You are on page 1of 14

facilities had four different sets of guidelines for recording

Managing Availability for downtime.


Improved Bottom-Line Results
© 2002 by Bill Keeter This paper examines availability in detail: the three types of
ARMS Reliability Engineers – USA, LLC availability and how they relate to each other, the factors
Affiliated with ARMS Reliability Engineers – Australia that determine availability, and recommendations for
www.reliability.com.au improving the setting of goals.

Abstract Availability Types


During the past five to eight years, the role of maintenance The three subtypes of availability are inherent, achievable,
manager has evolved from merely keeping equipment and operational (see Figure 1). Each subtype has specific
running to that of physical asset manager. The goal of the characteristics determined by several top-level factors.
physical asset manager is to maximize profits by managing
physical assets in a way that provides the optimum level of • Inherent Availability (Ai) — The
physical availability. This paper provides a framework for expected level of availability for the performance
managing availability goals to help meet the financial goals of corrective maintenance only. Inherent
of an organization. availability is determined purely by the design of
the equipment. It assumes that spare parts and
Introduction manpower are 100 percent available with no
Over the last several years, managers up through the CEO delays.
have come to recognize equipment uptime as a key part of
any successful operating strategy. Recognition of this need • Achievable Availability (Aa ) — The
expected level of availability for the performance
has generated the use of equipment availability as one of
of corrective and preventive maintenance.
the key performance indicators of a maintenance
Achievable availability is determined by the hard
organization. Goals are set based on “gut feel,” or by
design of the equipment and the facility. Aa also
benchmarking with similar facilities within the organization
or with similar organizations within the same industry. assumes that spare parts and manpower are 100
percent available with no delays.
Both these methods involve high levels of uncertainty that
can lead to overspending for maintenance and overtaxing of
• Operational Availability (Ao) — The
maintenance resources. The uncertainty of “gut feel”
bottom line of availability. It is the actual level of
speaks for itself. Benchmarking involves high levels of availability realized in the day-to-day operation
uncertainty due to the difficulties created by not knowing
of the facility. It reflects plant maintenance
the exact guidelines each facility uses for recording
resource levels and organizational effectiveness.
unavailability. The author has worked at a site where four

Figure 1. The Three Types of Availability

Percent
Inherent
Achievable
Operational
Availabili
ty

Over-Maintained
Under-Maintained Maintenance Induced Downtime
Failure Induced Downtime
Hours

Scheduled Maintenance

Bill Keeter – Page 1 of 14


Managing Availability for Improved Bottom-Line Results

It is important to understand the distinctions among overspending and overtaxing of maintenance


the three subtypes in order to design, measure, and resources.
manage integrated subgoals:
• Management must make strategic decisions
for long-term relative positions of the two
• Achievable availability fulfills the need to
distinguish availability when planned curves. As plant production increases over
time, changing operating conditions will
shutdowns are included.
place greater stress on equipment and drive
• Inherent availability fulfills the need to Aa down. Meanwhile, maintenance
distinguish expected performance between operation management will progressively
planned shutdowns. move Ao upward to meet the demands of
production. Eventually the two will
• Operational availability is required to isolate converge to the point that additional
the effectiveness and efficiency of availability can be acquired only by
maintenance operations. modifying plant design.
These definitions and distinctions lead to crucial The conclusion from these factors is that eventually
recognitions: Aa must be known. Otherwise, many of the current
goals to develop world-class maintenance operations
• The shape and location of the achievable are not possible. It is the organization that makes the
availability curve is determined by the most money — not the one with the highest
plant’s hard design. availability — that wins the game.
• An operation is at a given point on Aa,
based on whether scheduled versus Factors That Determine Availability
unscheduled maintenance strategies are Availability is a function of reliability and
selected for each failure. A goal of maintainability — in other words, how often
availability-based maintenance operations is equipment will fail and how long it takes to get the
to find the peak of the curve and operate at equipment back to full production capability.
that level. Reliability, maintainability, and therefore, availability
are determined by the interaction of the design,
• Operational availability is the bottom line of production, and maintenance functions.
performance. It is the performance
experienced as the plant operates at a given
The implication is that availability is largely
production level.
determined by how well designers, operators, and
• The vertical location of the Ao is controlled maintainers work together.
by decisions for resource levels and the
organizational effectiveness of maintenance Optimizing Availability
operations. By definition, its location cannot Profitable plant availability is the result of optimizing
rise above Aa. Ai, Aa, and Ao. Because no plant can achieve
availability higher than Aa, achievable availability is
These factors have the following strategic the first to be optimized (see
implications: Figure 2).

