HARGA SATUAN DASAR UPAH, BAHAN DAN PERALATAN

Pekerjaan : Pengeboran Air Bersih di Rumah Dinas Setda


Lokasi : Manado
Tahun Anggaran : 2018

Harga Satuan
No. Uraian SATUAN KET.
(Rp.)

A TENAGA
1 Pekerja OH 100,000.00
2 Mekanik OH 120,000.00
3 Mandor OH 120,000.00
4 Juru bor OH 125,000.00
5 Operator OH 150,000.00
6 Tukang Batu OH 125,000.00
7 Kepala Tukang OH 150,000.00
8 Tukang Kayu OH 125,000.00
9 Tukang Besi OH 125,000.00
10 Tukang OH 125,000.00
11 Tukang Cat OH 125,000.00
12 Geolistrik OH 140,000.00
13 Ass. Geolistrik OH 120,000.00
14 Driller OH 150,000.00

B BAHAN
1 Minyak Pelumas Oli LTR 30,000.00
2 Bahan Bakar Bensin (Eceran) LTR 8,000.00
3 Solar Ltr 6,500.00
4 Kabel NYY 3 x 2,5 mm M 11,000.00
Kabel NYM 2 x 2,5 mm M 9,500.00
5 Filter Gravel M3 200,000.00
6 Pasir Urug M3 120,000.00
7 Tanah M3 75,000.00
8 Batu Belah 15/20 cm M3 175,000.00
9 Semen Portland KG 1,200.00
10 Pasir Pasang M3 125,000.00
11 Pasir Beton M3 125,000.00
12 Koral/Kerikil Beton M3 250,000.00
13 Kayu Terentang M3 1,900,000.00
14 Paku Biasa 2" - 5" KG 20,000.00
15 Minyak Bekisting LTR 10,000.00
16 Besi beton polos KG 10,000.00
17 Kawat Beton KG 25,000.00
18 Kayu Kelas II, Balok M3 4,000,000.00
19 Tripleks 9 mm LBR 135,000.00
20 Dolken BTG 15,000.00
21 Batu Pecah M3 275,000.00
22 Kayu Bekisting M3 1,500,000.00
23 Paku KG 20,000.00
24 Bata Merah 5x11x12 BH 900.00
25 Ubin Keramik 30x30cm BH 10,000.00
26 Semen Warna KG 1,500.00
27 Plamir KG 10,000.00
28 Cat Meni Ltr 25,000.00
29 Kuas Bh 10,000.00
30 Cat Dasar KG 25,000.00
31 Cat Penutup KG 25,000.00
32 Gate Valve 2" BH 400,000.00
33 Seal Tape BH 25,000.00
34 Kayu Kaso 5/7 M3 4,000,000.00
Harga Satuan
No. Uraian SATUAN KET.
(Rp.)
35 Kayu Papan M3 4,000,000.00
36 Kayu Kelas III Balok M3 1,900,000.00
37 Kayu Kelas III Papan M3 1,900,000.00
38 Seng Gelombang BJLS 0,20 LBR 120,000.00
39 Paku Seng KG 35,000.00
40 Pipa PVC dia. 1 1/4" M1 30,000.00
41 Perlengkapan Pipa LS 10,000.00
42 Pipa PVC dia. 2" M1 20,000.00
43 Perlengkapan Pipa PVC dia. 2" LS 12,000.00
44 Pipa PVC dia. 4" M1 73,750.00
45 Pipa PVC dia. 3" M1 48,750.00
46 Pipa PVC dia. 1" M1 12,500.00
Pipa PVC dia. 6" M1 103,600.00
47 Besi baja INP 150.70 Kg 9,000.00
48 Besi Profil L 70.70 Kg 5,000.00
49 Besi Profil L 50.50 Kg 5,000.00
50 Plat Besi 5 mm Kg 10,000.00
51 Kawat las listrik Kg 32,000.00
52 Pipa PE dia. 1/2" M1 8,500.00
53 Pipa PE dia. 1" M1 15,000.00
54 Accesoris pipa LS 350,000.00

