Professional Documents
Culture Documents
7 - Analisa Harga Jar Listrik 1
7 - Analisa Harga Jar Listrik 1
TOTAL HARGA
NO URAIAN PEKERJAAN SAT VOLUME DAN UPAH
(Rp.)
(Rp.)
a b c d e f
22 Grounding / Pentanahan SKUTR (GTR) Unit 1
MDU
1 Stainless Steel Strap Mtr 3,60 453.000,00 1.630.800,00
2 Stoping Buckle (Yoke for stainless steel strip) Bh 5,00 110.000,00 550.000,00
3 Link Bh 3,00 75.000,00 225.000,00
4 Pipa Galvanis 3/4" 3 meter Btg 1,00 124.694,00 124.694,00
5 Tap Connector AL/CU 35-50/25-35 mm2 Bh 1,00 150.000,00 150.000,00
6 Grounding Rod 3/4-1,5 u/TR lengkap Clamp Bh 1,00 950.000,00 950.000,00
7 Copper Conductor 35 mm2 Mtr 14,00 45.000,00 630.000,00
Jasa Konstruksi
1 Kepala Tukang Listrik / Mandor HO 0,17 220.000,00 37.400,00
2 Tukang Listrik HO 0,17 200.000,00 34.000,00
3 Pekerja HO 0,17 200.000,00 34.000,00
Angkutan
1 Angkutan Darat Ls 1,00 55.000,00 55.000,00
2 Angkutan Laut Ls 1,00 182.000,00 182.000,00
JUMLAH 4.602.894,00
Jasa Konstruksi
1 Kepala Tukang Listrik / Mandor HO 0,17 220.000,00 37.400,00
2 Tukang Listrik HO 0,57 200.000,00 114.000,00
3 Pekerja HO 0,57 200.000,00 114.000,00
Angkutan
1 Angkutan Darat Ls 1,00 55.000,00 55.000,00
2 Angkutan Laut Ls 1,00 182.000,00 182.000,00
JUMLAH 12.793.529,33