• It is crucial to know the location and shape All equipment fails based on its design even when
of the achievable availability curve. operated and maintained perfectly. Every maintenance
Otherwise, it is not possible to determine activity, whether scheduled or unscheduled, is
what is reasonable and possible for representative of an equipment failure. Scheduled or
operational availability and, therefore, plant time-based maintenance seeks to correct failures
production. before they can affect equipment performance.
Unscheduled maintenance is corrective maintenance
• If the Aa curve is not known, manufacturing
performed as the result of breakdown or the detection
operations management may unknowingly
of incipient failure.
attempt to achieve performance beyond that
which is possible. The result is the

Bill Keeter – Page 2 of 14


Managing Availability for Improved Bottom-Line Results

Table 1. Top Level Factors That Affect Availability


Reliability Maintainability
Is increased as the frequency of outages is reduced. Time Is increased as the duration of plant, subsystem or
between failures or shutdowns is increased. equipment downtime is reduced.
Factors Driven by Design Decisions
Operating Environment Accessibility to the work point.
Equipment Rated Capacity Features and design that determine the ease of
maintenance.
Maintenance while the system, subsystem or item of Plant ingress and egress.
equipment continues to function.
Installed spare components within an equipment item. Work environments.
Redundant equipment and subsystems.
Simplicity of design and presence of weak points.

Factors Driven by Maintenance Decisions


Preventive maintenance based on failure-trend data How maintenance tasks are detailed, developed, and
analysis. presented to the maintenance technician.
Trend diagnoses and inspection of equipment conditions Quality of the system of maintenance procedures.
to anticipate maintenance needs.
Quality of maintenance tasks (including inspections). The probability of human, material, and facility resources
being available to maintenance tasks.
Skills applied to maintenance tasks. Training programs.
Management, supervision, and organizational
effectiveness.
Durability of handling, support, and test equipment.
Factors Driven by Operations Decisions
Use of equipment relative to its rated capacity. Organizational effectiveness as a factor in the
troubleshooting process.
How spares are incorporated in normal process operation. Organizational effectiveness and procedures to ready
equipment for maintenance and startup.
Shutdown and Startup Procedures
(Availability Engineering and Management, Richard G. Lamb)

Achievable availability is the result of several factors: race course. It could be done, but you would
never win the race.
• Plant hard design determines the shape and
• Trading off scheduled maintenance for
location of the Aa curve. Therefore, this
design establishes the possible achievable unscheduled maintenance results in a climb
back up the availability curve to the left. A
availability.
nearly linear increase in availability occurs
• Maintenance strategies determine the plant’s until you reach the point where unscheduled
location on the Aa curve. Therefore, these maintenance due to breakdowns takes away
strategies establish the actual achieved from availability gains. Operating farther to
availability. the left places the equipment under more
stress and increases organizational chaos.
• The right extreme of the Aa curve represents
100 percent scheduled maintenance. There • After reaching the left of the peak Aa,
are no surprises, because all maintenance is further reductions in scheduled maintenance
performed during a scheduled maintenance become poor strategies.
period. Availability is well below optimum.
This extreme can be compared to coming
into the pits during every lap of a race to
ensure that you have no breakdowns on the

