Professional Documents
Culture Documents
2
3
4
CDI
UNIT TRAINING MANUAL
5
CONTENTS
INTRODUCTION
Pulverizesd coal injection (PCI) is a process that involves injecting large volumes of
fine coal particles into the Raceway of a Blast Furnace. This provides not only a
supplemental carbon source but also a speeds up the production of liquid iron
besides reducing the need for Metallurgical coke for reactions in the Blast
Furnace. The desire to move away from the production of the Metallurgical coke
with its inherent environmental problems has motivated the use of Pulverized
coal injection in the Blast Furnace.
The PCI technology is based on simple concept of carrying the finely grounded
(pulverized) dried coal by a conveying gas (normally nitrogen) to the Blast Furnace
where it is distributed to different tuyers and injected through a lance in the blow
pipe. In the blow pipe it is mixed with hot blast and then supplied to the Blast
Furnace in Raceway. The raceway propagates coal and coke combustion and
melts the solid iron ore, releasing molten iron. Durgapur Steel Plant installed its
PCI (CDI) system in the year 2008 and started injection in Blast Furnace # 3 & 4.
After the initial period of stabilization (2008-09) the system has stabilised and
performing as per the expectation. Durgapur Steel Plant also started injecting fine
coal in Blast Furnace # 2 from 15.09.2014.
7
3. PROCESS –
I. Handling of Raw Coal.
II. Grinding of Raw Coal.
III. Injection of Fine Coal.
TECHNICAL DATA
1. GRINDING MILL :
CAPACITY – 35 T/HR
TYPE – ROLLER
DIAMETER – 2670 MM
LENGTH – 7561 MM
3. BAG FILTER :
NO. OF BAGS – 1176
4. MILL ID FAN :
FULL PRESSURE – 12220 Pa (0.1222 Kg/cm²)
R.P.M – 1460
TYPE – CENTRIFUGAL
7. INJECTION VESSELS :
NO. OF INJECTION VESSELS – 4
PERSONAL SAFETY
1. Always wear safety helmet and safety shoes outside control room.
7. Always move in a group of two along with gas monitor and walkie
talkie in furnace area.
15
EQUIPMENT SAFETY
1. Never allow any unauthorised person to operate the controls.
4. Always remain alert for taking necessary action for various alarms
given out by instruments.
5. Make sure that the air conditioning system is working to facilitate the
PLC operation.
2. Ensure that the two centrifugal compressors and the new booster
compressor are running smoothly.
3. Ensure that the three nitrogen distribution vessels at CDI : D01, D02
& DO3 have reached their set point pressure (6.0, 7.5 & 7.5 Kg/cm2
respectively).
10. Start ID FAN. Open the ID FAN inlet valve approx 25%.Close the
chimney valve PV103. Regulate the inlet valve FC104 to make the
system in proper pressure and flow rate. Mill negative pressure P104
should be approximately -160 mmWC.
vi) Drop the mill roller down after a delay and set the loading pressure
(approx. 70 bar).
12. Regulate the BF gas flow rate in HGG, Raise the temperature of
HGG. Control the temperature of Mill outlet (Bag Filter inlet) to be 80 –
85 °C and avoid too high temperature to damage the Bag Filter.
13. Control the mill inlet temperature T104 and make the same to be
250 – 280 °C. Regulate the coal feed rate of the coal feeder G03 to be
approx. 30 T/Hr and mill DP PD101 to be approx. 250 – 280 mmWC.
Ensure the mill outlet temperature is 80 – 85 °C. Observe the mill
vibration range and hard impurity discharging (mill rejection) status.
22
14. Monitor CDI chimney for any coal emission during Grinding.
15. Collect the fine coal sample. Measure SIZE, MOISTURE , VM and
ASH content of the sample. Control the moisture content of the fine
coal to be less than 1% and size of the fine coal to be less than 90
microns (more than 80%).
23
11. As the system temperature falls down, close the Mill Nitrogen
cooling valve PV1102.
13. Stop the Bag Filter and Vibrating Screen after 30 minutes delay.
INJECTION IN BF # 4
INJECTION VESSELS INVOLVED – VESSEL # 1 (T06A/1) and VESSEL # 2
(T06A/2).
Ensure there is sufficient Fine coal in the Fine coal silo. Depressurizing
valves of injection vessel # 1- PV115 and PV114 are open and pressure
in injection vessel is less than 0.2 kg/cm².
Ensure that the carrying Nitrogen to the Furnace is going through the
line of injection vessel # 1 i.e through PV118 and PV119 and flow of
Nitrogen through FC201 is Approx. 800 Nm³/Hr.
PROCEDURE
ii) Open Pressurizing valve PV113 and ensure that flow control valve
PC201 is 100% open.
iii) Open Fluidizing valve PV116 and control fluidizing flow rate as per
injection rate required.
iv) When Pressure of injection vessel is 2.8 kg/cm² - Open the injection
valve PV117.
vi) Note that pressure of injection vessel should be at least 1.1 kg/cm²
more than the Furnace Hot Blast Pressure.
27
PROCEDURE
1. Close the Depressurizing valves PV214 and PV215 of injection vessel
# 2.
2. Ensure that Pressurizing flow control valve PC202 is 100% open. Now
open Pressurizing valve PV213 and Open Fluidizing valve PV216
TROUBLE SHOOTING
COAL LIFTING SYSTEM :
TROUBLE CAUSES REMEDY
HIGH RISE BELT NOT EMERGENCY STOP PRESSED RELEASE EMERGENCY STOP
STARTING
TROUBLE SHOOTING
COAL GRINDING SYSTEM :
TROUBLE CAUSE REMEDY
G03 BELT NOT RUNNING BELT SWAY CALL MECHANICAL
VIBRO SCREEN TRIPPED BAG FILTER HOPPER JAM REPLACE THE SCREEN (CALL
MECHANICAL)
MOTOR FAULT CALL ELECTICAL
33
TROUBLE SHOOTING
COAL INJECTION SYSTEM
TROUBLE CAUSE REMEDY
nitrogen pressure low Booster compressor Start bypass line
down
Pneumatic Valve not Solonoid Valve
operating problem
Low pressure of
nitorgen