PLANO, TEXAS
2019-06-28
PROJECT MANUAL
TABLE OF CONTENTS
LEGEND
ISSUES
HKS 22514.000
TABLE OF CONTENTS PAGE - 1
2019-06-28
LEGACY WEST JPMORGAN CHASE - PHASE 2
PLANO, TEXAS
HKS 22514.000
TABLE OF CONTENTS PAGE - 2
2019-06-28
LEGACY WEST JPMORGAN CHASE - PHASE 2
PLANO, TEXAS
DIVISION 03 - CONCRETE
DIVISION 04 - MASONRY
DIVISION 05 – METALS
HKS 22514.000
TABLE OF CONTENTS PAGE - 3
2019-06-28
LEGACY WEST JPMORGAN CHASE - PHASE 2
PLANO, TEXAS
DIVISION 08 - OPENINGS
HKS 22514.000
TABLE OF CONTENTS PAGE - 4
2019-06-28
LEGACY WEST JPMORGAN CHASE - PHASE 2
PLANO, TEXAS
DIVISION 09 - FINISHES
DIVISION 10 - SPECIALTIES
DIVISION 11 - EQUIPMENT
DIVISION 12 - FURNISHINGS
HKS 22514.000
TABLE OF CONTENTS PAGE - 5
2019-06-28
LEGACY WEST JPMORGAN CHASE - PHASE 2
PLANO, TEXAS
DIVISION 22 – PLUMBING
2019-06-28 22 0500 Common Work Results For Plumbing SHG
2019-06-28 22 0513 Common Motor Requirements For Plumbing SHG
Equipment
2019-06-28 22 0516 Expansion Fittings And Loops For Plumbing Piping SHG
2019-06-28 22 0517 Sleeves And Sleeve Seals For Plumbing Piping SHG
2019-06-28 22 0518 Escutcheons For Plumbing Piping SHG
2019-06-28 22 0519 Meters And Gages For Plumbing Piping SHG
2019-06-28 22 0523 General-duty Valves For Plumbing Piping SHG
2019-06-28 22 0529 Hangers And Supports For Plumbing Piping And SHG
Equipment
2019-06-28 22 0533 Heat Tracing For Plumbing Piping SHG
HKS 22514.000
TABLE OF CONTENTS PAGE - 6
2019-06-28
LEGACY WEST JPMORGAN CHASE - PHASE 2
PLANO, TEXAS
HKS 22514.000
TABLE OF CONTENTS PAGE - 7
2019-06-28
LEGACY WEST JPMORGAN CHASE - PHASE 2
PLANO, TEXAS
DIVISION 26 – ELECTRICAL
2019-06-28 26 0500.1 Common Work Results For Electrical SHG
2019-06-28 26 0519 Low-voltage Electrical Power Conductors And Cables SHG
2019-06-28 26 0526 Grounding And Bonding For Electrical Systems SHG
2019-06-28 26 0529 Hangers And Supports For Electrical Systems SHG
2019-06-28 26 0533 Raceway and Boxes For Electrical Systems SHG
2019-06-28 26 0536 Cable Trays For Electrical Systems SHG
2019-06-28 26 0543 Underground Ducts And Raceways For Electrical SHG
Systems
2019-06-28 26 0544 Sleeves And Sleeve Seals For Electrical Raceways SHG
and Cabling
2019-06-28 26 0553 Identification For Electrical Systems SHG
2019-06-28 26 0572 Overcurrent Protective Device Short Circuit Study SHG
2019-06-28 26 0573 Overcurrent Protective Device Coordination Study SHG
2019-06-28 26 0574 Overcurrent Protective Device Arc-Flash Study SHG
2019-06-28 26 0923 Lighting Control Devices SHG
2019-06-28 26 0943 Network Lighting Controls SHG
2019-06-28 26 1200 Medium-voltage Transformers SHG
2019-06-28 26 2200 Low-voltage Transformers SHG
2019-06-28 26 2300 Low-voltage Switchgear SHG
HKS 22514.000
TABLE OF CONTENTS PAGE - 8
2019-06-28
LEGACY WEST JPMORGAN CHASE - PHASE 2
PLANO, TEXAS
DIVISION 27 – COMMUNICATIONS
DIVISION 31 - EARTHWORK
HKS 22514.000
TABLE OF CONTENTS PAGE - 9
2019-06-28
LEGACY WEST JPMORGAN CHASE - PHASE 2
PLANO, TEXAS
DIVISION 33 – UTILITIES
SUPPLEMENTAL INFORMATION
HKS 22514.000
TABLE OF CONTENTS PAGE - 10
2019-06-28
CRITICAL TECHNOLOGY SPACE &
INFRASTRUCTURE CABLING DESIGN
STANDARD
Version 1.0.2
July 1, 2018
1
TABLE OF CONTENTS
FOREWORD ........................................................................................................... 4
SECTION 01 00 00 – GENERAL REQUIREMENTS ................................................... 5
CRITICAL TECHNOLOGY SPACES .......................................................................... 5
Terminology ....................................................................................................... 27
Glossary ............................................................................................................. 27
GENERAL NOTES ................................................................................................ 29
Compliance with this Standard ......................................................................... 29
Copper and Fiber Systems ............................................................................... 30
Complete System ........................................................................................... 30
Owner Preferred Product Pricing and Delivery .................................................... 30
Subcontractors .............................................................................................. 31
Legacy Infrastructures .................................................................................... 31
Contractor personnel ...................................................................................... 32
Contractor notice to proceed............................................................................ 32
Contractor communication ............................................................................... 32
Contractor advertising .................................................................................... 32
Contractor badging ......................................................................................... 32
Omissions ..................................................................................................... 32
Interpretation ................................................................................................ 33
Equivalents ................................................................................................... 33
Substitutions ................................................................................................. 33
New Materials ................................................................................................ 33
General Cabling ............................................................................................. 33
Cable Protection ............................................................................................. 33
Quality Control............................................................................................... 34
Change Controls ............................................................................................ 34
Preferred Contractor List ................................................................................. 34
Site Safety .................................................................................................... 34
Material Interpretation .................................................................................... 34
Project Schedule ............................................................................................ 34
Installation .................................................................................................... 35
Construction Change Directive ......................................................................... 35
Testing ......................................................................................................... 35
Protection of Property ..................................................................................... 35
Partial Occupancy ........................................................................................... 36
Environmental Quality .................................................................................... 36
Cleaning and Trash ......................................................................................... 36
Storage and Staging ....................................................................................... 36
Work Schedule ............................................................................................... 36
Work Hours ................................................................................................... 36
Activity Tracking ............................................................................................ 37
Final authority ............................................................................................... 37
References .................................................................................................... 37
ACCEPTANCE ................................................................................................. 38
Acceptance Inspections ................................................................................... 38
Fault Correction Procedure .............................................................................. 39
Room Turnover and Substantial Completion ...................................................... 39
As-builts ....................................................................................................... 39
2
Test results ................................................................................................... 39
Transfer of Infrastructure Ownership ................................................................ 39
Project Close-out Documentation ..................................................................... 39
SECTION 01 45 00 – QUALITY CONTROL ............................................................. 40
SECTION 01 45 23 ......................................................................................... 40
TESTING ....................................................................................................... 40
SECTION 01 78 36 SUPPORT AND WARRANTY .................................................. 46
SECTION 21 00 00 – FIRE SUPPRESSION............................................................ 47
SECTION 21 07 16 FIRESTOP ......................................................................... 47
SECTION 27 00 00 - COMMUNICATIONS ............................................................. 49
SECTION 27 05 26 GROUNDING (EARTHING) INFRASTRUCTURE ........................ 49
SECTION 27 05 28.29 NON-CONTINUOUS CABLE SUPPORTS .............................. 51
SECTION 27 05 28.30 SLEEVES AND SLOTS ..................................................... 53
SECTION 27 05 28.31 GRIPS .......................................................................... 55
SECTION 27 05 28.32 POKE THRU .................................................................. 56
SECTION 27 05 28.33 CONDUITS AND PULL BOXES .......................................... 57
SECTION 27 05 28.34 INNERDUCT .................................................................. 58
Table 1 – Soft Duct Sizing Guideline ................................................................. 59
SECTION 27 05 28.35 ACCESS FLOOR ............................................................. 62
SECTION 27 05 53 IDENTIFICATION................................................................ 63
SECTION 27 11 23 ......................................................................................... 66
RELAY RACKS, NETWORK CABINETS, LADDER RACK, CABLE TRAY ....................... 66
SECTION 27 13 14 COPPER BACKBONE............................................................ 71
SECTION 27 13 24 MULTIMODE FIBER BACKBONE ............................................ 73
Table 2 – Multimode Fiber Cable Grading Schedule – Corporate ........................... 74
SECTION 27 13 25 SINGLE-MODE FIBER BACKBONE ......................................... 76
SECTION 27 13 34 DS-3 COAXIAL BACKBONE .................................................. 79
Table 3 – Coaxial Cable Grading Schedule ......................................................... 79
SECTION 27 15 00.19 CATEGORY 6 HORIZONTAL ............................................. 81
SECTION 27 21 33 CATEGORY 6A WIRELESS ACCESS POINT AND SECURITY
CAMERAS ................................................................................................. 84
SECTION 33 82 53 CABLE PULLING LUBRICANTS .............................................. 87
APPENDIX A – WTS DEFINITION AND CHECKLISTS FOR MER & TR ACCEPTANCE ........ 89
APPENDIX B – GLOBAL STANDARD MATRIX FOR CRITICAL TECHNOLOGY SPACE BUILDS
.......................................................................................................................... 90
APPENDIX C – FACEPLATE CONFIGURATIONS ........................................................ 91
APPENDIX D – GENERAL IDENTIFICATION STANDARD ............................................ 92
APPENDIX E – MATERIALS ................................................................................... 93
APPENDIX F – WTS DATA CLEAN SPECIFICATION & CLEANING POLICY FOR MER’s AND
TR’S .................................................................................................................... 94
APPENDIX G – WTS BIDDER PRICING FORM .......................................................... 98
APPENDIX H – WTS Cable Design and Engineering Installation Standard - WAP .......... 99
APPENDIX I – WTS Cable Design and Engineering Patching Standard ...................... 100
APPENDIX J – MER, TR AnD Technology Lab Security Design Standard .................... 101
APPENDIX K – EXCEPTION APPROVAL ................................................................. 102
APPENDIX L ................................................................................................. 103
3
FOREWORD
(This foreword is not part of this Standard)
Approval of Standard
These Standards were approved by the JPMorgan Chase & Co. Global WTS (Workplace Technology
Services) Cable Design and Engineering and the Remote Site Operations (RSO) teams. The teams
review and update these Standards on an as-needed basis in order to create a consistent technology
framework in JPMC properties. Suggested updates to be considered for the next revision should be sent
to any member of the WTS Cable Design and Engineering and/or the Remote Site Operations team.
Background
The Global WTS organization is comprised of many groups that encompass the JPMC technology
delivery from a Design / Build / Operate perspective. The varied perspectives provide enrichment to this
Standard. The Design group focuses on the engineering and design of structured cabling and support
infrastructure for all of our Technology Spaces (e.g., Main Equipment Rooms, Telecommunications
Rooms, Co-Lo facilities, etc.). The Build group provides the Project Management services for our Global
Technology Infrastructure (GTI) Global Real Estate (GRE) and various Line of Business (LOB) projects.
The Operate group provides the day-to-day control and operations for all Technology Spaces.
This document must be used as the Standard for; designing the structured cabling infrastructure, and
planning Critical Technology Spaces (CTS). Its purpose is to define the Standard baseline design and
utilization criteria for; structured cabling infrastructure designs, and three types of Critical Technology
Spaces (CTS) in order to make them easier to specify, utilize, and manage. To promote wide
understanding it is built upon a foundation of recognized industry Standards and best practices. This
document is not intended to replace the specific needs of those planning equipment for CTS areas or
design coordination. It shall be used in conjunction with those needs and proper design coordination.
If an element of this Standard cannot be met during the design and planning phases; the group
accountable to meet the requirement shall submit a request for exception approval prior to proceeding
with a deviation from this Standard. The request must be submitted via EURC (the End User Request
Center is an internal JPMC application) using the service titled 'Exception Approval - GTI-WTS Global
Standard for Critical Technology Space Builds'. The EURC request will be routed to the exception
approvers who will review the request, approve or deny, and document any exceptions for historical
record of the sites configuration. Due to varying business requirements and Business Continuity Plans
(BCP) affecting uptime needs, LOB's must be consulted for their uptime requirement to determine if the
level of resiliency needed is greater than the base requirement. A need for enhanced resiliency may also
inform other components of the design (i.e. risers, utility feeds, etc.). All appendices are normative and
are considered to be a mandatory part of this Standard.
4
SECTION 01 00 00 – GENERAL REQUIREMENTS
This document is intended to provide the information necessary to allow the construction team to plan
and implement telecommunications cabling infrastructures and to ensure that all new installations and
renovations are uniform and consistent with company-wide Standards. This document identifies the
telecommunications infrastructure requirements for Corporate MER, TR, and Co-Lo facilities.
It is envisioned that not all buildings will require the complete range of services and telecommunications
infrastructure described in this document. The exact solution that suits each particular building will be
defined at the commencement of each project by the project team.
CRITICAL TECHNOLOGY SPACES
PART 1 – GENERAL
1.1 PURPOSE
A. This Standard for Critical Technology Spaces and Infrastructure Cabling Design document is
intended as a standard. Its purpose is to define the baseline design and utilization criteria for three
types of Critical Technology Spaces (CTS) in order to make them easier to specify, utilize, and
manage, and to state the cabling infrastructure standards associated with these spaces. To
promote wide understanding it is built upon a foundation of recognized industry standards and best
practices.
This document must be used as a tool to plan Critical Technology Spaces based on WTS
operational standards. This document is not intended to replace the specific needs of those
planning equipment for CTS areas or associated design coordination. It must be used in
conjunction with needs assessment and proper design coordination.
If a standard cannot be met during the planning and design phases, the group accountable to meet
the requirements must submit a request for exception approval prior to proceeding with a deviation
from the standard. The request must be submitted via EURC (the End User Request Center is an
internal JPMC application) using the service titled “Exception Approval – GTI – WTS Global
Standard for Critical Technology Space Builds” (See Appendix K). The EURC request will be routed
to the exception approvers who will review the request, approve or deny, and document any
exceptions for historical record of the site’s configuration.
Due to varying business requirements and Business Continuity Plans (BCP) affecting uptime
needs, Lines of Business (LOB) must be consulted for their uptime requirement to determine if
the level of resiliency needed is greater than the base requirement. A need for enhanced
resiliency may also inform other components of power and cooling systems (i.e. risers, utility
feeds, etc.).
The three types of critical technology spaces, Main Equipment Room, Telecommunications Room, and Co-
location Space are defined below. Note that while the Main Equipment Room and Co-location Space are
not data centers, they may exhibit some characteristics of a data center, either through defined functional
requirements or through requirements set forth in this document.
5
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
MER provides access to internal and external services and applications via WAN and PSTN.
Associated functions within the MER include:
• Aggregation point for backbone cabling to TRs
• Network Core access and connectivity to Data Centers
• Telecommunications equipment location for WAN vendors
• Local building/campus PBX, in-building cellular, Wi-Fi, etc.
• Limited amount of server/computing equipment – only equipment with technical adjacency
requirements. Limited amount of server/computing equipment – only equipment with
technical adjacency requirements that have an approved RSO location waiver via the
Prime process.
• Vendor equipment specific to that floor, building or campus (e.g. analog/digital video
recording, etc.).
• Horizontal cable distribution from access switches to user locations when the MER is in
proximity to user space.
• Pre-connectorized cables
• Patch panels
• Racks
• Cabinets
6
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
1.3 TERMINOLOGY
A. The following terms identify an obligatory item: must, shall, will, is required, are required,
mandatory.
B. The following terms identify an optional item: can, may, should, preferably, prefers, desired,
desirable.
D. Regulation(s), Regulatory refer to requirements that may be legally binding, or that may be
imposed by a non-governmental authority.
E. NEC and NFPA 70 are used interchangeably to identify the National Electrical Code.
F. Authority Having Jurisdiction (“AHJ”) is as defined by Article 100 of the National Electrical Code
(NFPA 70), including the associated Fine Print (Informational) Note.
H. Access Provider is an entity, such as a Carrier, that provides physical connectivity into a building
for the delivery of ICT services. The services may be offered by an Access Provider itself or by
third parties using an Access Provider’s facilities.
A. All aspects of construction and installation must meet applicable local, state, and federal laws, as
well as any regulations specific to a site. Legally binding requirements must prevail if there are any
conflicts with requirements stated or implied in this document. The AHJ will be the arbiter in
situations where interpretation is necessary to clarify information, or to resolve conflicts involving
legally binding requirements.
B. Work safety must be in compliance with Public Law 91-596, Occupational Safety and Health Act
(OSHA). As applicable, requirements of the NFPA 101 Life Safety Code must be followed.
C. Codes, regulations, standards, and industry practices documents explicit to this Standard are
listed in SECTION 01 00 00, but they are not exhaustive. Even when not explicitly cited within this
document, there is an implied requirement of compliance with industry norms reflected in
recognized standards and practices, as well as requirements based in law.
D. Codes, regulations, standards, and industry practices documents change over time. Current
governing Codes and regulations at a site location, and the most recent edition of standards and
practices documents (including errata, annexes, and amendments) must be used at the time
facilities are designed and when they are utilized.
E. Although a number of standards and practices are cited in this document, ANSI/TIA-569
“Commercial Building Standard for Telecommunications Pathways” has both explicit and implicit
threads throughout.
F. Additionally influencing this standard are accepted industry practices documents such as those in
the NECA/BICSI-568 “Standard for Installing Commercial Building Communications Cabling”, and
the BICSI “Telecommunications Distribution Methods Manual (TDMM)”.
7
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
PART 3 – EXECUTION
3.1 ARCHITECTURAL
B. ROOM LOCATION
Applicability: See below
1. The location of MER, TR, and Co-location spaces must follow industry best practices, as well
as applicable ANSI/TIA-569 and ANSI/TIA-942 standards guidelines (including those in
associated informational annexes). Among these are:
2. For MER, TR and Co-locations:
a) Avoid locations that are restricted by building components, such as elevators, core, outside
walls, or other fixed building walls that limit expansion.
b) Avoid locations with large trunk ductwork, piping, or other items that cannot be relocated.
c) For the delivery of large equipment, location decisions should factor in the need for
accessibility.
d) Close proximity to backbone cabling pathways is desirable.
e) Never locate a room below grade, in flood zones, or near spaces that may present a threat
of water infiltration unless preventive measures against water infiltration are employed.
f) Components not related to the support of the room and its equipment (e.g. water supply
pipes, drain pipes, miscellaneous piping, ductwork, pneumatic tubing, etc.) must not be
installed in, pass through, or enter the room.
g) Rooms must be located away from sources of electromagnetic interference. Special
attention should be given to electrical power supply transformers, motors and generators,
x-ray equipment, radio or radar transmitters, and induction sealing devices.
h) Rooms must not be a pass through to other rooms, and rooms must not be located behind
other rooms that act as a pass through (e.g., MEP trades should not use rooms as a pass
through to other rooms, etc.).
i) Areas susceptible to heat gain from sunlight require mitigation to counter potentially
undesirable effects.
j) Rooms must not have any windows.