C PERALATAN
1 Concrete Vibrator Jam 20,000.00
2 Concrete Mixer Jam 20,000.00
3 Dump Truck Jam 150,000.00
4 Drilling Rigs / Peralatan Bor Jam 750,000.00
5 Alkon Hari 500,000.00
6 Pompa Lumpur Jam 20,000.00
7 Sewa alat perakitan baja Jam 500,000.00
8 Alat Bantu Set 50,000.00
ANALISA HARGA SATUAN

Pekerjaan : Pengeboran Air Bersih di Rumah Dinas Setda


Lokasi : Manado
Tahun Anggaran : 2018

ANALISA HARGA SATUAN PEMBUATAN SUMUR BOR

Harga Satuan Jumlah Harga


Uraian Koefisien Satuan
(Rp.) (Rp.)

1 m' pengeboran pilot hole dia. 6" kedalaman 0-52m tanah Berbatu
Bahan bakar Bensin 1.56 ltr 8,000.00 12,480.00
minyak pelumas oli 0.00070513 ltr 30,000.00 21.15
mesin / peralatan bor 0.55 Jam 750,000.00 412,500.00
geolistrik 0.2 Oh 140,000.00 28,000.00
ass. Geolistrik 0.2 Oh 120,000.00 24,000.00
driller 0.062 Oh 150,000.00 9,300.00
mekanik 0.062 Oh 120,000.00 7,440.00
mandor 0.1 Oh 120,000.00 12,000.00
juru bor 0.1 Oh 125,000.00 12,500.00
operator 0.1 Oh 150,000.00 15,000.00
pekerja 0.1 Oh 100,000.00 10,000.00
Jumlah 543,241.15
Overhead 10 % 54,324.12
Harga Satuan Pekerjaan 597,565.27

1 M1 Pasang Pipa PVC Tipe AW dia.4"


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Pipa PVC 4" 1.2 M1 73,750.00 88,500.00
Perlengkapan Pipa 0.35 Ls 25,812.50 9,034.38
TENAGA -
Pekerja 0.081 Oh 100,000.00 8,100.00
Tukang 0.135 Oh 125,000.00 16,875.00
Kepala Tukang 0.014 Oh 150,000.00 2,025.00
Mandor 0.041 Oh 120,000.00 4,920.00
Jumlah 129,454.38
Overhead 10 % 12,945.44
Harga Satuan Pekerjaan 142,399.81

1 M1 Pasang Pipa PVC Tipe AW dia.3"


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Pipa PVC 3" 1.2 M1 48,750.00 58,500.00
Perlengkapan Pipa 0.35 Ls 17,062.50 5,971.88
TENAGA -
Pekerja 0.081 Oh 100,000.00 8,100.00
Tukang 0.135 Oh 125,000.00 16,875.00
Kepala Tukang 0.014 Oh 150,000.00 2,025.00
Mandor 0.041 Oh 120,000.00 4,920.00
Jumlah 96,391.88
Overhead 10 % 9,639.19
Harga Satuan Pekerjaan 106,031.06
1 M1 Pasang Pipa PVC Tipe AW dia.2"
Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Pipa PVC 2" 1.2 M1 20,000.00 24,000.00
Perlengkapan Pipa 0.35 Ls 7,000.00 2,450.00
TENAGA -
Pekerja 0.081 Oh 100,000.00 8,100.00
Tukang 0.135 Oh 125,000.00 16,875.00
Kepala Tukang 0.014 Oh 150,000.00 2,025.00
Mandor 0.041 Oh 120,000.00 4,920.00
Jumlah 58,370.00
Overhead 10 % 5,837.00
Harga Satuan Pekerjaan 64,207.00

1 M1 Pasang Pipa PVC Tipe AW dia.6"


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Pipa PVC 1" 1.2 M1 103,600.00 124,320.00
Perlengkapan Pipa 0.35 Ls 7,000.00 2,450.00
TENAGA -
Pekerja 0.081 Oh 100,000.00 8,100.00
Tukang 0.135 Oh 125,000.00 16,875.00
Kepala Tukang 0.014 Oh 150,000.00 2,025.00
Mandor 0.041 Oh 120,000.00 4,920.00
Jumlah 158,690.00
Overhead 10 % 15,869.00
Harga Satuan Pekerjaan 174,559.00

