Correct
Sl. No. Question Text Option 1 (A) Option 2 (B) Option 3 (C) Option 4 (D) Answer
(A/B/C/D)
As per EC act, the definition of energy audit does not
1 Monitoring Verification Analysis Duration of Audit D
consider
The nodal agency at the centre for implementing the EC
2 CEA SDA BEE Ministry of Power C
act is
In order to ensure functional autonomy of LDCs, it is very Financial Personnel on direct control of
4 Corporate Structure B
important to have ____ independence deputation Ministry
Membership of Forum of Load Despatchers (FOLD) is SLDC / RLDC /
5 SLDCs RLDCs NLDC D
derived from personnel working in the ____ NLDC
As functionally Central Electricity State Electricity
6 National Load Despatch Center is mandated to work ___ Independent Under the MoP Regulatory Regulatory A
entity Commission Commission
Consolidation of all
Setting up of
7 The Electricity Act,2003 pays great attention to: Urban electrification Rural Electrification private electricity B
nuclear plants
companies
Judgment of the appellate tribunal can be appealed against
8 Sessions Court High Court Supreme Court Consumer court C
in:
Which was the first State in the Country to establish its
9 Andhra Karnataka Orissa Haryana C
Regulatory Commission?
10 Who is to frame the Tariff policy? Central Govt. CERC SERC State Govt. A
after consulting
11 Can a captive generator supply surplus power to the grid? Sometimes Always Never D
CTU/STU
Which of the following would act as the Central control Regional Load Control Room set up Control Room in National Load
17 room in case of natural & man made emergency/disaster Despatch Centre by CEA for this Ministry of Power Despatch Centre D
where it affects the power system operation. (RLDC) purpose for this purpose (NLDC)
With reference to CEA's Grid Connectivity Standards, the main and transfer double main and one and half breaker double bus double
27 A
preferable switching scheme for a 132 kV substation is: scheme transfer scheme scheme breaker scheme
The responsibility to frame technical standards has been Rules made by IEGC frame by
28 Electricity Act 2003 Resolution of RPCs B
entrusted to CEA through: Government CERC
41 Which generating unit can be used as a peaking station? nuclear combined cycle run of the river wind B
As the system frequency reduces, the lighting and heating increases decreases
50 reduces remains constant C
load of an electrical island____. proportionally exponentially
Automatic generation Economic load
51 The secondary frequency control is characterised by: Governor action Load damping A
control despatch
The change in unit output due to governor control is droop constant, unit unit terminal voltage, unit capacity, droop
52 frequency, unit capacity D
proportional to ___ and inversely proportional to ___. capacity frequency constant