100%(6)100% found this document useful (6 votes) 4K views274 pagesConstruction
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
Construction
PE Exam Review-Civil Discipline
Prepared by: John W. Strybos, P.E.
Test Masters Educational Services, Inc.
www.testmasters.compage CON2
THIS PAGE INTENTIONALLY LEFT BLANK
Copyright by www.TestMasters.com. All Rights Reserved,
page CON2TABLE OF CONTENTS
Tovic Page
Cover Page 1-2
Table of Contents 3-6
References 7-10
Exam Content 11-16
Formulas and Data 17-30
A.M. Topics
Quantity Take-off Methods and Cost Estimating Discussion 31-34
Quantity Take-off Methods and Cost Estimating Problems 35-40
Quantity Take-off Methods and Cost Estimating Solutions 41-44
Project Schedules and Activity Identification and Sequencing Discussion 45-52
Project Schedules and Activity Identification and Sequencing Problems 53-56
Project Schedules and Activity Identification and Sequencing Solutions 57-58
Construction Load, Methods, Temporary Structures and Facilities Discussion 59 - 68
Construction Load, Methods, Temporary Structures and Facilities Problems 69-78
Construction Load, Methods, Temporary Structures and Facilities Solutions 79 - 86
Excavation and Embankment, Construction site layout and control Discussion 87 - 96
Excavation and Embankment, Construction site layout and control Problems 97 — 102
Excavation and Embankment, Construction site layout and control Solutions 103 - 106
Temporary and permanent soil erosion and sediment control (e.g., construction 107- 110
erosion control and permits, sediment transport, channel/outlet protection) and
Impact of construction on adjacent facilities Discussion
Temporary and permanent soil erosion and sediment control (e.g., construction 111- 112
erosion control and permits, sediment transport, channel/outlet protection) and
Impact of construction on adjacent facilities Problems
page CON3 Copyright by www.TestMasters.com. All Rights Reserved, page CON3TABLE OF CONTENTS (Continued)
Topic
Page
Temporary and permanent soil erosion and sediment control (e.g., construction 113-114
erosion control and permits, sediment transport, channel/outlet protection)
Impact of construction on adjacent facilities Solutions
Safety (e.g., construction, roadside, work zone) Discussion 118-118
Safety (e.g., construction, roadside, work zone) Problems 119-120
Safety (e.g., construction, roadside, work zone) Solutions 121-122
Topics
Earthwork Construction and Layout Problems 123-134
Earthwork Construction and Layout Solutions 136-140
Estimating Quantities and Costs Problems 441-150
Estimating Quantities and Costs Solutions 151-158
Construction Operations and Methods Probiems 199-170
Construction Operations and Methods Solutions 171-176
Scheduling Problems 17-186
‘Scheduling Solutions 187-194
Material Quality Control and Production Problems 198-202
Material Quality Control and Production Solutions 203-212
Temporary Structures Problems 213-218
‘Temporary Structures Solutions 219-222
Health and Safety Problems 223-240
Health and Safety Solutions 241-252
page CON4 Copyright by www.TestMasters.com. All Rights Reserved. page CON4TABLE OF CONTENTS (CONTINUED)
Topic Page
Engineering Economics Discussion 253-262
Engineering Economics Problems 263-268
Engineering Economics Solutions 269-274
END OF SECTION
page CONS Copyright by www.TestMasters.com. All Rights Reserved, page CONSpage CONG
THIS PAGE INTENTIONALLY LEFT BLANK
Copyright by www-TestMasters.com. All Rights Reserved,
page CONS:NCEES Principles and Practice of Engineering Examination
CONSTRUCTION Design Standards
Effective Beginning with the April 2015 Examinations
ABBREVIATION DESIGN STANDARD TITLE
AM Books Required
1) ASCE 37 Design Loads on Structures During Construction, 2002, American
Society of Civil Engineers, Reston, VA, www.asce.org
2) NDS National Design Specification for Wood Construction, 2012, American
Forest & Paper Association/American Wood Council, Washington, DC,
www.awe.org.
3) CMWB Standard Practice for Bracing Masonry Walls Under Construction, 2012,
Couneil for Masonry Wall Bracing, Mason Contractors Association of America,
Lombard, IL, www.masoncontractors.org.
4) AISC Stee! Construction Manual, 14th ed., 2011, American Institute of Stee!
Construction, Inc., Chicago, IL, www.aisc.ora
5) ACI 318 Building Code Requirements for Structural Concrete, 2011, American
Concrete Institute, Farmington Hills, MI, www.concrete.org.
6) ACI 347 Guide to Formwork for Concrete, 2004, American Conerete Institute,
Farmington Hills, Ml, www,concrete.org (in ACI SP-4, 7th edition appendix).
7) ACI SP-4 Formwork for Concrete, 7th ed., 2005, American Concrete Institute,
Farmington Hills, MI, www.concrete.org.
8) OSHA Occupational Safety and Health Standards for the Construction Industry,
29 CFR Part 1926 (US federal version), US Department of Labor, Washington,
Oc.
9) MUTCD-Pt 6 Manual on Uniform Traffic Control Devices—Part 6 Temporary
Traffic Control, 2009, US Federal Highway Administration, www.fhwa.dot.gov
10) Testmaster course notes
page CON7 Copyright by www.TestMasters.com. All Rights Reserved. page CON7PM Books Required
1) ASCE 37 Design Loads on Structures During Construction, 2002, American
Society of Civil Engineers, Reston, VA, www.asce.org,
2) NDS National Design Specification for Wood Construction, 2012, American
Forest & Paper Association/American Wood Council, Washington, DC,
www.awe.org.
3) CMWB Standard Practice for Bracing Masonry Walls Under Construction, 2012,
Council for Masonry Wall Bracing, Mason Contractors Association of America,
Lombard, IL, www.masoncontractors.org.
4) AISC Stee! Construction Manual, 14th ed., 2011, American Institute of Steel
Construction, Inc., Chicago, IL, www.aisc.org
5) ACI 318 Building Code Requirements for Structural Concrete, 2011, American
Conerete Institute, Farmington Hills, MI, www.concrete.org,
6) ACI 347 Guide to Formwork for Concrete, 2004, American Concrete Institute,
Farmington Hills, MI, www.concrete.org (in ACI SP-4, 7th edition appendix),
7) ACI SP-4 Formwork for Concrete, 7th ed., 2005, American Conerete Institute,
Farmington Hills, MI, www.concrete.ora,
8) OSHA Occupational Safety and Health Standards for the Construction Industry,
29 CFR Part 1926 (US federal version), US Department of Labor, Washington,
DC.
9) MUTCD-Pt 6 Manual on Uniform Traffic Control Devices—Part 6 Temporary
Traffic Control, 2009, US Federal Highway Administration, www.thwa.dot.aov
10) Testmaster course notes
PM Books Recommended
1) PCA Design and Control of Concrete Mixtures, 2011, 15th edition, Portland
Cement Association, Skokie, IL.
2) Lindeburg, M.R., Civil Engineering Reference Manual, 2011, 12th Edition, Professional
Publications, Inc., Belmont, CA, ISBN 978-159126-341-8, www.ppi2pass.com
3) NCEES PE Civil Construction Sample Questions and Solutions, www.ncees.org, ISBN
978-1-932613-51-3.
page CONS __Copyright by www.TestMasters.com. All Rights Reserved. page CONSReference categories for Construction depth module
1) Construction surveying
2) Construction estimating
3) Construction planning and scheduling
4) Construction equipment and methods,
5) Construction materials
6) Construction design standards (see above)
END OF SECTION
page CONS Copyright by www.TestMasters.com. All Rights Reserved. page CONSpage CON10
THIS PAGE INTENTIONALLY LEFT BLANK
Copyright by www. TestMasters.com. All Rights Reserved.
page CON10NCEES Principles and Practice of Engineering Examination
CIVIL BREADTH and CONSTRUCTION DEPTH Exam Specifications
Effective Beginning with the April 2015 Examinations
+ The civil exam is a breadth and depth examination. This means that examinees work
the breadth (AM) exam and one of the five depth (PM) exams.
+ The five areas covered in the civil exam are construction, geotechnical, structural,
transportation, and water resources and environmental. The breadth exam contains
questions from all five areas of civil engineering. The depth exams focus more closely
on a single area of practice in civil engineering.
+ Examinees work all questions in the morning session and all questions in the
afternoon module they have chosen. Depth results are combined with breadth results
for final score.
+ The exam is an 8-hour open-book exam. It contains 40 multiple-choice questions in
the 4-hour AM session, and 40 multiple-choice questions in the 4-hour PM session.
+ The exam uses both the Intemational System of Units (SI) and the US Customary
‘System (USCS).
+ The exam is developed with questions that will require a variety of approaches and
methodologies, including design, analysis, and application. Some problems may require
knowledge of engineering economics.
