Crane Capacity in Radius = 5.5 m Boom Length= 15.5 m Which is covering the lifting capacity. Boom Angle 56 Deg to Max 66 deg. Height covering Near Twenty Meter. Panel Length = 4.01 M. Lifting Gear Length = 6 M Total Vertical Height will be = 4.01+ 6 =10.01M. Consider 56 Deg angle required boom length for 10.01 M will be 17.09 M. Our Crane is covering the requirement. - Radiant Panel Lift and place on trailer. - Tie-up with trailer body by belt or chain. - Shift the radian panel partly and off load to its pre-assembly location. - Pre-assembly part maintaining the sequence of installation drawing. - Make half circle & Complete bolt tightening.. - Cover-up the fire insulation at part joint location. Completed Half Circle. Lifting and placing completed half circle one on to another to make circle. - Completed Circle will be lift in tandem lift. - Two Crane will be used for that lift. - 35T crane will be the main lift & 30T Crane will be used for the tailing. - After lift the full part in vertical position tailing crane will be released and main crane will be complete the position of object to its final location - Lifting belt/sling will be remove by using 30T crane and man basket after completing the tack-weld of all legs.