1 FDP- 1.0 Add Wherever Major Non
COM-52-PP- applicable the conformance
SP-GE-007 requirements of
surface
preparation and
coating
application pre-
during-after of
above
specifications
shall be followed
for underground
application.
2 FDP- 1.0 Add Coating/ Major Non
COM-52-PP- wrapping conformance
SP-GE-007 systems shall be
included.