1 M1 Pasang Kabel NYY 3 x 2,5


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Kabel NYY 3 x 2,5 mm 1.2 M1 11,000.00 13,200.00
Perlengkapan Instalasi 0.3 Ls 3,300.00 990.00
TENAGA -
Pekerja 0.150 Oh 100,000.00 15,000.00
Tukang 0.015 Oh 125,000.00 1,875.00
Jumlah 31,065.00
Overhead 10 % 3,106.50
Harga Satuan Pekerjaan 34,171.50

1 M1 Pasang Kabel NYM 2 x 2,5


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Kabel NYM 2 x 2,5 mm 1.2 M1 9,500.00 11,400.00
Perlengkapan Instalasi 0.3 Ls 2,850.00 855.00
TENAGA -
Pekerja 0.150 Oh 100,000.00 15,000.00
Tukang 0.015 Oh 125,000.00 1,875.00
Jumlah 29,130.00
Overhead 10 % 2,913.00
Harga Satuan Pekerjaan 32,043.00

1 Jam pumping test / pemompaan uji


bahan bakar Bensin 2.25 Ltr 8,000.00 18,000.00
minyak pelumas oli 0.25 Ltr 30,000.00 7,500.00
sewa alat 0.011 Hr 500,000.00 5,500.00
mandor 0.005 Oh 120,000.00 600.00
pekerja 0.094 Oh 100,000.00 9,400.00
Jumlah 41,000.00
Overhead 10 % 4,100.00
Harga Satuan Pekerjaan 45,100.00

1 Jam Pembersihan sumur dengan water jetting


bahan bakar Bensin 1.5 Ltr 8,000.00 12,000.00
minyak pelumas oli 0.25 Ltr 30,000.00 7,500.00
sewa alat 0.013 Hr 500,000.00 6,500.00
mandor 0.019 Oh 120,000.00 2,280.00
pekerja 0.094 Oh 100,000.00 9,400.00
Jumlah 37,680.00
Overhead 10 % 3,768.00
Harga Satuan Pekerjaan 41,448.00

1 M3 Galian Tanah Biasa


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
TENAGA
Pekerja 0.9 Oh 100,000.00 90,000.00
Mandor 0.045 Oh 120,000.00 5,400.00
Jumlah 95,400.00
Overhead 10 % 9,540.00
Harga Satuan Pekerjaan 104,940.00
1 M3 Urugan Pasir
Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Pasir Urug 1.2 M3 120,000.00 144,000.00
TENAGA
Pekerja 0.3 Oh 67,000.00 20,100.00
Mandor 0.1 Oh 90,000.00 9,000.00
Jumlah 173,100.00
Overhead 10 % 17,310.00
Harga Satuan Pekerjaan 190,410.00

1 M3 Lantai Kerja Beton Tumbuk, 1PC:3Ps:5Kr, t = 5cm


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Semen Portland 10 Kg 1,400.00 14,000.00
Pasir Beton 0.026 M3 125,000.00 3,250.00
Koral Beton 0.044 M3 225,000.00 9,900.00
TENAGA
Pekerja 1.15 Oh 67,000.00 77,050.00
Tukang Batu 0.02 Oh 80,000.00 1,600.00
Kepala Tukang 0.002 Oh 125,000.00 250.00
Mandor 0.006 Oh 90,000.00 540.00
Jumlah 106,590.00
Overhead 10 % 10,659.00
Harga Satuan Pekerjaan 117,249.00

