Lesson 7 * Alerting on Changes
Triggering an Alert
124
When a requirement, test, test instance, or defect in your project changes,
Quality Center can notify those responsible for any associated entities. You
can associate tests with requirements (see “Creating and Viewing
Requirements Coverage” on page 61) and defects with other Quality Center
entities (see “Linking Defects to Tests” on page 115). In addition, you can
create traceability links between requirements. For more information on
creating traceability links between requirements, see the HP Quality Center
User's Guide.
Quality Center can generate alerts for these changes:
When a requirement changes (excluding change of status), Quality Center
adds an alert flag to its associated tests and notifies their designers by e-mail
When the status of a defect changes to “Fixed”, Quality Center adds an alert
flag to its associated test instances and notifies their responsible testers by
e-mail.
When a test runs successfully, Quality Center adds an alert flag to its
associated defects and notifies the users assigned to them by e-mail
When a requirement changes, Quality Center adds an alert flag to its traced
to requirements and child requirements, and notifies their authors by
e-mail
In this exercise, you will trigger alerts for tests by changing the associated
requirement. You will modify the Cruise Booking requirement and then you
will view the flagged tests
To trigger an alert:
Display the requirements tree.
Click the Requirements button on the sidebar, and choose View >
Requirement Details.
Select the requirement that you want to change.
Under Cruise Reservation, select the Cruise Booking requirement.