cluster configuration & testing IBM (TSS) Maruti Pending
39 ORACLE_forms server Migration IBM (TSS) Maruti (Ravi) Pending 14-Apr-19 21-Apr-19
a) LPAR creation IBM (TSS) Maruti Pending
b) Storage disk allocation Maruti Storage Team IBM (TSS) Pending
c) AIX installation IBM (TSS) Maruti Pending
d) Filesystems creation IBM (TSS) Maruti Pending
ACTUAL DOWNTIME CALCULATION FROM IBM LAB DB
e) Database migration IBM LABS IBM (TSS) Pending
TEAM
40 PowerHA Cluster for ORACLE_forms IBM (TSS) Maruti Pending
a) Take all kind of consistent backups Maruti Backup Team IBM (TSS) Pending
b) Install powerHA filesets IBM (TSS) Maruti Pending
c) Assign LPAR new hostname & IP address for
ORACLE_forms_PR & ORACLE_forms_PR_FO
IBM (TSS) Maruti Pending
Note : ORACLE_forms with current IP would become
flotting IP in cluster
d) assign 10G cluster repository disk Maruti Storage Team IBM (TSS) Pending
e) cluster configuration & testing IBM (TSS) Maruti Pending 17
© 2018 International Business Machines Corporation
S/ Tentative Start Tentative End
Action Item Responsible Advisor Status Pre-Req's
N Date Date
AIX image media/ storage team dependancy / downtime
41 LPAR pre Migration & Migration Activites for SR1 IBM (TSS) Maruti (Ravi) Pending 21-Apr-19 28-Apr-19
dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks at
Maruti Storage Team IBM (TSS) Pending
storage level
e) Remove power8 WWPN from storage host / map all disks
Maruti Storage Team IBM (TSS) Pending
to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
g) sync cluster IBM (TSS) Maruti Pending
AIX image media/ storage team dependancy / downtime
42 LPAR pre Migration & Migration Activites for SR2 IBM (TSS) Maruti (Ravi) Pending 28-Apr-19 05-May-19
dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks at
Maruti Storage Team IBM (TSS) Pending
storage level
e) Remove power8 WWPN from storage host / map all disks
Maruti Storage Team IBM (TSS) Pending
to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
g) sync cluster IBM (TSS) Maruti Pending
AIX image media/ storage team dependancy / downtime
43 LPAR pre Migration & Migration Activites for SR3 IBM (TSS) Maruti (Ravi) Pending 05-May-19 12-May-19
dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks at
Maruti Storage Team IBM (TSS) Pending
storage level
e) Remove power8 WWPN from storage host / map all disks
Maruti Storage Team IBM (TSS) Pending
to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
g) sync cluster IBM (TSS) Maruti Pending
AIX image media/ storage team dependancy / downtime
44 LPAR pre Migration & Migration Activites for KDPROD IBM (TSS) Maruti (Ravi) Pending 12-May-19 19-May-19
dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks at
Maruti Storage Team IBM (TSS) Pending
storage level
e) Remove power8 WWPN from storage host / map all disks
Maruti Storage Team IBM (TSS) Pending
to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
g) sync cluster IBM (TSS) Maruti Pending 18
© 2018 International Business Machines Corporation
S/ Tentative Start Tentative End
Action Item Responsible Advisor Status Pre-Req's
N Date Date
AIX image media/ storage team dependancy /
45 LPAR pre Migration & Migration Activites for SR11 IBM (TSS) Maruti (Ravi) Pending 19-May-19 26-May-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks
Maruti Storage Team IBM (TSS) Pending
at storage level
e) Remove power8 WWPN from storage host / map all
Maruti Storage Team IBM (TSS) Pending
disks to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
g) sync cluster IBM (TSS) Maruti Pending
AIX image media/ storage team dependancy /
46 LPAR pre Migration & Migration Activites for SR9 IBM (TSS) Maruti (Ravi) Pending 26-May-19 02-Jun-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all disks
Maruti Storage Team IBM (TSS) Pending
at storage level
e) Remove power8 WWPN from storage host / map all
Maruti Storage Team IBM (TSS) Pending
disks to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
g) sync cluster IBM (TSS) Maruti Pending
AIX image media/ storage team dependancy /
47 LPAR pre Migration & Migration Activites for SR10 IBM (TSS) Maruti (Ravi) Pending 02-Jun-19 09-Jun-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
Downtime required for AIX upgrade & LPAR
b)Upgrade AIX 6.1 to 6100-09-12-1838 or later IBM (TSS) Maruti Pending
migration
c) shutdown DB / APP Maruti IBM (TSS) Pending
d) LPAR shutdown IBM (TSS) Maruti Pending
e) Add power9 wwpn to storage host / unmap all disks
Maruti Storage Team IBM (TSS) Pending
at storage level
f) Remove power8 WWPN from storage host / map all
Maruti Storage Team IBM (TSS) Pending
disks to new power9 storage host
g) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
48 PowerHA Cluster for SR10 IBM (TSS) Maruti Pending 09-Jun-19 09-Jun-19 5 Hrs downtime required
BACKUP TEAM/ AIX
a) Take all kind of consistent backups IBM (TSS) Pending
Team
b) Install powerHA filesets IBM (TSS) Maruti Pending
c) Assign LPAR new hostname & IP address for SR10_PR
& SR10_PR_FO
Maruti Storage Team IBM (TSS) Pending
Note : SR10 with current IP would become flotting IP in
cluster
d) assign 10G cluster repository disk Maruti Storage Team IBM (TSS) Pending
e) cluster configuration & testing IBM (TSS) Maruti Pending
19
© 2018 International Business Machines Corporation
S/ Tentative Tentative
Action Item Responsible Advisor Status Pre-Req's
N Start Date End Date
AIX image media/ storage team dependancy /
49 LPAR pre Migration & Migration Activites for SR16 IBM (TSS) Maruti (Ravi) Pending 09-Jun-19 16-Jun-19
downtime dependancy
a) Take all kind of consistence backups Maruti IBM (TSS) Pending
b) shutdown DB / APP Maruti IBM (TSS) Pending
c) LPAR shutdown IBM (TSS) Maruti Pending
d) Add power9 wwpn to storage host / unmap all
Maruti Storage Team IBM (TSS) Pending
disks at storage level
e) Remove power8 WWPN from storage host / map
Maruti Storage Team IBM (TSS) Pending
all disks to new power9 storage host
f) Activate LPAR , AIX , network health check IBM (TSS) Maruti Pending
50 PowerHA Cluster for SR16 IBM (TSS) Maruti Pending
BACKUP TEAM/ AIX
a) Take all kind of consistent backups IBM (TSS) Pending
Team
b) Install powerHA filesets IBM (TSS) Maruti Pending
c) Assign LPAR new hostname & IP address for
SR16_PR & SR16_PR_FO
Maruti Storage Team IBM (TSS) Pending
Note : SR16 with current IP would become flotting
IP in cluster
d) assign 10G cluster repository disk Maruti Storage Team IBM (TSS) Pending
e) cluster configuration & testing IBM (TSS) Maruti Pending

Please note : For application migration CL01,CL02, Cl03 support will be required from the maruti application
team for testing and UAT

© 2018 International Business Machines Corporation 20


Thank You!