You are on page 1of 5

SWIMMING POOL HEATING SYSTEM

Like Money saved is Money earned, Power Saved is Power Generated - "Stevie Nicks"

SWIMMING POOL
Pune, India
11-12-2018

INNOVATIVE TECHNOLOGIES™
D-54, Sector 7
Noida-201301 (UP), INDIA
Mob: 91 8744905197
Office: 91 9990342748
E-mail : innovativetechnologies01@gmail.com
www.theheatingexpert.co.in
Write-up
Design Basis and selection of equipment’s for central water heating systems:

We have designed centralized Swimming Pool heating system to avoid heavy investment
and to leave the beauty of resort untouched.

Summary:
System is designed to Heat up the pool up to 28 deg. Celsius. Heat pump heat-up the water
till the atmospheric temperature is above 10deg. Celsius.

Temperature Considerations:
We have divided the 12 months in 2 Zones. Summers, April to September, where the
minimum average temperature is 200C and average maximum temperature is 290C.
Winters, October to March, where the minimum average temperature is 50C and average
maximum temperature is 250 C.

Heating with Heat Pump system


System is designed putting into consideration that with the help of

Makes of the Equipment’s:


Hot Water Heat Pumps` Midea/The Heating Expert
Internal Piping’s PPR with SS and Brass fittings.
Valves & Fittings Taconova/TiSUN/Reflex

Payback period:
Payback period for this system will be maximum 2.5 years if used on designed capacity.
Swimming Pool Heat Pump - Selection.

Conditions and requirements Project : Location : Pune

Pool dimensions : Ambient conditions : April-Sept Oct-Mar


L= length 5.1 [m] T1= desired pool temperature 22 [°C] 28 [°C]
W= width 3.9 [m] T2= initial water temperature 30 [°C] 20 [°C]
Ds= shallow-end depth 1 [m] T3= max/min aver. amb. temp. 28 [°C] 12 [°C]
Dd= deep-end depth 1 [m] ΔT1= daily pool temp raise/drop [K] [K]
AD= average depth 1.000 [m] ΔT2= dif between |T1-T2| 8 [K] 8 [K]
A= Area of pool 19.89 [m²] ΔT3= dif between |T1-T3| 6 [K] 16 [K]
V= Volume of pool 19.89 [m³] NOTE: Make changes only in the highligted cells.

Wind velocity Select from below 1 Client specified requirements :


w= 5~8km/h multip. factor 1 θ1= 14 [h] initial heating-up/cooling-down period
w= 8~16km/h multip. factor 1.25 θ2= 1 [h] daily running hours (12~max.16h)
w= ≥ 16km/h multip. factor 2

Heating & cooling capacity requirements


Cooling Capacity : SUMMER Heating Capacity : WINTER Heater Chiller model selected
Initial cool down Initial heating up Code.

q1= 13.19 kW q1= 13.19 kW Heating Load 60.00 KW


Daily heat gains ( from amb. Air & radiant energy) Daily heat loss ( from the surface) Cooling Load KW

q2= 0.24 kW q2= 9.55 kW Qty. 1 nos.


I= 32.24 kW/m²
Total Cooling Loads Total Heat Losses
Qcooling = 45.67 kW Qheating = 22.74 kW

q1= V*ρ*ΔT1/860*θ or q2=U*A*ΔT3 /2*


q1=( ρ*cp*V*ΔT2)/3600*θ q2= heat loss/gain from pool surface [kW]
q1 = Pool heat up/cool down rate [kW] U= surface heat transfer coefficient
ρ= density of water @ 998kg/m³ Uheatihg @ 0.060 [kW/m²]
cp= specific heat of water @ 4.18 [kJ/kgK] Ucooling @ 0.004 [kW/m²]
V= pool volume [m³] A= pool surface area [m²]
ΔT1= daily pool temperature drop / raise [K] ΔT3= pool temperature-ambient temperature [K]
*
ΔT2= desired temp. of water - initial temp. of pool [K] = As q2 is calculated for peak temperatures during
θ= pool heat up time [h] the respective seasons, the surface loss is considered
as 1/2 on daily basis and the Total heat losses as the
I= ((E*A)/θ2 )*0.25 (Applicable for Heat & Chill Pumps and Chillers) sum of The initial heat / cooling value & daily energy
I= Radiant energy loss. ( refer ASHRAE applications chapter 48.19)

E= Solar daily heat gain on the horizontal surface (ASHRAE Fundamentals Chapter 26.30)
24° North altitude, month of August E=6.484 kW/m² (Consider 6 hrs of sunny days on an average)
Swimming Pool Water Heating System
DESCRIPTION OF GOODS WITH PRICES

S.No. Description of Goods Qty. Price Amount Remarks


1 Hot Water Heat Pump
Make : Midea
Model: LRSJ-140/NYN1-A1 1 Set INR 125,000.00 INR 125,000.00 GST: 18% Extra
Output : 13.6 KW
Input : 2.5 KW
COP : 5.33
Power : 220-240/1/50

2 Control Panel for Heat Pump 1 Set INR 10,000.00 INR 10,000.00 GST: 18% Extra
To Avoid any Shock during Surge Voltages.
Panel will be equipped with contactors
Circulation pump
Panel will be also equipped with Single phase
preventor

TOTAL : ONE LAKH THIRTY FIVE THOUSAND ONLY. INR 135,000.00 GST@18% extra
Note :
GST is not mentioned in the shown prices and will be charged at the time of billing.
Actual pictures may very than what has shown in the quotation.
Offer is not including accessories except those which are mentioned.
Terms & Conditions :
1. Price : Prices are ex- Noida and Excluding, GST and any other taxes if applicable.

2. Delivery Period :
Within 2 weeks.

3. Installation & Commissioning: Excluded. Installation cost extra @15000/-

4. Payments :
50% with PO.
50 % before despatch.

5. Warranty : 12 months from the date of installation.


whichever is earlier.
Warranty is subjected to replacement of parts within 12 months from the date of installation
Warranty period doesnot cover:
Normal wear and tear.
Damages/defects arising out of wrong operation of equipment by buyer and/or arising out of
accidents, riots, fire etc.

6. Customer's Scope :
· Arrangements for Unloading, Lifting and placement of Equipments.
. Staying of Engineers during project.
. Civil Works with material.
. Plumbing Works with material for tank and Heat Pump
. Supply of Electricity to system with material.
. Proper Non-fluctuating 3-phase/1-Phase voltage is required for operation of system.
. Proper supply of raw water should be provided at the time of commissioning.
. Plumbing work with material.

7. Transportation & Transit Insurance:


. Transportation cost is in scope of buyer.
. Transportation service can be arranged by seller,only after confirmation and complete
transportation payment in advance by seller before dispatch.
. Transit Insurance will be in favour of buyer only.