+ The knowledge areas specified as examples of kinds of knowledge are not exclusive
or exhaustive categories
+ The specifications for the AM exam and the Construction PM exam are included
here. The design standards applicable to the Construction PM exam are shown on the
page 6
CIVIL BREADTH Exam Specifications
Approximate
Number of
Questions
|. Project Planning 4
A. Quantity take-off methods
B. Cost estimating
C. Project schedules
D. Activity identification and sequencing
page CON11 Copyright by www. TestMasters.com. All Rights Reserved. __ page CON11CIVIL BREADTH Exam Specifications Continued
Approximate
Number of
Questions
|, Means and Methods 3
A. Construction loads
B. Construction methods
C. Temporary structures and facilities
Il. Soil Mechanics 6
A. Lateral earth pressure
B. Soil consolidation
C. Effective and total stresses
D. Bearing capacity
E. Foundation settlement
F. Slope stability
IV. Structural Mechanics 6
‘A. Dead and live loads
B. Trusses
C. Bending (e.g., moments and stresses)
D. Shear (e.g,, forces and stresses)
E. Axial (e.g,, forces and stresses)
F, Combined stresses
G. Deflection
H. Beams
|. Columns
J. Slabs
K. Footings
L. Retaining walls
V. Hydraulics and Hydrology 7
A. Open-channel flow
B. Stormwater collection and drainage (e.g., culvert, stormwater inlets, gutter flow,
street flow, storm sewer pipes)
C. Storm characteristics (e.g., storm frequency, rainfall measurement and distribution)
D. Runoff analysis (e.g., Rational and SCS/NRCS methods, hydrographic application,
runoff time of concentration)
E. Detention/retention ponds
F. Pressure conduit (e.g., single pipe, force mains, Hazen-Williams, Darcy-Weisbach,
major and minor losses)
G. Energy and/or continuity equation (e.g., Bernoulli)
page CON12 Copyright by www.TestMasters.com. All Rights Reserved. __ page CON12CIVIL BREADTH Exam Specifications Continued
Approximate
Number of
Questions
VI. Geometrics 3
A. Basic circular curve elements (¢.g., middle ordinate, length, chord, radius)
B. Basic vertical curve elements
C. Traffic volume (e.g., vehicle mix, flow, and speed)
VII. Materials 6
A. Soil classification and boring log interpretation
B. Soil properties (e.g., strength, permeability, compressibility, phase relationships)
C. Concrete (e.g., nonreinforced, reinforced)
D. Structural steel
E. Material test methods and specification conformance
F. Compaction
Vill, Site Development 5
‘A. Excavation and embankment (e.g., cut and fill)
B. Construction site layout and control
C. Temporary and permanent soil erosion and sediment control (e.g., construction
erosion control and permits, sediment transport, channel/outlet protection)
D. Impact of construction on adjacent facilities
E. Safety (e.g., construction, roadside, work zone)
pageCON13 Copyright by www.TestMasters.com. All RightsReserved. __ page CON13.CIVIL-CONSTRUCTION DEPTH Exam Specifications
Approximate
Number of
Questions
|. Earthwork Construction and Layout 6
‘A. Excavation and embankment (e.g., cut and fil)
B. Borrow pit volumes
C. Site layout and control
D. Earthwork mass diagrams and haul distance
E. Site and subsurface investigations
II, Estimating Quantities and Costs 6
A. Quantity take-off methods
B. Cost estimating
C. Cost analysis for resource selection
D. Work measurement and productivity
Ill Construction Operations and Methods 7
A. Lifting and rigging
8. Crane stability
C. Dewatering and pumping
D. Equipment operations (e.g., selection, production, economics)
E, Deep foundation installation
IV. Scheduling 5
‘A. Construction sequencing
B. Activity time analysis
C. Critical path method (CPM) network analysis
D. Resource scheduling and leveling
E. Time-cost trade-off
V. Material Quality Control and Production 6
A. Material properties and testing (e.g., soils, concrete, asphalt)
B. Weld and bolt installation
C. Quality control process (QA/QC)
D. Concrete proportioning and placement
E. Concrete maturity and early strength evaluation
VI. Temporary Structures 7
‘A. Construction loads, codes, and standards
B. Formwork
C. Falsework and scaffolding
D. Shoring and reshoring
E. Bracing and anchorage for stability
F. Temporary support of excavation
page CON14 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON14CIVIL-CONSTRUCTION DEPTH Exam Specifications
Approximate
Number of
Questions
VIL. Health and Safety
A. OSHA regulations and hazard identification/abatement
B. Safety management and statistics
C. Work zone and public safety
3
END OF SECTION
page CON15 __Copyright by www. TestMasters.com. All Rights Reserved.
page CON15page CON16
THIS PAGE INTENTIONALLY LEFT BLANK
Copyright by www.TestMasters.com. All Rights Reserved,
page CON16FORMULAS AND DATA
Earthwork Construction and Layout
\V = Volume of Earthwork in cubic yards or cubic feet.
1 cubic yard = 27 cubic feet
L = Distance (spacing) between cross-sections in feet.
L= Length of a triangular spoil pile in feet
R = Angle of Repose in degrees (a property of a soil)
B = Base width of triangular spoil pile in feet.
H = Height of a triangular or conical spoil pile in feet.
D = Diameter of a conical spoil pile in feet
‘A= cross section area in square feet
Average end area method: V = (0.5)(A; + Ag)(L)/27
Prismoidal formula: V = (L/6)*(Ai + 4Am + Aa)
Triangular Spoil Bank: B= (4V/(L*tanR))°*
Triangular Spoil Bank: H = 0.5°B*tanR.
Conical Spoil Pile: D = (7.64Vi(tanR))°?
Conical Spoil Pile H = 0.5*D*tan(R)
Overhaul (cy-stations) = Overhaul volume (cy) * Overhaul distance (stations)
Overhaul distance (stations) = Total haul — Free haul (stations)
Total haul = distance (stations) between centers of mass outside free haul
H = E/O = Excavation cost/Over haul cost
E = Excavation cost in $/cy
O = Overhaul cost in $/ey-ft
Length of economical haul = Free haul distance + H
pageCON17 Copyright by www.TestMasters.com. All Rights Reserved. __ page CON17FORMULAS AND DATA
Earthwork Construction and Layout
Earthwork volume for a grid (in CF) = (Average cut depth in feet) * (Area of grid in SF)
If multiple grids, then sum volumes of each grid
Q = “Area in a section of a mass haul diagram in cy-stations
\V = Maximum or minimum volume in CY that corresponds with the Q.
Average Haul distance = Q/V
Estim:
ing Quan
Outside Perimeter = 2 x (length + width + recess)
OP =2(L+W+R)
Inside perimeter = OP — 8*footing width
IP = OP -8w
Mean Perimeter = OP -4* footing width = IP +4* footing width
MP = OP -4w=IP +4w
BF = board foot = [Length (feet)]*[nominal size (inches x inches)}(12 inches/foot)
SFCA = square foot of contact area
Formwork Conversions
To Obtain Gross area of Forms Multiply Net Areas by
Industrialize Wall Forms 1.20
Table forms for slabs 1.40
Tunnel and half-Tunnel forms 1.15
page CON18 Copyright by www.TestMasters.com. All Rights Reserved, __page CON18.FORMULAS AND DATA
‘Scheduling
INTERFERING FLOAT (IF) of activity j = (LATE FINISH (LF) of activity j) - (SMALLEST
EARLY START (ES) OF ALL SUCCESSOR ACTIVITIES)
FREE FLOAT (FF) of activity j = (MINIMUM EARLY START (ES) OF ALL SUCCESSOR
ACTIVITIES) — (EARLY FINISH of activity j)
TR =FF+IF
TF=LS-ES
TF =LF-EF
Forward Pass = (EF) Early Finish, =(ES) Early Start, + (D) Duration,
Backward Pass: = (LS) = Late Start, = (LF) Late Finish, ~ (D) Duration,
Lag = the amount of time an activity must be delayed from the start of finish of a
predecessor.
Lead = the amount of time by which an activity precedes the start or finish of a
successor.
Four precedence relations ships are:
Finish to Start (FS)
Early Start (ES) n+1 = Early Finish (EF), + Lag
Late Finish (LF) » = Late Start (LS) ps1 - Lag
Start to Start (SS)
Early Start (ES) q.1 = Early Start (ES), + Lag
Late Finish (LF) » = Late Start (LS) nt - Lag
Finish to Finish (FF)
Early Start (ES) n.1 = Early Finish (EF), + Lag ~ Duration (D)nv1
Late Finish (LF) . = Late Start (LS) n+1 - Lag
Start to Finish (SF)
page CON19 __Copyright by www.TestMasters.com. All Rights Reserved. __ page CON19FORMULAS AND DATA.
TEMPORARY STRUCTURES FORMWORK
P (psf) = Co*Cy*(150 + 9000R/T) for R <7 fuhr and H < 14 ft
P (psf) = Cc*C,, "(150 + 43,400/T + 2800R/T) for H > 14 ftand 7 |
tor tocol Pen)
Tos ees] To
Pope See oe
pow [ ose
i a a
5 a a
j [ea
7 is [es
7 [66
a
7 a
i 5
ceneerne comes 115
page CON24
Copyright by www.TestMasters.com. All Rights Reserved,
page CON24Engineering Economics (A.M. and
Factor Table 1 050%
PF Pe PP
ve cet tae
116 cmesmcecomurs
page CON25
Copyright by www.TestMasters.com. All Rights Reserved.
page CON25,=| Fm
1]
200%
= 7a a
execu semen 117
page CON26 Copyright by www.TestMasters.com. All Rights Reserved. __ page CON26pews wu ceuey:
118 seenemcscomomes
page CON27 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON27.Engineering Economics (A. ind P.M. Topit
Factor Table i= 800%
lnsseeuee
meres econoucs 119
page CON28 Copyright by www.TestMasters.com. All Rights Reserved. __ page CON28Engineer
Factor Table == 1200%
pseseuven
| ees | sa Sime
pe owe eusuusenszeer:
120 ormeemmc ccomomes
page CON29 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON29.|
iff
fie i
Lot;
E i
—
semen ttl Buon teh See
a] EE Gh ae oi 8 aL
lh ey it a a E
5h) Bea it i Bal Hu
B) Han Hee Hs Hea
‘ P)HAH RE a
sls a 5 a] ie
| 8 elaliel a |i a [His] be | Gly
afi lava) i aU Gecbal|:
e e/a ml a] il] Gf He
| [a balalal gla TEER
ye [state] a fa a fefs [sfa] =
i 1a |
g z ra
i lates | ale [E
ul a [als a ‘
4) e, leales [ode 82,2
Be 2
ah ..|.|!
Fe eee || FI!
el le aly
ulema eR eae Tisclnnar so vou Hy
cam
END OF SECTION
cy ae
page CON30___Copyright by www.TestMasters.com. All Rights Reserved. __ page CON30A.M. Topics
1. Project Planning - Discussion
A. Quantity Take-off Methods
B. Cost Estimating
page CON31 __ Copyright by www.TestMasters.com. All Rights Reserved. __page CON31Estimating Quantities and Costs
Outside Perimeter = 2 x (length + width + recess)
OP =2(L + W+R)
Inside perimeter = OP — 8*footing width
IP = OP -8w
Mean Perimeter = OP -4 footing width = IP +4* footing width
MP = OP —4w=IP + 4w
BF = board foot = [Length (feet)]*{nominal size (inches x inches)}/(12 inches/foot)
SFCA = square foot of contact area
Formwork Conversions
To Obtain Gross area of Forms Multiply Net Areas by
Industrialize Wall Forms 1.20
Table forms for slabs 4.10
Tunnel and half-Tunnel forms 4.15
Reinforcement Bar Size and Weights
Bar# Diameter Inch Area (sq. in.) Weight (Ibift)
3 0.375 om 0.376
4 0.500 0.20 0.668
5 0.625 0.31 1.043
6 0.750 044 | 4.502
7 0.875 0.60 2.044
8 1.000 0.79 2.670
9 1.428 1.00 3.400 _|
10 1.270 1.27 4.30
11 1.410 1.56 5.31
14 1.693 2.25 7.65
78 2.257 4.00 73.60
An estimate is the “prediction” of future construction costs. It is the process of looking
into the future and predicting cost and resource requirement. It will need to determine
the anticipated cost of materials, labor, and equipment of a proposed project
page CON32 __Copyright by www.TestMasters.com. All Rights Reserved, _ page CON32Types of Construction Costs:
Direct costs and Indirect Costs.