1 M3 Membuat Sloof Beton Bertulang (175 kg besi + bekisting)


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Kayu terentang 0.27 M3 1,900,000.00 513,000.00
Paku Biasa 2" - 5" 2 Kg 20,000.00 40,000.00
Minyak bekisting 0.6 Lt 10,000.00 6,000.00
Besi Beton Polos 175 Kg 10,000.00 1,750,000.00
Kawat Beton 3 Kg 25,000.00 75,000.00
Semen Portland 323 Kg 1,200.00 387,600.00
Pasir Beton 0.52 M3 125,000.00 65,000.00
Koral / Kerikil Beton 0.78 M3 250,000.00 195,000.00
TENAGA
Pekerja 4.85 Oh 100,000.00 485,000.00
Tukang Batu 0.35 Oh 125,000.00 43,750.00
Tukang Kayu 1.56 Oh 125,000.00 195,000.00
Tukang Besi 1.4 Oh 125,000.00 175,000.00
Kepala Tukang 0.331 Oh 150,000.00 49,650.00
Mandor 0.17 Oh 120,000.00 20,400.00
Jumlah 4,000,400.00
Overhead 10 % 400,040.00
Harga Satuan Pekerjaan 4,400,440.00
1 M3 Membuat Kolom Beton Bertulang (100 kg besi + bekisting)
Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Kayu terentang 0.4 M3 1,900,000.00 760,000.00
Paku Biasa 2" - 5" 4 Kg 20,000.00 80,000.00
Minyak bekisting 2 Lt 10,000.00 20,000.00
Besi Beton Polos 100 Kg 10,000.00 1,000,000.00
Kawat Beton 4.5 Kg 25,000.00 112,500.00
Semen Portland 323 Kg 1,200.00 387,600.00
Pasir Beton 0.52 M3 125,000.00 65,000.00
Koral / Kerikil Beton 0.78 M3 250,000.00 195,000.00
Kayu Kelas III, balok 0.15 M3 1,900,000.00 285,000.00
Tripleks 6mm 3.5 Lbr 135,000.00 472,500.00
Dolken 20 Btg 15,000.00 300,000.00
TENAGA
Pekerja 7.3 Oh 100,000.00 730,000.00
Tukang Batu 0.35 Oh 125,000.00 43,750.00
Tukang Kayu 3.3 Oh 125,000.00 412,500.00
Tukang Besi 2.1 Oh 125,000.00 262,500.00
Kepala Tukang 0.57 Oh 150,000.00 85,500.00
Mandor 0.25 Oh 120,000.00 30,000.00
Jumlah 5,241,850.00
Overhead 10 % 524,185.00
Harga Satuan Pekerjaan 5,766,035.00

1 M2 Pengecatan Permukaan Baja dengan Meni Besi


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Cat Meni 0.1 Ltr 25,000.00 2,500.00
Kuas 0.01 Kg 10,000.00 100.00
TENAGA
Pekerja 0.020 Oh 100,000.00 2,000.00
Tukang cat 0.200 Oh 125,000.00 25,000.00
Kepala Tukang 0.020 Oh 150,000.00 3,000.00
Mandor 0.010 Oh 120,000.00 1,200.00
Jumlah 33,800.00
Overhead 10 % 3,380.00
Harga Satuan Pekerjaan 37,180.00

