SUBJECT: REHABILITATION & RE-ASPHALTING OF ACCESS ROAD AND CAR STALAG TRUCK LOADING AREA

Item Description Qty Unit Unit cost Amount


A. Area for Rotomilling ang Asphalting
1.0 Rotomilling of existing asphalt pavement 100 mm thk 410.00 sq. m. 600.00 246,000.00
including compaction
2.0 Cleaning and application of SS1 820.00 sq. m. 25.00 20,500.00
3.0 Supply and compact of ready mix asphalt
a) 50 mm thk wearing coarse 49.20 m. t. 8,950.00 440,340.00
b) 50 mm thk binder coarse 52.00 m. t. 8,950.00 465,400.00