Types of Estimates
Conceptual (Rough Order of Magnitude)
Preliminary
Engineer
Bid
Rona
Elements of construction Costs
Labor
Materials,
Equipment
Subcontractors
Overhead and Profit
hens
Labor Costs
To price labor estimate the work hours required to do a unit of work of all trades
involved. (work crew productivity). Multiply the hours required by wages and benefits =
total cost of labor per unit of work.
Factors affecting labor are productivity and availability of qualified labor including
unions.
‘Material Costs
‘Supplies purchased by the contractor and incorporated into the finished construction
project (lumber, windows, concrete, etc.)
Equipment Costs
Cost of equipment including maintenance, taxes and insurance on the equipment,
maintenance, depreciation, and allowance for repairs. Operating costs (cost per hour),
rental costs and depreciation and maintenance.
Overhead Costs
Costs that cannot be attributed to any particular job “Office expenses.” Management
and Staff including salaries, fringe, benefits and transportation. Business offices
including rent, furniture and depreciation, office supplies, communications, telephone,
faxes, and advertising
page CON33 Copyright by www.TestMasters.com. All Rights Reserved. __page CON33—S Direct Costs of all the resources = Labor + Material + Equipment
5 Indirect Costs include bond premiums, insurance premiums, fees for licenses and
permits, services such as water, electricity, communications, home office overhead
allocation,
Quantity Take-off
Review drawings and specifications
Measure quantities of work to be performed in appropriate units
Loss factors as applicable
vt uerr
Contingency as applicable.
END OF SECTION
page CON34 __ Copyright by www.TestMasters.com. All Rights Reserved. __ page CON34|. Project Planning - Problems
page CON35:
A. Quantity Take-off Methods
B. Cost Estimating
Copyright by www.TestMasters.com. All Rights Reserved,
page CON35,Estimating Quantities and Costs Problems
101. A 200-foot by 100-foot room has been prepared for painting. The walls are 7-feet
high and will require two coats of paint on the previously painted surface for proper
coverage. If 1 gallon of paint covers 300-square feet, the number of gallons of paint
needed to paint the walls is most nearly:
A) 14 gallons
©) 67 gallons
D) 81 gallons
102. The outside perimeter of a brick walll is 53 ft Calculate the bricks required to build
this wall if its height is 8 feet and the bricks will all be laid in a running bond, Standard
non-modular bricks have been specified for the project. Assume a 1% waste factor.
Mortar joints are 3/8-inch. Brick size is 3-5/8 inches by 2-1/4 inches by 8 inches.
A) 1,402 Bricks
B) 1,500 Bricks
c)
‘805 Bricks
D) 3,000 Bricks
103. A 250-foot by 125-foot room has been prepared for painting. The walls are 9-feet
high and will require two coats of paint on the previously painted surface for proper
coverage. If 1 gallon of paint covers 325-square feet, the number of gallons of paint
needed to paint the walls is most nearly:
A) 21 gallons
B) 28 gallons
D) 55 gallons
page CON36___ Copyright by www.TestMasters.com. All Rights Reserved. __ page CON36.104. What is the volume of conerete (cy) required for a 4,500 foot long channel with
10% waste. The channel cross-section is shown below.
A) 235 cubic yards
CB) 6,368 cubic yards > G, DEI cy
©) 57,222 cubic yards
D) 174,666 cubic yards
TIN THICK
‘SIDE SCOPES 2V:3H
7 oe
AF.
“ ~
‘ con ee a. eget
OT AI :
Figure 1. Problem 104 Channel Cross-Section
page CON37___Copyright by www.TestMasters.com. All Rights Reserved. _ page CON37_Use the Figure shown below to answer problems 105, 106 and 107.
——
30°
15°
15°
3
Figure 2. Problems 105, 106 and 107 Foundation Wall
105. Calculate the outside perimeter of the wall shown in the Figure above,
asin OCs DO+1E +343’ + 18 430%:
B) 60 ft
D) 120 ft
106. The width of the foundation wall shown in the figure above is four feet. Calculate
the volume of concrete required to build this foundation wall if its cross sectional area is
85h
A) 12.25 cy MP Of- Hy, = fo2'~4 (a) = 80-4
B) 18 cy x Peer
page CON38 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON381A4 rate HD (Ae of We
107. If the wall shown in the figure above is two feet in height what is the required
formwork in sfca.
0”: 1o7 t+
A) 172 sfca
TP: OP- hw = 1o2- Blu) Fok
B) 200 sfca
Cea (WU) +AN(2) +311 shes
D) 400 sfea (N. Ferme Camnrs ve)
108. Calculate the number of bricks (3.75" x 2.25” x 8") laid in running bond required for
a double wythe wall 8-feet high by 14-feet wide having one penetration 48-inches x 72-
inghes and one opening 32 inches by 48 inches. Mortar joints are 0.5-inches and there
is 3% brick waste. .
rt pci
A) 500 bricks
B) 1,000 bricks
a
C) 1,500 bricks
s D) 2,000 bats
He
109. Calculate the volume of mortar (cf) for the following brick wall. A double wythe wall
B-feet high by 14-feet wide having one opening 48-inches by 72-inches and one
972 opening 32 inches by 48 inches. Mortar joints are 0.5-inches and there is 25% mortar
waste, The joint thickness between the wythes is 0.5-inch. There are 982 total bricks
B75" x 2.25" x 8") for both wythes including 3% brick waste
re
ger a~ yer Ap 43. PE Ger
2 10> bevks
Does? B) 18.3 of 1.0% sed
©) 27.4 cf
vez | | 6, O122-£4 Acie’
D) 366 cf .
0.5 "elas
—— S$. 6251S brick
as FOB 4 AY wek
pageCON39___Copyright by www,TestMasters.com. All Rights Reserved. _ page CON39110. Calculate the longitudinal #6 reinforcing steel in the wall shown below (not the
footing). The wall is 60 ft long and 6 in. of cover is required at each end. The bars
come in 20-ft lengths and will have to be lapped 6 in. How many tons of #6 steel should
be ordered? (i3)« lo’. o 7 of cob
A) 0.298 Tons x Lsort he
B) 0.300 Tons A ! Let va
zo’ Mae’ as
D) 0.600 Tons y 4 TE 58
ho Gu
2” Clear
Space
j+-2” Clear Space
{13 18 cont @12" 06 p>
vertical bars
PEir' ec
"oO
Weep Hole
@ woc
y
Clear
3” Clear Space Space
86"
Figure 3. Problem 110 Wall Cross-Section
END OF SECTION
page CON40___Copyright by www.TestMasters.com. All Rights Reserved. _ page CON4O.1. Project Planning - Solutions
A. Quantity Take-off Methods
B, Cost Estimating
page CON41 Copyright by www.TestMasters.com. All Rights Reserved. _page CON41Estimating Quantities and Costs Solutions
101. B) 28
jons
Perimeter = (2*200 ft)+ (2"100 ft) = 600 ft
Wall surface area = 600 ft * 7 ft = 4,200 f?
Number of gallons = (4,200 ft? / coat)(2 coats)/(300 ft?/gallon) = 28 Gal
Reference: Frank R. Walker Company, Walker's Building
Estimator's Reference Book.
102, C) 2,805 BRICKS,
REFERENCE: LINDEBURG PAGE 67-3
USE 0.375 INCH STANDARD MORTAR JOINT
Area of wall = 53x 8 => 424 sq ft
Area of one soldier brick =
A= (24+ 0.375 in.) x (8 + 0.375 in.) 21.98 sq in/144 sq inisf = 0.1526 sfibrick
Briok per sq. ft= (144 sq.in/sf)/(21.98 sq. in./brick) => 6.55 bricks per square foot
Number of bricks without waste =
424 sq ft x 6.55 brick per sq. ft => 2,777 brick
Number of bricks with waste =
2,777 brick x 1.01 = 2,805 bricks
103. C) 42 Gallons
Perimeter = (2°250 ft)+ (2"125 ft) = 750 ft
Wall surface area = 750 ft* 9 ft = 6,750 ff
Number of gallons = (6,750 ft? / coat)(2 coats)/(325 f?/gallon) = 42 Gallons
Reference: Frank R. Walker Company, Walker's Building
Estimator’s Reference Book.
page CON42 Copyright by www.TestMasters.com. All Rights Reserved. __ page CON42104. B) 6,358 cy
Length of side slopes using 2 vertical to 3 horizontal
141K = 2/3 > X = 21-feet = horizontal length
Side Slope Length = (14? + 217)° = 25.23 ft
Cross-Section Area = (7/12)[2(25.23) + 9]
= 34.68 sf
Volume = (4,500 ff)(34.68 sf)(1.1)(toyl27 of) =
Volume = 6,358 cy
105. _C) 402 ft
Outside perimeter = 2 x (length + width + recess)
Outside perimeter = 2 x (30 + 18 + 3) = 102 ft
108. C) 25.5 cy
Outside perimeter = 2x (30 + 18 + 3) = 102 ft
Mean perimeter = 102-4 (4) = 86 ft
Volume concrete = 86 ft x 8 sf => 688 cf or 25.5 cy
107. C) 344 sfca
Inside perimeter = OP + 4 x (2 x (-4))
Inside perimeter = 102 + 4 x (- 8) > 70ft
Outside forms = 102 x 2 = 204 sfca
Inside forms = 70 x 2 = 140 sfca
Total formwork = 204 + 140 = 344 sfca
page CON43 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON43,108. B) 1,000 bricks
NET WALL AREA = (8*14) — (46) — (2.67*4) SF
= 77.33 SF
AREA OF ONE BRICK = (2.25 + 0.5)*(8 + 0.5)(144 sq. in/sf)
= 0.1632 SF
N= (77.33/0.1632)'2"1.03 = 982 BRICKS
109. B) 18.3 CF
VOLI BRICK = (0.5 in,)*(8+2.25+0.5 in.)*(3.75 in.)/(1728 cu. In/ef)
= 0.01166 CFibrick
VOL. PER WYTHE = 0.01166(982/2) =5.7 CF
VOL. BETWEEN WYTHE = (0.5 in)(77.33 sf)/(12 in/sf) = 3.2CF
MORTAR REQUIRED = (1.25)*(2°5.7+3.2) = 18.3 CF
110. C. 0.586 Tons
Number of longitudinal bars for 60 ft of wall: 3
space (cover)= 0.5 ft
firstbar = «20.0%
secondbar = 19.5%
thirdbar = 19.5 ft
Cover = O5tt
Total = 600
Number of longitudinal bars: 3 x 13 = 39
Total length of longitudinal bars: 20 ft x 39 = 780 ft of #6 bars
Weight of #6 bars: 780 ft total length x 1.502 Ib per If = 1,171.56 Ib
Weight of #6 bar
586 tons
END OF SECTION
pageCON44 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON441. Project Planning - Discussion
C. Project Schedules
D. Activity Identification and Sequencing
NOTE: Critical Path Method (CPM) and network Analysis are identified as PM
Construction Topics. Discussion is included on CPM due to its relationship to Activity
Time Analysis.
page CON45 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON45Project Schedules Formulas
INTERFERING FLOAT (IF) of activity j= LATE FINISH (LF of activly|- SMALLEST EARLY START (ES) OF ALL SUCCESSOR
ACTIVITIES
FREE FLOAT (FF) of aly = MINMUM EARLY START (ES) OF ALL SUCCESSOR ACTIVITISS ~ EARLY FINISH of cut
TR =FF+IF
TF=LS-ES
TF =LF-EF
Forward Pass = (EF) Early Finish, =(ES) Early Start, + (D) Duration,
Backward Pass: = (LS) = Late Start, = (LF) Late Finish, — (D) Duration,
Lag = the amount of time an activity must be delayed from the start of finish of a
predecessor.
