PETRONAS GAS DEHYDRATION PLANT PHASE 2

TECHNICAL REQUISITION FOR


ENGINEERING SERVICES
REV.: A Attachment-3

ATTACHMENT-3

DEVIATION LIST

DEVIATIONS LIST
PETRONAS GAS DEHYDRATION PLANT PHASE 2
TECHNICAL REQUISITION FOR
ENGINEERING SERVICES
REV.: A Attachment-3

Sr. Document Clause Abstract of Description of Reason/ Alternate


No No. & Title No / Requiremen Deviation Justification Proposal
Section / t against for Deviation
Para which
deviation is
presented
1 FDP-113-52- 4.1 To be added CO2 Corrosion Factors
PRS-RE- to existing also depends on affecting CO2
GE-003 para. following factors corrosion are
1. Water wetting to be listed in
characteristics description to
2. Hydrocarbon CO2
Characteristics Corrosion.
3. Top of the line
wetting .
4. Partial
Pressure of
CO2
5. Temperature
6. pH
7. Carbonate
scale
2 FDP-113-52- 7.2 To be added CS+ CA 3 mm for
PRS-RE- to existing aboveground Not
GE-003 para. portion mentioned

3 FDP-113-52- 7.3 Zinc To be Zinc polarity


PRS-RE- Sacrificial checked.Maximu changes at 60
GE-003 anode m temperature for deg C and
located at the Hot oil to be above.
tank base for specified.
mitigation of
corrosion
4 FDP-113-52- 7.11 SS 316L may To be added Basic material
PRS-RE- be used
GE-003
5 FDP-113-52- 8.4 Monitoring Frequency to be As per best Frequency
PRS-RE- frequency for changed from international may be
GE-003 Cl,Dissolved monthly to 3-4 practices. increased /
metals, pH, times per week decreased
Fe count, initially for one after
suspended year. corrosion
solids and rates are
chemical verified by
residual- Corrosion
Monthly Specialist.
PETRONAS GAS DEHYDRATION PLANT PHASE 2
TECHNICAL REQUISITION FOR
ENGINEERING SERVICES
REV.: A Attachment-3

6 FDP-113-52- 8.4 NDE NDE to be carried As per Frequency


PRS-RE- Methods-on out within one international may be
GE-003 Annual Basis year of best practices increased /
commissioning as decreased
a baseline and after
thickness corrosion
verification for rates are
piping and verified by
components.Freq Corrosion
uency to be fixed Specialist
on corrosion rate
half life
philosophy or on
RBI frequency or
proposed by
Corrosion
Specialist
7 FDP-113-52- 8.4 Guided wave Guided wave As per Frequency
PRS-RE- frequency of examination- international may be
GE-003 2.5 years Guided wave best practices increased /
examination- to decreased
be carried out after
based on corrosion
External and rates are
internal corrosion verified by
at 2 to 5 years Corrosion
frequency . Specialist
8 FDP-113-52- 8.4 CP TR Monitoring - As per Frequency
PRS-RE- inspection Monthly Basis. international may be
GE-003 Frequency of best practices increased /
2 years Potential survey- decreased
Bi annually after
preferred but corrosion
minimum rates are
annually. verified by
Corrosion
Specialist
9 FDP-113-52- 8.4 Corrosion MIC Monitoring NACE Frequency
PRS-RE- coupon- To ring On monthly may be
GE-003 be added basis increased /
-SRB Test decreased
-APB Test. after
Location at water corrosion
sampling points rates are
(Any two) verified by
Corrosion
Specialist
PETRONAS GAS DEHYDRATION PLANT PHASE 2
TECHNICAL REQUISITION FOR
ENGINEERING SERVICES
REV.: A Attachment-3

10 FDP-113-52- 8.4 Inline Baseline Best


PRS-RE- Inspection inspection before practices.
GE-003 commissioning
and next
inspection based
on IRP
Baseline
inspection within
6 months of
commisioning.Ne
xt inspection after
5 years
11 FDP-113-52- 8.4 CP CIPS ,DCVG
PRS-RE- Inspection- survey during Best practices
GE-003 CIPS,DCVG installation as a shall be
Frequency of baseline surveyed
2 years survey.Next together with
inspection after 5 ILI
years interval.