8
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
9
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
D. CEILING
Applicability: MER, TR, Co-location
1. Critical technology spaces must not have a suspended ceiling.
2. Height of the room from finished floor to the underside of the ceiling floor slab must be at least
3.05 m (10 ft).
3. Unobstructed ceiling height must be at least 2.74 m (9 ft), although at least 3.05 m (10 ft) is
desirable.
4. Exposed ceilings and sprayed on fireproofing in an exposed ceiling must be treated to mitigate
dust.
NOTE: The assumptions under which the minimum allowed ceiling height is based are that: a)
the space for cable pathways and other items above racks and cabinets will be adequate for
current and future needs; b) it allows adequate access for maintenance and other functions; c)
it meets the requirements of this document; d) the space allows for an efficient flow of return
air to air conditioning units. If any of these conditions is not true, then the minimum unobstructed
ceiling height must be increased.
E. WALLS
Applicability: See below
1. For MER and TR:
a) All walls must extend slab to slab and be at least 1 hour fire rated..
10
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
b) All walls must be treated to mitigate dust. Where no equipment is intended to be mounted,
drywall (wallboard, plasterboard) walls must be taped, spackled and sanded to a smooth
finish, and painted a light color to enhance room lighting.
c) All metal wire mesh cages (if required) must extend slab to slab.
2. For Co-location:
a) If the Co-location space is contained within a metal wire mesh cage, the space in the facility
in which the cage is contained must have at least 1 hour fire rated walls.
b) If the Co-location space has one or more slab to slab walls, then the walls must be at least
1 hour fire rated.
c) All metal wire mesh cages (if required) must extend slab to slab.
F. DOORS
Applicability: See below
Doors on MER and TR spaces must comply with the following requirements. Doors on Co-location
spaces must comply with these requirements as applicable to the space.
1. Swinging doors must be fire rated with a UL classification label, and have been tested compliant
with the UL10C standard. In no case must a door in a 1 hour fire rated wall have less than a 1
hour fire rating.
2. For all spaces the door size must be at least 0.91 m (3 ft) wide and 2.44 m (8 ft) high and not
have a center support.
3. A doorway must not have a sill.
4. Code permitting, swing doors must open outward.
5. Doors must automatically close.
6. Doors must be equipped with floor sweeps to contain air, minimize dust infiltration, and
minimize external noise.
7. The quantity of doors will be defined by Code and by ingress and egress requirements.
8. Spaces with multiple doors must have only one designated primary entrance/exit door.
Secondary doors must be used only as emergency exits (see Security – Room Access and
Appendix J).
9. All doors must have a lock (see Security – Room Access and Appendix J for additional
requirements for primary and secondary doors, including CARD Reader / PIN Pad).
G. LIGHTING
1. LIGHTING SOURCE, CONTROL, AND PROXIMITY
Applicability: MER, TR, Co-location
Lighting must:
a) Be controlled from occupancy sensors providing coverage throughout the space.
b) Not be on dimmer switches.
c) Not be on the same electrical panel as the ICT equipment.
d) Be kept at least 305 mm (12 in) away from cable pathways, racks, cabinets and equipment.
11
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
e) Be controlled by one or more switches located near the entrance door(s) to the room.
f) Be located in aisle ways and coordinated with cabinet and rack layout.
2. ILLUMINATION LEVEL
Applicability: MER, TR, Co-location
a) Per the ANSI/TIA-569 standard requirements, light intensity measured in the middle of rack
and cabinet aisles 0.91 m (3 ft) above the finished floor must be at least:
• 500 lux (50 foot-candles) in the horizontal plane
• 200 lux (20 foot-candles) in the vertical plane
3. EMERGENCY LIGHTING
Applicability: See below
a) For MER, TR, and Co-location: Sufficient emergency lighting and signs must be properly
placed such that an absence of primary lighting will not hamper emergency exit. These
must be compliant with Code or AHJ requirements. If no generator is present, lighting must
be on battery-backup.
b) For MER and Co-location: Lighting must be on the building backup generator. If no
generator is present, lighting must be on battery-backup.
H. PLYWOOD
Applicability: See below
1. For all spaces, as a minimum, plywood must be:
a) compliant with Codes
b) kiln dried (15% max. moisture)
c) 19 mm (¾”) thick A-C grade (mounted with best side facing the room), or FSC Certified
board
d) fastened securely to a wall
e) Either;
i. Fire rated (with a UL FR-S classification), or FSC Certified - covered with two coats of
white fire retardant paint on both sides and edges. For fire-rated plywood the
classification stamp must not be obscured.
And/Or;
ii. In accordance with the AHJ’s guidance.
2. For MER: At least two contiguous sheets of plywood 1.22 m (4 ft) wide and 2.43 m (8 ft) high
and beginning 153 mm (6 in) above the finished floor must be installed on a wall in a location
best suited for their use.
3. For TR: At least one sheet of plywood 1.22 m (4 ft) wide and 2.43 m (8 ft) high and beginning
153 mm (6 in) above the finished floor must be installed on a wall in a location best suited for
its use.
4. For Co-location: There is no requirement for plywood.
12
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
I. SIGNAGE
Applicability: See below
Spaces must be identified with a sign outside doorways. When applicable to the site, the location,
size, and other attributes of the sign must comply with requirements of the Americans with
Disabilities Act (ADA).
1. For MER and TR:
Room Naming Convention
• Building abbreviations should also come from GS&I
• Room Type should reflect Technology room definitions as identified in the space
classification document (TR for Telecommunication Room or MER for Main Equipment
Room)
• Identifier should be included if there are more than one TR located on the floor and can be
listed in Numbers, Letters, or Colors (i.e. “1, 2, A, B, Orange, Blue, etc.)
Updated signage should also accompany the activation of any new technology rooms. The
room signage should be in compliance with existing standards as provided by facilities. It
should not change the look and feel of the existing floor signage within the office space, but
should clearly indicate the room names in accordance with the GTI technology space
classification as illustrated below:
13
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
3. Additionally, for all spaces, secondary exit only doorways must have a sign:
• On the ingress side stating “No Entry – Emergency Exit Only”
• On the egress side stating Emergency Exit Only – Alarm Will Sound”
1. For TR: There are no storage and staging area requirements for TR’s, but a TR itself must not
be used for these functions.
2. For MER: A secure storage and staging room should be planned adjacent to the MER.
3. For Co-location: A secure storage and staging room should be planned in proximity to the co-
location room (cage).
14
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
D. Cameras must be placed both on the inside and the outside of the entrance door and any secondary
exits that the room might have.
E. All doors leading into the space must be monitored for immediate forced open and door held open
(longer than 60 seconds) alarms.
F. Access records from the Card Reader / PIN Pad will be the logging system. An adjunct or alternate
logging method is not required.
3.3 ELECTRICAL
A. ELECTRICAL POWER
1. UTILITY FEED
Applicability: See below
a) For MER and Co-location: These spaces require N+1 utility feeds, where N denotes the
number of feeds needed to satisfy the base requirements. Feeds must have diverse
routing into the facility.
b) For TR: Only a single utility feed is required.
2. GENERATOR
Applicability: See below
a) For MER and Co-location: The spaces which have been determined to need generators
will require generator backup in the event of utility feed failure. Only “N” generators are
required, where “N” denotes the minimum number needed to meet the base requirement.
Generators must activate automatically in response to a power failure, and the startup
delay must be well within the hold time of shorter duration uninterruptible power sources
(UPS) that respond to the initial failure.
b) For TR: UPS, generation, static transfer switches (STS), etc. should be provisioned when
required by the specific LOB’s resiliency, redundancy, and disaster recovery plans
(recommended groups typically requiring UPS, generation, and STS’s are trading floors,
call centers, and any other groups deemed critical requiring this additional resiliency).
15
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
iii. The power capacity of the uninterruptible power supply system must be sized to handle
the maximum expected equipment load.
iv. An uninterruptible power source system, and any of its components, may only be
housed within an MER or Co-location space if it is dedicated to serving that space.
Otherwise it must not be housed within these spaces. Additionally, it is recommended
(per ANSI/TIA-569) that a UPS with a rating over 100kVA not be located within an MER
or Co-location space.
v. UPS systems must not compromise required electrical system transient voltage surge
suppression (TVSS).
b) For TR:
Uninterruptible power is not a requirement for a TR. A TR may take advantage of the
availability of uninterruptible power sources if it is in a facility that can provide
uninterruptible backup power in the same manner as required for MER and Co-location
spaces. UPS, generation, static transfer switches (STS), etc. should be provisioned when
required by the specific LOB’s resiliency, redundancy, and disaster recovery plans
(recommended groups typically requiring UPS, generation, and STS’s are trading floors,
call centers, and any other groups deemed critical requiring this additional resiliency).
a) Electrical circuits powering equipment in MER, TR, and Co-location spaces must be
protected with Transient Voltage Surge Suppression (TVSS) devices. These must be effective
at the breaker panel level (branch circuit distribution), but should also be present at each level
of electrical distribution.
6. AC ELECTRICAL CIRCUITS
Applicability: See below
a) For all types of spaces ICT equipment must be powered from dedicated circuits. In this
document a “dedicated circuit” is defined as a circuit that must be on its own breaker, and
have both a separate neutral conductor and a separate equipment grounding conductor
(EGC) that are not shared with any other circuits.
b) Branch circuit distribution must be redundant:
i. For MER and Co-location: Circuits must be redundant and diversely fed.
ii. For TR: The lowest acceptable level of redundancy is two separately wired circuits
derived from a common breaker panel (panel board). However, advantage must be
16
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
taken of whatever redundancy in the electrical system is available at a site beyond the
minimum required, and what is practical to upgrade at a site to provide greater
redundancy and diversity.
c) Isolated (Insulated) Ground (IG) electrical circuits and receptacles (IGR) must not be
specified unless required by a manufacturer for a specific piece of equipment or system.
IG circuits must conform to NEC requirements (also as a reference for usage, IEEE
Standard 1100 “The Emerald Book”).
d) Lighting, air conditioning and other HVAC and mechanical systems must not share
transformers and breaker panel feeds and circuits with ICT equipment.
e) All spaces must have duplex 20 Amp convenience outlets spaced at Code compliant
intervals and height around the room on walls and/or columns - as appropriate to the space
– but at intervals no greater than:
i. For MER and Co-location: 3.66 m (12 feet) as per ANSI/TIA-942
ii. For TR: 1.83 m (6 feet) as per ANSI/TIA-569
7. DC POWER
Applicability: MER, Co-location
When it is necessary to provide DC power instead of AC power:
a) The DC source must:
i. Be derived from diverse electrical utility feeds
ii. Have a nominal voltage of 48V DC unless a specific piece of equipment has special
requirements, or by 3-phase AC to DC conversion is required.
iii. Be connected by the largest cable size practical (e.g. 750 MCM) to allow power
upgrades without replacing power cables
b) Bulk DC power feeds (100A – 600A) must terminate on JPMC BDCBB(s).
17
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
18
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
e) Equipment with dual power cords for use with diverse power feeds must:
i. Use special ordered White cords to plug into the “A-side” feed
ii. Use Black cords to plug into the “B-side” feed
f) RACK AND CABINET MOUNTED POWER DISTRIBUTION UNITS (“PDUs”)
Applicability: MER, TR, Co-location
All rack and cabinet PDU’s must:
i. Be certified compliant with UL 60950-1 for safety of information technology equipment.
ii. Be sized in power rating to properly handle expected loads.
iii. Use 208V AC (or country specific equivalent).
19
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
I. All open frame racks shall be equipped with horizontal rack mounted ground busbars (RBB),
for the grounding of network equipment. Horizontal rack mounted ground busbar shall be
mounted on the rear of the cabinet/rack.
A. PRIMARY COOLING
Applicability: See below
1. For MER and Co-location: These spaces require “N+1” independent Computer Room Air
Handlers (CRAH) or Computer Room Air Conditioners (CRAC) - as applicable to the site -
where “N” denotes the number of units needed to satisfy the base requirements. However,
only “N” associated conveyance components (e.g. ducts, etc.) are required.
2. For TR: “N” CRAH or CRAC units and “N” conveyance components are required, where “N”
denotes the minimum number of units needed to satisfy the base requirements.
B. BACKUP COOLING
Applicability: See below
1. For MER and Co-location: The requirements for primary cooling cover backup.
20
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
2. For TR: Portable air conditioning unit(s) must be provided along with associated means for
exhausting hot air and disposing of condensate. These units must not be stored in a TR or in
an MER.
C. PIPING LOCATION
Applicability: MER, TR, Co-location
Piping for chilled water or glycol coolant must be routed outside the room and penetrate the room
at the shortest path – compliant with other requirements of this document - to connect to
CRAH/CRAC units.
D. LEAK CONTAINMENT
Applicability: MER, TR, Co-location
A condensate containment pan and/or curb wall with leak detection is required for floor/wall
supported CRAH/CRAC units. A drip pan with leak detection is required for ceiling mounted
CRAH/CRAC units. Ceiling mounted cooling units should be installed outside the room and ducted
in.
E. ENVIRONMENTAL CONDITIONS
Applicability: MER, TR, Co-location
1. Environmental conditions must be kept within the “Recommended” range for all “A Classes”
per ASHRAE TC9.9 “2011 Thermal Guidelines for Data Processing Environments” which
include:
a) Humidity Range, Non-Condensing: 20% to 80% Relative Humidity with 17⁰C (62.6⁰F)
Maximum Dew Point
2. Additional restrictions of ASHRAE TC9.9 must be applied as applicable to the site.
3. Measurement of temperature and humidity must follow ANSI/TIA-569 and ASHRAE
requirements and guidelines.
A. LEAK DETECTION
Applicability: MER, TR, Co-location
Leak detection must be installed in drip pans, around fluid piping and other locations with the
possibility of a leak threat.
A. SUPERVISION
Applicability: See below
1. For MER and TR: Fire suppression systems must be in GRE controlled space.
2. For Co-location: Fire suppression systems will be in Co-location facility controlled space.
21
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
6. Sprinkler associated piping must not be routed directly above ICT equipment or enclosures,
but instead must be routed in aisles for optimal clearance.
7. Spaces built for compliance to NEC Article 645 (Information Technology Equipment) must
comply with the NFPA 75 “Standard for the Protection of Information Technology Equipment”
requirements as well.
C. FIRE EXTINGUISHERS
Applicability: MER, TR, Co-location
1. All spaces must have ready access to a listed portable fire extinguisher compliant with the
NFPA 10 standard, local Codes and OSHA requirements. Extinguishers must not use dry
chemicals, and must have a suitable tank capacity, and appropriate fire type category ratings
per the UL 711 standard.
3.6 INTERNAL CABLE PATHWAYS, SUPPORT, ROUTING, AND MANAGEMENT
A. General
Applicability: MER, TR, Co-location
Cable trays, raceways, routing assemblies, and other pathway and cable support products for use
within MER, TR, and Co-location spaces:
1. Manufacture compatible waterfalls or radius drop-outs must be installed in a manner that
ensures that the bend radius of cables will be compliant with the ANSI/TIA-568 group of
standards, or manufacturer’s requirements if those are stricter.
2. Must utilize installation components that are manufacturer approved for the specific product,
and that are compliant with Codes and standards applicable to these components. They must
not compromise the Code or standards compliance of the product.
B. Metallic Cable Trays
Applicability: MER, TR, Co-location
1. Cable tray systems must be compliant with NEC Article 392.
2. Cable tray systems must be planned for at least 15% growth, with a maximum allowable fill of
50%, unless restricted by the NEC or by the ANSI/TIA 569 standard (whichever is stricter) to
a lesser fill amount for the particular type of cable tray, its usage, or it’s environment.
22
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
3. Cable trays must be independently supported from the ceiling and/or walls and not via
attachment to cabinets and racks.
4. Cable trays must be installed in a manner that allows at least 305 mm (12 in) of clearance
above the top of the tray.
5. Cable trays must be installed 101.6 mm – 152.4 mm (4 in – 6 in) above cabinets and racks.
6. Metallic cable tray must be compliant with the NEMA VE-1 standard. Installation should follow
the guidelines and recommendations – as applicable – in the NEMA VE-2 standard.
7. All metallic cable trays must be bonded to ground per NEC requirements. When tray sections
are not mechanically continuous, bonding conductors must be installed across the sections.
This includes trays whose section connecting hardware is not approved as a means for
providing ground continuity.
3.7 Non-metallic Raceways and Cable Routing Assemblies
Applicability: MER, TR, Co-location
NOTE: Aside from fittings, assembly details, and structural properties, the primary difference between
Raceways and Cable Routing Assemblies is that Raceways are enclosed and Cable Routing
Assemblies are channels that may or may not be enclosed (i.e. has a removable cover).
Non-metallic Raceways and Cable Routing assemblies:
A. May be attached to cabinets and racks when intended for patching or other local connections
within a row. Otherwise they must be independently supported and – as applicable - meet the
requirements of Item #’s 4 and 5 in Section 3.6 above for metallic cable trays.
B. Must be listed to UL2024 or UL2024A standards as appropriate to application, including fire
resistance.
C. Must be compliant for the intended use with the appropriate NEC Article (which may vary
depending upon the governing NEC edition at a site), and with the NEC required fire rating for the
environment it will employed in (i.e. plenum, riser, general purpose).
D. Must be planned for 15% growth, with a maximum allowable fill of 50% unless restricted to less
by the NEC or the ANSI/TIA-569 standard for the type of application.
3.8 EXTERNAL CABLE PATHWAYS AND SUPPORT STRUCTURES
Applicability: MER, TR, Co-location
All cable pathways (e.g. conduit), cable support structures (e.g. cable tray), and sleeves penetrating
the walls of MER, TR, and Co-location spaces:
A. Must be firestopped per the requirements of this Standard, ATSM E814, UL1479, and the
manufacturer.
B. Must meet the applicable requirements for internal cable pathways in Section 3.6 of this
document.
C. Must be installed in a manner that ensures that the bend radius of cables will be compliant with
the ANSI/TIA-568 group of standards, or manufacturer’s requirements if those are stricter.
D. Must be planned for 15% growth, with a maximum allowable fill of 50% unless restricted to less
by the NEC or ANSI/TIA-569 for the type of application.
E. Must not contain Carrier or other Access/Service Provider cabling and JPMC structured cabling
(i.e. must not be shared).
3.9 ACCESS PROVIDERS (CARRIER & OTHER)
Applicability: MER, Co-location
A. A minimum of two Access Providers are required. The physical entry points of their cabling into a
building must be separated by at least 65 feet (20 meters).
B. Within a building Access Providers cabling must be diversely routed in rigid metallic conduit that
complies with prevailing Codes. Flexible/corrugated metallic conduit must not be used.