Bill Keeter – Page 3 of 14


Managing Availability for Improved Bottom-Line Results

Figure 2. Optimal Availability/Cost

Dollars
Achievable Availability (Aa)
Availability (Revenue) Costs & Income

Loss Income Loss

Costs (Capital & Active Repair)

Hour
Degree of Scheduled Maintenance

The cost curve represents strategic decisions to invest The shape and location of the operational availability
large amounts of capital up front to increase Aa curve are determined by the level of maintenance
through hard design, or to spend operating dollars to operation resources and organizational effectives.
increase Aa through more intensive maintenance Resources and organizational effectiveness have upper
strategies. These decisions are driven by many factors, bounds above which additional spending will not yield
such as the need to get a product to market quickly, better results. At that point, achievable availability
the availability of capital, and the operating mentality must be increased to give Ao room to move upward.
of the company. Aa can be increased by new maintenance strategies,
provided that the plant is not operating at the peak of
The availability/cost curve relationship highlights the the Aa curve. Capital investment is required to move
fact that availability is a proxy of revenues. At some the Aa curve upward if the plant is operating on the
point of either extreme of the cost curve or the peak.
availability curve, the cost of availability will exceed
the income it allows. Without availability This is an important point. Without availability
management, operating beyond those intersections can engineering and management, it is easy to
occur without management’s awareness; normal unknowingly spend beyond the point of maximum
accounting practices and other maintenance return. This may occur when plant performance falls
performance indicators cannot easily reveal this short of management’s desired productive capacity.
practice. Management tries to achieve gains with increased
stress on maintenance support. However, the
The difference between achievable and operational operational availability curve has already been
availability is the inclusion of maintenance support. unknowingly forced against the achievable availability
Achievable availability assumes that resources are 100 curve. The result is throwing good money after bad.
percent available and no administrative delays occur Spending is in the loss zone to the right of the
in their application. Therefore, maximum operational intersection of the achievable availability and cost
availability theoretically goes to achievable curves.
availability. In reality, every human endeavor has a
natural upper limit of obtainable perfection that
prevents Ao from reaching Aa.

Bill Keeter – Page 4 of 14


Managing Availability for Improved Bottom-Line Results

Reliability in Serial and Parallel Fully


Determining Achievable Availability Redundant Systems
for an Existing Facility It is important to note the reliability implications of
Few physical asset managers have had the luxury of the two types of systems presented in Figures 3 and 4.
being an integral part of the design phase of their Serial systems are inherently unreliable. The failure of
physical plant. Therefore, this section of the paper is a single element in the system results in a stoppage of
dedicated to analyzing the current physical plant to the overall system. Fully redundant parallel systems
determine its achievable availability. are inherently reliable. The system stops only if all the
redundant systems fail at the same time. Redundancy
Determining achievable availability is a four-step is an important tool in improving overall system
process: reliability. See Improving Machinery Reliability, by
Heinz P. Bloch, for a more complete discussion.
1. Build a reliability block diagram (RBD) of
the plant’s critical systems. Refining the RBD
– Use publicly available reliability data All complex machines are built from the same few
for failures. Using plant data skews the basic machine elements of couplings, bearings, gears,
results based on plant organizational motors, belts, and so on. The RBD is refined by
effectiveness. breaking down the top-level RBD into several RBDs
– Use plant data or works estimation that represent each top-level system (see Figures 5 to
techniques to determine mean time to 7).
repair. Again, using plant data skews
the results based on plant Obtaining Failure and Repair Data
organizational effectiveness. After the RBDs are built, failure and repair data must
be obtained for use in availability simulations.
2. Determine logistical delays created by plant
Obtaining these data is a time-consuming task. The
hard design
desired degree of certainty dictates the level of effort
– To/From shops. required for this stage of building the model. It is
– To/From stores. important to remember that this is not an exact
science. Perfection is not required. You need only be
– Accessing equipment. better than your toughest competition.
3. Add in scheduled maintenance downtime for
the chosen preventive maintenance strategy. There are many sources for failure data. This is by no
means an exhaustive list.Binomial and Weibull
4. Perform availability simulations. distributions typically are used to present failure data
for modeling purposes. Most availability simulators
The scope of the analysis is determined by resources, accept either type of data.
time, and the desired quality of the result.
Obtaining repair data is a much more difficult task.
Building the Reliability Block Repair data is typically not available anywhere in
tabular form. Repair times are very dependent on the
Diagram (RBD) configuration of the equipment and the plant.
The reliability block diagram is a graphical
Equipment with a great deal of guarding and with
representation of the plant systems, subsystems, and
parts located in tight spots requires much longer repair
components arranged a way that reflects equipment
times than equipment with little guarding and plenty
interdependence (see Figures 3 and 4). The RBD is the
of space in which to work. The two primary methods
cornerstone of the availability model because it shows
of obtaining repair time data are analyzing current
how failure in a plant element affects process uptime.
plant data and using works estimation systems such as
MOST ® to estimate times. Each method has its own
set of difficulties.