Lead = the amount of time by which an activity precedes the start or finish of a
successor.
Four precedence relationships are:
Finish to Start (FS)
Early Start (ES) nei = Early Finish (EF), + Lag
Late Finish (LF) , = Late Start (LS) n+: - Lag
Start to Start (SS)
Early Start (ES) 41 = Early Start (ES), + Lag
Late Finish (LF) » = Late Start (LS) n+: -Lag
Finish to Finish (FF)
Early Start (ES) n+: = Early Finish (EF), + Lag — Duration (D)n+1
Late Finish (LF) , = Late Start (LS) .+1-Lag
Start to Finish (SF)
page CON46 __Copyright by www.TestMasters.com. All Rights Reserved. _ page CON46:Objectives include the ability to create a simple bar chart and a simple Critical Path
Method (CPM) logic network and an understanding of how to use a CPM for
determining project status and in identifying float. The ability to calculate resource
needs and an understanding of resource leveling strategies. The ability to create a
velocity diagram. The ability to develop a linear schedule.
‘Acommon technique used to understand and organize complex undertaking is to divide
the problem into smaller subparts. In construction this technique is applied in both
estimating and planning
The critical path method (CPM) is a planning and control technique that provides an
accurate, timely, and easily understood picture of the project. The logic diagram
graphically portrays the relationships between project activities
Planning creates an orderly sequence of events. It serves the manager by pointing out
the things to be done, their sequence how long each task should take and who is
responsible for which tasks or actions. A common technique used to understand and
organize complex undertakings is to divide the problem into smaller subparts. Each
activity is a discrete task.
+ Activities consume time.
+ Activities usually consume physical resources.
+ Activities have definable start and finish points.
+ Activities are assignable.
+ Activities are measurable
The bar chart is widely used as a construction-scheduling tool because of its simplicity,
ease of preparation, and understandable format. Normally the activities are listed in
chronological order according to their start date. Discontinuous bars are sometimes
used on hand drawn bar charts to represent interruptions of activities. It does not clearly
show the detailed sequence of the activities It does not show which activities are critical
to the successful, timely completion of the project
Example Bar Chart
[TASK | JAN | FEB | MAR | APR | MAY | JUNE | JULY | AUG | SEP |
1
2
3
page CON47 __Copyright by www.TestMasters.com. All Rights Reserved. __page CON47The CPM is a too! that assists the planning, scheduling, & controlling of the project. The
logic diagram graphically portrays the relationships between project activities. With this
information, itis easier to plan, schedule, & control the project. Before the diagram can
be developed, the project must first be constructed mentally to determine activity
relationships.
Figure 4, Example Critical Path Method Schedule
‘OVERALL PROJECT DURATION
page CON48
Figure 5. Example Critical Path Method Schedule
Copyright by www.TestMasters.com. All Rights Reserved,
page CON48:For each activity ask:
= Can this activity start at the beginning of the project? (Start activities)
Which activities must be finished before this one begins? (Precedence)
For each activity ask:
— Which activities may either start or finish at the same time this one does?
(Concurrence)
Which activities cannot begin until this one is finished? (Succession)
The two basic logic symbols on the precedence diagram are the node and the
precedence arrow.
Figure 6. CPM Logic Symbols
Forward Pass
+ The earliest time each activity in the network can start and finish.
+ The minimum overall duration of the project.
+ Early Finish, = Early Start, + Duration,
Backward Pass
page CON49__Copyright by www. TestMasters.com. All Rights Reserved. _ page CON49.+ A backward pass through the logic network will produce the latest point in time
that each network activity can start and finish, and still maintain the minimum
overall project duration.
OURATION
Figure 7. CPM Forward Pass Equation
Figure 8. CPM Node Notation
> Early start time (ES) of an activity is the earliest point in time, taking into
account the network logic, that an activity may start
> Early finish time (EF) is the earliest time the activity may finish.
page CONSO Copyright by www.TestMasters.com. All RightsReserved. __ page CONSO+ Late finish time (LF) is the latest time that an activity may finish without delaying
the entire project,
[=
[FT 90
Figure 9. Backward Pass Equation
A critical activity can be determined from the logic network by applying either of the
following rules:
> The early start and late start times for a particular activity are the same.
> The early finish and late finish time for a particular activity are the same.
The duration must be equal to the difference between the ES and the EF or the
difference between the LS and the LF.
EF - ES = Duration or
LF - LS = Duration
Critical activities are linked together forming a path from the start activity to the finish
activity called a critical path.
FREE FLOAT = (FF) = The duration of time that an activity can be delayed without
delaying the project's estimated completion time and without delaying the start of any
succeeding activity. Free float is the property of an activity not a network path.
FREE FLOAT (J) = MINIMUM EARLY START OF ALL SUCCESSOR ACTIVITIES ~ EARLY FINISH (J)
INTERFERING FLOAT = (IF) = The time available to delay an activity without delaying
the project's estimated completion time, but delaying an activity into interfering float will
delay the start of one or more following noncritical activities.
INTERFERING FLOAT (J) = LATE FINISH (J)- SMALLEST EARLY START OF ALL SUCCESSOR ACTIVITIES
page CONS1 Copyright by www.TestMasters.com. All Rights Reserved. _page CON51TOTAL FLOAT = (TF) = The amount of time that an activity can be delayed without
delaying the projects estimated completion time. Total float assumes that all preceding
activities are finished as early as possible and all succeeding activities are started as
late as possible.
TR = FF +IF
TF=LS-ES
TF =LF-EF
Float is the duration of time that is available to complete an activity beyond the activity's
duration,
Late start time (LS) is the latest time the activity may start without delaying the entire
project.
Velocity diagrams present a graphical picture of the relationship between time and the
accomplishment of an activity. The vertical axis of the diagram represents
accomplishment of a work task; cubic yards excavated, miles of road built, miles of
pipeline constructed. The horizontal axis presents construction time.
km 10
production
velocity
IS
LET LL
LA
o 1 2 3 4 5 6 7 8 9 10 month
Figure 10, Example Velocity Diagram
END OF SECTION
page CONS2___Copyright by www.TestMasters.com. All Rights Reserved. __ page CONS2|. Project Planning - Problems
C. Project Schedules
D. Activity Identification and Sequencing
201. The estimate for a five-story office building included 72 doors on each of the upper
three floors. In developing the bid, the estimator used a production rate of 2.0 carpenter
man-hours to hang a door. The project superintendent is organizing the carpenter
crews to include three carpenters per crew. What is the duration (in days) of the activity
to hang all the doors on the upper three floors? Assume an eight-hour workday.
‘Assume one crew.
A) 6 Days
B) 12 Days
C) 18 Days
D) 24 Days
202. The estimate for a three-story dormitory included 30 plumbing fixtures on each of
the floors. In developing the bid, the estimator used a production rate of 1.6 man-hours
to install a fixture. The project superintendent is organizing the plumbing crews to
include two plumbers per crew. What is the duration (in days) of the activity to install all
the fixtures in the dormitory? Assume an eight-hour workday. Assume one crew.
A) 6 Days
B) 9 Days
C) 18 Days
D) 24 Days
page CONS3 __Copyright by www.TestMasters.com. All Rights Reserved. __page CONS3203. What type of Gantt chart is illustrated below?
A) Milestones Gantt
B) Gantt with dependencies
C) Baseline Gantt
D) Timeline Gantt
TASK
JAN
FEB
MAR
APR
JUNE
JULY | AUG
‘SEP
oor] | c|13} =|
204. What is the duration in days of the project given the activities below using start to
finish precedence logic?
Activity Duration (Days)
AtoB
Btoc
CtoH
CtoD
DtoE
EtoF
FtoG
GtoH
A) 13 days
B) 17 days
©) 21 days
D) 24 days
page CONS4
3
6
Copyright by www.TestMasters.com. All Rights Reserved,
page CON54205. Given the following data, how much is spent at the end of the 10" day?
Activit Expenditures ($1,000) Duration (days)
A 5 3
B 10 A 3
c 12.5 B 4
Do 4 A 2
E 3 D 5
A) $27,500
B) $31,500
C) $34,500
D) $36,000
208. In the activity-on-arrow network, below, the early start of Activity N is most nearly:
A) 16
B) 21
©) 23
D) 24
page CON55 Copyright by www.TestMasters.com. All Rights Reserved. __ page CONS207 A CPM arrow diagram is shown below. Nine activities have been estimated with
durations ranging from 5 to 36 days. The minimum time (days) required to finish the
project is most nearly:
A) 40
B) 42
C) 45
D) 50
ORDER & DELIVER METAL BUILDING
TOE OETA DY
6. PROCURE
/ REINFORCING \
| ste.
i/ rane \
[: vogn REGUS ec TINE
AEXCAVATE \2. FORM S ef
FOOTINGS (5) OCS —~ ONGRADE AX BUILDING ELEMENTS
soar oe es sons “(0 owe" (©) NSH
\ ee
\_ snes _/ |
an /
\
\ _eprocurcuscsumeoussuonsneers /
‘35 DAYS
208. A workforce of six electricians has to install 420 light fixtures in a new office
building. Normally, two electricians working can install one fixture in 20 minutes. The
crews expect to have a 0.8 efficiency factor due to environmental conditions on this job.
