NAMA : RAHMAT PANDAPOTAN SIAGIAN

KELAS : EL – 6F
MATKUL : MANPRO
NIM : 1605033012

NORMAL CEPAT
KODE AKTIFITAS PENDAHULU LANJUTAN
T $ T $

A PONDASI A B, C 5 500 2 575

B TIANG B D, E 5 250 2 550

C AIR C F 4 500 4 500

D DINDING D G 4 400 4 400

E SALURAN E H 2 100 1 150

F LISTRIK F H 4 400 3 800

G ATAP G I 6 300 2 500

H JENDELA H I 3 600 3 600

I FINISHING I - 3 300 3 300

Biaya Tak Langsung Minggu ke 10 $ 200/Minggu


Minggu ke 11 $ 100/Minggu

A. Jaringan Kerja
B. Jalur Kritis
C. Waktu Penyelesaian dan Total Biaya Normal/Biaya Cepat
Diagram Network Waktu Normal

Jalur Kritis = A, B, D, G,I


Waktu Pengerjaan = 23 Hari

HM1 = SPAi + 1 SPAi = Saat Paling Awal


HS1 = SPAi + L L = Waktu Kegiatan

HM1 A =0+1 =1 HS1 A =0+5 =5


B =5+1 =6 B = 5 + 5 = 10
C =5+1 =6 C =5+4 =9
D = 10 + 1 = 11 D = 10 + 4 = 14
E = 10 + 1 = 11 E = 10 + 2 = 12
F = 9 + 1 = 10 F = 9 + 4 = 13
G = 14 + 1 = 15 G = 14 + 6 = 20
H = 13 + 1 = 14 H = 13 + 3 = 16
I = 20 + 1 = 21 I = 20 + 3 = 23
Diagram Network Waktu Cepat

Jalur Kritis = A, C, F, H, I
Waktu Pengerjaan = 15 Hari

HM1 A =0+1 =1 HS1 A =0+2 =2


B =2+1 =3 B =2+2 =4
C =2+1 =3 C =2+4 =6
D =4+1 =5 D =4+4 =8
E =4+1 =5 E =4+5 =9
F =6+1 =7 F =6+3 =9
G =8+1 =9 G = 8 + 2 = 10
H = 9 + 1 = 10 H = 9 + 3 = 12
I = 12 + 1 = 13 I = 12 + 3 = 15