Bill Keeter – Page 5 of 14


Managing Availability for Improved Bottom-Line Results

Table 2. Sources of Failure Data


Source Data Available
Reliability Analysis Center Electronic Parts Reliability Data – EPRD
Non Electronic Parts Reliability Data – NPRD
Available in print and software versions.

Paul Barringer’s Web site: www.barringer1.com Weibull data for many components plus links to other
available data and reliability Web sites.

Improving Machinery Reliability (Practical Machinery Table of equipment failure data plus practical information on
Management for Process Plants, Volume 1). Heinz P. Bloch, improving equipment and system reliability.
ISBN: 087201455X.

Plant data Failure data depends on the robustness of the data-collection


system. Using plant data skews the analysis by including plant
organizational effectiveness.

Figure 3. Top-Level Reliability Diagram of a Serial System

Figure 4. Top-Level Reliability Diagram of a Parallel System

Bill Keeter – Page 6 of 14


Managing Availability for Improved Bottom-Line Results

Figure 5. System-Level RBD of a Printing Deck

Figure 6. Subsystem-Level RBD of an Inking System

Figure 7. Component-Level RBD of a Doctoring Subsystem

Bill Keeter – Page 7 of 14


Managing Availability for Improved Bottom-Line Results

Table 3. Sources of Repair Data


Method Advantages Disadvantages
Analyzing Plant Data • Usually does not require special • Data may be unreliable.
training. • Data is affected by organizational
• Data is usually available in plants effectiveness.
that have mature maintenance
reliability programs.

Works Estimation Systems • Eliminate organizational • Require training on the system used.
effectiveness as a factor. • Require much time to analyze the
• Provide a good standard against equipment and break repairs into tasks.
which to judge actual achieved
repair times.
• Provides detailed work steps and
procedures.

Identifying and Removing Process maintenance and operating procedures. By making


changes in the availability model the engineers can
Bottlenecks analyze the CBR of changes in strategy, design, and
operating parameters and make those changes which
Availability is a proxy for revenue and throughput. optimize capacity and create the lowest life cycle costs
The implication therefore, is that availability models for the plant.
can be used to find process bottlenecks created by
equipment issues. This is in fact the case. Organizational Implications
During the design phase the availability model can be
The need to understand and manage the top-level
used to pinpoint changes in equipment design that will factors that affect availability and to model and
increase plant throughput. The availability model understand the achievable availability of a plant has
enables the design engineer to make decisions about important implications for the shape of the
redundancy levels, plant access, and equipment maintenance and engineering organization. The typical
specifications based on their impact to overall
organization does not have the necessary resources to
throughput and the cost-benefit ratio (CBR) of the accomplish these objectives. Industrial engineering
changes. and reliability engineering functions are required.
During the operating life of the plant the reliability Figures 8 and 9 illustrate the functional makeup of a
engineer and the process engineer can work together
typical maintenance organization versus the functional
using the availability model and Weibull Analysis to makeup of an Availability Management driven
ferret out process bottlenecks created by poor organization.
maintenance strategies, poor initial design, and poor