The crews will be scheduled for 9 hour work days which include a one hour break for
lunch. The duration of this construction activity (days, hours) is most nearly:
Days hours
AS 8
B65
c)7 3
D218
page CONS8 __Copyriaht by www.TestMasters.com. All Rights Reserved. _page CONS6|. Project Planning - Solutions
A. Project Schedules
B. Activity Identification and Sequencing
201. C. 18 DAYS
Using the number of doors and the production rate from the estimate:
Production rate: = (1 door/2 man hours)*(3 carpenters) =1.5 doors per hr
Per floor activity duration hours: (72 doors/floor)*(1 hour/1.5 doors) = 48 hr per floor
Per floor activity duration days: = (48 hours per floor/8 hours per day) = 6 days per floor
3 FLOORS * 6 DAYS PER FLOOR = 18 DAYS.
Using the number of fixtures and the production rate from the estimate:
Production rate: = (1 fixture/1.6 man hours)*(2 plumbers) = 1.25 fixtures per hr
Per floor activity duration hours: = (30 fixturesifioor)*(1 hour!1.25 fixtures) = 24 hr per floor
Activity duration days: = (24 hours per floor)/8 hours per day)*(3 floors) = 9 days
203. D) Timeline Gantt
This is a basic timeline Gantt. No milestones, dependencies, or baselines are included
204. D) 24 Days
A (3) B (6) ¢ (4) H
(2) (4)
D (3) EF (2 G
Path A to B to C to H duration = 3 + 6 + 4 = 13 days
Path A to B to C to Dto Eto F to G to H duration = 3 +6 +2+3+4+2+4= 24 days
page CONS7 __ Copyright by www.TestMasters.com. All Rights Reserved. _ page CONS7205. C) $34,500
A(3) B(3) c(4)
D(2)
E(5)
Path A-B-C duration = 3+ 3 + 4 = 10 days
expenditures = 5,000 + 10,000 + 12,500 = $27,500
Path A-D-E duration = 3 +2 + 5 = 10 days
Expenditures = 4,000 + 3,000 = $7,000
Total Expenditures = 7,000 + 27,500 = $34,500
Do not double count expenditures for Task A.
206. C) 23
The longest path to the start of Activity N is defined by Path C-G-J-L and duration along
that path is 9+3+8+3=23
207. D) 50 days
Activities 7-4-5
30 + 10 + 10 = 50 days
208. C) 7 days, 3 hours.
Duration = (420)/(1/(20*2)*6*0.8*60"8)
Duration = 7.29 = 7 days, 3 hours.
END OF SECTION
page CONS8 __Copyright by www.TestMasters.com. All Rights Reserved. _ page CONS8.Il, Means and Methods - Discussion
A. Construction Loads
B. Construction Methods
C. Temporary Structures and Facilities
Asphalt Designations
RC = RAPID CURE
MC = MEDIUM CURE
SC = SLOW CURE
PG = PERFORMANCE GRADING
RAP = RECYCLED ASPHALT PAVEMENT
HMA = HOT MIX ASPHALT
AC = ASPHALT CONCRETE
BM = BITUMINOUS MIX
HCM = HOT MIX ASPHALTIC CONCRETE
PG 64-22
PG = Performance Grading
64 = Seven day average high temperature (°C) of the pavement that the project location
will likely experience in its lifetime.
22 = Seven day average low temperature (°C) of the pavement that the project location
will likely experience in its lifetime
Productivity Rate(R), is the total quantity to be installed (Q) divided by the total
installation time (T)
Efficiency Factor = Actual working Time/ Total Time
Production Cost = Equipment costs per hour! Equipment production per hour
Backhoe (hoe) Productivity Example Problem 1
With a 45 minutes per-hour efficiency what is the best probable production in LCY/hr for
a 3.5cy short stick hoe excavating well blasted rock (fill factor =0.75)? The average
depth of excavation is 12 feet and the angle of swing is 50° (Cycle time = 22 seconds).
page CON5S9 _Copyright by www.TestMasters.com, Alll Rights Reserved. _page CONS9Bucket size (Ley) 3.5 cy
Material well blasted rock fill factor 0.75 (given information)
Cycle time, (load, swing load, dump and swing empty) = 22 seconds (given information)
Looking for @ LCY solution, so do not need to apply a swell factor.
Efficiency = 45 minutes/60 minutes =0.75
Probable Production
= (Capacity)*(Efficiency)*(Fill Factor)/(Cycle Time)
3.5 CY * (0.75) * 0.75/ (22 seconds/60 seconds per minute)*(60 minutes/hour)
= 322 LCY/HR
Backhoe (hoe) Producti
Example Probl
2
If the loose well blasted rock weighs 2,640 pounds per cubic yard, what is the
productivity in tons per hour.
P = (322 LCY/HR)*(2,640 pounds/LCY)*(1 ton/ 2,000 pounds) = 425 tons per hour
To estimate loading time you need to know:
> Payload capacity of the hauling unit
> Payload of the hoe bucket
> Hoe cycle time
Payload will be limited by either the heaped (volumetric) capacity or by the load weight
(gravimetric).
Total loading time = (number of bucket passes) x(hoe cycle time)
Number of bucket passes = Payload of Hauler/Payload of Bucket
ox |
Number of bucket passes =
page CON60___Copyright by www.TestMasters.com. All Rights Reserved. _ page CON60page CON61
Figure 12. Vertical Formwork - A Layered System
Copyright by www.TestMasters.com. All Rights Reserved.
page CON61A temporary Structure is any means or methods which provide temporary suppor,
access, enhancement, or otherwise facilitate the construction of permanent structures,
These include:
v
Concrete Formwork
Scaffolding
Falsework/shoring
Cofferdams
Underpinning
Diaphragmislurry walls
Earth-retaining Structures
Construction Dewatering
v
vvvvvyY
Horizontal pressure on the surface of the forms, proportional to the density and depth of
the conerete in a liquid or semiliquid state.
Lateral pressure of concrete on vertical forms. Figure (a) shows a full liquid head
pressure. Figure (b) shows a situation where the concrete began to harden, thus
exerting a pressure at the lower part of the form that is less than the full liquid head
pressure (depth of fluid concrete from top of placement is fy). Figure (c) shows a
situation similar to Figure (b), but with a lower rate of filing the forms; this results in yet
a lower maximum pressure and a smaller height of liquid head pressure, hz < Mn
(a) (b) (o)
page CONG2 __Copyright by www.TestMasters.com. All Rights Reserved. __ page CONG2BCWS = Budgeted Cost of Work Scheduled = Planned Value
BCWP = Budgeted Cost of Work Performed = Earned Value
ACWP = Actual Cost of Work Performed = Actual Value
Variances
SCHEDULE VARIANCE =SV= — BCWP-BCWS
‘SV > Ois good (ahead of schedule)
The SV will be 0 at project completion because then alll of the planned values will have
been earned
COST VARIANCE =CV= BCWP - ACWP
CV > 0 is good (under budget).
Indices
Cost Performance Index = CPI = (BCWP/ACWP) = (Eamed/Actual)
CPI < 1 means that the cost of completing the work is higher than planned (over budget)
GP1=1 means that he cost of completing the work is right on plan (good)
CPI > 1 means that the cost of completing the work is less than planned (under budget)
(good or sometimes bad)
‘Schedule Performance Index = SPI = (BCWP/BCWS) = (Earned/Planned)
SPI > 1 is good (ahead of schedule).
Forecasting
BAC
Budget at Completion = Original Project Estimate
ETC = Estimate to Complete = (BAC - BCWP)/CPI
EAC = Estimate at Completion = (ACWP + ETC)
‘To-Complete Performance Index (TCP!)
page CON63 __Copyright by www.TestMasters.com. All Rights Reserved. _ page CON63The TCPI provides a projection of the anticipated performance required to achieve
either the BAC or the EAC. TCPI indicates the future required cost efficiency needed to
achieve a target BAC (Budget At Completion) or EAC (Estimate At Complete). Any
significant difference between CPI, the cost performance to date, and the TCPI, the cost
performance needed to meet the BAC or the EAC, should be accounted for by
management in their forecast of the final cost.
For the TCPI based on BAC (describing the performance required to meet the original
BAC budgeted total)
TCPI = (BAC — BCWS)BAC — ACWP)
For the TCPI based on EAC (describing the performance required to meet a new,
revised budget total EAC):
‘TCPI = (BAC - BCWP)(EAC — ACWP)
Independent Estimate At Completion (IEAC:
The IEAC is a metric to project total cost using the performance to date to project
overall performance. This can be compared to the EAC, which is the manager's
projection
IEAC = ACWP + (BAC - BCWP)/CPI
Equipment Productivity
LOADER PRODUCTION = (3600°Q*F*E)/[T*60*(1+SWELL)] (Units are CY/hour)
LOADER PRODUCTION = (3600*Q"F*E*W)/[T*60*2000] (Units are Ton/hour)
Q = Heaped bucket capacity (LCY)
F = Bucket fill factor
E = Efficiency (minutes per hour)
T= Cycle time (seconds)
W= Aggregate weight (LB/CY)
National Pollutant Discharge Elimination System (NPDES)
page CON64 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON641. Load with exchange
3. Dump and
maneuver
Figure 13. Earthwork Operations
Manufacturer's specification sheets will list both struck and heaped capacities.
‘Struck material measured straight across the top of the body.
SSsnnonnn
Figure 14. Dump Truck with Struck Material
Figure 15. Heaped material based on a 2:1 slope above hauler bodies.
page CON65 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON65‘Trucks Required = (Truck Cycle Time)/Loader Cycle Time
Tower Cranes
The flexibility of its freely suspended hook moving in three planes provides a
tremendous advantage in terms of load pick-up and positioning. Advantage of having
both the operator and jib above the construction site. The hoist cable runs from the hoist
drum located on the crane's counter jib, through the jib and then to the trolley and down
to the hook.
SLEWING RING LOCATION
Fixed tower-type crane has the slewing ring located at the top of the tower and the jib
slews around the vertical axis of the tower
Slewing ring located at the base of the tower and both the tower and jib slew relative to
the base.
Fixed base (stationary) — either free standing or braced to the building structure
Climbing ~ lifts itself on the building structure as the work progresses. Usually climbs
through an opening within the structure. Must insure that the structure's framing has
sufficient load carrying capacity to support the added stresses of the combined weight
of the crane and the lifted loads.
Traveling — on rails or wheels
Maximum free standing height is the height to which a tower crane can safely rise from
its base without the need of external bracing for lateral stiffing. Maximum braced height
is the height to which a tower crane can safely rise from its base with additional external
bracing for lateral sttfing
page CON66__Copyright by www.TestMasters.com. All Rights Reserved. _page CON66.page CON67
Boom tip extension (jib)
__— Crawler mounting
+——Hook
Copyright by www.TestMasters.com. All Rights Reserved.
page CON67Trt
Horizontal jib Ling boom Articulate >
FIGURE 3-29. Major types of tower cranes.