1 M3 Membuat Beton Tumbuk 1PC:3Ps:5Kr


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Semen Portland 218 Kg 1,200.00 261,600.00
Pasir Beton 0.52 M3 125,000.00 65,000.00
Koral Beton 0.87 M3 250,000.00 217,500.00
TENAGA
Pekerja 1.65 Oh 100,000.00 165,000.00
Tukang Batu 0.25 Oh 125,000.00 31,250.00
Kepala Tukang 0.025 Oh 150,000.00 3,750.00
Mandor 0.08 Oh 120,000.00 9,600.00
Jumlah 753,700.00
Overhead 10 % 75,370.00
Harga Satuan Pekerjaan 829,070.00
1 M3 Ringbalk beton bertulang (100kg besi+bekisting)
Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Kayu Klas III Balok 0.14 M3 1,900,000.00 266,000.00
Kayu Klas III Papan 0.23 M3 1,900,000.00 437,000.00
Paku Biasa 2"-5" 3.2 Kg 20,000.00 64,000.00
Minyak Bekisting 1.6 Lt 10,000.00 16,000.00
Besi Beton Polos 100 Kg 10,000.00 1,000,000.00
Kawat Beton 3 Kg 25,000.00 75,000.00
Semen Portland 232 Kg 1,200.00 278,400.00
Pasir Beton 0.52 M3 125,000.00 65,000.00
Koral Beton 0.78 M3 250,000.00 195,000.00
TENAGA
Pekerja 0.1 Oh 100,000.00 10,000.00
Tukang Batu 0.033 Oh 125,000.00 4,125.00
Tukang Kayu 0.033 Oh 125,000.00 4,125.00
Tukang Besi 0.033 Oh 125,000.00 4,125.00
Kepala Tukang 0.01 Oh 150,000.00 1,500.00
Mandor 0.005 Oh 120,000.00 600.00
Jumlah 2,420,875.00
Overhead 10 % 242,087.50
Harga Satuan Pekerjaan 2,662,962.50

1 M3 Plat beton bertulang (100kg besi+bekisting)


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Kayu Klas III Balok 0.14 M3 1,900,000.00 266,000.00
Kayu Klas III Papan 0.23 M3 1,900,000.00 437,000.00
Paku Biasa 2"-5" 3.2 Kg 20,000.00 64,000.00
Minyak Bekisting 1.6 Lt 10,000.00 16,000.00
Besi Beton Polos 100 Kg 10,000.00 1,000,000.00
Kawat Beton 3 Kg 25,000.00 75,000.00
Semen Portland 232 Kg 1,200.00 278,400.00
Pasir Beton 0.52 M3 125,000.00 65,000.00
Koral Beton 0.78 M3 250,000.00 195,000.00
TENAGA -
Pekerja 0.1 Oh 100,000.00 10,000.00
Tukang Batu 0.033 Oh 125,000.00 4,125.00
Tukang Kayu 0.033 Oh 125,000.00 4,125.00
Tukang Besi 0.033 Oh 125,000.00 4,125.00
Kepala Tukang 0.01 Oh 150,000.00 1,500.00
Mandor 0.005 Oh 120,000.00 600.00
Jumlah 2,420,875.00
Overhead 10 % 242,087.50
Harga Satuan Pekerjaan 2,662,962.50

1 M1 Pasang Pipa Tipe PE dia. 1/2"


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Pipa PE dia. 1/2" 1.2 M1 8,500.00 10,200.00
Perlengkapan Pipa 0.35 x 8,500.00 2,975.00
TENAGA
Pekerja 0.054 Oh 100,000.00 5,400.00
Tukang 0.09 Oh 125,000.00 11,250.00
Kepala Tukang 0.009 Oh 150,000.00 1,350.00
Mandor 0.0027 Oh 120,000.00 324.00
Jumlah 31,499.00
Overhead 10 % 3,149.90
Harga Satuan Pekerjaan 34,648.90
1 M1 Pasang Pipa Tipe PE dia. 1"
Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Pipa PE dia. 1" 1.2 M1 15,000.00 18,000.00
Perlengkapan Pipa 0.35 x 15,000.00 5,250.00
TENAGA
Pekerja 0.054 Oh 100,000.00 5,400.00
Tukang 0.09 Oh 125,000.00 11,250.00
Kepala Tukang 0.009 Oh 150,000.00 1,350.00
Mandor 0.0027 Oh 120,000.00 324.00
Jumlah 41,574.00
Overhead 10 % 4,157.40
Harga Satuan Pekerjaan 45,731.40

Memasang 1 kg rangka baja INP


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Besi baja INP 150.70 1.150 Kg 9,000.00 10,350.00
-
TENAGA -
Pekerja 0.060 Oh 100,000.00 6,000.00
Tukang las 0.060 Oh 125,000.00 7,500.00
Kepala tukang 0.006 Oh 150,000.00 900.00
Mandor 0.003 Oh 120,000.00 360.00
Jumlah 25,110.00
Overhead 10 % 2,511.00
Harga Satuan 27,621.00