Bill Keeter – Page 8 of 14


Managing Availability for Improved Bottom-Line Results

Figure 8. Typical Maintenance Organization

Typical Maintenance Organization

Figure 9. New Organization

New Skill Sets

Bill Keeter – Page 9 of 14


Managing Availability for Improved Bottom-Line Results

• Minimize the number and length of scheduled


outages to drive Aa closer to Ai.
Closing the Gaps • Minimize the number and length of unscheduled
Natural gaps exist between Ai and Aa and Aa and Ao.
outages to drive Ao closer to Aa.
Closing these gaps in a cost-effective way makes the
plant more successful. Closing the gaps requires a
thorough understanding of the top-level factors that Minimizing the Number and Length
determine availability and finding ways to improve in of Scheduled Outages
each aspect of those factors. The goal is to select The number and length of scheduled outages can be
strategies that … decreased by making operational and non-capital
equipment improvements:

Improve Maintenance Operations


Optimize the Preventive/Predictive Maintenance Analyze failure data to target specific equipment for
System specific tasks.

Analyze equipment using Reliability Centered


Maintenance techniques to determine the best PM/PdM
tasks to perform.

Use Predictive Maintenance Techniques Perform Vibration Analysis


o Monitor new installations for minimum
vibration
o Monitor existing installations for overall
vibration level, signatures, and trends
o Monitor repaired equipment to insure that
repairs were done properly.

Use Thermography
o Monitor Electrical Equipment
o Monitor Like Mechanical Equipment for
Temperature Differences

Perform Lubricant Analysis


o Analyze incoming lubricants
o Track trends

Improve Outage Planning & Scheduling Use Project Planning Techniques


o Gantt Charts
o CPM
o Reverse Planning

Ensure Good Planning for Every Job


o Parts Staged
o Good Written Procedures
o Adequate Resources

Bill Keeter – Page 10 of 14


Managing Availability for Improved Bottom-Line Results

Improve Equipment
Modify equipment to allow for accomplishing PM’s on Lubrication
uptime Belt checks
Etc.
Modify equipment for easier access Quick-release guards
Open space around equipment

Minimizing the Number and Length maintenance techniques and making non-capital
equipment modifications:
of Unscheduled Outages
The number and length of unscheduled outages or
breakdowns can be decreased by using precision

Improve Maintenance Operations


Use predictive maintenance techniques Vibration analysis
Thermography
Lubricant analysis
Failure trend data

Manage spare parts Kanban


Poke-a-Yoke
Failure trend analysis
Storage standards
Repair standards for repairables
Remote spares locations
PM procedures for spares

Manage lubricants Lubricant list


Lubrication routes
Proper storage
Ensure clean lubricant of correct type in correct amount at
correct spot

Manage failures Use “canned procedures.”


Be prepared.
Analyze for root cause.
Physical root
Human root
Organizational root
Train Maintenance personnel
o Precision installation and repair techniques
o Equipment monitoring techniques
o Failure analysis
o Importance of being proactive
o Cost of failures
o Business goals
Front-line supervision and operators
o Proper equipment operation and its relationship
to availability
o Their role in achieving availability goals
o What to clean and how to clean it
o Equipment monitoring techniques
o Importance of being proactive
o Cost of failures
o Business goals

Bill Keeter – Page 11 of 14


Managing Availability for Improved Bottom-Line Results

Improve Equipment Capital Improvements for Increasing


Quick-release guarding Availability
Open space After achievable availability is optimized by
Better replacement parts improving maintenance operations and making non-
capital equipment modifications, the only recourse is
Further increases in availability may be obtained only to increase availability by capital investment in the
by capital investment to increase inherent availability plant or by capital investment in the equipment to
and achievable availability. increase inherent availability.

Increasing Achievable Availability


Modify surroundings Add space around equipment for easier access.
Improve ingress and egress.