4.0 BACKBONE
23
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
24
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
25
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
7. Have perforated single front and double rear doors, each with a lock
8. Have side panels
9. Cabinets for use in air containment buildouts must use blanking panels to close off empty
mounting spaces.
G. Clearances
Applicability: MER, TR, Co-location
Room size and layout, and rack and cabinet locations, must provide:
1. A minimum of 915 mm (3 ft) of clearance in front and in back of racks and cabinets. More
clearance must be provided when deemed prudent or necessary for use, installation, and
removal of equipment, or to meet thermal requirements.
2. A minimum of 1219 mm (4 ft) of clearance at the end of a row of racks or cabinets.
3. A minimum of 305 mm (1 ft) additional clearance from a Carrier (Service Provider) wall field
beyond the minimums specified for racks and cabinets.
4. At least 610 mm (2 feet) of clearance above racks and cabinets, with cable support systems
being the only allowable exception.
5. In access floor environments, at least one full floor tile must be free of obstruction in front and
in back of a row of racks or cabinets to allow under floor access.
4.2 FIRESTOPPING
Applicability: MER, TR, Co-location
A. All through-penetrations and membrane-penetrations of fire rated walls and floors must be
firestopped. Installation methods and firestopping materials and systems must be qualified for the
specific circumstances under which they will be used. Firestopping must, as a minimum, preserve
the fire rating of the penetrated surface(s).
B. Firestopping materials, systems, and installation methods must adhere to the requirements of
governing Codes, the ANSI/TIA-569 standard, and the manufacturer required and recommended
procedures.
C. Through-penetration firestop systems must be qualified to the ASTM E814 and UL1479
standards. “F”, “T”, and “L” ratings must be chosen as required by Code and/or an AHJ, and must
be appropriate to the situation. Where water penetration is of concern, the firestop should have a
“W” rating as well.
D. See Section 21 07 16 for additional requirements.
4.4 CONNECTIVITY
Applicability: MER, TR, Co-location
A. Fiber based connectivity must be presented for use on LC connectors and must:
1. Between critical spaces (e.g. MER to TR): Utilize LC adapter (coupler) panels connected via
fiber cables with field terminated LC connectors.
2. Utilize appropriate adaptation patch cords when necessary to convert to an LC from a
different connector type (e.g. SC, ST).
B. ICT infrastructure cabling must be separated by a minimum of 305 mm (12 in) from electrical
power cables.
C. Copper cable terminated on modular 8-pin (“RJ45” style) jacks must use the T568B pin/pair
assignment as per the ANSI/TIA-568 standards.
4.5 PATCHING
Applicability: MER, TR, Co-location
A. Centralized patching fields (cross-connect) must be implemented only if approved by the OPR or
management and must be:
1. LC connector based for fiber
2. Modular 8-pin (“RJ45” style) based for copper
3. DS-3 Coax (where applicable)
26
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
B. All equipment locations (rack, cabinet, wall field) must have dedicated connectivity to the
centralized patching fields with cable media suited to the type of equipment and
speeds/bandwidth to be hosted at the location.
C. Chassis based access switch copper (RJ45) port cards must be port replicated to the centralized
patching field. (If required)
D. Stackable switches must follow the WTS patching scheme illustrated in the diagram in Appendix I
of this document.
E. As appropriate and necessary for a neat and manageable installation, patch cords must be
supported in wire managers.
F. Patch cords must be routed neatly and in a manner that does not obstruct access to equipment
and the cabling infrastructure.
G. Patch cord minimum bend radius requirements per manufacturers specifications and the
ANSI/TIA-568 standards must not be violated.
H. Patch cord length must not be excessive. Plan for no more than 0.305 m (1 ft) of slack on either
end.
I. ICT equipment patch cords and power related cords and cables must utilize separate pathways.
4.6 Labeling and Administration
Applicability: MER, TR, Co-location
See Section 27 05 53 and Appendix D
4.7 Design Tools
A. AutoCAD is the minimum required design software. The project engineer must identify to the
project team the AutoCAD save version necessary to share files.
B. When shared electronically, documents must be provided in both PDF and DWG file formats. All
drawings must be scaled and the drawing must identify the scale that is used.
TERMINOLOGY
Within this document:
1. The following terms identify an obligatory item: must, shall, will, is required, are required, mandatory.
2. The following terms identify an optional item: can, may, should, preferably, prefers, desired, desirable.
4. Regulation(s), Regulatory refer to requirements that may be legally binding, or that may be imposed
by a non-governmental authority.
5. NEC and NFPA 70 are used interchangeably to identify the National Electrical Code.
6. Authority Having Jurisdiction (“AHJ”) is as defined by Article 100 of the National Electrical Code (NFPA
70), including the associated Fine Print (Informational) Note.
8. Access Provider is an entity, such as a Carrier, that provides physical connectivity into a building for
the delivery of ICT services. The services may be offered by an Access Provider itself or by third
parties using an Access Provider’s facilities.
9. “Standard” refers to this “Critical Technology Space and Infrastructure Cabling Design” document.
GLOSSARY
27
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
28
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
GENERAL NOTES
COMPLIANCE WITH THIS STANDARD
Contractor shall comply with and enforce all requirements specified in this Standard including defined
materials and acceptable practices. In the same token, materials and practices that are not specified
(e.g. splitting copper terminations across multiple jacks, implementation of a MUTOA), or are missing
from this Standard shall not be deployed. As a general rule, any deviations from this Standard that may
result in a performance impact are not permissible except when waived as specified herein.
This requirement may be waived only via written approval by a member of the Remote Site Operations
and/or Cabling Engineering team. Contractor failure to comply with this requirement may result in
immediate removal from the JP Morgan Chase Preferred Cabling Contractor Master List.
29
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
Copper Infrastructure
For copper infrastructure, Owner has negotiated discounted pricing with the suppliers listed
below. For all legacy infrastructure installations (typically Systimax) contractor shall match
existing manufactures solution to ensure operational efficiencies and compliance to
manufactures warranties.
Copper supplier: CommScope, Berk-Tek-Leviton
COMPLETE SYSTEM
Specifications contained herein are intended to result in a complete, fully functional telecommunications
infrastructure. Even though some materials (e.g. bolts, cage nuts) may not be expressly specified in this
Standard, Contractor is expected to furnish and install all necessary miscellaneous materials to ensure a
fully functional infrastructure.
Mike Tully
609-354-8800
mtully@chatsworth.com
CommScope
Rich Cohen
917-468-7445
rcohen@commscope.com
Corning
Brad Bookless
614-246-8004
Bradley.bookless@corning.com
30
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
JT Kosty
817-807-2169
James.Kosty@corning.com
Berk-Tek Leviton
Mike Brady
201-341-6105
Mbrady@triadinfosys.com
John Russell
972-660-6300
jon@datacomsales.com
Distribution Partners
Anixter
Craig Carter
614-210-2515
Craig.carter@anixter.com
Eric Lawell
224-521-4487
Eric.Lawell@anixter.com
Larry Paniccia
631-297-5202
lpaniccia@wescodist.com
Graybar
Lance Gross
216-573-6107
Lance.Gross@graybar.com
Scott Berwick
732-978-0050
scott.berwick@gbe.com
SUBCONTRACTORS
JPMC infrastructure projects as defined by this Standard shall only be implemented by contractors on the
Preferred Cabling Contractor Master List. The installation contractors on this list shall not subcontract
work to others without prior written OPR approval. Failure to comply with this requirement may result in
removal from consideration for future JPMC projects. Contractor shall evaluate staffing requirements for
contemplated JPMC projects, and submit request for said OPR approval at the time that they tender their
initial proposal.
LEGACY INFRASTRUCTURES
In cases where the cabling infrastructure is being installed in a building not currently occupied by JPMC,
or where the new infrastructure is part of a strategic refresh of the entire existing (Legacy) infrastructure,
31
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
the infrastructure design and installation (including architecture and hardware components) shall follow
the current prevailing version of this Standard. In cases where the new infrastructure is being installed in
a building currently occupied by JPMC, and is not part of a strategic refresh of the entire existing (Legacy)
infrastructure, Contractor shall furnish to OPR a detailed written report describing deviations from the
prevailing Standard, and OPR will furnish direction regarding which elements of the project shall follow
the Legacy Standard, and which elements of the project shall follow the prevailing Standard. In no case
shall JPMC Standard architectures be waived.
In cases where JPMC is acquiring new space that has existing infrastructure, JPMC may consider the
retention of the existing infrastructure (not dependent on manufacturer). The determination of whether or
not JPMC retains the existing infrastructure or not will be based on sample testing, warranty transfer, etc.,
and may result in full testing and re-labeling. A new wireless heat map will be done which may require
some re-cabling to accommodate JPMC’s needs.
CONTRACTOR PERSONNEL
Access to JPMC facilities is controlled, and Contractor personnel must undergo security screening before
facility access may be permitted. Access to our Technology Rooms is provided on an escort basis.
CONTRACTOR COMMUNICATION
While Contractor is expected to communicate with site users to ensure their needs are met, a successful
project outcome is determined in the sole discretion of JPMC technical project personnel. Accordingly,
Contractor shall minimally furnish to OPR and other designated personnel progress reports, including, but
not limited to, installation details on a daily basis or as otherwise approved in writing by OPR. OPR may
further define other reasonable reports and communication deliverables that Contractor shall substantially
provide. Misrepresentation of progress, which might result in project delay, may result in a probation
event.
The Contractor shall immediately advise JPMC of; any changes made to your firm’s escalation points of
contact, associations, organization, or certifications.
CONTRACTOR ADVERTISING
Contractor shall not solicit written or verbal testimonials from JPMC personnel at any time. Contractor
shall not install or post in JPMC properties any form of signage that contains Contractor name, address,
telephone number, or logo. Photographs within JPMC buildings including technology spaces are strictly
prohibited without prior approval of JPMC IT Risk Management and the local JPMC Site Manager. All
requests shall be submitted to the OPR for routing.
CONTRACTOR BADGING
When working in JPMC properties, contractors should wear either badges or clothing that displays their
employer’s name. Where badges are employed, they should be worn in a conspicuous location on the
contractor’s shirt, and on outerwear if it is worn over the shirt.
OMISSIONS
Contractor omission of any requirement described in Project Documents shall not be construed as to
relieve Contractor of any responsibility or obligation required to affect the complete and satisfactory
delivery, operation, and support of any and all materials or services.
32
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
INTERPRETATION
Contractor is solely responsible for developing a structured cabling bill of materials from design
documents provided. In all cases where Contractor identifies unclear or imprecise drawings or
Specifications during the bidding or quotation process, Contractor shall contact OPR, who shall furnish
appropriate interpretation. Upon award, Contractor assumes responsibility for correcting any and all
inconsistencies at no additional cost to Owner.
Where the requirements of certain sections of the Specifications are more stringent than applicable
codes, rules, regulations, and ordinances, the Specifications shall apply.
If the contractor should note items in the drawings or the Specifications, construction of which would
result in code violations, the contractor shall promptly call them to the attention of the OPR in writing.
EQUIVALENTS
It is the sole responsibility of Contractor to ensure that all products installed at this facility are compatible
with the application. Owner makes no representation regarding the accuracy of the part numbers listed.
SUBSTITUTIONS
Materials shall be as listed or shall be equivalent products of other manufacturers meeting the intent and
quality level of this specification. Materials must be compatible with the end-to-end solution being
proposed. Proposals for equivalent products must be presented to the OPR via RFI’s, Submittals, and/or
Shop Drawings. OPR written approval is required before any substitutions are made.
NEW MATERIALS
All cable and materials shall be new, unless previously approved in writing by OPR. New equipment and
materials shall be without blemish or defect. New equipment and materials shall be Underwriters
Laboratories, Inc. (U.L.) labeled and/or listed where specifically called for, or where normally subject to
such U.L. labeling and/or listing services.
GENERAL CABLING
The inside/outside wiring plant shall be installed per requirements of these Specifications using materials
and methods that meet all applicable TIA/EIA, ISO-IEC 11801 Generic Cabling for Customer Premises,
and BICSI reference manuals.
Unless approved in advance by OPR, all products shall be brought to the job site in original
manufacturer's packaging. Electrical components shall bear the Underwriter's Laboratories label. All
communications cable shall bear flammability testing ratings as follows:
- CM Communications Cable
- CMR Riser-rated Communications Cable
- CMP Plenum-rated Communications Cable
- LSZH Cable rated according to IEC test:
- IEC 754 part 2
- IEC 1034 part 2: smoke emission
- IEC 60332-1: Flammability and fire retardant
- NES 713: Toxicity index.
CABLE PROTECTION
All cabling runs that remain within JPMC areas shall be properly supported in accordance with all JPMC
Standards. All cabling that is run in common building areas and other tenant spaces must be in conduit
for the full run outside of JPMC areas such that no JPMC cabling is accessible to anyone other than
JPMC personnel. Junction and pull boxes and other access points required in common areas shall be
provided with locks so that the cabling is inaccessible to anyone other than JPMC personnel.
33
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
QUALITY CONTROL
Initial Cable Inspection: Contractor shall inspect all cable prior to installation to verify that it is identified
properly on the reel identification label, that it is of proper gauge, containing the correct number of pairs,
etc. Note any buckling of the jacket, which would indicate possible problems. Damaged cable, and/or
any other components failing to meet Specifications shall not be used in the installation.
CHANGE CONTROLS
Work within operational JPMC technology spaces including TRs, MERs, and Co-Lo’s should be preceded
via implementation of the Enterprise Change Management (ECM) process, which results in issuance of a
change control number. The ECM record may limit work to specific categories, locations, dates and times.
This process is administered by JPMC, and provides a consistent method of tracking work that may have
an impact on technology production. It is Contractor's responsibility to request and retain change control
numbers before performing work in these technology spaces. If Contractor is informed by JPMC
personnel that an ECM is not necessary, it is in Contractor's best interest to solicit written confirmation to
avoid impact to Contractor standing. Other Contractor actions may be required In addition to ECM as
part of access to, and conduct of work within technology spaces, and Contractor is encouraged to ask
about such requirements during initial engagement on each project.
SITE SAFETY
Contractor shall provide safety cones, barricades, caution tape, or other safety equipment or devices to
direct personnel around the work area in order to protect personnel and property. All aspects of
construction and installation must meet applicable local, state, and federal laws, as well as any
regulations specific to a site. Legally binding requirements must prevail if there are any conflicts with
requirements stated or implied in this Standard document. The AHJ will be the arbiter in situations where
interpretation is necessary to clarify information, or to resolve conflicts involving legally binding
requirements.
Work safety must be in compliance with Public Law 91-596, Occupational Safety and Health Act (OSHA).
As applicable, requirements of the NFPA 101 Life Safety Code must be followed.
MATERIAL INTERPRETATION
Contractor should not assume that materials listed in this specification must be installed merely because
they are listed in this specification. Project-specific detail on required materials is further defined in the
accompanying project specific drawings.
PROJECT SCHEDULE
Provision of a quotation for a project indicates that Contractor understands its scope, and has included in
their quote sufficient monies to provide the labor and materials necessary to install a top-quality, fully-
functional system while meeting all scheduled deadlines.
34
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
INSTALLATION
All projects should be considered to be “showcase” installations. Accordingly, all work shall be superior
both functionally, and wherever possible, aesthetically. All cables shall be dressed in accordance with
manufacturer’s Standards to insure that performance characteristics of the cable are supported. All
hardware should be mounted plumb and level, and where multiple hardware units are installed, spacing
should be uniform from unit to unit so as to ensure a visually pleasing appearance. Contractor shall take
care to prepare cable lengths that are neither too shortresulting in kinks and out-of-specification bends
nor too long resulting in difficult cable management and sloppy appearance. Manufacturer’s
Standard pulling tension and minimum bend radii shall be complied with at all times.
Cable Lubricants: Lubricants specifically designed for installing communications cable may be used to
reduce pulling tension as necessary when pulling cable into conduit. After installation, exposed cable and
other surfaces shall be cleaned free of lubricant residue. See Sections 01 45 23 and 33 82 53 for further
detail.
TESTING
The OPR shall be furnished a minimum of 24 hours’ notice prior to any and all cable testing. The OPR
may attend and/or participate in some or all testing.
Contractor shall be available during equipment installation and testing to help isolate faults that may exist
in the cabling system installation.
Contractor shall coordinate with other vendors where necessary to resolve any discrepancies between
the cabling system and the vendors’ cabling or equipment.
PROTECTION OF PROPERTY
Extreme care shall be taken by Contractor to protect all components of the property from damage.
Contractor shall replace any damaged ceiling and floor tiles that are broken during cable installation.
Contractor shall provide all protective devices and coverings required to protect areas adjacent to the
work area. Contractor shall repair damage to areas adjacent to the work area at no cost to the Owner, or
the Owner shall make the repairs and back charge against the Telecom Contractor. Contractor shall
assume complete responsibility for damages to third parties incurred as a result of Contractor’s work in
this project. Protection of property shall include, but not be limited to, the following protective measures:
- Keeping the Co-Lo’s, TR, and MER free of food and drink at all times.
- Leaving Co-Lo’s, TR, and MER doors closed at all times.
- Employing HEPA vacuum whenever drilling, cutting, coring, or performing any work that will
impact air quality.
- Vacuuming the top surface and edge area of all floor tiles with a HEPA vacuum before removing
them from floors to prevent false alarms.
- Minimizing the size of floor tile cutouts to limit the unnecessary loss of cooling air and static
pressure.
- Coordinating bypass or disabling of fire detection systems before removing floor or ceiling tiles to
prevent false alarms.
- Removing no more than six raised floor tiles at any time in any one area to ensure maximum
static pressure and uphold the structural integrity of the floor, and for as short a period of time as
practicable.
- Removing no raised floor stringers, except under approval and supervision of OPR.
- Replacing all previously cut floor tiles no longer in use with full tiles to prevent the loss of static
35
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
PARTIAL OCCUPANCY
Owner may occupy or use any completed or partially completed portion of the work at any stage as
determined by the OPR. Such partial occupancy or use may commence whether or not the portion is
substantially complete. Unless agreed in writing otherwise, partial occupancy or use of a portion or
portions of the work shall not constitute acceptance of the work’s non-compliance with the requirements
of the Project Documents. Corrective work required in these areas shall occur so as not to disturb Owner
or Owner’s operations.
ENVIRONMENTAL QUALITY
Structured cabling performance is subject to degradation when exposed to contaminants including dust.
Fluctuations in temperature and humidity may also impact cabling longevity and performance.
Accordingly, where environmental quality within a space may reasonably be determined to have a
negative impact on structured cabling, Contractor shall not place structured cabling and associated
hardware in said space unless permitted in writing by OPR.
WORK SCHEDULE
The work shall be scheduled and coordinated with the OPR, who shall approve all phasing and
scheduling of the work. The OPR shall be notified in writing at least two business days prior to the start of
demolition or construction.
WORK HOURS
Any work in spaces occupied by Owner shall be coordinated with the OPR. Work requiring disruption of
electrical power shall be scheduled at least one week in advance with the OPR and shall only be
performed on the weekend and not exceeding eight hours. Any work generating noise, dust, or
inconvenience to Owner or other tenants, at the sole discretion of the OPR, will be performed during
either nighttime hours or on weekends. Contractor shall coordinate with the OPR to assure work is
accomplished during approved change control (ITSM) work windows.