1 Kg Memasang besi profil L 70.70


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Besi Profil L 70.70 1.150 Kg 5,000.00 5,750.00
-
TENAGA -
Pekerja 0.060 Oh 100,000.00 6,000.00
Tukang las 0.060 Oh 125,000.00 7,500.00
Kepala tukang 0.006 Oh 150,000.00 900.00
Mandor 0.003 Oh 120,000.00 360.00
Jumlah 20,510.00
Overhead 10 % 2,051.00
Harga Satuan 22,561.00

1 Kg Memasang besi profil L 50.50


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Besi Profil L 50.50 1.150 Kg 5,000.00 5,750.00
-
TENAGA -
Pekerja 0.060 Oh 100,000.00 6,000.00
Tukang las 0.060 Oh 125,000.00 7,500.00
Kepala tukang 0.006 Oh 150,000.00 900.00
Mandor 0.003 Oh 120,000.00 360.00
Jumlah 20,510.00
Overhead 10 % 2,051.00
Harga Satuan 22,561.00
1 Kg Memasang Plat Besi 5 mm
Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Plat Besi 5 mm 1.150 Kg 10,000.00 11,500.00
-
TENAGA -
Pekerja 0.060 Oh 100,000.00 6,000.00
Tukang las 0.060 Oh 125,000.00 7,500.00
Kepala tukang 0.006 Oh 150,000.00 900.00
Mandor 0.003 Oh 120,000.00 360.00
Jumlah 26,260.00
Overhead 10 % 2,626.00
Harga Satuan 28,886.00

Mengerjakan 100 kg pekerjaan perakitan


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Solar 1.000 Liter 6,500.00 6,500.00
Minyak pelumas 0.100 Liter 30,000.00 3,000.00
TENAGA -
Pekerja 0.100 Oh 100,000.00 10,000.00
Tukang besi 0.100 Oh 125,000.00 12,500.00
Kepala tukang 0.001 Oh 150,000.00 150.00
Mandor 0.005 Oh 120,000.00 600.00
Sewa alat perakitan baja 0.800 Jam 500,000.00 400,000.00
Jumlah 432,750.00
Overhead 10 % 43,275.00
Harga Satuan 100 Kg 476,025.00
1 Kg 4,760.25

Mengerjakan 10 cm pengelasan dengan las listrik


Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Kawat las listrik 0.400 Kg 32,000.00
Solar 0.300 Liter 6,500.00 1,950.00
Minyak pelumas 0.040 Liter 30,000.00 1,200.00
TENAGA -
Pekerja 0.040 Oh 100,000.00 4,000.00
Tukang besi 0.020 Oh 125,000.00 2,500.00
Kepala tukang 0.002 Oh 150,000.00 300.00
Mandor 0.002 Oh 120,000.00 240.00
Sewa alat perakitan baja 0.170 Jam 500,000.00 85,000.00
Jumlah 95,190.00
Overhead 10 % 9,519.00
Harga Satuan 10cm 104,709.00
1 cm 10,470.90
Pembuatan Tower Tangki Air (Besi Siku)
Harga Satuan Jumlah Harga
Komponen Koef. Satuan
(Rp.) (Rp.)
BAHAN
Besi Plat Perletakan (tebal 8 mm, sudah dibor) 4.000 bh 4.00 16.00
Angkur Penahan + Bout Mur 16.000 bh 16.00 256.00
Besi Siku 40.40.4 2,259.960 kg 10,500.00 23,729,580.00

TENAGA
Pekerja Oh -
Tukang besi Oh -
Kepala tukang Oh -
Mandor Oh -
Sewa alat perakitan baja Jam -
Jumlah 23,729,852.00
Overhead 10 % 2,372,985.20
Harga Satuan 26,102,837.20
ENGINERING ESTIMATE
(HPS)
Pekerjaan : Pengeboran Air Bersih
Lokasi : Tampusu
Tahun Anggaran : 2019

HARGA SATUAN JUMLAH HARGA


NO. URAIAN SAT. VOLUME
(Rp.) (Rp.)