‘pane
FIGURE S-30, Terminology of horizontal jib tower crane. (Courtesy of Manitowo:)
END OF SECTION
page CON68___Copyright by www.TestMasters.com. All Rights Reserved. __ page CON68.Mh Means and Methods - Problems
A. Construction Loads
B. Construction Methods
C. Temporary Structures and Facilities
301. Which of the following would a cast-in-place ground slab or floor not use to
separate steel reinforcing bars or wire mesh from the ground?
|. Precast cementitious blocks
Il Metal chairs
Ill. Wood risers
IV. Wire bolsters
V. Plastic bar supports
VI. Cellulose spacer blocks
A) Iiland VI
B) |, Il, and VI
C) LIV, and V
D) Hi, 1V, Vand VI
302. Which of the following types of joints typically does not use dowels?
|. Construction joints
N. Control joints
I. Contraction joints
\V. Expansion joints
V. Isolation joints
A) land V
B) land V
©) Illand iv
D) 1, Ml, Vand V
page CON69___Copyright by www.TestMasters.com. All Rights Reserved. _page CON69303. In addition to location of the pour, tremie concrete poured underwater differs from
common conerete poured in the air primarily in its
‘A) placement method and equipment
B) components and additives
C) specific gravity
D) aggregate size
304. In very hot weather, thin floor slabs of newly poured concrete would most normally
be:
A) Sprinkled with rock salt or potassium chloride
B) Sprayed with or submerged with water
C) Kept insulated by dry burlap insulation
D) Covered by cube or slush ice.
305. Which statement about the placement of asphalt is NOT true?
A) The hotter the mix temperature above 300°F at the time of initial compaction, the
better the results.
B) In general, too low a percentage of air voids results in a shortened roadway life.
C) Poor compaction will result if the mix is too cold at the time of initial compaction.
D) The mix is usually in the temperature range of 260°F to 280°F at the time of
spreading,
306. If the water-to-cement ratio of concrete is decreased, which statement about the
concrete is NOT true?
‘A) Water tightness is decreased.
B) Workability is decreased
C) Strength is increased
D) Durability is increased.
page CON70 Copyright by www.TestMasters.com. All RightsReserved. _ page CON70307. When a concrete slab is placed on a hot windy day, it is NOT permissible to:
‘A) Add field water as needed to obtain the desired consistency and workability
B) Keep mix water cool and aggregate moist by shading and sprinkling,
C) Spray or protect the concrete surfaces with wet burlap to retard hardening.
D) Moisten the forms and the reinforcement prior to placement of concrete to
minimize evaporation.
308. A four lane concrete highway is to be paved in two passes, two adjacent lanes at a
time. To facilitate connecting with the subsequent pour, the edge of the concrete is fitted
with concrete dowels running transverse to the direction of travel, and the edge is
keyed. This joint would most likely be referred to as a
A) Transverse, tied and keyed expansion joint
B) Transverse, tied and keyed construction joint
©) Skewed contraction joint
D) Longitudinal tied construction joint
309. It is 100° F and you are placing concrete. In order to keep your aggregate cool,
which of the following methods are applicable?
|. Add ice to the conorete mix
II. Shade and cool (spray water on) your aggregate piles.
Ill, Paint your equipment white
Al
B) Il
©) land tl
D) 1,1. And tit
page CON71 Copyright by www.TestMasters.com. All RightsReserved. _page CON71310. The compressive strength of concrete depends primarily on which of the following
factor(s):
1 Shape of aggregate particles
MV Water- cement ratio
Ml Conditions of mixing
IV. Curing and aging time
A) land il
B) Honly
C) |, Wand iv
D) All of the above
311. Without taking special precautions, water used in mixing concrete must be:
A) Clean and free of substances deleterious to concrete or reinforcement
B) Non potable
C) Deionozed
D) Salty
312. A loader has a full-bucket capacity of 3 cubic yards and the average time required
to place one bucket load of soil into a truck is one minute. The loader is supported by
four trucks with a volume of 15 cubic yards each and a cycle time of 12 minutes plus the
time to load the truck.
What is the ideal productivity of this system?
A) 180 cy/hr
B) 212 cy/hr
C) 277 cyfhr
D) 300 cy/hr
page CON72 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON72Use the following information to work Problems 313 and 314.
A backhoe with a bucket capacity of 1 cubic yard has a standard production rate of 960
cubic yards per day for an 8 hour day with a 30 second cycle time. The following work
conditions at the site affect the productivity of the backhoe.
Work Conditions at the Site Factors
Bulk Composition 0.954
Soil Properties and water content 0.983
Equipment idle time for worker breaks 0.800
Management efficiency 0.700
313. Determine the job site productivity of the backhoe.
A) 504 CY
B) 637 CY
c) 800 CY
D) 960 CY
314, Determine the actual cycle time of the backhoe.
‘A) 30 seconds
B) 40 seconds
C) 50 seconds
D) 87 seconds
page CON73 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON73.Use the following information to work Problems 315 and 316
A dump truck with a capacity of six cubic yards is used to dispose of excavated
materials. The distance from the dump site is 4 miles and the average speed of the
dump truck is 30 mph. The dump truck standard dumping time is 30 seconds. The job-
site productivity of the backhoe is 504 cubic yards per 8-hour day with a cycle time of 57
seconds. The backhoe has a bucket with a capacity of 1 cubic yard, The job site
productivity of the backhoe is modified by a swell factor of 1.1. The only factors affecting
the job-site productivity of the dump truck are 0.80 for equipment idle time and 0.70 for
management efficiency.
315. Determine the job site productivity of one dump truck per 8 hour day.
A) 60.0 CY
B) 72.6CY
C) 80.0 CY
D) 92.0 CY
316, Determine the number of trucks needed daily.
A) 6 Trucks
B) 7 Trucks
C) 8 Trucks
D) 9 Trucks
page CON74 __Copyright by www.TestMasters.com. All Righls Reserved. _ page CON74317. In shored construction, which factors do not influence the length of time between
pouring concrete and stripping the forms?
I
Ml
I.
v.
Vi
Weather
Project specifications
Developed concrete strength
ACI 347
Project schedule
Local ordinances
A) land Ill
B) land IV
©) Hand IV
D) Vand VI
318, What is the design load for an 8-foot tall concrete wall to be poured at a rate of 4
fthr, internally vibrated at a temperature of 90° F? The conorete mixture will use Type |
cement without retarders and is estimated to weigh 150 pef.
A) 275 PSF
B) 550 PSF
C) 600 PSF
D) 1100 PSF
page CON75 Copyright by www.TestMasters.com. All Rights Reserved. _page CON75.319, Determine the maximum design wall pressure (psf) on concrete forms that will be
used for the following data.
Conerete weight = 180 pef
Height of wall = 124t8in
Rate of Placement (R) = 5 ft/hr
Concrete Temperature = = 80°F
A) 600 psf
B) 712 psf
C) 1,900 psf
D) 2,000 psf
320. Normal weight concrete with a 3-inch slump is poured at the vertical rate of 4-feet
per hour into the form for a 12-foot high retaining wall. The concrete is vibrated to a
depth of 4-feet. The temperature is 60 °F. Most nearly, what is the design hydrostatic
pressure experienced by the formwork?
A) 500 PSF
B) 600 PSF
C) 750 PSF
D) 1,800 PSF
321. Per ASCE 37-02, the formwork for slabs must be designed to resist all but which
one of the following:
‘A) Impact loading from the placement of concrete.
B) Weight of the concrete
C) Construction loads
D) Additional live load generated by workers and equipment.
page CON76 __ Copyright by www.TestMasters.com. AllRights Reserved. __ page CON76322, Recently your company was awarded a large commercial office building project
which is comprised of a reinforced concrete superstructure. You have the task of
designing the formwork. If you use Douglas-fir-larch (d-F) for the basis of your design
calculations, the proper value to use for the load duration factor Cx for the wood is most
nearly:
A) 0.90
B) 1.00
©) 1.15
D) 1.25
323. You are designing a free-standing masonry wall that is 16 feet in height. It will be
laterally braces during construction. According to CMWB 2012, the required strength of
masonry elements and connections to bracing systems must be designed in
accordance with which of the following load combinations:
1.0.90 + 1.3W
I. 1.20 + 1.6W
Ill, 0.9D + 1.6W
IV, 1.20 + 1.3W + 1.2P
A) | only
B) | and IV
C) Ill and IV
D) Il only
324. The minimum factor of safety against rotational failure for permanent slopes under
long-term, non-seismic conditions influence occupied structures is closest to:
A) 1.0
B) 14
co) 1.5
D) 3.0
page CON77 __Copyright by www. TestMasters.com. All Rights Reserved. _ page CON77.325. A wall form is subjected to a wind load of 20 psf is prevented from overturning by
diagonal braces spaced at 8 feet on center along the length of the wall form as shown
in the figure. The connection at the base of the form at Point A is equivalent to a hinge.
Ignore the weight of the form. The axial force (in pounds) resisted by the brace is most
nearly:
‘A) 2,050 pounds
B) 2,560 pounds
C) 2,900 pounds
D) 4,525 pounds
326. A crane with a 100-foot boom is being used to set a small load on the roof of the
building shown. The minimum standoff (Point A) from the center of the building to the
centerline of the boom is indicated. What is the maximum distance (in feet) from the
edge of the building that the load can be placed on the roof?
A) 16 feet
B) 25 feet
C) 30 feet
D) 36 feet
crane boom foot
BUILDING
5 ft 10 fils
®
centerline
crane
END OF SECTION
page CON78 Copyright by www.TestMasters.com. All RightsReserved. _ page CON78.ll. Means and Methods - Solutions
A. Construction Loads
B. Construction Methods
©. Temporary Structures and Fa
page CON79___ Copyright by www.TestMasters.com. All Rights Reserved. __ page CON79.301. A. IILAND VI
After curing, wood and cellulose products would absorb moisture and attract termites.
They are not used to support bars in slabs. All of the other listed items are used to
separate steel reinforcing bars or wire mesh from the ground.
302. B) land V
Control joints, as a method of controlling where cracking will occur, are typically created
by saw cutting, Although steel reinforcing may be present at a control joint, dowels will
not, Isolation joints separate concrete slabs from columns, footing, and walls, They are
used to separate elements that experience differences in loading (soil pressure) and
settlement. No connection between the elements should exist. Expansion and
contraction joints can be doweled; the slab slides along the dowel bar as the slab
expands or contracts. Construction joints are doweled to ensure complete load transfer
when subsequent portions of the slab are poured
303. A) Placement method and equipment
Tremie concrete gets its name from the delivery pipe (the tremie) that reaches from
above the water surface to the lowest submerged delivery point. The lower end of the
tremie is kept buried in freshly delivered concrete. The concrete is fairly normal in its
chemistry and components,
304. B) Sprayed with or submerged with water
While ice could be used to reduce temperatures until the cooler night arrives, it is easier
and more cost effective to rely on evaporation of liquid water (that is the swamp cooler
effect) to lower the temperature.
305. A)The hotter the mix temperature above 300°F at the time of initial
compaction, the better thi Its.