36
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
ACTIVITY TRACKING
When performing work in MERs, TRs, or Co-Los, the Project Manager shall be notified at the
commencement of daily installation work, before such work begins, and at the conclusion of daily
installation work, before departing the facility.
FINAL AUTHORITY
Owner has final authority on all issue resolutions.
REFERENCES
Unless otherwise specifically stated in this document, all work shall be performed in full compliance with
the requirements set forth in the following reference Standards. In any case where regional Standards
disagree, local codes and Standards apply. Even when not explicitly cited within this Standard document,
there is an implied requirement of compliance with industry norms reflected in recognized Standards and
practices, as well as requirements based in law. Current governing codes and regulations at a site
location, and the most recent edition of Standards and practices documents (including errata, annexes,
and amendments) must be used.
A. Americans With Disabilities Act (ADA)
B. ANSI/ESD STM7.1 Standard Test Method for the Protection of Electrostatic Discharge
Susceptible Items - Floor Materials - Resistive Characterization of Materials
C. ASHRAE TC9.9 2011 Thermal Guidelines for Data Processing Environments
D. ASTM E84 Standard Test Method for Surface Burning Characteristics of Building Materials
E. ASTM E119 Standard Test Methods for Fire Tests of Building Construction and Materials
F. ASTM E814 Standard Test Method for Fire Tests of Penetration Firestop Systems
G. ASTM F150 Standard Test Method for Electrical Resistance of Conductive and Static
Dissipative Resilient Flooring
H. BICSI Telecommunications Distribution Methods Manual, (Current edition)
I. CENELEC prEN 50173-1(Current edition), Information Technology—Generic Cabling
Systems—Part 1: General Requirements.
J. CENELEC prEN 50173-2(Current edition), Information Technology—Generic Cabling
Systems—Part 2: Office Premises.
K. EIA/ECA-310 Cabinets, Racks, Panels, and Associated Equipment
L. European Union Regulation No. 305/2011 – Construction Product Regulation (CPR)
M. IEEE 802.3 Ethernet (group of Standards)
N. IEEE Standard 1100, “The Emerald Book” Recommended Practice for Powering and
Grounding Electronic Equipment
O. ISO/IEC 11801(Current edition), Information Technology—Generic Cabling for Customer
Premises.
P. ISO/IEC 14763-1(Current edition), Information Technology—Implementation and Operation of
Customer Premises Cabling—Part 1: Administration.
Q. ISO/IEC TR 14763-2(Current edition), Information Technology—Implementation and Operation
of Customer Premises Cabling—Part 2: Planning and Installation of Copper Cabling.
R. ISO/IEC TR 14763-3(Current edition), Information Technology—Implementation and Operation
of Customer Premises Cabling—Part 3: Testing for Optical Fibre Cabling.
S. ISO/IEC 18010(Current edition), Information Technology—Pathways and Spaces for Customer
Premises Cabling.
T. National Electric Code (NEC) (Current edition)
U. National Uniform Seismic Installation Guidelines (NUSIG)
V. NEMA VE-1 Metal Cable Tray Systems
W. NEMA VE 2(Current edition) Cable Tray Installation Guidelines
X. NFPA 10 Standard for Portable Fire Extinguishers
37
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
ACCEPTANCE
System is considered to be accepted when the following items are satisfactorily completed: 1) as-builts
furnished and accepted; 2) test results furnished and approved; 3) infrastructure checklist and signoff
worksheet signed off with no open items; 4) all punch list items resolved; 5) warranty documentation
furnished. Final contractor payment shall be withheld pending completion of all acceptance criteria. In
the sole judgment of OPR, the acceptance process may be comprised of multiple intermediate steps
followed by final acceptance, or final acceptance only.
ACCEPTANCE INSPECTIONS
All inspections (intermediate or final) shall employ the WTS Definition and Checklists for MER and TR
Acceptance found in Appendix A of this document. Inspections will consist of an initial review of the
project installation progress, giving specific attention to technical installation issues, locations, and
Standards referred to in the Project Documents. Any installation deficiencies will be documented and
forwarded to the appropriate party (e.g. Contractor foreman, GC) for action.
38
SECTION 01 00 00 – CRITICAL TECHNOLOGY SPACES
AS-BUILTS
Any and all costs for document processing and conversion (if necessary), printing, etc., are the
responsibility of Contractor. Contractor shall provide drawings that include final single line diagram(s);
floor plan(s) showing final cable locations and all cable pathways that are utilized by the project; TR and
MER plan views showing pathways, new racks and cabinets; rack, cabinet, and wall elevations showing
equipment, hardware and cabling that has been installed as part of the project. Contractor shall keep all
documentation current throughout the installation and build-out process. If changes occur which affect
any documentation, the Contractor shall formally re-issue the affected documentation. Contractor shall
submit drawings to the OPR in AutoCAD 2013 version. JPMC utilizes a Secure Drop Zone email system
for large file exchanges, with attachments that are up to 1GB.
TEST RESULTS
Upon project completion, and before issuance of final payment, Contractor shall provide complete test
results as defined in 01 45 23 of this specification.
39
SECTION 01 45 00 – QUALITY CONTROL
SECTION 01 45 23
TESTING
PART 1 – GENERAL
1.1 DESCRIPTION
A. Prior to the testing commencing, the Contractor is to provide a comprehensive testing
methodology document for approval, prior to any testing commencing. This document shall
include the following information:
1. Brief overview of the project (location, scope etc.)
2. Overview of the testing procedure including supporting documentation, onsite equipment
calibration/ referencing and cleaning procedure.
3. Details of the equipment to be used.
4. Calibration requirements and certification for the equipment to be used
5. Test result backup procedure
6. Details of procedure for remediating any test results which do not pass the required tests
7. A program of works for the testing, should this not be clear in the overall installation
program
B. All electronic and optical measuring (test) equipment shall be within 12 months of a calibration
that has been carried out by an approved calibration house. All calibration certificates shall be
available on site during the testing phase. All test results shall identify the equipment serial
number (local and remote) of test equipment used
C. The “Store plot data” function of the tester must be enabled prior to any testing commencing.
This is to enable electronic re-testing at a later date should this be required. Test results issued
without the plot data enabled will be considered non-compliant and re-testing will be required
at the contractors cost.
D. All marginal (or star *) passes shall be considered fails and will require remediation until a pass
is achieved.
E. Once all products (i.e. cables and associated hardware) have been fully installed in their final
locations and labelled, testing of all cores/ cables may commence.
F. All cables/ cores shall be 100% tested in accordance with the sections below.
G. It is the contractor’s responsibility to remediate all faults found whilst testing at its own expense.
All test equipment shall be by the contractor.
H. JPMC may choose to witness test random elements of the installation, which should have
already been allowed for in the costs. The contractor shall provide 2 testing engineers and all
equipment required to undertake the witness testing (including fully charged test equipment).
Channel testing (including existing previously installed infrastructure may also be required as
part of the witness testing, to ensure that the full channel is compliant.
I. The project shall not be considered complete until all SCS infrastructure has been 100% tested
and test result issued to JPMC in both tester and PDF format. Test results are to be broken
down into 10Mb file sizes and emailed (FTP sites, CDs or flash drives are not permitted).
40
SECTION 01 45 23 TESTING
PART 2 – PRODUCTS
2.1 The Following products should be used when testing Structured Cabling Infrastructure:
A. Test equipment which is capable of electronically storing test result data. The tester shall
exceed ANSI/TIA-1152 Level 2G
B. Category 6 and Category 6A permanent and channel adapters
C. Single-mode and multi-mode fiber adapters
D. Encircled flux reference cords
E. Fiber inspection probe/ microscope
F. Appropriate connector cleaning tools/ tapes
G. 2m Category 6 patch leads if channel testing Category 6 cabling
H. 2m Category 6A patch leads if channel testing Category 6A cabling
PART 3 - EXECUTION
3.1 Fiber Testing (Pre-terminated Fiber)
A. Tests shall be carried out at 850nm and 1300nm for multi-mode testing and 1310nm and
1550nm for single-mode testing in one direction.
B. The fiber manufacturer’s warranty conditions shall be used to perform all fiber testing. These
standards are more stringent than International and National standards. The contractor is
required to perform custom tests using the tester and is therefore to adjust the contactor loss
values in the tester software accordingly.
C. Should installed fibers be required to be connected directly into a switch in a harness link
topology, all fibers will be patched prior to testing commencing, then individually un-patched,
tested, and finally re-patched. This is to mitigate polarity concerns.
D. When referencing fiber optic testers the 1 jumper (Method B) methodology shall be employed.
E. Fiber testers shall be compliant with encircle flux launch sources/ conditions. Encircled flux
testing patch leads shall be used and should not be mated beyond the maximum of 500 times.
F. Delivered cable tests are not required, however a Certificate of Conformance shall be supplied
with each trunk cable and copies made available on site and provided in the final handover
documentation.
G. Individual cable runs shall be traceable to the delivered trunk certification.
3.2 Fiber Testing (Field Terminated Fiber)
A. Multimode Optical Fiber OM3/OM4: The mandatory unidirectional, power meter and light
source field test in accordance with ANSI/EIA/TIA-526-14 in accordance with launch
conditions specified within TSB-178 shall verify link attenuation scaled to the installed cable
length (dB/km), connector and splice attenuation using the following formulas:
41
SECTION 01 45 23 TESTING
d. Loss Budget (±10%) = [Optical Fiber Attn] + [Connector Attn] + [Splice Attn] Field
terminated
e. Optical Fiber Attenuation = [Link distance in meters] x .00350 dB
f. Connector Attenuation = [Qty of connector pairs] x .75 dB
g. Splice Attenuation = [Qty of splices] x .3 dB
h. Loss Budget (±10%) = [Optical Fiber Attn] + [Connector Attn] + [Splice Attn]
B. Single-mode Optical Fiber OS1: The mandatory unidirectional, power meter and light source
field test in accordance with ANSI/EIA/TIA-526-7 shall verify link attenuation scaled to the
installed cable length (dB/km), connector and splice attenuation using the following formulas:
1. Loss Budget @ 1310 nm ±10 nm in accordance with ANSI/EIA/TIA-526-7 (Indoor
Cable)
Factory terminated
- Optical Fiber Attenuation = [Link distance in meters] x .00075 dB (Indoor Cable)
- Connector Attenuation = [Qty of modules or harness/fanout assemblies] x 1.3 -
Splice Attenuation = [Qty of splices] x .3 dB
- Loss Budget (±10%) = [Optical Fiber Attn] + [Connector Attn] + [Splice Attn] Field
terminated
- Optical Fiber Attenuation = [Link distance in meters] x .001 dB (Indoor Cable)
- Connector Attenuation = [Qty of connector pairs] x .75 dB
- Splice Attenuation = [Qty of splices] x .3 dB
- Loss Budget (±10%) = [Optical Fiber Attn] + [Connector Attn] + [Splice Attn]
42
SECTION 01 45 23 TESTING
A. NOTE: Module and harness/fanout assembly connector attenuation includes attenuation due
to one (1) MPO connector pair and one (1) LC connector pair.
Category 6 Category 6A
43
SECTION 01 45 23 TESTING
16. ELTCTL (Equal Level Transverse 18. PS ANEXT (Power Sum Alien Near-End
Conversion Transfer Loss) – recorded for Crosstalk)
information only
19. Average PS ANEXT (Average Power Sum
Alien Near-End Crosstalk)
20. PS AACR-F (Power Sum Alien Attenuation
to Crosstalk Ratio Far-End)
21. Average PS AACR-F (Average Power
Sum Alien Attenuation to Crosstalk Ratio Far-
End)
E. All marginal (or star *) passes shall be considered fails and will require remediation until a pass
is achieved
3.4 Copper Backbone Testing (Category 5e)
A. The mandatory field test shall verify:
1. Wire Map
2. Correct installed length
3. Correct attenuation scaled to the installed cable length
3.5 Coaxial Testing
A. DS-3 coaxial backbone. The mandatory field test shall verify:
1. Cable length does not exceed the Coaxial Cable Grading Schedule in Section 27 13 34
2. Center conductor continuity to the remote end
3. Shield continuity to the remote end
4. Shorts between the center conductor and the shield
5. Impedance of 75Ω ±3Ω
6. Link attenuation no greater than 6.9 dB
3.6 DOCUMENTATION
A. All test results are to be issued in the tester software and PDF format a maximum of two days after
final completion of the testing. The project will not be considered complete and invoices will not be
paid until this is achieved.
B. Tester Software and PDF file sizes are to be no greater than 10Mb as email is the only option of
issuing them. Paper copies are not required.
C. The test results in the pdf document are to be sequenced in numerical order, and the port
description should match the labelling nomenclature. It is imperative that the test results detail the
local length measurement units (Metres for EMEA and APAC and Feet for the US).
D. It is the contractor’s responsibility to ensure all ports have been 100% tested prior to submitting the
test results.
END OF SECTION
44
SECTION 01 45 23 TESTING
45
SECTION 01 78 36
PART 1 - GENERAL
1.1 DESCRIPTION
A. General System Warranty: Contractor is responsible for the successful delivery of extended
labor and materials warranties. In all cases, extended warranties are furnished and
supported by the manufacturer. Contractor shall not provide structured cabling services to
JPMC where Contractor is not certified by the manufacturer to offer an extended warranty for
the cabling that they are installing.
B. The warranty for work not otherwise listed shall be one (1) year following the date of
acceptance. Contractor shall assume sole responsibility for providing this paperwork and
delivering to Owner. Final payment may be withheld until said paperwork is delivered to
Owner.
C. Contractor shall deliver manufacturer's warranties to Owner in addition to the General System
Guarantee. These warranties shall be submitted on each item in list form with shop
drawings. Where appropriate, Contractor shall detail individual system components that are
subject to separate warranty. Contractor shall warranty proprietary equipment and systems
involved in this contract during the warranty period. Final payment may be withheld until said
paperwork is delivered to Owner.
D. If, in the judgment of the OPR, sub-Standard materials or workmanship are identified during
the course of Contractor’s work, Contractor will be instructed to correct such defects, up to
and including removal and replacement of defective items, at the sole cost of Contractor.
E. Warranty-related defects shall be corrected by the end of the first business day following the
date Contractor has been notified of the defect.
END OF SECTION
46
SECTION 21 00 00 – FIRE SUPPRESSION
SECTION 21 07 16
FIRESTOP
PART 1 - GENERAL
A. Contractor shall properly fill with firestop compound any firewall breaches created, opened,
expanded, used, or otherwise provided for telecommunications pathways, including all floor
penetrations. Fire-stopping shall be provided for all penetrations of conduit, wireways, bus
ducts, cable trays, etc., through fire-rated walls and floors and other fire-rated separations.
Floor penetrations provided by others but used for telecommunications cable are the
responsibility of Contractor regarding proper firestopping practice. The Standards of the local
governing code and all governing agencies are to be adhered to with respect to the materials
used, the method of installation, and the maximum allowable space permitted between
openings and the installed item and between installed items. Firestop compound shall
conform to both flame and temperature ratings as required by local building codes and as
tested by nationally accepted test agencies per ASTM E814 or UL 1479 fire tests.
B. Contractor shall assume sole responsibility for firestopping firewall breaches associated with
third party installation of cable tray.
C. All horizontal cable penetrations through rated walls shall be sealed in a manner that will
provide a fire rating equal to the wall construction, and shall have both sides firestopped.
D. All vertical cable penetrations through slabs shall be sealed in a manner that will provide a
fire rating equal to the slab construction, and shall have one side of the slab firestopped.
E. All firestopping materials shall be easily removable without damaging the cables after being
set or cured for at least one week.
F. Where mechanical firestopping systems are employed, Contractor shall adhere to all
manufacturer specifications. Particular attention shall be paid to limiting the quantity of
cables passing through each mechanical firestop assembly to the maximum capacity
designed in the firestop plans.
I. Engineering judgements can only be made by the manufacturer of the firestopping system.
J. A firestop label must be located at all high-traffic firestop system penetrations, and a library
must be maintained on-site recording all materials used and their locations in the building.
The label must be updated or replaced if changes are made to the firestop system.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. SpecSeal
47
SECTION 21 07 16 FIRESTOP
B. STI
C. Hilti
D. 3M
2.3 MATERIALS
PART 3 - EXECUTION
3.1 GENERAL
A. Where mechanical firestop assemblies are employed, Contractor shall familiarize themselves
with the proper procedure for construction of assemblies before beginning system installation.
At a minimum, installers should review manufacturer-provided video tutorial that
demonstrates the installation process.
B. Contractor shall avoid penetration of fire-rated walls. Sleeving shall be installed for access
where necessary.
C. Any penetration through fire-rated walls (including those in sleeves) will be resealed with an
Underwriter Laboratories (UL) approved sealant. Contractor shall also seal all floor, ceiling,
and wall penetrations in fire or smoke barriers and in TRs, and MERs.
D. Sleeves shall not be over-populated with cables. Sufficient spare capacity shall be allowed in
each sleeve to accommodate appropriate firestopping materials in accordance with
manufacturer specifications and the UL Fire Resistance Directory. Note that manufacturers
typically specify a 20% to 40% sleeve fill for their products.
END OF SECTION
48
SECTION 27 00 00 - COMMUNICATIONS
SECTION 27 05 26
PART 1 - GENERAL
1.1 GENERAL
A. JPMC’s Real Estate group is responsible for proper installation of a grounding (earthing)
backbone that has been designed and installed in accordance with J-STD-607 or equivalent
regional Standard. If such grounding (earthing) backbone does not appear to be in place,
Contractor shall inform OPR, who will take action as appropriate.
B. All bonding and grounding (earthing) shall track methods and procedures described in J-
STD-607 or equivalent regional Standard.
PART 2 – PRODUCTS
2.1 MATERIALS
PART 3 – EXECUTION
A. Contractor is responsible for furnishing and installing a Secondary Bonding Busbar (SBB) at
all new equipment racks and cabinets per design documents. Each rack-mounted SBB shall
be bonded to the SBB that has been installed in the room.
B. A # 6 conductor shall be bonded to each rack-mounted SBB, then coiled and stored neatly at
each rack for future use.
C. Contractor is responsible for bonding sections of cable tray together utilizing #6 grounding
(earthing) straps, then installing a # 6 grounding (earthing) conductor between the tray and
the SBB that has been installed in the room.
D. If grounding (earthing) must be applied to a location where bare metal is not exposed, the
covering (e.g. paint) shall be fully removed to expose bare metal and facilitate bonding. At
each such bonding point, no greater than 12 mm (.5 in) and no less than 6 mm (.25) in of
exposed metal shall remain after bonding is completed.
E. Where armored cable is deployed, it shall be bonded to ground (earth) at one end in
accordance with AHJ and in accordance with the manufacturer's guidelines.
F. The Rack Bonding Busbar (RBB) must be cleaned and have anti-oxidant applied prior to
fastening any connectors to the busbar.
