Planned Actual % Show chart for Planned Show status What is current DEADLINE 32
27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 Remarks
List of Activities Allocated workshop Start Dur Start Dur Done 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
A SHIPYARD ARRIVAL 1 1 0 0 0%
B DOCKING 1 11 0 0 0%
C UNDOCKING 12 1 0 0 0%
E SAILING 13 19 0 0 0%
REPAIR SPECIFICATION
2 SERVICES
TELEPHONE INSTALLATION 1 11 0 0 0%
SHORE POWER 440V/60HZ CONNECTION 1 11 0 0 0%
COOLING WATER CONNECTIONS 1 11 0 0 0%
FIRE LINE CONNECTION 1 11 0 0 0%
F.W. SUPPLY WHEN INSTRUCTED 0 0 0 0 0%
BWTKS BOTTOM PLUGS REMOVE/REFIT - 15NOS Ms. Cuneti 2 1 0 0 0%
RUDDER BALDE BOTTOM PLUG REMOVE/REFIT Ms. Cuneti 2 1 0 0 0%
VACUUM TEST FOR ALL BOTTOM PLUGS WHEN INSTALLED 10 1 0 0 0%
CEMENTING OF ALL OPNED PLUGS TO BE ARRANGED Ms. Hanganu 10 1 0 0 0%
SCUPPERS INSTALLATION FOR BLASTING AND PAINTING 2 1 0 0 0%
TRANSDUCER'S PROTECTION AGAINST BALSTING&PAINTING (ECHO SOUNDER, SPEED LOG,
2 1 0 0 0%
ICCCP, ETC)
TANK CLEANING AS FOLLOW: #1 PORT/STBD HFO; #2 STBD HFO (related to ballast treatment);
DO TK STBD 2 5 0 0 0%
0 0 0 0 0%
HULL TREATMENT: FB-7500SQM 2TU/1FC; VERTICAL BOTTOM -4000SQM 2TU/2FC;
4 0 0 0 0 0%
BOOTTOP-4500SQM 2TU/1FC; TS-3650SQM 2TU/1FC
FW HPJ HULL WASHING INCLUDING RUDDER, SEACHESTS BOXES AND GRIDS, PROPELLER 1 10 0 0 0%
HULL BLASTING 1 10 0 0 0%
HULL PAINTING ACCORDING TO PAINT SPECIFICATION, INCLUDING SEA CHESTS, RUDDER AND
1 10 0 0 0%
SEA CHEST'S GRIDS
HULL MARKINGS: NAME, DRAFTS, IMO, PLIMSOL, TANKS AND HOLDS, PILOT, ETC 1 10 0 0 0%
CHAFING CHAIN WASHING, BLASTING (SAME TIME WITH HULL) & PAINTING - after inspection 2 1 0 0 0%
Page 1 / 6
27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 Remarks
List of Activities Allocated workshop Start Dur Start Dur Done 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
5.08 PIPING
CARGO LINES DRESSER COUPLING - RUBBER PACKING RENEWAL - 2NOS 2 9 0 0 0%
ER PIPES REMOVAL FOR INSPECTION AS MARKED - LIST TO BE ARRANGED 2 9 0 0 0%
PR BALLAST PIPES REMOVAL FOR INSPECTION AS MARKED - LIST TO BE ARRANGED 2 9 0 0 0%
M DECK PIPE REMOVAL FOR INSPECTION AS MARKED - LIST TO BE ARRANGED 2 9 0 0 0%
CARGO REDUCERS FLANGES RECONDITIONING - MACHINING IN WORKSHOP - 4NOS 2 9 0 0 0%
FABRICATE AND CONNECT PIPE LINE FROM VACUUM TO ATMOSPHERIC CONDENSER 2 9 0 0 0%
GRAY WATER PIPING RENEWAL AS MARKED; GALVANIZING TO BE INCLUDED FOR OLD SPOOLS 2 9 0 0 0%
Page 2 / 6
27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 Remarks
List of Activities Allocated workshop Start Dur Start Dur Done 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
Page 3 / 6
27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 Remarks
List of Activities Allocated workshop Start Dur Start Dur Done 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
HEATERS OVERHAULING AS FOLLOW: (3 nos confirmed 1 still pending) Mec Hidro Naval
M/E HFO PURIFIER HEATER 3 7 0 0 0%
M/E HFO HEATER 3 7 0 0 0%
G/E HFO HEATER 3 7 0 0 0%
AUX BOILER HFO HEATER 3 7 0 0 0%
LO PURIFIER HEATER
M/E JACKET FW PRE-HEATER
HEATERS SAFETY VVS OVERHAULING - 11NOS Ms. Bejan 3 7 0 0 0%
AJO
Page 4 / 6
Symbols to be used
Types of Gant for % complete
Planned █
Actual ↓
•
calendaristice)
progres lucrare