I. PEKERJAAN PERSIAPAN 5,500,000.00


1 Pembersihan Awal LS 1.000 1,000,000.00 1,000,000.00
2 Pengadaan Air Kerja Ls 1.000 2,000,000.00 2,000,000.00
3 Pekerjaan Mobilisasi dan Setting Alat Ls 1.000 2,500,000.00 2,500,000.00

II. PEKERJAAN SUMUR BOR KEDALAMAN 60 M 59,184,312.03


1 Pengeboran Pilot Hole dia. 6" kedalaman 0 - 60 m M1 60.000 597,565.27 35,853,916.15
2 Pemasangan Pipa Sumur dia.6" M1 6.000 174,559.00 1,047,354.00
3 Pemasangan Pipa Sumur dia. 4" M1 54.000 142,399.81 7,689,589.88
4 Pemasangan Pipa Sumur dia. 2" M1 60.000 64,207.00 3,852,420.00
5 Pembersihan Sumur dengan Water Jetting Jam 24.000 41,448.00 994,752.00
6 Pumping Test Jam 12.000 45,100.00 541,200.00
7 Pemasangan Mesin Pompa Interdub 1 HP dan Asesories UNIT 1.000 6,250,000.00 6,250,000.00
8 Pasang Kabel NYY 3 x 2,5 mm M1 50.000 34,171.50 1,708,575.00
9 Pasang Kabel NYM 2 x 2.5 mm M1 35.000 32,043.00 1,121,505.00
10 Pekerjaan Pasang Bois 30 cm + Penutup M3 0.500 250,000.00 125,000.00

III. PEKERJAAN AKHIR 700,000.00


1 Pekerjaan Pembersihan Akhir LS 1.000 700,000.00 700,000.00

REKAPITULASI
I. PEKERJAAN PERSIAPAN 5,500,000.00
II. PEKERJAAN SUMUR BOR KEDALAMAN 60 M 59,184,312.03
III. PEKERJAAN AKHIR 700,000.00

Sub Total 65,384,312.03


PPN 10 % 6,538,431.20
Total 71,922,743.23
Dibulatkan 71,920,000.00

Terbilang : Tujuh Puluh Satu Juta Sembilan Ratus Dua Puluh Ribu Rupiah

Dibuat,
PT. ASRI ABADI KONSULTAN

ALIFAH SAMIR, ST, M.Ars


Direktur Utama
HARGA PERKIRAAN SENDIRI
(HPS)
Pekerjaan : Pengeboran Air Bersih di VVIP Bandara
Lokasi : Manado
Tahun Anggaran : 2018

HARGA SATUAN JUMLAH HARGA


NO. URAIAN SAT. VOLUME
(Rp.) (Rp.)

I. PEKERJAAN PERSIAPAN 4,500,000.00


1 Pembersihan Awal LS 1.000 500,000.00 500,000.00
2 Pengadaan Air Kerja Ls 1.000 1,500,000.00 1,500,000.00
3 Pekerjaan Mobilisasi dan Setting Alat Ls 1.000 2,500,000.00 2,500,000.00

II. PEKERJAAN SUMUR BOR KEDALAMAN 52 M 50,750,935.38


1 Pengeboran Pilot Hole dia. 6" kedalaman 0 - 52 m M1 52.000 597,565.27 31,073,394.00
2 Pemasangan Pipa Sumur dia.6" M1 6.000 174,559.00 1,047,354.00
3 Pemasangan Pipa Sumur dia. 4" M1 46.000 142,399.81 6,550,391.38
4 Pemasangan Pipa Sumur dia. 1" M1 52.000 64,207.00 3,338,764.00
5 Pembersihan Sumur dengan Water Jetting Jam 24.000 41,448.00 994,752.00
6 Pumping Test Jam 12.000 45,100.00 541,200.00
7 Pemasangan Mesin Pompa Interdub 1 HP dan Asesories UNIT 1.000 4,250,000.00 4,250,000.00
8 Pasang Kabel NYY 3 x 2,5 mm M1 50.000 34,171.50 1,708,575.00
9 Pasang Kabel NYM 2 x 2.5 mm M1 35.000 32,043.00 1,121,505.00
10 Pekerjaan Pasang Bois 30 cm + Penutup M1 0.500 250,000.00 125,000.00