49
SECTION 27 05 26 GROUNDING (EARTHING) INFRASTRUCTURE
G. Rack bonding busbars (RBB) are recommended for cabinets and racks that need to support
bonding for multiple pieces of equipment or patch panels for shielded cabling. When used,
the RBB must be bonded to the rack. The telecommunications equipment bonding conductor
(TEBC) connects the RBB, on the rack/cabinet, to the primary or secondary busbar in the
distributor room.
END OF SECTION
50
SECTION 27 05 28.29
PART 1 – GENERAL
C. Care shall be taken in the design of non-continuous cable support infrastructure to ensure
that they do not de-rate the performance of copper cables (e.g. Category 6).
D. Non-continuous cable supports may be used to support fiber cable located in innerduct,
provided spacing does not exceed 1.2 m (4 ft.).
PART 2 – PRODUCTS
2.2 MATERIALS
PART 3 – EXECUTION
3.1 INSTALLATION
A. Cable shall not be laid directly on ceiling tile or rails. Cables routed below access floor shall
be supported in such a fashion such that cables do not touch the concrete sub-floor. Non-
continuous cable support shall be placed in accordance with requirements in this Section 27
05 28.29.
B. Nothing (including outlet, pull and junction boxes and fittings) shall depend on conduits,
raceways or cables for support. Nothing shall rest on, or depend for support on, suspended
ceiling media (tiles, lath, plaster, as well as splines, runners, bars, ducts and the like in the
plane of the ceiling).
C. Support larger runs directly from structural slabs, decks or framing members.
D. As a minimum procedure, where weight applied to the attachment points is 45 kg (100 lbs) or
less, and in coordination with a structural engineer, fastened to building elements of 1)
Wood—with wood screws; 2) Concrete except pre-cast and solid masonry—with bolts and
51
SECTION 27 05 28.29 NON-CONTINUOUS CABLE SUPPORTS
E. In TRs, cables shall be Velcro tied to ladder racks, trays, cabinets, strain relief bars, etc. at
intervals not to exceed 600 mm (24 in.). Tie wraps are not acceptable.
F. See Section 27 05 28.35 for minimum clearances between cables and floor tiles.
G. When supporting cable above ceiling tiles, a minimum of 75 mm (3 in.) clear vertical space
shall be available above the ceiling tiles for the horizontal cabling and pathway.
H. An independent ceiling support rod or wire shall be used to mount appropriate cable
fasteners loaded with multiple cables up to the total weight for which the fastener is
approved. The fastener design shall not interfere with the inserting or removing of the ceiling
tile.
I. Non-continuous cable supports should be located at intervals not to exceed 1.5 m (60 in.).
K. All components of the non-continuous cable support shall be free of burrs, sharp edges, or
projections that can damage cable insulation. Abrasive supports (e.g., threaded rod) shall
have the abrasive portion protected with a smooth, non-scratching covering so that cable can
be pulled without physical damage.
L. Where innerduct or cable is supported to access floor pedestals without the use of pre-
fabricated J-hooks, they shall be secured to pedestals using Velcro® or Millepede® Mille-Ties
releasable cable ties for easy modification as needed.
M. Cables may be bound together with properly rated Velcro® or Millepede® Mille-Ties
releasable cable ties for neatness between support structures.
END OF SECTION
52
SECTION 27 05 28.30
PART 1 – GENERAL
1.1 RESPONSIBILITY
A. The labor and materials associated with work described in this Section may be furnished by
other trades.
A. Contractor is responsible for satisfying all structural concerns before floor penetrations are
implemented.
1.3 SUBMITTALS
A. Contractor shall submit plans for location of all sleeves and slots to the building’s structural
engineer for approval, in the form of three copies of the appropriate drawings. Upon
approval, one copy will be returned to Contractor, at which time Contractor shall be permitted
to commence cutting.
B. Where x-rays are required, original films shall be transferred within three days of completion
of coring or cutting to Building Owner.
PART 2 – PRODUCTS
2.1 MATERIALS
A. All materials required for installation of sleeves are the responsibility of Contractor. This
includes, but is not limited to conduit, clamps, and approved firestopping materials. See
Section 21 07 16 for firestop detail.
PART 3 – EXECUTION
53
SECTION 27 05 28.30 SLEEVES AND SLOTS
A. In occupied buildings, core drilling shall be completed after regular office hours and under the
supervision of a structural engineer.
3.2 INSTALLATION
A. Sleeves or slots shall not be left open except during cable installation and shall be properly
firestopped per applicable codes.
B. Where a slot is used, it shall have a minimum 25 mm (1 in) curb around the top of the slot.
Where a sleeve is used, it shall extend 25-75 mm (1-3 in) above the floor.
C. Cutting and patching: Provide, per the OPR’s requirements, cutting, core drilling, and related
patching.
E. When developing penetrations through solid walls, caulk conduit penetrations for full
thickness of the wall to ensure adequate waterproofing. At fire-rated floors and partitions,
pack the sleeves with approved packing for the full depth of the sleeve, including caulking
both ends.
F. Brace all systems to withstand lateral and vertical forces that result from earthquake or wind,
in accordance with NUSIG guidelines.
END OF SECTION
54
SECTION 27 05 28.31
GRIPS
PART 1 – GENERAL
A. All vertical cables shall be supported so as to ensure a structurally sound cable plant. Grips
shall be placed so as to ensure that the failure of a single grip will not cause a “cascade”
failure down the riser stack.
B. Groups of cables may be gripped, provided manufacturer specifications are complied with.
1.2 SUBMITTALS
PART 2 – PRODUCTS
2.1 MATERIALS
PART 3 – EXECUTION
3.1 INSTALLATION
A. Grips shall be secured to surfaces that have been verified to support the rated capacity of the
grip(s). These surfaces may be walls or floors or vertical ladder racks. Grips shall not be
supported by sleeves.
B. Where grips are placed to support cables located in conduit, they shall be located in
accessible pull boxes.
C. If, in the opinion of the OPR, additional cable strain relief is required, Contractor shall provide
additional grips.
D. Kellems® grips shall be taped at the bottom with friction tape to prevent slippage.
END OF SECTION
55
SECTION 27 05 28.32
POKE THRU
PART 1 – GENERAL
1.1 RESPONSIBILITY
A. The labor and materials associated with work described in this Section are typically furnished
by other trades.
PART 3 – EXECUTION
3.1 INSTALLATION
A. Wherever poke thru devices are employed, particular care shall be taken to ensure that the
cable routing through the poke thru is terminated in the TR that serves that floor. In no case
shall cables served via poke thrus be terminated in the TR on the floor below the poke thru
outlet location.
B. Where poke thru cabling penetrates into space that is not occupied by JPMC, reasonable
steps shall be taken to mitigate Information Technology risk associated with access to JPMC
infrastructure by others.
C. In all cases, proper firestopping procedures shall be employed in the installation and
administration of poke thrus. See Section 21 07 16 for additional information.
END OF SECTION
56
SECTION 27 05 28.33
PART 1 – GENERAL
1.1 RESPONSIBILITY
A. The labor and materials associated with work described in this Section are typically furnished
by other trades.
1.2 SUBMITTALS
PART 3 – EXECUTION
3.1 GENERAL
A. Installation of cables shall follow the completion of the items identified for Shell Ready in
Appendix A – WTS Definition and Checklists for MER and TR Acceptance.
B. Utilize nylon snakes or metallic fish tapes with ball type heads to set up for pulling.
C. In raceways 2” trade size and larger, utilize a pulling assembly ahead of wires consisting of a
suitable brush followed by an 85% diameter ball mandrel. Submit certifications that
mandreling has been performed as specified.
D. Slack on cables located in cabinets and pull boxes shall be formed and set in place in
groupings corresponding to their occupancy of raceways. They shall also be arranged, with
insulators and supports provided where necessary, such that cable shims or other such
temporary expedients do not have to be left permanently in place to prevent the cable from
shifting when covers or trims are removed.
A. Conduit sizing is directly related to the planned diameter of the cable and the maximum pull
tension that can be applied to the cable without degradation of the cable transmission
properties. The pull tension limit is based on the strength of the conduit (including sidewall
pressure), the strength of the pull line, the geometry of the conduit system, and the strength
of the cable. The position of the bends and length of the conduit system will affect the pull
tension that will be imposed on a cable. For instance, pulling cable in one direction may
cause a cable pull tension of 2700 N (600 lbf) whereas pulling from the opposite direction
may cause a tension of 1350 N (300 lbf). The pull tension of the planned cable to be installed
shall be calculated in both directions. The greater of the calculated pull forces shall not
exceed the pull force requirements of the planned cable to be installed. To reduce friction
during pulls, see Section 33 82 53.
END OF SECTION
57
SECTION 27 05 28.34 INNERDUCT
SECTION 27 05 28.34
INNERDUCT
PART 1 – GENERAL
To allow for future communication upgrades, including transitioning from multi-pair copper cables to
optical fiber media, a specific number of conduits shall be dedicated for that purpose. And to further that
effort and achieve maximum conduit utilization, those conduits shall contain innerduct.
A. Innerduct is a nonmetallic raceway placed within a larger raceway. For the purposes of this
Section, it may be hard-sided (hereinafter referred to as “innerduct”), or soft-sided flexible
textile raceway (hereinafter referred to as “Soft Duct”). If multiple cables are to be pulled
through a single innerduct or Soft Duct cell, they should be pulled at the same time. Soft
Duct provides multiple sleeves within conduits and empty cells should be provided for future
growth.
B. Innerduct is employed when fiber optic cables are routed in unprotected areas.
E. Contractor should coordinate a site visit from the Soft Duct manufacturer to oversee the
installation when 1) the contractor has never utilized this product in the past; or 2) when the
aggregate length of the installation exceeds 1,500 m (5,000 ft).
PART 2 - PRODUCTS
A. Innerduct shall be rated for the purpose. Innerduct listed in this section is not plenum rated.
Contractor shall exercise diligence in ensuring that the innerduct installed meets the
requirements of authorities having jurisdiction.
B. Local or national codes may or may not require plenum or Low Smoke Zero Halogen in some
applications. It is Contractor’s responsibility to install materials that are appropriate to the
environment. If Contractor installs innerduct or Soft Duct that is inappropriate to the
environment (e.g. plenum-rated in spaces that do not require plenum, or non-plenum-rated in
spaces that require plenum), Contractor shall be expected to remove the inappropriate
innerduct or Soft Duct and install appropriate innerduct or Soft Duct at their sole expense.
2.2 SIZING
A. Consistent use of innerduct can result in rapid exhaustion of cable pathways. Accordingly,
contractor shall always employ the smallest diameter innerduct for the purpose of the project.
B. Contractor shall seek OPR approval before employing 50 mm (2 in) diameter innerduct.
C. Except as noted herein, conduit that is 50 mm (2 in) in diameter should be equipped with 2”
3-cell Soft Duct quantity 1. Conduit that is 75 mm (3 in) should be equipped with 3” 3-cell
58
SECTION 27 05 28.34 INNERDUCT
Soft Duct, maximum quantity 2; and 100 mm (4 in) in diameter should be equipped with 3” 3-
cell Soft Duct, maximum quantity 3.
D. When 3” 3-cell Soft Duct is too small to accommodate large diameter cables and large O.D.
factory terminated pulling grips, conduit that is 75 mm (3 in) should be equipped with 4” 3-cell
Soft Duct, maximum quantity 1; and 100 mm (4 in) in diameter should be equipped with 4” 3-
cell Soft Duct, maximum quantity 2.
E. The outside diameter of pulling grips associated with factory terminated fiber trunk cables will
affect the selection of Soft Duct. See Table 1 for detail,
2.4 MATERIALS
A. Standard Outdoor Textile Innerduct: Micro (33mm), 2-inch, 3-inch and 4-inch single or multi-
cell polyester/nylon textile innerduct containing 1250lb polyester flat woven pull tape.
B. Detectable Outdoor Textile Innerduct: Micro (32mm), 2-inch, 3-inch and 4-inch single or multi-
cell polyester/nylon textile innerduct containing 1250lb polyester flat woven pull tape, and a
solid copper, polyvinyl color coated conductor (19AWG minimum) for tracing and rated for a
minimum of 6 amps and 600 volts. Conductor shall be placed in the sidewall edge fold of the
textile sleeve.
C. Indoor Textile Innerduct (Riser-listed): Micro (32mm), 2-inch, 3-inch and 4-inch single or
multi-cell nylon textile innerduct containing 1250lb polyester flat woven pull tape which meets
UL2024A for flame propagation and smoke density values for general applications.
D. Plenum-Listed Textile Innerduct: Micro (32mm), 2-inch and 3-inch single or multi-cell nylon
textile innerduct containing 200lb nylon-resin flat woven pull tape which meets UL2024A for
flame propagation and smoke density values for use in air handling spaces.
2.6 TEXTILE INNERDUCT FITTINGS
A. Conduit Plugs: Compression-type conduit plugs with locking nuts for sealing and securing
one or more textile innerducts within a 4-inch inside diameter conduit, e.g.:
59
SECTION 27 05 28.34 INNERDUCT
a. 4-inch plug with nine holes for cables in a 3 pack (9-cell) configuration
B. Termination Bags: Inflation-type bags for sealing and securing around one or more textile
innerducts and cables within 2-inch outside diameter or larger conduit.
2.7 PULL TAPE
A. Pull Tape: measuring and pulling tape constructed of synthetic fiber, printed with accurate
sequential footage marks. Color-coded.
2.8 PENETRATION SEALING MATERIALS
A. Duct Water Seal: products suitable for closing underground and entrance conduit openings
where innerduct or cable is installed, to prevent entry of gases, liquids, or rodents into the
structure.
PART 3 – EXECUTION
A. Protect products from the effects of moisture, UV exposure, corrosion and physical damage
during construction.
B. Where practical, plan the installation of innerduct in ladder rack and cable tray so that innerducts
are installed and secured to one side of the ladder rack and cable tray, stacked where possible,
to reserve space for other cable types.
C. Where innerduct is installed below access floors, preserve cabinet and vertical manager space by
stubbing the innerduct within 50 mm (2 in) of its emergence through the access floor.
A. Provide textile innerduct in conduit and wire ways, and place textile innerduct within and under
cable trays using continuous un-spliced lengths of textile innerduct between maintenance holes,
pull boxes, and/or termination points as indicated on the drawings.
B. Make a 2" incision, approximately 18" from the end of textile innerduct. Pull out and cut off
approximately 2 feet of pull-tape. Thus allowing the pull tape ends to retract back into the cells.
C. Using approximately 6 feet of pull tape, tie a non-slip knot to the incision. Then tie 3 to 6 half-hitch
knots down to the end of textile innerduct. Apply black vinyl tape over all knots and the end of
textile innerduct. Using a Bow Line knot tie a swivel to the end of 3 feet pull tape. For multi-pack
installations one swivel is sufficient with staggers in each textile innerduct.
D. Using a Bow Line knot, attach the pull rope located in the rigid conduit to the other end of the
swivel. Install textile innerduct – ensuring that no twist is introduced to the innerduct.
E. Provide suitable textile innerduct slack in the maintenance holes, hand holes, pull boxes, and at
turns to ensure there is no kinking or binding of the product.
60
SECTION 27 05 28.34 INNERDUCT
1. Design & install hangers and other similar fittings adequate to support loads and so as to not
damage innerduct.
2. Do not fasten textile innerduct to steam, water, or other piping, ductwork, mechanical
equipment, electrical equipment, electrical raceways, or wires
3. When appropriate, use the following cable ties to secure textile innerduct through previously
created incisions:
a) Plenum areas: plenum-rated plastic or stainless steel
b) Non plenum areas: Conventional flame retardant nylon ties
c) Underground locations : Conventional plastic cable ties
1. At locations where textile innerduct will be continuous through a manhole or hand hole, allow
sufficient slack so that the innerduct may be secured to the side of the vault maintaining the
minimum bend radius.
2. At maintenance holes serving as the junction location, pull the exposed end of the innerduct
to the far end of the vault, install termination bag, and secure to the vault.
H. Cable Tray and Runway Installation: Cut incisions every 24 inches into the edge of the textile
innerduct and cable wrap to one side of vertical ladder rack or horizontal ladder-type cable tray at
each incision.
A. Seal all conduit and textile innerduct entering structures at the first box or outlet to prevent
entrance into the structure of gases, liquids or rodents.
B. Inspect fire stopping installation by others between building structure and conduit, wire way, and
cable tray to verify integrity of installation.
C. Exposed Textile Innerduct Penetrations: Install conduit sleeves or fire barrier sealing systems in
all openings where open and exposed textile innerduct passes through fire-rated walls and floors.
After installation, install intumescent fire barrier penetration sealing material (Hilti system)
between textile innerduct and sleeves or fire barrier system.
D. Raceway Penetrations: After textile innerduct installation, install intumescent fire barrier
penetration sealing material (Hilti system) between textile innerduct and conduit or wire way at all
exposed penetration locations.
E. Protect adjacent surfaces from damage during water seal or fire stop installation. Repair any
damage.
END OF SECTION
61
SECTION 27 05 28.35
ACCESS FLOOR
PART 1 – GENERAL
A. Minimum clearance from the bottom of the access panel to any cables or innerduct located
beneath the floor shall be 20 mm (0.75 in)
B. There shall be a minimum of 50 mm (2 in) of free space between the top of the cable tray
side rails and the underside of the stringers.
C. If cable trays with covers or raceways are used under the access floor, the free space above
the tray shall allow for easy removal of covers.
PART 3 – EXECUTION
3.1 INSTALLATION
A. Telecommunications cables below access floors shall be routed below the floor parallel to
floor grid lines, never diagonally between end points.
B. Stringers form a framework of receptacles into which tiles are inserted. They provide lateral
support by interlocking with the pedestals. Stringers shall not be removed unless previously
approved on a per-case basis by OPR.
C. From time to time, it will be necessary to cut floor tiles in order to create a pathway between
the space below the access floor and the space above the access floor. Floor tiles shall not
be cut within the TR, MER, or Co-Lo space. Cutting and other fabrication shall be performed
in designated areas.
D. Cutouts in floor tiles shall be protected with permanent grommets to prevent harm to
personnel or property.
E. To contain under-floor static air pressure, cutouts in access floors shall be equipped with “L”
shaped grommets and brushes, which limit the escape of air but allow installation of cables
through the openings as needed.
END OF SECTION
62
SECTION 27 05 53
IDENTIFICATION
PART 1 - GENERAL
A. System Acceptance shall be withheld until OPR has reviewed and approved all labeling as
defined elsewhere in this section.
B. In cases where the cabling infrastructure is being installed in a building that is not currently
occupied by JPMC, the identification methodology shall follow the current prevailing version
of this Standard. In cases where new infrastructure is being installed in a building that is
currently occupied by JPMC, Contractor shall follow the labeling methodology employed in
the pre-existing infrastructure.
D. All labels shall be installed in accordance with information contained in project drawings and
termination schedules as specified in this Section.
E. All labels shall be indelible, pre-printed (not hand-written), and permanent, using Brady
printer or equivalent, Arial font or equivalent. The text color shall be black, unless affixed on
a black surface, in which case the label shall be black and text shall be white. Text and label
colors may be modified when reflecting cable route diversity as defined elsewhere in this
Section 27 05 53.
