RENCANA ANGGARAN BIAYA

Bill Of Quantity
Lokasi Pekerjaan : RUMAH BPK HASAN PANDEGLANG
Jenis pekerjaan : RENOVASI
Titik pekerjaan : LANTAI 1
No Description Sat Qty Price Total remark
I PEKERJAAN AWAL
1 Bowplang M2 85.50 45,000 3,847,500
2 Pembuatan Sumur Bor 15 Mtr + Cassing (non pompa) M1 15.00 375,000 5,625,000
Sub – total 1 9,472,500

II PEKERJAAN PONDASI DAN DAK BETON


1 Galian pondasi batu kali M3 8.16 54,000 440,640
2 Galian pondasi cakar ayam M3 3.60 54,000 194,400
3 Besi cakar ayam 40X60 X40@12 Unit 15.00 215,700 3,235,500
4 Begisting Tiang kolom (20x2.5x400)xm12 M1 60.00 56,547 3,392,820
5 Tiang kolom (20x2.5x400)xm12 M3 3.00 1,874,500 5,623,500
6 Begisting sloof dan ring Balk (20x1.5)xm10 Ls 136.00 56,750 7,718,000
7 Beton Sloof dan ring balk (20x1.5)xm10 M3 6.80 1,874,500 12,746,600
8 Urukan pasir kembali M3 10.80 124,500 1,344,600
9 Rabat beton lantai kerja K125 M3 7.20 750,000 5,400,000
10 Pasangan HEBEl Ex Supreme M2 161.00 119,700 19,271,700
11 Plester aci Ex Semen MP setara M2 322.00 61,456 19,788,832
Sub – total 2 79,156,592
III PEKERJAAN AREA ATAP
1 Pasang rangka atap baja ringan C 75-75 / R33 – 0.45 M2 115.00 11,200 1,288,000
2 Genteng p standar (standar 1 atap) (metalroof) M2 115.00 68,500 7,877,500
3 Pekerjaan plafon gypsun 9mm Ex Raja/ setara M2 72.00 90,000 6,480,000
Sub – total 3 15,645,500
IV PEKERJAAN PASANGAN DAN PENGECATAN
1 Pasang Granit lantai semua ruangan 60x60 ex lokal M2 72.00 198,000 14,256,000
2 Pasang kanopi Garasi Dengan Alderon Rangka Hollow 6x4 M2 13.50 540,000 7,290,000
3 Pasang Keramik Dinding dapur & Kamar mandi ex asia tile M2 21.00 125,500 2,635,500
4 Instalasi air bersih M1 37.00 46,500 1,720,500
5 Instalasi air kotor M1 44.00 68,000 2,992,000
6 Pengecatan interior dengan Davis Clean M2 322.00 27,500 8,855,000
7 Pengecatan plafon dengan metrolite super white M2 72.00 25,500 1,836,000
8 Pasang pintu utama Double panel Unit 1.00 3,500,000 3,500,000
9 Pasang pintu + kusen Unit 4.00 2,134,000 8,536,000
10 Pasang Pintu KM PVC Unit 1.00 1,250,000 1,250,000
11 Pasang Jendela + kusen aluminium +kaca Unit 9.00 750,000 6,750,000
12 Pasang pintu lipat aluminium uk 2.2 X 3 + kaca 5 mm riben M2 1.00 830,000 830,000
13 Pasang Sanytari Ex standar toho ( closed,wastafl,shower ) Ls 1.00 3,750,000 3,750,000
14 Instalasi Stop kontak Ex Broco standar SNI titik 12.00 217,500 2,610,000
15 Instalasi Saklar Lampu Ex Broco standar SNI titik 8.00 125,000 1,000,000
16 Instalasi Lampu titik 14.00 225,750 3,160,500
17 Instalasi MCB INDUK Ex HAGER Unit 1.00 345,000 345,000
Sub – total 4 71,316,500
Total RAB 175,591,092
GRAND TOTAL 175,591,092
Note : Pekerjaan sudah termasuk suntik kolom penguatan strukture dan tangga beton
Downpayment pekerjaan 50% setelah harga disepakati
Pembayaran berikutnya perpengajuan sesuai kebutuhan dilapangan

DP Total Downpayment 40 % plus Material semen 150 zak Rp 70,236,437


Downpaymen kedua progress 50% Rp 52,677,328
Pembayaran terahir 100 % Rp 52,677,328

Tangerang 04 November 2018


Diajukan Oleh,
Disetujui oleh

Pandu
Kontraktor Pemilik Rumah