WEEKLY SCHEDULE INSPECTION

PT. WASA MITRA ENGINEERING


Tanjung Jati B Re-Expansion Project (TJB 5&6)
2x1000 MW Coal Fired Power Plant
Date : 29/06/2019
Jul-19
No. Work Description This Week Next Week Remark
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A MECHANICAL
OPERATING FLOOR (FL +16.000)
a U5 MSV/CV ST
Setting & Levelling
b U5 CRV ST
Setting & Levelling
c U5 Bench Mark STG
Setting & Levelling
d U5 HP & IP Outer Casing ST (Lower Casing)
Level & Alignment Check
e U6 Setting Clip & Rail OHC
Fit-up, Visual, Welding, Tightening & Alignment

MIZZANINE FLOOR (FL +8.000)


a U5 Monorail & Hoist for BFPT
Fit-up & Alignment
Welding Visual & PT
b U5 Gland Steam Condenser
Levelling/Centering & Alignment
Grouting Equipment
c U5 LP Heater Drain Tank
Levelling/Centering & Alignment
Grouting Equipment
d U5 Jacking Oil Pump
Levelling/Centering & Alignment
Grouting Equipment
e U5 Duplex Oil Filter
Levelling/Centering & Alignment
Grouting Equipment
f U5 Main Oil Cooler A/B
Levelling/Centering & Alignment
Grouting Equipment
g U5 Main Oil Conditioner Unit
Levelling/Centering & Alignment
Grouting Equipment

GROUND FLOOR (FL ±0)


a U5 BFPT (A)
Packer Plate Installation
b U5 Generator
MBFP Seal Oil Unit
Packer Plate Installation
c U5 BFPT (B)
Base Plate/Sole Plate Installation
d U5 LP Heater Drain Pump
Levelling/Centering & Alignment
Grouting Equipment
e U5 Auxiliary Water Pump A/B
Levelling/Centering & Alignment
f U5 Condenser Vacum Pump A/B
Levelling/Centering & Alignment

BASEMENT FLOOR (FL -2500)


a U5 Condensat Extraction Pump A, B, C
Levelling/Centering & Alignment
Grouting Equipment
b U5 Condenser (Lower Sheel)
Fit-up & Alignment
c U5 CCCW Heat Exchanger Strainer A/B
Packer Plate Installation
d U5 Polisher Mix Bed Vessel A/B
Levelling/Centering & Alignment
Grouting Equipment
e U5 Recirculating Pump A/B
Levelling/Centering & Alignment
Grouting Equipment

B PIPING
BASEMENT FLOOR (FL -8600)
a U5 CW Piping
Fit-Up & Visual Inspection

GROUND FLOOR (FL ±0) to MIZZANINE FLOOR (FL + 8000)


a U5 CCCW Piping
Fit-Up & Visual Inspection
b U5 Living Water Pipe
Fit-Up & Visual Inspection
c U5 LP Heater Vent Piping
Fit-Up & Visual Inspection
d U5 Gland Steam Pipe
Fit-Up & Visual Inspection

OPERATING FLOOR (FL +16000)


a U5 Lube Oil Pipe
Fit-Up & Visual Inspection
b U5 BFP Minimum FLow Pipe
Fit-Up & Visual Inspection

DEAERATOR FLOOR (FL +23000)


a U5 Feed Water Pipe
Fit-Up & Visual Inspection
C ELECTRICAL
TRANS YARD AREA
a U5 Excitation Transformer
Bolt Tightness Torque Check (After Assy)
b U5 Generator Transformer
Bolt Tightness Torque Check (After Assy)
c U5 Auxiliary Transformer A & B
Bolt Tightness Torque Check (After Assy)
d U5 Anchor Bolt Structure IPB
Setting &Installation

GROUND FLOOR (FL ±0)


a U6 Cable Tray (Horizontal)
External Inspection Installation
b U6 Cable Tray (Vertical)
External Inspection Installation

MIZZANINE FLOOR (FL +8000)


a U5 LV SWGR
Inspection Installation Panel
b Common LV SWGR
Inspection Installation Panel
c U5 UPS BATTERY
Inspection Installation Battery
d U5 MV SWGR
Inspection Installation Base Panel
e U6 Cable Tray Vertical
Inspection Installation

CABLE CELLAR & CONTROL BUILDING (FL +12300)


a U6 Cable Tray (Horizontal)
Inspection Installation

OPERATING FLOOR (FL +1600)


a U6 Control Equipment Room
Inspection Installation Base Panel
b U6 Setting Busbar OHC
Inspection Installation & Tightening

D TEST
COMPRESSIVE STRENTH TEST GROUTING
a U5 CEP A/B/C Test for 3 Day
b U5 Gland Steam Condenser Test for 3 Day
c U5 LP Heater Drain Tank Test for 3 Day
d U5 Jacking Oil Pump Test for 3 Day
e U5 LP Heater Drain Pump Test for 3 Day
f U5 Duplex Oil Filter Test for 3 Day
g U5 Main Oil Cooler A/B Test for 3 Day
h U5 Main Oil Conditioner Unit Test for 3 Day
i U5 Polisher Mix Bed Vessel A/B Test for 3 Day
j U5 Recirculating Pump A/B Test for 3 Day

Jepara, 29 Juni 2019


Approved by, Checked by, Prapared by,