If a mix is too hot it will push up in front of the roller and cause poor compaction
Reference (Asphalt Handbook, P. 289).
page CON80___Copyright by www.TestMasters.com. All Rights Reserved. _ page CON80htness
306.
Water, reased
Water tightness is the ability of concrete to hold or retain water without visible leakage
Generally, less permeable concrete is more watertight. A lower water-cement ratio
reduces permeability, thereby increasing water tightness.
Reference: Portland Cement Association, Design and Control of Concrete Mixtures.
307. A) Add field water as needed to obtain the desired consistency and
workability.
308. D) Longitudinal tied construction joint
The joint runs longitudinally along the highway and is tied by the dowels to the next
phase of construction (that is the next pour). The key is probably an unnecessary detail,
as the dowels will prevent both vertical and lateral separation of the separate pours.
309 D)
All of the above conditions are allowable for keeping your concrete cool. Ice is water
and does not change the actual water to cement ratio of the mix as long as the mix is
designed for the added ice.
310. B) Il only
The compressive strength of concrete depends primarily on the water-cement ratio.
However, other factors such as characterization of the cement, conditions of mixing,
character and grading of the aggregate, size of the aggregate, size and shape of the
specimen, curing and aging, temperature and moisture content at the time of testing
also have bearing on the compressive strength.
344. A) Water for concrete should not contain deleterious substances.
page CON81 __ Copyright by www. TestMasters.com. All RightsReserved. _ page CON81342, A) 180 cy/he
Time to load one truck = (15 cy)/(3 cy/min) = 5 minutes,
Cycle time for one truck = 5 minutes to load + 12 minutes to travel, dump and return
= 17 minutes
Loading time for four trucks = 4*5 = 20 minutes
Therefore, an empty truck is always available to load
Ideal Productivity = [(60 minutes/hour)/(5 minutes/truck)}*(15 cubic yardsitruck)
= 180 cy/hr
313. A) 504 CY
Productivity = (960 cy)(0.964)(0.983)(0.8)(0.7) = 504 CY
314, D) 57 seconds
Cycle Time = (30 seconds)[0.954*0,983°0.8*0.7) = 57 seconds
315. — B) 72.6 CY
Truck travel time = [(2)(4 miles)(3,600 seconds/hour)}/{(30 mph)(0.8)(0.7)
= 1,714 seconds
Truck fill time = [(67 seconds)/(0.8°0.7)}*(6 oy/1 cy)
= 611 seconds
Truck dump time = (30 seconds)/(0.8*0.7)
= 54 seconds
Total cycle time = 1,714 + 614 + 54 = 2,379 seconds
Job site productivity of one dump truck
= (6 CY)(8 hours)(/3,600 seconds/hour)/(2,379 seconds)
=72.6CY
page CON82 __Copyright by www.TestMasters.com. All Rights Reserved. _ page CON82346. C) 8 Trucks
N= (1.1)(604 CY)(72.6 CY) = 7.6
Round up use 8 trucks
317. D) V AND VI
The length of time that formwork is left on before being stripped is an engineering
decision, under the jurisdiction of the project engineer. Guidance to the contractor will
be placed in the project specifications. The engineer will consider various factors when
writing the specifications including developed conerete strength and loading. ACI 347
recommendations may be considered in some situations when the actual requirements
are difficult to determine. The specifications may have options dependent on the local
temperature, the need to remove insulating formwork, or cool the conerete during
curing. The project schedule and local ordinances should not be permitted to dictate the
time between pouring concrete and stripping forms
348. C. 600 PSF
REFERENCE: ACI 347, LINDEBURG CH 49
P = Cw'Co"(150 + 9000°RIT)
Cw = 1.0 UNIT WEIGHT COEFFICIENT
Cc= 1.0 CHEMISTRY COEFFICIENT
R=4
T=90
P = 1*1"(150 + 9000*4/90) = 550 PSF
Pmax = WH = 150 * 8 = 1,200 PSF
Pmin = 600(1) = 600 PSF
550 < 600 < 1200
DESIGN LOAD = 600 PSF
page CON83 __Copyright by www.TestMasters.com. All Rights Reserved.
_page CON83349. B) 712 psf
Reference ACI 347
R= 5 fhr
T=80°F
H= 1267 ft
Cw = 1.0 UNIT WEIGHT COEFFICIENT
Co= 1.0 CHEMISTRY COEFFICIENT
P = Co*Cw*(150 + 9000R/T)
P = (1)(1)(150 + 9000(5)/80))
P=712 psf
Pmax = 150H = 150(12.67) =
900 psf
Pmin = Cw*600 = 1(600) = 600 psf
Pmin < P< Pmax
600 < 712 < 1900
Use P Design = 712 psf
page CONS4 Copyright by www. TestMasters.com. All Rights Reserved.
page CON84320. C) 750 psf
Reference ACI 347, LINDEBURG P. 49-7
R=4 hr
T= 60°F
H=12¢t
Cw = 1.0 UNIT WEIGHT COEFFICIENT
Co= 1.0 CHEMISTRY COEFFICIENT
P = (1)(1)(150 + 9000R/T) = (1)(1)(150 + 9000(4)/60)
P= 750 psf
Pmax = 150H = 150(12) = 1,800 psf
Pmin = Cw"600 = 1(600) = 600
Pmin < P < Pmax
600 < 750 < 1800
Use P Design = 750 psf
324. D) Addi /@ load generated by workers and equipment.
Reference: Per 4.1.1 of code, Page 11
322, D) 1.25
Reference: NDS Table 2.3.2 Page 11 Construction Load.
323. C) Ill and IV
Reference Page 19 section 5.4.2, eq. 5.4.2-1 and 5.4.2-2
324.C.1.5
References: Day, Geotechnical and Foundation Engineering, 1999 Pages 10-27
page CON85 Copyright by www.TestMasters.com. All Rights Reserved.325. C) 2,900 Pounds
Reference: Hurd, Formwork for Concrete, ACI SP-4, Seventh Edition, 2005.
w = (20 psf)(8 ft) = 160 Ib/ vertical foot per brace location
ZMa=0
EMa = (160 Ib/t)(16 #)(16 U2) — 10f4(R,)
Rx= 2,048 pounds
Axial Load in brace = (2,048)'2°° = 2,896 pounds
1
326, B) 25 feet
Reference: Shapiro, Shapiro and Shapiro, Cranes and Derricks, Third Edition, 2000,
page 244
Tan@= 40/30 = = 53.13°
(cos 53.13° ) * (100 feet) = 60 feet 40 ft 50 ft
60-35 = 25 feet s0f ©
END OF SECTION
page CON86__Copyright by www.TestMasters.com. All Rights Reserved. _ page CON86VII, Site Development Discussion
A. Excavation and Embankment (e.g. cut and fill)
B. Construction site layout and control
Earthmoving is defined as the process of moving soil or rock from a location to a new
location to changing its conditions according to engineering requirements of a project,
(grading, elevation, compaction...)
Earthmoving activities are excavating, loading, hauling, placing (dumping and
spreading), compacting, grading, and finishing.
Figure 16. Three Link Earthwork System
Earthwork is based on surveying coordinates (centerline or baseline, stations, horizontal
curves and vertical curves) and the corresponding geometric views (plan, profile and
cross-sections)
Figure 17. Plan View of Highway
page CONS? _Copyright by www. TestMasters.com. All Rights Reserved. __ page CON87The plan view is looking down on the proposed work and presents the horizontal
alignment of features. The profile view is a cut view typically along the centerline of the
work. It presents the vertical alignment of features.
gle 8
ag a8
a +e PVIELEV = 123.73,
ile Sa] |e, eustasnems al
5g ea] |t8 as
#8) lag 2g
288% | >. & Bla
ce IK] 188 slg
Ss IRB a\e
é
&
5
le Se ge sis ge ais ae a ze |p 5
7-00 Toeo0 Tr Tee 0 ry
Figure 18. Profile View of Highway
Cross-Section View is a view formed by a plane cutting the work at a right angle to its
long axis. When the ground surface is regular, cross-sections are typically taken at
every full station (100 feet). When the ground is irregular, sections must be taken at
closer intervals and at points of change in elevation
page CONS8 __Copyright by www.TestMasters.com. All Rights Reserved. __ page CON88.
}CLStation = 0+00
CL Road Elevation = 158.00
Sketch not to scale
Figure 19. Cross-Section View
Existing Natural Ground
Finished Grade
Existing Natural Ground
CL Station = +50,
CL Road Elevation = 134.00
Sketch not to scale
Figure 20. Cross-Section View
page CON89___Copyright by www.TestMasters.com. All Rights Reserved. _ page CON89.Excavation volume measurement uses average cross-sections along the alignment
(typically at 50 feet or 100 feet intervals). Plot the natural ground level and the proposed
grade profile and indicate areas of cut and fill
Calculate volume of earthwork between cross-sections.
Assumes volume between two cross sections is the average of the areas multiplied by
the distance between the cross-sections.
Average end area method: V = (0.5)(A; + Ag)(L)/27
Figure 21. Average End Area Method
Use of the Average end area method technique may lead to volume errors when cross-
sections taper between cut and fill sections,
For better accuracy use the Prismoidal formula. V = (L/6)*(A1 + 4m + Az)/27
V = Volume in cubic yards
L = Length (distance between cross-sections in feet
A\= Cross-section area in square feet
27 = unit conversion (27 cubic feet per cubic yard)
page CON90 Copyright by www.TestMasters.com. All RightsReserved. _page CON90Am = Cross section area of mid-section in square feet
Mass Haul Diagram is a curve with its horizontal axis (X) as the distance from the
original station and its vertical axis (Y) as the mass ordinate. Ordinate is the net
accumulation of volume from an arbitrary starting point. Earthwork computations involve
calculation of earthwork volumes balancing of cuts and fills and planning of the most
economical material hauls. Earthmoving is basically an operation where material is
removed from high spots and deposited in low spots with the “making up" of any deficit
with borrow or the wasting of excess cut material.
Mass Haul Diagram Terms
1. Free haul distance
2. Free haul balance points
3. Balance points
4. Center of mass
5, Total haul distance
6. Overhaul distance
7. Overhaul volume
8. Average Haul Distance
Bank cubic yards (bey) Loose cubic yards (ley) Compacted cubic yards (ccy)
page CON91 __Copyright by www.TestMasters.com. All Rights Reserved. __page CON91i
€
Cross section for a fill
page CON92
Figure 24. For Fill Sections Add the Stripping Volume
Copyright by www.TestMasters.com. All Rights Reserved. _ page CON92For fill sections the stripping is a cut quantity; plus an equal amount must be added to
the embankment quantity.
Mass Haul Diagram Properties
>
>
>
>
Maximum is where the cut transitions into fill
Minimum is where the fill transitions into cut.