Modify shops Relocate closer to equipment.


Improve shop and support equipment.
o Better cranes
o Better tools
o Better technology
Improve layout
Modify stores Relocate closer to equipment.
Improve storage equipment.
Improve stores’ management software.
Provide for controlled remote stores

Increasing Inherent Availability


Upgrade equipment Match equipment to production need.
Improve control system and embed troubleshooting tools
Modify equipment Reduce part count.
Modify guarding.
Modify lubricant delivery system.
Add redundancy

performance measure. Business decisions that either


Matching Availability Goals to enhance or impair availability are made every day at
every level of the organization. Availability goals
Annual Business Need must be reviewed and managed the same as any other
No business operates in a static environment. business goals because of their sensitivity to available
Availability goals that are appropriate today may not capital and operating funds. Figure 10 shows typical
be appropriate next year, next month, next week, or inputs and outputs of the maintenance process.
even tomorrow. Equipment availability is as sensitive
to the vagaries of the business climate as any other key

Bill Keeter – Page 12 of 14


Managing Availability for Improved Bottom-Line Results

Figure 10. The Maintenance Process

Outputs
Inputs Availability
Manpower Maintenance Cost/Unit of Output
Materials Process Percent of CRV
Equipment MTBF
Contractors MTTR

The business situation determines whether inputs or


outputs are optimized. During times of overcapacity, References
the business is cost constrained. The input side of the
process must be optimized to reduce costs. During Availability Engineering & Management for
times of undercapacity, business is output constrained.
Manufacturing Plant Performance. Richard G. Lamb,
The output side of the process must be optimized to Prentice Hall Publishers, ISBN: 0-13-324112-2.
increase business output. The important point to
remember is that at best, business output will remain Improving Machinery Reliability (Practical
constant during periods in which process inputs are Machinery Management for Process Plants, Volume
being optimized. The longer inputs are constrained,
1). Heinz P. Bloch, Gulf Publishing Company, ISBN:
the more negative the effect on the outputs. 087201455X.

Conclusion The Reliability Handbook From downtime to uptime –


in no time. John D. Campbell, editor; Plant
Using Availability Modeling and Simulation to Engineering and Maintenance; Volume 23, Issue 6.
engineer availability into a manufacturing facility by
laying out equipment and facilities for optimum
reliability and maintainability, installing reliable
Acknowledgements
equipment, and engineering maintenance procedures Thanks go to:
prior to startup will give an organization its best
• Perry Lovelace, Chief Associate, Nepenthe
chance of having a reliable plant that is optimally
Institute, 57 Don Jose Loop, Santa Fe, New
available from day one. Using Availability Modeling
Mexico for content advice and moral
and Simulation to continually monitor operational
support
needs, improve maintenance and operating
• My editor Fran Blauw, Owner, See Spot
procedures, and to thoroughly understand the three
Run, Indianapolis, IN.
subtypes of availability and the plants current status in
relationship to Achievable Availability will help
promote long term success by improving bottom-line
results throughout the life of the plant.

ARMS Reliability Engineers has successfully used


AvSim Plus® to and RCMCost® by Isograph, LTD to
model, analyze, and optimize facility designs and
maintenance strategies to help improve capacity and
reduce costs in a variety of industries. To find out
more about ARMS Reliability Engineers visit
www.reliability.com.au.

Bill Keeter – Page 13 of 14


Managing Availability for Improved Bottom-Line Results

Contact Information
Australia
Mick Drew, Director
ARMS Reliability Engineers
PO Box 501
Ocean Grove
Victoria 3226
Phone: +61 (03) 5255 5357
mdrew@reliability.com.au

USA
Bill Keeter, President
ARMS Reliability Engineers – USA, LLC
8450 N. Devonshire Woods Place
Phone: 812-535-1445
bkeeter@armsreliabilityusa.com

Canada
John Byers
John-byers@shaw.ca

Bill Keeter – Page 14 of 14

You might also like