GEOMECANICA APLICADA AL
PLANEAMIENTO Y EXPLOTACION
DE YACIMIENTOS EN MINERIA
SUBTERRANEA
Dr. Vidal Navarro Torres
Consultor Intercade
1
I. PLANEAMIENTO
DE EXPLOTACION SUBTERRANEA
INTERCADE www.intercade.org
CONSULTANCY & TRAINING
2
EL PLANEAMIENTO Y TIPOS DE PLANEAMIENTO
Planning is the process to get the right material out of the mine at the right time
to obtain the lowest possible cost per unit of final commodity product in order to
fulfil the business targets of the company
With the right. Planning is divided into two major segments, often classified as
strategic or operational:
• Strategic planning is the broadest, highest level, and longest term effort
concerned with defining the objectives of the firm—where the firm wants to
go and how it will get there.
• Operational planning, often relates to the activities of the organization that
concern he near term, but its primary focus is controlling the actions to
achieve the stated objectives.
objectives
LA ESTRUCTURA DEL PLANEAMIENTO DE MINA
Planning
Planning
Controlling
Organizing
<1 year
Functions Strategio Operational 1 – 5 years
of
Time Span - Long Term >10 yeras - Short and intermediate Term
Management
Performed By Mission Objetives - Operating Management
- Mission,
Establishes - Mission, Objetives - Action to Achieve
Mission & Objectives
Implementing
4 I. Planeamiento de explotación subterránea
INTERCADE www.intercade.org
CONSULTANCY & TRAINING
3
PLANEAMIENTO A LARGO, MEDIO Y CORTO PLAZO
Long-range plans, can set the direction of the enterprise and may be
analogous to strategic planning (more to five years). These plans focus
on the mission, objectives, and strategies of the company, but also
influence and guide intermediate-
intermediate and short
short-range
range operational planning.
Short-range plans, cover a span of one year or less. Ideally, these would
b geared
be d tto llong-term
t and
d intermediate-term
i t di t t programs as wellll as th
the
overall strategic plan. Here investment funds, revenues, production, and
activities can be budgeted with a more reliable degree of accuracy and can
be measured on quarterly or more frequent bases.
5 I. Planeamiento de explotación subterránea
INFORMACION TECNICA NECESARIA PARA EL PLANEAMIENTO
DE EXPLOTACION
Geológica y geotécnica:
• Topografia del terreno y de las bocas de sondages;
• Dimensiones del área a ser explotado;
• Buzamiento, morfologia, ley
Buzamiento morfologia ley de corte, grado de alteración
de corte grado de alteración del macizo;
• Comportamiento geotécnico del macizo rocoso.
Información estrutural:
• Profundidade de cobertura de roca;
• Estructura de las rocas encajantes y del depósito;
• Leyes del metal principal y de los subprodutos.
Información económica:
• Reservas probadas, probables
Reservas probadas probables e inferidas;
e inferidas;
• Regalias y lucros;
• Localización de la mina en relación a las vias de transporte;
• Situación política local, regional, nacional e internacional;
• Costos y valorizaciones de mineral.
6 I. Planeamiento de explotación subterránea
INTERCADE www.intercade.org
CONSULTANCY & TRAINING
4
PLANEAMENTO CICLICO DE MINA
CICLICAL MINE PLANNING
Geological model - Resources Optimisation inputs Production constraints
Mining methods and layout
Geotechnical
Geotechnical engineering Hydrogeological
Metallurgical engineering Processing
Extraction strategy
Geographical information
Loss and dilution factors Terrain
Cost - mining / processing / other Climate
Commodity price regional information
Optimisation Work schedule
Labour availability / productivity
Whittle
Political / safety situation
DRO Mine design Religion
Final pit Operational information
Underground layout Maintenance
Equipment selection Availability / Efficiency
Feedback Supply lines
7 I. Planeamiento de explotación subterránea
MODELAMIENTO DEL DEPOSITO MINERAL
8 I. Planeamiento de explotación subterránea
INTERCADE www.intercade.org
CONSULTANCY & TRAINING
5
MODELAMIENTO DE LOS ACCESOS Y SECUENCIA DE
EXPLOTACION
9 I. Planeamiento de explotación subterránea
PLAN DE DESARROLLO Y EXPLOTACION
Design and Schedule
• Gemcom/Surpac and MineSched
• Datamine and Mine 24D
• Maptek – Vulcan and Chronos
• Mintec – MineSight
• GMSI – mineCAD
• Promine
Russian programs: Digimine, Geomix
Stratiform deposits : Minex
10 I. Planeamiento de explotación subterránea
INTERCADE www.intercade.org
CONSULTANCY & TRAINING
6
EXEMPLO DA MINA DE TAQUARI VASSOURAS ‐ BRASIL
11 I. Planeamiento de explotación subterránea
EXEMPLO PLANEAMIENTO EN LA TAQUARI VASSOURAS ‐
BRASIL
12 I. Planeamiento de explotación subterránea
INTERCADE www.intercade.org
CONSULTANCY & TRAINING
7
DIMENSIONAMIENTO DE LA CAPACIDAD DE PRODUCCION
100
80 0,25
60 VOE (Años) = 6,5 )Reservas-Mt) . (1 + 0,2)
10
RITMO ANUAL DE PRODUCCION (Mt. / a)
10
8
NORTEAMERICA
2
SLIDAMERICA
ASI Y OCEANIA
EUROPA
AFRICA
0.8
REGLA DE TAYLOR
0.4
0.2
0.1
0.1 0.2 0.4 0.6 0.8 1 2 4 6 8 10 12 40 60 80 100 200 400 600 800 1000 2000 4000 9000 0000
RESERVAS DE MINERAL (Mt.)
13 I. Planeamiento de explotación subterránea
TAMAÑO DE PRODUCCION OPTIMO
Ritmo óptimo de producción (ROP)
ROP (t/año) = 4.22 (Reservas – t) 0.756
Limites de aplicación:
50.000 (t/año)< Ritmo anual < 6.000.000 t/año
Valor óptimo de explotación (VOE)
A. Cobre
VOE (Años) = 5.35. ( Reservas – Mt)0.273
B. Oro n = 10 minas
VOE (Años) = 5.08. ( Reservas – Mt)0.31 r = 0.80
n = 36 minas
r = 0.81
14 I. Planeamiento de explotación subterránea
INTERCADE www.intercade.org
CONSULTANCY & TRAINING
8
TAMAÑO DE PRODUCCION OPTIMO
nversión y e producción ‐‐ $/t
Costos de in
15 I. Planeamiento de explotación subterránea
INTERCADE www.intercade.org
CONSULTANCY & TRAINING