WORK SCHEDULE In-charge: Charrie Dela Peňa

PROJECT: 2-STOREY DORMITORY percentage done TARGET TO FINISH


LOCATION: Lote (Laundry) as of 06/13/19 June 14-15 June 17-22 June 24-29
MASONRY WORKS
Ground Floor
Drainage 40
Exterior wall (CHB) 100
Floor tapping 100
CR tile installation 30
Second Floor
Floor tapping
CR tile installation
CARPENTRY WORKS
Ground Floor
Interior wall 100
Exterior wall 50
Ceiling works 30
Doors installation 40
Vinyl installation
Cabinets & Drawers
Second Floor
Interior wall
Exterior wall
Ceiling works
Doors installation
Vinyl installation
Cabinets & Drawers
FABRICATION WORKS
Ground Floor
Wall Framing 80
Windows installation 60
Second Floor
Wall Framing 20
Windows installation
Trusses 100
ELECTRICAL WORKS
Ground Floor
Lighting Layout 90
Power Layout 90
Home run Layout 50
Second Floor
Lighting Layout
Power Layout
PLUMBING WORKS
Ground Floor
Sanitary Line 90
Water Line 90
Drainage
Fixtures Installation
Second Floor
Sanitary Line 30
Water Line
Down spout
Fixtures Installation
PAINTING WORKS
Interior wall
Exterior wall