II. PEKERJAAN SUMUR BOR KEDALAMAN 60 M 36,507,655.88


1 Pengeboran Pilot Hole dia. 6" kedalaman 0 - 60 m M1 60.000 269,621.00 16,177,260.00
2 Pemasangan Pipa Sumur dia. 6" M1 6.000 174,559.00 1,047,354.00
3 Pemasangan Pipa Sumur dia. 4" M1 54.000 142,399.81 7,689,589.88
4 Pemasangan Pipa Sumur dia. 1" M1 60.000 64,207.00 3,852,420.00
5 Pembersihan Sumur dengan Water Jetting Jam 24.000 41,448.00 994,752.00
6 Pumping Test Jam 12.000 45,100.00 541,200.00
7 Pemasangan Mesin Pompa Interdub 1 HP dan Asesories UNIT 1.000 3,250,000.00 3,250,000.00
8 Pasang Kabel NYY 3 x 2,5 mm M1 50.000 34,171.50 1,708,575.00
9 Pasang Kabel NYM 2 x 2.5 mm M1 35.000 32,043.00 1,121,505.00
10 Pekerjaan Pasang Bois 30 cm + Penutup M1 0.500 250,000.00 125,000.00

III. PEKERJAAN MENARA AIR TINGGI 6 M


A Pekerjaan Tanah dan Pondasi 7,746,596.28
1 Galian Tanah Pondasi M3 2.720 104,940.00 285,436.80
2 Urugan Pasir bawah pondasi M3 0.680 190,410.00 129,478.80
3 Cor Lantai Kerja 1:3:5 tebal 5cm M3 0.600 829,070.00 497,442.00
4 Pekerjaan Cor Telapak Beton Bertulang M3 1.200 2,662,962.50 3,195,555.00
5 Pekerjaan Cor Kolom 25 x 25 cm Beton Bertulang M3 0.425 5,766,035.00 2,450,564.88
6 Pekerjaan Cor Sloof 15 x 20 cm Beton Bertulang M3 0.270 4,400,440.00 1,188,118.80

B Pekerjaan Menara 26,102,837.20


1 Pembuatan Tower Rangka Besi Siku 60x60x6 h = 6 m Unit 1.000 26,102,837.20 26,102,837.20

C Pekerjaan Instalasi Air 14,464,890.00


1 Pekerjaan Pemasangan Pipa PE 1/2" M1 100.000 34,648.90 3,464,890.00
3 Pekerjaan Pemasangan Tanki Air Steenlisteel 2000 L Bh 2.000 5,500,000.00 11,000,000.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SAT. VOLUME
(Rp.) (Rp.)

IV PEKERJAAN AKHIR 500,000.00


1 Pekerjaan Pembersihan Akhir LS 1.000 500,000.00 500,000.00

REKAPITULASI
I. PEKERJAAN PERSIAPAN 4,500,000.00
II. PEKERJAAN SUMUR BOR KEDALAMAN 52 M 50,750,935.38
III. PEKERJAAN SUMUR BOR KEDALAMAN 60 M 36,507,655.88
PEKERJAAN MENARA AIR TINGGI 6 M 48,314,323.48
A Pekerjaan Tanah dan Pondasi 7,746,596.28
B Pekerjaan Menara 26,102,837.20
C Pekerjaan Instalasi Air 14,464,890.00
IV PEKERJAAN AKHIR 500,000.00

Sub Total 140,572,914.73


PPN 10 % 14,057,291.47
Total 154,630,206.20
Dibulatkan 154,630,000.00

Terbilang : Seratus Empat Puluh Delapan Juta Tujuh Ratus Sembilan Belas Ribu Rupiah

Manado, …………………… 2017