F. Where route diversity is employed, and the near and far end locations are identical, route
diversity shall be indicated through the use of blue and white labels, where white indicates
the primary route and blue indicates the diverse route.
G. Cable jackets shall be labeled for all factory-terminated and pre-terminated cables.
PART 2 - PRODUCTS
2.2 MATERIALS
PART 3 - EXECUTION
63
SECTION 27 05 53 IDENTIFICATION
A. For corporate sites, the following infrastructure components shall be included and fully
labeled in the identification schema:
A. Each information outlet identifier shall be numbered in accordance with the Identification
Standard (see Appendix D), using paper labels and clear windows included with each
appropriate information outlet faceplate. Where clear windows are not applicable, Contractor
shall coordinate a compliant label that is resistant to damage or degradation over time (e.g.
vinyl). Text height and positioning shall be in accordance with the Faceplate Configuration
Standard (see Appendix C).
B. Information outlets shall be located in each faceplate in accordance with the Faceplate
Configuration Standard (see Appendix C).
A. Pre-connectorized cabling shall be fully compliant with the Identification Standard (see
Appendix D).
C. Labels shall be affixed to both ends of each pre-connectorized cable conspicuously displayed
just prior to each cable being routed into the termination device.
A. All cable numbering shall be fully compliant with the Identification Standard (see Appendix D).
B. Break-out cabling (e.g. one 36-strand fiber cable under a single sheath, furcated into three
12-fiber fan-outs, each of which is separately sheathed) should be labeled at the largest
incremental level, not at the sub-group level.
D. Labels shall be affixed to both ends of each riser, horizontal, and tie cable conspicuously
displayed just prior to each cable being routed into the termination device.
A. Copper patch panel port identification shall be fully compliant with the Identification Standard
(see Appendix D).
B. If label is affixed to a black or dark gray surface, label information shall be white in color. If
label is affixed to beige or light-colored surface, label information shall be black in color.
64
SECTION 27 05 53 IDENTIFICATION
C. Copper patch panel labels shall employ manufacturer-supplied labeling materials and covers
(if applicable), affixed to each panel in accordance with manufacturer specifications.
D. Copper patch panel labels shall be black and text shall be white. Text and label colors may
be modified when reflecting route diversity as defined elsewhere in this Section 27 05 53.
A. Fiber patch panel strand identification shall be fully compliant with the Identification Standard
(see Appendix D).
B. If label is affixed to a black or dark gray surface, label information shall be white in color. If
label is affixed to beige or light-colored surface, label information shall be black in color.
C. Self-adhesive laser-printed sheet affixed to the inside door of the patch panel enclosures.
Affixed sheet shall be sized 10 mm (½ in.) smaller in the vertical and horizontal dimension
than the fiber patch panel door (e.g. 130 mm H X 500 mm W (5.25” H X 19” W) door = 120
mm H X 490 mm W (4.75” H X 18.5" W) label). Use of more than one label sheet per panel
is permissible.
65
SECTION 27 11 23 - RELAY RACKS, NETWORK
CABINETS, LADDER RACK,
CABLE TRAY
SECTION 27 11 23
PART 1 – GENERAL
A. Ladder rack and cable tray are employed to carry bulk volumes of cable vertically or
horizontally in applications where conduit can be avoided, thereby reducing project costs.
B. Relay racks and network cabinets offer a uniform location for the mounting and servicing of
telecommunications equipment.
C. Unequal flange relay racks are employed to accommodate Direct Current wiring that may
route within the channels of the rack. The large flange is positioned at the front and the small
flange is positioned at the rear.
D. In some regions, cabinets are utilized in lieu of racks for some applications. Cabinets and
patching frames other than those listed within this Standard may be considered, provided
they have been reviewed and approved through the exception process.
PART 2 - PRODUCTS
2.1 MATERIALS
B. As part of their base quotation, Contractor is responsible for furnishing and installing all
miscellaneous hardware (e.g. cage nuts, screws), required to accomplish a complete’
working installation.
A. Cable pathway specified herein includes overhead wire basket tray, ladder rack, fiber patch
cord tray, under floor wire basket tray, under floor mat, and cable channel. Only cable
pathway products defined herein are acceptable for deployment within JPMC facilities.
B. Cable pathway specified herein shall be sized to accommodate the initial calculated fill plus a
minimum growth factor of 25%.
66
SECTION 27 11 23 - RELAY RACKS, NETWORK
CABINETS, LADDER RACK,
CABLE TRAY
A. Full support across the base of the tray is required. For overhead support, trapeze mount is
preferred. Center tray support of overhead tray is not acceptable.
F. Where tray is exposed, it shall be powder coated or OEM painted in a color that matches the
racks/cabinets color scheme. If the wire basket tray is located in air handling space,
treatment shall be pre-galvanized or powder coated or OEM painted in a color that matches
the racks/cabinets color scheme.
G. When supporting from below with threaded rod, employ only 16 mm (⅝ in) threaded rod.
When supporting from above with threaded rod, employ only 13 mm (½ in) threaded rod.
A. Full support across the base of the ladder rack is required. For overhead support, trapeze
mount is preferred. Center tray support of overhead tray is not acceptable.
D. Standard widths shall be 300 mm, 450 mm, and 600 mm (12 in, 18 in, 24 in).
F. At 1500 mm (5 ft) support intervals, ladder rack shall be capable of supporting a minimum of
1367 N/m (217 lbs/ft)
G. Where ladder rack is exposed, it shall be powder coated or OEM painted in a color that
matches the racks/cabinets color scheme. If the ladder rack is located in air handling space,
treatment shall be powder coated or OEM painted in a color that matches the racks/cabinets
color scheme.
H. When supporting from below with threaded rod, employ only 16 mm (⅝ in) threaded rod.
When supporting from above with threaded rod, employ only 13 mm (½ in) threaded rod.
B. Fiber patch cord tray is constructed of plastic. Metal hardware (e.g. screws) may be used to
assemble and mount the tray.
67
SECTION 27 11 23 - RELAY RACKS, NETWORK
CABINETS, LADDER RACK,
CABLE TRAY
C. Side rails shall be a minimum of 25 mm (1 in) and a maximum of 150 mm (6 in) High.
E. To mitigate accumulation of metal whiskers when the space below the access floor is utilized
for air handling, only pre-galvanized and powder-coated finish are acceptable. Where access
floor tray is powder coated or OEM painted, the color may indicate its function.
A. Floor mat may be used in EMEA and APAC regions when necessary. It is used for placing
cables directly on the permanent floor.
B. Floor matting should be a minimum of 13mm (1/2”) thick and fill the aisle between the floor
pedestals.
C. Where floor matting is deployed, it shall be secured to the sub-floor using manufacturer
approved materials to prevent lifting where few or no cables are present, and to prevent
disturbance of the under floor airflow.
D. Foam matting shall comply with the fire performance requirements for the space it occupies,
and as further dictated by the Authority Having Jurisdiction.
A. Cable channel tray may also be referred to as trunking or duct. It is comprised of bottom,
sides, and a top cover, all of which are constructed of solid, non-vented metallic materials. It
is typically located below the access floor and in other areas where it is necessary to isolate
cable from surroundings, typically for reasons of security or code compliance.
B. Standard sizes are 100 mm x 100 mm (4 in x 4 in) and 150 mm x 150 mm (6 in x 6 in).
C. Where channel tray is exposed, it shall be powder coated or OEM painted in a color that
identifies its function. If the channel tray is located in air handling space, construction shall
be aluminum, pre-galvanized, or powder coated or OEM painted in a color that identifies its
function.
PART 3 – EXECUTION
3.1 INSTALLATION
A. Deliver materials to the site in Standard lengths, and store where continuously protected from
moisture and weather.
68
SECTION 27 11 23 - RELAY RACKS, NETWORK
CABINETS, LADDER RACK,
CABLE TRAY
C. All relay racks, cabinets, ladder rack, and cable tray shall be bonded to ground (earth) in
accordance with manufacturer specifications, and prevailing codes and Standards.
E. The inside of the cable tray, cable runway and wireway shall be free of burrs, sharp edges, or
projections that can damage cable insulation. Abrasive supports (e.g., threaded rod) shall
have all visible portions, including the portion within the tray, protected using threaded rod
cover as specified herein for the purposes of cable protection and aesthetics. All basket tray
shall be cut so that the exposed wire end is square (not pointed or “V” shaped), and all sharp
edges removed.
F. In all cases, cables that enter ladder rack or basket tray from below shall employ appropriate
means of support to ensure proper cable performance, such as radius drops and dropouts as
listed above. In no case shall cables enter basket tray from below over the top edge of
basket tray side rails. This requirement does not relieve contractor of the requirement to
neatly dress cables as specified in this section 27 11 23.
G. Where relay racks are equipped with significant quantities of fiber or copper patch panels,
cables terminated into the back of the panels shall be routed through vertical managers
employing careful planning, so as to result in efficient use of vertical manager space, and
reduction or elimination of “dead spots” where space is present but cannot practically be
used. In such cases, where cables route into vertical managers from above, the bottom-most
panel shall be cabled first, then the panel above it, and so forth. Where cables route into
vertical managers from below, the opposite practice shall be employed.
H. All relay rack configurations shall be compliant with Uniform Building Code, ANSI-T1E1, and
Telcordia NEBS Standards compliant regarding seismic activity. Seismic zone 1 racks shall
have side restraints. Seismic zone 2-4 racks shall be of heavy-duty construction with side
restraints, and shall be equipped with additional floor anchor points wherever required.
I. Relay racks shall be assembled and mounted in locations shown in the Drawings and as
described herein. Each rack shall be assembled in accordance with the manufacturer's
instructions and recommendations. Each rack shall be mounted such that the side rails are
plumb. Bolts shall be tightened to the extent that it holds the mounting hardware firmly, but
not so tight as to distort the hardware or strip the threads. Equipment racks are to be co-
located with power outlets to allow for easy connection of rack-mounted equipment to the
power system. Racks and cable management hardware shall be securely bolted together.
J. The rack should be attached to TR and MER floors with ⅜ in threaded rod and anchors
designed for the purpose. The floor under the rack should be level within 5 mm (3/16 in). Use
a floor-leveling cement compound if necessary. Where the MER and TR are served by
access floors, lag screws shall be extended through the access floor into the concrete slab
below.
K. Support tray so that the ends of the section are not directly on the support or at mid-span.
The support span should not be greater than the straight section length or as otherwise
specified by the manufacturer. No more than one splice shall be located between supports.
L. Where the TR, MER, or Co-Lo is served by access floors that are mounted less than 900 mm
(36 in) above the subfloor, rack shall be supported to the concrete slab below using ⅜ in
69
SECTION 27 11 23 - RELAY RACKS, NETWORK
CABINETS, LADDER RACK,
CABLE TRAY
threaded rod and anchors designed for the purpose. When the rack is secured to the access
floor by means of threaded rod protruding through the rack base plate mounting hole and is
secured by a nut, the threaded rod shall protrude no more than 13 mm (.5 in) above the nut
and all sharp edges shall be removed. For access floors that are 900 mm (36 in) or more
above the subfloor, see OPR personnel for attachment requirements. In all cases,
requirements regarding environmental contaminants shall be adhered to as described in
Protection of Property at the beginning in Section 01 00 00 above.
M. Threaded rod that is suspended from overhead to support trapeze mounted tray shall
protrude no more than 13 mm (.5 in) below the lowest nut.
N. All overhead cable trays shall be located at the same height above the finished floor. Where
obstacles are present along the path of the tray, Contractor shall document such obstacles
and necessary adjustments in tray design, submitting said documentation to OPR for written
approval before proceeding.
O. The mounting height of wire basket tray that is installed below the access floor shall be
closely coordinated with the project team in order to avoid air dams and conflicts with other
below-floor infrastructure (i.e. power whips, smoke detectors). Where possible, the tray
bottom should be located at a depth equal to 150 mm (6 in) plus the depth of the tray below
the access floor tile.
END OF SECTION
70
SECTION 27 13 14
COPPER BACKBONE
PART 1 – GENERAL
B. All backbone cables are terminated, one pair per port on RJ-45 Patch panels.
PART 2 – PRODUCTS
A. Appendix E includes part numbers for CMP, CMR, and LSZH cable. Local or national codes
may require specific cable grading in specific applications. It is Contractor’s responsibility to
install cable that is appropriate to the environment. If Contractor installs cable that is
inappropriate to the environment (e.g. plenum-rated cable in spaces that do not require plenum
cable or riser-rated cable in spaces that require plenum cable), the Contractor shall be
expected to tear out the inappropriate cable and install appropriate cable at their sole expense.
A. Utilize Category 6 patch cords between backbone and horizontal patch panels.
2.3 MATERIALS
B. Materials shall be as listed or shall be equivalent products of other manufacturers meeting the
intent and quality level of this specification. Materials must be compatible with the end-to-end
solution being proposed. Proposals for equivalent products must be presented to the OPR via
RFI’s, Submittals, and/or Shop Drawings. OPR written approval is required before any
substitutions are made.
A. In legacy installations that include visually exposed cables, the cable jacket color should match
the color of the existing cable jackets.
71
SECTION 27 13 14 COPPER BACKBONE
PART 3 – EXECUTION
3.1 INSTALLATION
A. Sleeves shall not be over-populated with cables. Sufficient spare capacity shall be allowed in
each sleeve to accommodate appropriate firestopping materials in accordance with
manufacturer specifications and the UL Fire Resistance Directory. Note that manufacturers
typically specify a 20% to 40% fill for their products.
B. Backbone cabling shall be terminated on RJ-45 Patch panels in the TRs and MER.
C. Cables shall be dressed-in, Velcro® or Millepede® Mille-Ties releasable cable ties, and
secured to the ladder rack, plywood backboard, and/or other suitable surfaces to ensure a
professional appearance and run straight, level, and parallel to building lines, with 90°
corners where possible. Contractor shall comply with manufacturer’s Standard pulling
tension and minimum bend radii at all times.
D. See 27 11 23 regarding cable routing and management when employing ladder rack and
basket tray.
E. Contractor shall furnish and install adequate cable strain relief (e.g. cable dropouts) to
accommodate the anticipated magnitude of cabling. Wherever fiber and copper cables are
segregated, strain relief shall be provided, including adequate provision for cable route
diversity where applicable.
END OF SECTION
72
SECTION 27 13 24 MULTIMODE FIBER BACKBONE
SECTION 27 13 24
PART 1 - GENERAL
B. Cables leaving the MER are routed directly to one or more evenly dispersed Intermediate
Cross-connects or Horizontal Cross-connects. In keeping with established Standards, the
segments or links will be limited to no more than two hierarchical levels of cross-connects in
this backbone cabling. Therefore from the Horizontal Cross-connect, only one cross-connect
point can be passed through to reach the MER, and interconnections between any two
Horizontal Cross-connects will pass through three or fewer cross-connects.
C. Field terminated fiber employing the manufacturer’s system should be performed by properly
trained personnel using approved tools and methods.
PART 2 - PRODUCTS
A. Appendix E includes part numbers for CMP, CMR, and LSZH cable. Local or national codes
may require specific cable grading in specific applications. It is Contractor’s responsibility to
install cable that is appropriate to the environment. If Contractor installs cable that is
inappropriate to the environment (e.g. riser-rated cable in spaces that require plenum cable),
Contractor shall be expected to tear out the inappropriate cable and install appropriate cable
at their sole expense.
A. Existing infrastructures that employ OM1 or OM2 fiber should be replaced with new
OM3/OM4 fiber. Materials listed presume use in a 100% new infrastructure.
B. It is contractor’s responsibility to ensure that the fiber cable type is compatible with the
environment.
A. Only factory terminated and field terminated fiber may be utilized in JPMC facilities. Fiber that
is pre-terminated (e.g., patch cords created by personnel not directly employed by the
manufacturer) is not permissible, unless previously approved in writing by OPR.
B. Field-terminated fiber is the preferred termination method. Fusion, anaerobic or UniCam®
terminations are permitted.
A. Multimode fiber shall be terminated into LC connectors unless approved in writing by OPR.
73
2.5 CABLE JACKETING
A. Cable jacketing may or may not be armored, depending upon the environment and the
application. See OPR for direction on cable jacketing requirements.
A. The fiber infrastructure serving each facility shall utilize the grade of cable that
accommodates the worst-case (longest) channel length required for that specific facility. At
the commencement of the installation process, Contractor shall identify and measure the
linear distance of the longest cable channel serving the facility (including appropriate length
patch cords at both ends), and establish the appropriate cable grade using Table 2 below as
appropriate. Contractor shall submit their findings and recommendations in writing to OPR.
Final assignment of cable grading shall be made in writing by OPR.
2.8 MATERIALS
A. In cases where the cabling infrastructure is being installed in a building not currently occupied
by JPMC, or where the new infrastructure is part of a strategic refresh of the entire existing
(Legacy) infrastructure as part of the project, competitive quotations including comparative
products from Corning and Systimax shall be furnished.
PART 3 – EXECUTION
3.1 INSTALLATION
A. Sleeves shall not be over-populated with cables. Sufficient spare capacity shall be allowed in
each sleeve to accommodate appropriate firestopping materials in accordance with
manufacturer specifications and the UL Fire Resistance Directory. Note that manufacturers
typically specify a 20% to 40% fill for their products.
74
SECTION 27 13 24 MULTIMODE FIBER BACKBONE
B. After fiber cable has been successfully tested in accordance with 01 45 23, all connector dust
covers shall be securely restored.
D. Whenever ordering factory-terminated cables, Contractor shall order cable in the exact length
desired, making allowance for slack requirements as set forth elsewhere in this section.
E. For new infrastructure, contractor shall practice care in installation of connectorized cable, as
any defective strands tested post-installation and pre-acceptance shall result in the
replacement of the entire defective cable / connector assembly at Contractor’s sole expense.
F. Manufacturer’s Standard pulling tension and minimum bend radii shall be complied with at all
times. Cables shall be dressed-in, Velcro® or Millepede® Mille-Ties releasable cable tied,
and secured to the ladder rack, plywood backboard, and/or other suitable surfaces so as to
ensure a professional appearance, run straight, level, and aligned with building lines, with 90°
corners where possible, bearing in mind manufacturer's recommended bend radii.
G. See 27 11 23 regarding cable routing and management when employing ladder rack and
basket tray.
H. In spaces where any airborne dust or contaminants may be present, especially during
construction, Contractor shall fully and properly protect any and all connectorized cables to
avoid transmission performance degradation associated with dust coming in contact with
connector contact points. If at all possible, and where allowed by the project timeline,
Contractor’s first choice should be to avoid this problem by refraining from installing any such
components until the risk of airborne dust and contaminants is eliminated (e.g. after floors
and ceilings are treated, and walls receive the final coat of paint).
J. Contractor is solely responsible for securing factory-terminated fiber cables to fiber housings
in accordance with manufacturer requirements. This includes furnishing and installing
appropriate attachment hardware at no additional charge to Owner.