Above the zero line indicates waste.
Below the zero line indicates borrow.
Table 1. Mass Haul Diagram Example Earthwork Worksheet (10% Fill
Factor)
‘Station | End Area | Volume (CY) | Stripping | Total (CY) | Adjusted | Algebaric | Mass
(SF) (ey) Fil |” Sum | Ordinate
Cut_[ Fi_|-Gut_[-Far_| Cut | Fi | Cut | FN Yecyy | (en) | (cr)
drool oO; of o| o| of of of o 0 0 0
or50 | 0/745] 0] 706| 0| 78| 0|7%24| 138-708] 138
1400 |_| 112| 0[210| Of 30| 0|240| 267| -267 | -405
200 | o| S4| 0[307| o| 44] o|351| 300| -300| -796
2+50 | 64| 30] 59| 78| 0|22| 59/100; 111] -52| -847
3+00 | 120| 0| 470 28| 26| 0| 744| 28[ 31] 114-734
4+00 | 160| 0[519| O| 76] 0] 443] 0 oO, 443-201
5+00 | 317| 0/ 883| 0| 74] 0|809| 0 o[ 800] 518
6+00 | 51| 0|681| 0| 60| O|e2t| 0 of 62% | 7,140
6+50 | 46/ 6| 90| 6| 24] o| 69] 6 6 63 | 1,202
7+00 | 0] 425] 43| 421| 0| 25] 43| 146| t63|__-120| 1,082
+00 | 0} 1a6| 0|576| 0| 61| o|657| 730] -730| 352
e+50 | 0[332[ o|4s0| o|69| o|s49| 610] -t60| -257
pageCONS3 Copyright by www.TestMasters.com. All Rights Reserved. __page CON93.EXAMPLE MASS HAUL DIAGRAM PLOTTED FROM
EARTHWORK WORKSHEET
¥ ~ r
1000 | |_|
500
500
(CUMULATIVE EARTHWORK VOLUME (CY)
|
0.00 100 © 2.00 3.004.00 «5.00» 6.00 7.00» 8.00 9.00
STATION (STATIONS)
Figure 25, Example Mass Haul Diagram Plotted From Table 1 Data
page CONS4 __Copyright by www.TestMasters.com. All Rights Reserved. _ page CON94Figure 26.
page CON95
Relationship Between Profile View and Mass Haul Diagram
Copyright by www TestMasters.com. All Rights Reserved.
page CONSS:Direction
Profile view of haul
Profile grade line c
Mass diagram
Average haul distance
Cutting, Filling
Balance line
B (Maximum haul distance)
Figure 27. Average Haul Distance
END OF SECTION
page CON96 __Copyright by www. TestMasters.com. All Rights Reserved. __ page CON96.Vil. Site Development Problems
A. Excavation and Embankment (e.g. cut and fill)
B. Construction site layout and control
401. Find the base width in feet of a triangular spoil bank containing 100 BCY if the pile
length is 30 feet, the soil's angle of repose is 37° and its swell is 25%.
A) 12.2 feet
B) 18.3 feet
C) 24.4 feet
D) 30.5 feet
402. Find the height of a triangular spoil bank containing 100 BCY if the pile length is 30
feet, the soil's angle of repose is 37° and its swell is 25%.
A) 2.3 feet
B) 4.6 feet
C) 9.2 feet
D) 18.4 feet
403. Find the base diameter of a conical spoil pile containing 100 BCY of excavation, if
the soil's angle of repose is 32° and its swell is 12%.
A) 10.4 feet
B) 22.1 feet
C) 32.2 feet
D) 46.5 feet
404. Find the height of a conical spoil pile containing 100 BCY of excavation, if the soils
angle of repose is 32° and its swell is 12%.
A) 10.1 feet
B) 22.1 feet
C) 32.2 feet
D) 46.5 feet
page CON97 __Copyright by www.TestMasters.com. All Rights Reserved. _ page CON97_shown. Values shown at each corner are depths of excavation.
A) 100 CY
B) 200 CY
C) 300 CY
D) 400 cy
Basement Plan View
405. Estimate the volume of excavation (CY) required (bank measure) for the basement
eof 25.0 ft wide a2ft
>
30.0 ft long
58 ft 76 ft
right by www.TestMasters.com. All Rights Reserved. __page CON98408. Laboratory testing was performed on a soil sample with the following results.
Sieve# % Passing Liquid Limit = 32
3 inch 100 Plastic Limit = 25
1.5 inch 98
0.75 inch 96
#4 7
#10 -
#20 55
#40 =
#100 30
#200 18
According to the Unified Soil Classification System, the classification of the sample is
most nearly:
A) Sw
8) SP
c) SM
D) sc
407. A reading of 9.00 feet is taken on a 13-foot level rod when the top is 1.00 feet out
of plumb (vertical). The correct reading (reading if the rod had been truly vertical) is
most nearly:
A) 8.96 Feet
B) 8.97 Feet
C) 9.03 Feet
D) 9.04 Feet
page CONS9 Copyright by www.TestMasters.com. All Rights Reserved. __ page CON99408. Cross-Section areas to be excavated (cut) are given below. The volume of earth to
be excavated between station 4+35 and 5+65 is most nearly (using prismoidal method):
Station End Area (SF) ]
3+00 247
4+00 269
4435 322,
500 305
5+65 418
____6+00 294
700 168 1
A) 1,460 CY
B) 1,840 CY
C) 1,860 CY
D) 1,900 cy
409. Using the average-end-area method calculate the cut volume for stations 129 + 00
through 130 + 00.
A) 1,200 bey
B) 2,500 bey
C) 5,200 bey
D) 8,300 bey
Station End Area Cut (SF) End Area Fill (SF)
125 + 00 0 785
126 + 00 652 0
127 + 00, 2,150 0
128 + 00, 3,210 0
129 + 00, 1,255 147
130 +00 95 780)
131 +00, 0 3,666
page CON100__Copyright by www. TestMasters.com. All Rights Reserved. _ page CON100 I410. Using the average-end-area method calculate the fill volumes for stations 22 + 00
through 23 + 00.
A) Occy
B) 150 ccy
C) 550 coy
D) 600 ccy
Station End Area Cut (SF) End Area Fill (SF)
19 +00 326 0
20+ 00 157 0
21 +00 a4 0
21 +50 0 0
22 +00 0 147
23 +00 0 165
24+ 00 0 133
411. Using the average-end-area method calculate the net cut and fill volume for
stations 28 + 00 to 29 + 00.
A) 0 boy
B) 3,150 bey
C) 4,550 bey
D) 6,850 boy
Station End Area Cut (SF) End Area Fill (SF)
25 + 00 0 3,525
26 +00 355 985
27 +00 786 125
28 +00 2,515 55
29+ 00 1,255 23
29+ 25 620 0
2950 25 845
30+ 00 0 3,655
34400 0 8,560
pageCON101 Copyright by www.TestMasters.com. All Rights Reserved. page CON101412. Refer to the following test data:
% passing #200 sieve 60
Liquid limit 55
Plastic limit 25,
‘The USCS Classification of the soil is:
A)A7-6
B) Clay Loam
©). CL
D) CH
413. Which of the following formulas for bank cubic volume (BCY), loose volume (LCY),
compacted volume (CCY), swell factor (S), shrinkage factor (D) and load factor (LF) is
NOT correct?
A) CCY = BCY(1 - D)
B) BCY = LF*LCY
C) LCY = (1 + S)(BCY)
D) CCY = LCY((1 +S)
END OF SECTION
page CON102 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON102VII. Site Development Discussion Solutions
A. Excavation and Embankment (e.g. cut and fill)
B. Construction site layout and control
401. C) 24.4 feet
References” Nunnally Construction Methods and Management.
B= (4vi(LttanR))?>
V = Loose Volume = 100 BCY * 27 oflCY"1.25
V=3,375 of
L=30ft
R=37°
B= [(4°3,375)/(30*tan(37))] °° = 24.4 feet
402. C) 9.2
References” Nunnally Construction Methods and Management.
H = 0.5*B(tank)
B= (4Vi(L*tanR))°>
V = Loose Volume = 100 BCY * 27 cflCY"1.25
V=3,375 cf
L=30f
R=37°
B = [(4*3,375)/(30*tan(37°)] °° = 24.4 feet
H = 0.5*24.4*tan(37°) = 9.2 feet
pageCON103 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON103403. C) 32.2 feet
References” Nunnally Construction Methods and Management.
V= Loose Volume = 100 BCY * 27 cflCY"1.12
V= 3,024 of
D = (7.64Vi(tanR))°?
D = [(7.64"3,024)/tan(32°)] °° = 32.2 feet
404. A) 10.4 feet
References” Nunnally Construction Methods and Management.
V= Loose Volume = 100 BCY * 27 cfiCY"1.12
V= 3,024 of
D = (7.64Vi(tanR))°*?
D = [(7.64*3,024)/tan(32°)] °° = 32.2 feet
H = 0.5*D"tan(R)
H = 0.5°32,2"tan(32°) = 10.1 feet
405. B) 200 BCY
References” Nunnally Construction Methods and Management.
Area = 25 ft*30 ft = 750 sf
Average Depth = (6.0 + 8.2 + 7.6 + 5.8)/4
=6.9ft
Volume = (750 sf* 6.9 ft)/(27cfley)
Volume = 191.7 BCY = 200 BCY
page CON104 Copyright by www.TestNMasters.com. All Rights Reserved. _ page CON104References” Nunnally Construction Methods and Management.
Based on 77% passing the #4 sieve and 82% retained on the #200 sieve, the soil is
classified as a sand, either SM or SC. Based on the fines having LL = 32 and PI =7, the
fines would be classified as ML, nonplastic. Therefore, according to the Unified Soil
Classification System, the sample is classified as SM
407. B) 8.97 FEET
THETA = SIN“(1/13) = 4.412°
E = 9.00 COS (4.412°) = 6.97 FEET
408. C) 1,860 CY
V = 130 FT(322 +4°395 +418)SF/[6"27CFICY]
V= 1,862 CY
409. B) 2,500 BCY
V = 0.5"(1,255+95)"100/27
V= 2,500 BCY
Station End Area Cut | EndAreaFill | Volume of | Volume of
(SF) (SF) Cut(BcY) | Fill (CCY)
125 + 00, 0 785 0 0
126 + 00 652 0 7207 7454
127 +00 2,150 0 5,189 0
128 +00 3,210 0 9,926 0
129 + 00, 1,255 147 8,269 272,
130 + 00, 95 780 2,500 i717
131 +00 0 3,686 176 8,233
page CON105 Copyright by www.TestMasters.com. All Rights Reserved. _ page CON105