K. Contractor is solely responsible for ensuring compliance with proper polarity utilizing proper
(e.g., Alpha/Beta) orientation of modules.
L. Contractor is solely responsible for populating the infrastructure so that any given Module
Housing contains consistent (e.g., Alpha/Beta) orientation. For example, all 12 modules are
mounted in a sample 4U Module Housing so that that the Alpha designation is located at the
top. Deviations from this requirement are permissible only with advance written OPR
approval. Likewise, where multiple Module Housings are mounted in a cross-connect field,
all modules in all Module Housings shall be populated with consistent (e.g., Alpha/Beta)
orientation.
M. Contractor shall furnish and install adequate cable strain relief (e.g. cable dropouts) to
accommodate the anticipated magnitude of cabling. Wherever fiber and copper cables are
segregated, dedicated multimode strain relief shall be provided, including adequate provision
for cable route diversity where applicable.
END OF SECTION
75
SECTION 27 13 25
PART 1 - GENERAL
PART 2 - PRODUCTS
A. Appendix E includes part numbers for CMP, CMR, and LSZH cable. Local or national codes
may require specific cable grading in specific applications. It is Contractor’s responsibility to
install cable that is appropriate to the environment. If Contractor installs cable that is
inappropriate to the environment (e.g. riser-rated cable in spaces that require plenum cable)
Contractor shall be expected to tear out the inappropriate cable and install appropriate cable
at their sole expense.
A. Only factory terminated and field terminated fiber may be utilized in JPMC facilities. Fiber that
is pre-terminated (e.g., patch cords created by personnel not directly employed by the
manufacturer) is not permissible, unless previously approved in writing by OPR.
B. Field-terminated fiber is the preferred termination method. Fusion, anaerobic or UniCam®
terminations are permitted.
A. Single-mode fiber shall be terminated into LC connectors unless approved in writing by OPR.
A. Cable jacketing may or may not be armored, depending upon the environment and the
application. See OPR for on cable jacketing requirements.
A. Where any part of a fiber cable routes beneath access floor supported by non-continuous
supports, or through more than one space unprotected by conduit, install within innerduct.
76
SECTION 27 13 25 SINGLE-MODE FIBER BACKBONE
2.7 MATERIALS
A. In cases where the cabling infrastructure is being installed in a building that is not currently
occupied by JPMC, or where the new infrastructure will be not connected to an existing
(Legacy) infrastructure as part of the project, competitive quotations including comparative
products from Corning and Systimax shall be furnished.
PART 3 – EXECUTION
3.1 INSTALLATION
B. Whenever ordering connectorized cables, Contractor shall order cable in the exact length
desired, making allowance for slack requirements as set forth elsewhere in this section.
D. Manufacturer’s Standard pulling tension and minimum bend radii shall be complied with at all
times. Cables shall be dressed-in, Velcro® or Millepede® Mille-Ties releasable cable tied,
and secured to the ladder rack, plywood backboard, and/or other suitable surfaces so as to
ensure a professional appearance, run straight, level, and aligned with building lines, with 90°
corners where possible, bearing in mind manufacturer's recommended bend radii.
E. See 27 11 23 regarding cable routing and management when employing ladder rack and
basket tray.
F. In spaces where any airborne dust or contaminants may be present, especially during
construction, Contractor shall fully and properly protect any and all connectorized cables to
avoid transmission performance degradation associated with dust coming in contact with
connector contact points. If at all possible, and where allowed by the project timeline,
Contractor’s first choice should be to avoid this problem by refraining from installing any such
components until the risk of airborne dust and contaminants is eliminated (e.g. after floors
and ceilings are treated, and walls receive the final coat of paint).
77
SECTION 27 13 25 SINGLE-MODE FIBER BACKBONE
H. Contractor is solely responsible for securing factory-terminated fiber cables to fiber housings
in accordance with manufacturer requirements. This includes furnishing and installing
appropriate attachment hardware at no additional charge to Owner
I. Contractor is solely responsible for ensuring compliance with proper polarity utilizing proper
(e.g., Alpha/Beta) orientation of modules.
J. Contractor is solely responsible for populating the infrastructure so that any given Module
Housing contains consistent (e.g., Alpha/Beta) orientation. For example, all 12 modules are
mounted in a sample 4U Module Housing so that that the Alpha designation is located at the
top. Deviations from this requirement are permissible only with advance written OPR
approval.
K. Contractor shall furnish and install adequate cable strain relief (e.g. cable dropouts) to
accommodate the anticipated magnitude of cabling. Wherever fiber and copper cables are
segregated, dedicated single-mode strain relief shall be provided, including adequate
provision for cable route diversity where applicable.
END OF SECTION
78
SECTION 27 13 34
PART 1 – GENERAL
A. The DS-3 backbone is designed to support coaxial-based DS-3 digital services. Cabling for
DS-3 digital circuits is comprised of two discrete coaxial cables for each circuit (one transmit
and one receive).
B. DS-3 coaxial backbone cables shall be equipped with BNC connectors at both ends of each
cable.
PART 2 – PRODUCTS
A. Appendix E includes part numbers for CMP and CMR cable. Local or national codes may
require specific cable grading in specific applications. It is Contractor’s responsibility to install
cable that is appropriate to the environment. If Contractor installs cable that is inappropriate
to the environment (e.g. plenum-rated cable in spaces that do not require plenum cable, or
riser-rated cable in spaces that require plenum cable), Contractor shall be expected to tear
out the inappropriate cable and install appropriate cable at their sole expense.
A. For patch cords, employ 735 cross-connect cable as specified herein. If DS-3 patch cord
lengths may exceed 6m (21 ft.), see OPR.
A. The DS-3 infrastructure serving each facility shall utilize either 734 or 735 grade cable, which
shall be determined based upon cable lengths as specified in the Coaxial Cable Grading
Schedule below.
2.4 MATERIALS
79
SECTION 27 13 34 DS-3 COAXIAL BACKBONE
OPR via RFI’s, Submittals, and/or Shop Drawings. OPR written approval is required before
any substitutions are made.
PART 3 – EXECUTION
3.1 INSTALLATION
A. Where applicable, sleeves shall not be over-populated with cables. Sufficient spare capacity
shall be allowed in each sleeve to accommodate appropriate firestopping materials in
accordance with manufacturer specifications and the UL Fire Resistance Directory. Note that
manufacturers typically specify a 20% to 40% fill for their products.
B. The minimum bend radius for coaxial cable shall not be less than recommended by the
manufacturer. If no recommendation is provided or known, the minimum bend radius shall be
10 times the cable outside diameter under no-load conditions and 20 times the cable outside
diameter when the cable is under a tensile load.
C. BNC connectors shall be matched to the cable type. Manufacturer-approved methods shall
always be employed when mounting connectors on cable ends.
D. See 27 11 23 regarding cable routing and management when employing ladder rack and
basket tray.
E. Except where required to accommodate cable route diversity, coaxial cables routing into the
back of BNC bulkhead panels shall be dressed so that no cables will cross an imaginary
vertical line that bisects the patch panel.
F. Cables shall be dressed-in, Velcro® or Millepede® Mille-Ties releasable cable tied, and
secured to the ladder rack, plywood backboard, and/or other suitable surfaces to ensure a
professional appearance and run straight, level, and parallel to building lines, with 90°
corners where possible. Contractor shall comply with manufacturer’s Standard pulling
tension and minimum bend radii at all times.
G. For each rack-mounted BNC bulkhead panel, install Chatsworth Wire Management bar, and
neatly Velcro® or Millepede® Mille-Ties releasable cable tie terminated cables to bar in
accordance with requirements as set forth elsewhere in this Section 27 13 34.
H. Contractor shall furnish and install adequate cable strain relief (e.g. cable dropouts) to
accommodate the anticipated magnitude of cabling. Wherever fiber and copper cables are
segregated, dedicated coaxial strain relief shall be provided, including adequate provision for
cable route diversity where applicable.
END OF SECTION
80
SECTION 27 15 00.19
CATEGORY 6 HORIZONTAL
PART 1 - GENERAL
A. All Category 6 cables originate either in the MER and are routed to work area outlets, or
originate in multiple Horizontal Cross-connects and are routed to work area outlets. In no
case shall Category 6 cable runs exceed 90m (295 ft) in length.
C. In all new construction environments, all Category 6 horizontal cable shall be installed in
accordance with this Section 27 15 00.19. Where new horizontal cable is being added to an
existing (Legacy) infrastructure that follows an earlier version JPMC cabling Standard,
Contractor shall furnish to OPR a detailed description of deviations from this Standard, and
upon OPR written approval, follow instead the Legacy Standard. In the case of Legacy
facilities that are served by cable that performs at Category 5e level or less, category 5e
cable shall be installed.
PART 2 – PRODUCTS
A. Appendix E includes part numbers for CMP, CMR, and LSZH cable. Local or national codes
may require specific cable grading in specific applications. It is Contractor’s responsibility to
install cable that is appropriate to the environment. If Contractor installs cable that is
inappropriate to the environment (e.g. plenum-rated cable in spaces that do not require
plenum cable or riser-rated cable in spaces that require plenum cable), Contractor shall be
expected to tear out the inappropriate cable and install appropriate cable at their sole
expense.
B. Only factory terminated patch cords may be utilized in JPMC facilities. UTP patch cords that
are pre-terminated (e.g., created by personnel not directly employed by the manufacturer) are
not permissible, unless previously approved in writing by OPR.
A. All patch cords for workstations shall be of length necessary to connect devices.
B. All patch cords for printers, facsimile machines, etc. shall be of length necessary to connect
devices.
C. Quantities and lengths of TR and MER patch cords shall be furnished by the Contractor, to
ensure appropriate lengths and timely material procurement.
81
SECTION 27 15 00.19 CATEGORY 6 HORIZONTAL
A. Faceplate colors shall be as specified in new construction environments and in other cases
may be modified via written OPR approval to ensure compatibility with the pre-existing
environment.
2.4 MATERIALS
A. As defined elsewhere within this Standard, Category 6 cable is the default product for all UTP
cabling within JPMC facilities.
B. Category 6A shall be deployed for all new wireless access points and all new security camera
locations, and equipped with all related termination and connection materials. See SECTION
27 21 33 for full requirements for this application.
A. In legacy installations that include exposed cables, the cable jacket color should match the
color of the existing exposed cable jackets.
PART 3 – EXECUTION
3.1 INSTALLATION
B. Bundles of Category 6 cable shall be combed (neatly aligned) and carefully dressed in order
to achieve a desirable aesthetic appearance.
C. Except where required to accommodate cable route diversity, category 6 cables routing into
the back of RJ45 patch panels shall be dressed so that no cables will cross an imaginary
vertical line that bisects the patch panel (e.g. facing the back of a 48 port patch panel, cables
terminated in ports 1-12 and 25-36 shall route to the left vertical manager and cables
terminated in ports 13-24 and 37-48 shall route to the right vertical manager).
D. At the cross-connect point, all conductors of each Category 6 cable shall be terminated.
Refer to design drawings for configuration information.
82
SECTION 27 15 00.19 CATEGORY 6 HORIZONTAL
E. Category 6 cables shall not be kinked or unduly twisted, nor shall the integrity of the cable
sheath be compromised in any fashion. Cable bundles shall not be clinched together with
excessive force, thereby holding jacket deformation to a minimum. Tie wraps shall not be
employed for securing category 6 cables. Individual cable bend radii may be no less than
four times the cable diameter or 15 mm (0.6 in.), whichever is greater.
F. In spaces where any airborne dust or contaminants may be present, Contractor shall properly
protect any and all connectorized cables to avoid transmission performance degradation
associated with dust coming in contact with connector contact points.
H. Wall mounted patch panels shall be provided with hinged frames or wall mounted enclosures
that swing out to provide rear access to the patch panel terminations.
I. Where the furniture system does not contain an integral raceway, and no apparent cable
management method is provided, cabling shall be neatly dressed and concealed upon review
and approval by the OPR. Velcro, double sided tape or other adhesive materials will only be
accepted if specifically stated by the OPR.
J. Cabling to wall mounted workstation outlets shall terminate in a single- or double-gang box
provided by others. Contractor shall provide the necessary connectors (as described
elsewhere) under a single single-gang faceplate. The type of faceplate to be used shall be
coordinated with the architect for color, finish, etc.
K. Cabling to floor mounted workstation outlets shall be terminated in a flush or surface mounted
poke-thru or service fitting provided by others. All cabling and connectors shall remain within
the poke-thru or service fitting housing. If necessary, the Contractor shall modify the blank
plates provided with the poke-thru or service fitting in order to accommodate the connectors.
See Section 27 05 28.32 for additional information regarding poke-thru fittings.
L. For patch panels mounted on hinged frames or wall enclosures that swing out, cables shall
approach the rear of patch panels from the hinged side to allow the patch panel to swing out
freely, after all cables have been terminated.
M. Cables shall be dressed-in, Velcro® or Millepede® Mille-Ties releasable cable tied, and
secured to the ladder rack, plywood backboard, and/or other suitable surfaces to ensure a
professional appearance and run straight, level, and parallel to building lines, with 90°
corners where possible. Contractor shall comply with manufacturer’s Standard pulling
tension and minimum bend radii at all times.
N. Contractor shall furnish and install adequate cable strain relief (e.g. cable dropouts) to
accommodate the anticipated magnitude of cabling. Wherever fiber and copper cables are
segregated, dedicated category 6 strain relief shall be provided, including adequate provision
for cable route diversity where applicable.
END OF SECTION
83
SECTION 27 21 33 CATEGORY 6A WIRELESS ACCESS POINT
SECTION 27 21 33
PART 1 - GENERAL
A. Wireless LANs represent information security risk, and should only be deployed under
carefully controlled and properly managed conditions.
B. Each wireless access point (WAP) is connected to the network via two Category 6A
connections that track requirements specified in Section 27 15 00.19. .
C. To maintain plenum rating, the WAP connections shall be terminated into jacks that are
mounted in a metallic faceplate that is installed on a metallic box (WAP Work Station Outlet).
D. All Category 6A WAP cables either originate in the MER and are routed to the WAP, or
originate in the Horizontal Cross-connect and are routed to the WAP. In no case shall
Category 6A cable runs exceed 90m (295 ft) in length.
E. Except as otherwise specified in this Section 27 21 33, WAP cabling shall be integrated with
other elements of the horizontal infrastructure, employing products and execution in
accordance with Section 27 15 00.19.
F. Products and execution of Category 6A wireless access points shall be in accordance with
this Standard, including, but not limited to Sections 01 00 00, 27 05 28.29, 21 07 16, 01 45
23, 27 05 53, and 01 78 36.
NOTE: All new security camera locations shall be equipped with Category 6A and follow
the guidance within this section of the Standard.
PART 2 – PRODUCTS
A. Where mandated by the Authority Having Jurisdiction, all wireless access point cabling shall
employ plenum rated cable and patch cords.
A. Patch cords at the wireless access point shall be Category 6A with a preferred length of 1 m
or 2 m (3ft. or 6 ft.) where possible, with slake (service) loops managed in the horizontal
cable. Should conduit be required to the WAP outlet, Category 6A patch cords may be used
up to 5 m (16 ft.) in length to allow for potential repositioning of the WAPs.
A. The cable, information outlets, patch cords, and patch panels (where applicable) shall be as
specified.
84
SECTION 27 21 33 CATEGORY 6A WIRELESS ACCESS POINT
end solution being proposed. Proposals for equivalent products must be presented to the
OPR via RFI’s, Submittals, and/or Shop Drawings. OPR written approval is required before
any substitutions are made.
2.4 ASSEMBLY
A. At the WAP Work Station Outlet, materials for each wireless access point shall include
sufficient cable for two Category 6A connections, one deep device box, two information
outlets, one faceplate, and two patch cords of the required length.
B. At the telecommunications room or MER location, materials for each wireless access point
shall include sufficient cable for two Category 6A connections. If no un-terminated RJ45
patch panel ports are available in the serving telecommunications room, one new suitably
sized patch panel shall be installed. All materials including patch cords shall be as specified
in this Section 27 21 33.
A. In cases where the cabling infrastructure is being installed in a building not currently occupied
by JPMC, or where the new infrastructure is part of a strategic refresh of the entire existing
(Legacy) infrastructure as part of the project, competitive quotations including comparative
products shall be furnished.
A. The preferred WAP cable color is white, but must be coordinated with GRE to satisfy
architectural site variations. See Appendix E for product listings.
A. In legacy installations that include exposed cables, the cable jacket color should match the
color of the existing exposed cable jackets.
PART 3 – EXECUTION
3.1 INSTALLATION
A. Where practicable, the WAP Work Station Outlet shall be located no greater than 1 m (3 ft)
from the WAP.
B. The WAP Work Station Outlet shall be attached to approved building elements, using suitable
fastening methods. Attachment to conduit or other pipes is not permissible. Contractor shall
coordinate device box installation details with OPR.
C. To protect cable entering the extra deep device box, pre-install Raco connector or equivalent
in the device box knockout. These connectors are equipped with a screw-down cable clamp.
To avoid de-rating the Category 6A cables, cable jacketing shall not be compressed
whatsoever by the screw-down cable clamp.
D. Except where required to accommodate cable route diversity, Category 6A cables routing into
the back of RJ45 patch panels shall be dressed so that no cables will cross an imaginary
vertical line that bisects the patch panel (e.g. facing the back of a 48 port patch panel, cables
terminated in ports 1-12 and 25-36 shall route to the left vertical manager and cables
terminated in ports 13-24 and 37-48 shall route to the right vertical manager).
85
E. At the cross-connect point, all conductors of each Category 6A cable shall be terminated.
Refer to design drawings for configuration information. In spaces where any airborne dust or
contaminants may be present, Contractor shall properly protect any and all connectorized
cables to avoid transmission performance degradation associated with dust coming in contact
with connector contact points.
G. All cables and outlets shall be labeled in accordance with Section 27 05 53.
END OF SECTION
86
SECTION 33 82 00 – COMMUNICATION TRANSMISSION AND DISTRIBUTION
SECTION 33 82 53
PART 1 – GENERAL
A. To avoid damage to cables during their installation within conduit, cable pulling lubricants
should be employed. In all cases, this activity shall be closely coordinated with OPR.
PART 2 – PRODUCTS
2.2 Materials shall be as listed or shall be equivalent products of other manufacturers meeting the
intent and quality level of this specification. Materials must be compatible with the end-to-end
solution being proposed. Proposals for equivalent products must be presented to the OPR via
RFI’s, Submittals, and/or Shop Drawings. OPR written approval is required before any
substitutions are made.
2.3 In regions where the specified aerosol lubricant is not available, See OPR for suitable water-
based lubricant substitute.
PART 3 – EXECUTION
3.1 INSTALLATION
A. For normal cable pulls, prelubricate the conduit by spraying five to ten squirts of pulling
lubricant into the conduit before pulling. Saturate a wipe by spraying with lubricant and lightly
wipe lubricant on jacket to fully coat the cable as it enters the conduit.
B. For more difficult cable pulls, completely prelubricate the conduit. Squirt appropriate amount
of lubricant into the conduit and pull through a sponge or lubricant spreader to coat the
interior of the entire length. Wipe lubricant on cables as they enter the conduit as described
in above.
C. High efficiency spray pulling lubricants are effective with very thin coats in the range of 1 to 5
mg/cm2 of jacket surface. Estimate lubricant volume for a job using the following formula:
Q=4XnXD
Where:
Q = Quantity of lubricant in fluid ounces per 100 feet
87
n = Number of cables in conduit
D = Average cable diameter in inches
Note: A high volume trigger sprayer injects one fluid ounce per 20 sprays.
D. The appropriate quantity for use on any given pull can vary from this recommendation by
50%, depending on the complexity of the pull. Adjust the volume of pulling lubricant in
accordance with the following modifying factors:
1) Cable weight and jacket hardness – Increase quantities for stiff, heavy cable (e.g.
armored).
2) Conduit Type and Condition – Increase quantities for old, dirty, or rough conduits.
3) Conduit Fill – Increase quantities for conduit fills greater than 40%. Increase quantities
for large bundles of cable and be sure all cables are coated.
4) Number of Bends – Increase quantities for pulls with more than one bend
5) Temperature – Increase quantities for high ambient temperatures (above 27°C/80°F).
END OF SECTION
88
APPENDIX A – WTS DEFINITION AND CHECKLISTS FOR MER & TR ACCEPTANCE
Appendix A_WTS
Definition and Checklists for MER and TR Acceptance_1Jul2018.xlsx
89
APPENDIX B – GLOBAL STANDARD MATRIX FOR CRITICAL TECHNOLOGY SPACE
BUILDS
General Notes:
This Standard shall be used as a tool to plan Critical Technology Spaces (CTS) based on WTS operational
standards. This document is not intended to replace the specific needs of those planning equipment for CTS
areas or design coordination. It shall be used in conjunction with those needs and proper design coordination.
If a standard cannot be met during the design and planning phases the group accountable to meet the
requirement shall submit a request for exception approval prior to proceeding with a deviation from the
standard. The request must be submitted via EURC using the service titled 'Exception Approval - GTI-WTS
Global Standard for Critical Technology Space Builds'. The EURC request will be routed to the exception
approvers who will review the request, approve or deny, and document any exceptions for historical record of
the sites configuration.
Due to varying business requirements and BCP plans affecting uptime needs, LOB's must be consulted for
their uptime requirement to determine if the level of resiliency needed is greater than the base requirement.
A need for enhanced resiliency may also inform other components of power and cooling systems (i.e. risers,
utility feeds, etc.)
Definition of Room Type:
A critical technology space that serves a building that is a common network distribution point for the TR’s,
within that building. This room also provides access to services & applications from the Data Center over
the WAN and PSTN.
Services Associated with Room Type:
Consist of; Telecomm equipment for WAN vendors, Core network and network distribution layer, Local
building/campus PBX, in-building cellular, Wi-Fi, etc., Limited server/compute equipment – only equipment
with proven technical adjacency requirements, and Vendor equipment specific to that floor, building or
campus (Analogue VR etc.).
Appendix B_WTS
Matrix_v1.02_1Jul2018.docx
90
Appendices APPENDIX C – Faceplate Configurations
Appendix C_STS
Faceplate Configurations.docx
91
APPENDIX D – GENERAL IDENTIFICATION STANDARD
Appendix D_WTS
General Identification Standard_Ver 1.0.3_1Jul2018.docx
92
Appendices APPRENDIX E – Corporate Product List
APPENDIX E – MATERIALS
JPMC has negotiated significant discounts with manufacturers and distributors for materials listed in the
Appendix E. Contractor shall deploy materials as specified in this Appendix except in such cases where
Remote Site Operations or Infrastructure Cabling Design personnel approve specific deviations in writing.
Appendix
E_Materials_1Jul2018.xlsx
93
APPENDIX F – WTS DATA CLEAN SPECIFICATION & CLEANING POLICY FOR
MER’S AND TR’S
Appendix F_STS
Data Clean Specification and Cleaning Policy for MERs and TRs.docx
94
APPENDIX G – WTS BIDDER PRICING FORM
Appendix G WTS
Bidder pricing form v8.xlsx
95
APPENDIX H – WTS CABLE DESIGN AND ENGINEERING INSTALLATION
STANDARD - WAP
Appendix H_WTS
Cable Design and Engineering Installation Standard _ WAP_v6.0.1_Bulletin NEXT.doc
96
APPENDIX I – WTS CABLE DESIGN AND ENGINEERING PATCHING STANDARD
Appendix I_WTS
Cable Design and Engineering Patching Standard_v6.0.1_Bulletin NEXT.docx
97
APPENDIX J – MER, TR AND TECHNOLOGY LAB SECURITY DESIGN STANDARD
Appendix J_Main
Equipment Room, Technology Room, and Technology Lab Security Design Standard Bulletin_NEXT.docx
98
APPENDIX K – EXCEPTION APPROVAL
Appendix
K_Exception Approval.docx
99
APPENDIX L – Low Voltage Responsibility Matrix V1.0
NOTE: The Responsibility Matrix may contain more System & Equipment Categories than may be
required for a given project. In this case rows that are not applicable to the project should be hidden.
Appendix L_Low
Voltage Responsibility Matrix V1.0.xlsx
100
THIS PAGE INTENTIONALLY BLANK
Key
Project: JPMC Legacy West - Phase 2 Abbreviation Definition Abbreviation Definition
Document: Low Voltage Responsibility Matrix L = Lead Provide design direction S = Specify Ultimate design responsibility (engineer of record/construction documents)
Updated: July 20, 2018 A = Approve Responsibility to approve design F = Furnish Furnish equipment
Verision: 1.0 C = Coordinate Coordinate with designer I = Install Install equipment
D = Design Develop concepts / show on drawings for pricing, but not to be built from
CALLISON / RTKL
CONTRACTOR
CONTRACTOR
CONTRACTOR
CONTRACTOR
AUDIOVISUAL
ELECTRICAL
SYSKA ICT -
SYSKA MEP
EC/TC/AVC)
3RD PARTY
SYSKA ICT
EXTENETS
JPMC GRE
JPMC DAS
SECURITY
SECURITY
TELECOM
JPMC GTI
VENDOR
VENDOR
KDC
HKS
SYSTEM & EQUIPMENT CATEGORY
1 Structured Cabling (TI Spaces)
a. Copper and fiber optic backbone L/A A A D/S F/I
b. Telecom Room racks L/A A A C C D/S F/I
c. Installation Details L/A A A D/S F/I
d. Telecom Horizontal Cabling, Terminations, & Testing L/A A A C C D/S F/I
e. Telecommunications Cable Trays (within TRs/MERs) L/A A A C C D/S F/I
f. Telecommunications Cable Trays (outside TRs/MERs) L/A A A C C D/S F/I
g. Conduits for Structured Cabling L/A A A C S D F/I
h. Power for IT systems L/A A A C D/S C F/I
i. Switch to Patch Panel Patch Cords L/A A A D/S F/I
i. Desktop Patch Cords L/A A A D/S F/I
j. Grounding – Backbone (to the busbars) L/A A A D/S C F/I
k. Grounding – Backbone (racks to the busbars) L/A A A C D/S F/I
l. Grounding – To chassis switches L/A A A C D/S F/I
m. Non-Mechanical Firestopping of Telecom Pathways L/A A A C C D/S F/I
n. Mechanical Firestopping System L/A A A C C D/S F/I
o. Telecom outlet location and mounting height. L/A A A S C D F/I
p. Supplemental Cooling in Telecommunications Rooms. L/A A A C D/S C F/I
q. Plywood, doors, walls, etc. for TR/MER Construction L/A A A S C D F/I
r. UPS systems L/A A A C D/S C F/I
s. Rack Mounted PDUs L/A A A C D/S F/I
2 IT Equipment
a. LAN/WAN L/A/S/F A A C I
b. Phones L/A/S/F/I A A C
c. Desktop L/A/S/F/I A A C
3 Wireless Network
a. Site Survey / Predictive Survey / AP Location L/A/S A A C C D D/S
b. WLAN APs L/A/F A A C C D I S
c. Cabling to APs L/A A A C C D/S F/I
4 Service Providers
a. Voice Circuits - T1/PRI/SIP/MBLs/POTS L/A/D/S A A C F/I
b. Data Circuits L/A/D/S A A C F/I
c. Conduit Pathways L/A A A C S D F/I
d. Voice demarc extensions L/A A A D/S F/I
5 DAS (Distributed Antenna System)
a. Headend L/A A A C D/S/F/I
b. Floor Distribution (cabling, terminations & cable testing) L/A A A D S F/I
c. Floor Distribution (antennas) L/A A A D F/S I
d. Fiber backbone & fiber terminations/testing L/A A A S D F/I
e. Wireless Providers Connection L/A A A C D/S/F/I
f. Conduit pathways to roof L/A A A S D/C D F/I
g. Programming & Commissioning L/A A A C D/S/F/I
h. Jumpers L/A A A S D F/I
i. Splitters L/A A A C D/S/F I
j. Fiber patch cords L/A A A S D/I F
k. Fiber Remotes L/A A A C D/S/F/I
l. Power for Fiber Remotes L/A A A S C D F/I
6 Life Safety DAS
a. Headend A L/A C C D/S/F/I
b. Floor Distribution (cabling & antennas) A L/A C F/I D/S
c. Antenna to Public Safety System A L/A C F/I D/S
7 Audiovisual
a. Containment Conduit, Junction Boxes, wireways and
other electrical rough-in L/A A A C D C S F/I
b. AC Power Receptacles and related electrical requirements L/A A A C S D F/I
c. lighting fixtures, including wall switches and zoning L/A A A D S C F/I
d. IT and Tele/data as required for AV L/A A A S D F/I
e. Room Construction, including but not liminted to framing,
walls, hanging gyp board, carpet installation, ceiling work L/A A A D/S C F/I
f. Low voltage audiovisual cabling L/A A A D/S F/I
g. Low voltage audiovisual terminations L/A A A D/S F/I
h. Ceiling speakers(with backboxes,transformers and grilles) L/A A A C D/S F/I
i. Shade and lighting control interface to AV control system L/A A A D/S F/I
j. Microphones L/A A A C D/S F/I
k. Control system and audio system programming L/A A A D/S F/I
l. Computers with keyboard and mouse L/A/S/F/I A A D
m. Testing and evaluation of AV system L/A A A D/S F/I
n. Patching of walls, repalcement of ceiling tiles, floor
carpet, etc damaged during the installation L/A A A F/I
o. Conference table connection table box L/A A A D C F/I
p. AV patch cables for end user connections L/A A A D/S F/I
q. Video Camera L/A A A D/S F/I
r. Non-CBC Training Room Camera Box L/A A A D/S I F
s. Audiovisual equipment cabinets L/A A A D/S F/I
t. Blocking for wall mounted displays L/A A A D S F/I
CONTRACTOR
CONTRACTOR
CONTRACTOR
CONTRACTOR
AUDIOVISUAL
ELECTRICAL
SYSKA ICT -
SYSKA MEP
EC/TC/AVC)
3RD PARTY
SYSKA ICT
EXTENETS
JPMC GRE
JPMC DAS
SECURITY
SECURITY
TELECOM
JPMC GTI
VENDOR
VENDOR
KDC
HKS
SYSTEM & EQUIPMENT CATEGORY
u. Wall mounted flat panel displays L/A A A D/S F/I
v. Non-motorized wall mounted flat panel display mounts L/A A A C C C D/S F/I
w. Floor pole mounted flat panel display mounts L/A A A C C C D/S I F
x. Ceiling pole mounted flat panel display mounts L/A A A C C C D/S I F
x. Motorized wall mounted flat panel display mounts L/A A A C C C D/S I F
x. Motorized ceiling mounted flat panel display mounts L/A A A C C C D/S I F
y. Faceplate for wall and floor box L/A A A C C D/S F/I
z. Ladder rack in AV equipment rooms L/A A A D/S F/I
aa. Firestopping L/A A A D/S F/I
bb. Telecom patch cables of appropriate length L/A A A D/S F I
8 Security (Access control / surveillance)
a. Access Control Devices (Card Readers, contacts, etc.) A A D/S F/I
b. Surveillance Devices (CCTV Cameras, Headend) A A D/S F/I
c. Network drops to security panels & IP cameras within
and mounted to the exterior of Buildings B A A S D F/I
d. Access control wiring (Card Readers, Door Contacts,etc.) A A D/S F/I
e. Conduit and Pathways A A S D F/I
9 IT Move Management
a. Network Rack & Stack L/A/D/F A A C C I
b. Desktops / Monitors L/A/D/F/I A A C C C
c. Phone System / handsets L/A/D/F/I A A C C C
10 Miscellaneous
a. Sound Masking A A C F/I
b. Building Automation System A A C D/S C F/I
c. Elevator phones A L/A/D/S C F/I
d. POTS - fire alarm & elevator A L/A/D/S C
e. Lighting Controls A A C F/I
GTI/STS-RSO
Version: 1.3.1
Document Status
This document is currently approved and published.
Feedback Contacts
Feedback from the readers/users of this document is critical to its value. Such Feedback can include;
- Errors
- Omissions
- Suggestions for Improvement
Revision History
Version Description Date By
1.0 Developed for review 6/1/2015 D. Anselmo
1.1 Reviewed and approved 6/10/2015 D. Anselmo
1.2 Moved firestopping from shell ready to room ready 8/17/2015 D. Anselmo
1.3 Move cable test review from room ready to prod. Ready 10/5/2015 D. Anselmo
Changed door gaskets being required to only door sweeps,
1.3.1 and changes to the Shell/Room/Production Ready 7/1/2017 M. McMurray
Checklists. Added comments section to inspection tabs.
Removed "(so cabling can commence)" from Acceptance
Sign-off on Shell, Room and Production Checklists. Various
1.3.2 7/1/2018 M. McMurray
changes made to Shell and Room Ready checklists. Added
a new tab "Work to Complete".
Appendix A
2 The GTI-RES PM will manage the check list throughout the project performing the following tasks.
A. Distributing the document during initiation to the project team and general contractor.
B. Identifying information identified under 'A' in figure 1 below and distributing to WTS-RSO and GRE representatives by the beginning of the construction
phase.
C. Collecting the completed documents at the completion of walk-throughs and managing any open items identified to completion.
D. Distributing completed documents to the RSO and GRE reps once acceptance has been received and for archiving to RSO's SharePoint site.
3 If an exception has been approved, the GTI-RES PM will identify that by stating the EURC number in the area identified under 'B' in Figure 1 below.
4 Reviewers at the room ready walk through will document their approval of a line item by listing the date in their respective field next to the line item as identified
under 'C' in Table 1.
5 Reviewers may find an entry grayed out under their field for entry as noted under 'D' in Figure 1 below. The reviewer is not expected to be able to provide a
response to these items.
6 Reviewers will sign-for final acceptance at the point they are accepting the state of the room under 'E' in Figure 1 below and submit their forms to the GTI-RES
PM.
7 Sign off at Shell Ready and Room Ready typically signed off by Structured Cabling Engineer (Sitehands may act as a proxy).
8 Sign off at Production Ready typically signed off by RTM.
Figure 1.
STS (CORP-CAB, RSO, GTI-RES PM) Appendix A
Exceptions WTS
Plan Date Actual Date Inspection Item Description (CORP-CAB GRE
EURC # / RSO / GTI-RES PM)
Walls are built w/ 1-hour fire rating or greater if local code is more stringent.
Ceiling has been encapsulated to prevent firestopping from flaking and creating dust in the room.
All conduits have been completely installed and labeled in compliance with WTS standard.
Plywood backboard has been installed and painted with fire retardant paint and fire-rating certification stamp is left unpainted.
In raised floor environments, flooring installed completely, grounded, and all tile cuts completed with brushed grommets installed.
In non raised-floor environments, anti-static VCT tile is completely installed and grounded.
All duct work and diffuser installations have been completed and fire dampers installed where required to maintain fire rating of
room.
Permanent lighting and switches installed. Lighting located in aisle ways and coordinated with cabinet and rack layout.
MER/TR is vacuumed, broom swept, and cleaned to a level that is adequate to safely maintain space for pulling and terminating
cable.
Exceptions WTS
Plan Date Actual Date Inspection Item Description (CORP-CAB GRE
EURC # / RSO / GTI-RES PM)
Generator on-site, placed and wired (MER only) (If required by LOB resiliency levels.)
Convenience power outlets have been installed, energized, tested, and labeled.
Air handling units have been installed, including leak detection, pipes, valves, drip pans, ductwork, condensate piping, and drains.
Fire alarm, smoke detection devices and panels installed and wired, in MER/TR.
Service clearances from MEP equipment (air handlers, UPS, breaker panels) have been met.
Card reader/pin pad back boxes installed, camera backboxes installed and security micro mounted.
Exceptions WTS
Plan Date Actual Date Inspection Item Description (CORP-CAB GRE
EURC # / RSO / GTI-RES PM)
All racks, cabinets and cable management is assembled and in their final positions.
All clearances have been met - 3 ft (915 mm) minimum service clearance from the front of equipment in racks or cabinets. 3 ft (915
mm) minimum service clearance from the rear of equipment in racks or cabinet. 4 ft (1219 mm) minimum service clearance on one
side of the row of racks or cabinets. 1 ft (305 mm) minimum additional service clearance in front of telco wall field.
Racks have been bolted to the floor, and seismic bracing installed if required.
If more than one cabinet, bay and bolt together. Cabinets have been taken off casters, leveled and bolted to slab.
Overhead and any under floor pathways (ladder rack or cable tray) have been installed and grounded, inside MER/TR.
Pathways outside MER/TR are installed including; J-hooks, cable tray (overhead/underfloor), and any conduit pathways.
Acceptance Sign-Off
WTS: Date:
(first and last name of approver)
GRE: Date:
(first and last name of approver)
Comments
Section / Row Number
Exceptions WTS
Plan Date Actual Date Inspection Item Description (CORP-CAB GRE
EURC # / RSO / GTI-RES PM)
Data cleaning completed; room is clean and dust free. (Based on Appendix F Requirements)
Any openings or penetrations through walls have been sealed with firestop.
Automatic closer is operational on door and final locking hardware has been installed.
Any secondary doors that lead into the room must be treated as emergency exits and must have a door contact, local alarm sounder, signage,
no handle on hallway side of door, and crash bar on inside of door.
Door sweeps have been installed on doors.
Exceptions WTS
Plan Date Actual Date Inspection Item Description (CORP-CAB GRE
EURC # / RSO / GTI-RES PM)
Generator installed, commissioned, and failover tests complete (MER Only) (If required by LOB resiliency levels.).
Permanent UPS system installed, grounded, energized, tested and fully commissioned. (If required by LOB resiliency levels.).
Electrical distribution on permanent power.
EPO button (if required by code) installed, tested, covered, and identified with signage.
BMS system operational to all equipment in MER/TR. (Not monitored)
Piping at air handling units hydrostatically pressure tested throughout.
Air handling units fully commissioned and operational 24 x 7.
Fire alarm and smoke detection devices tested and operational.
Fire suppression system fully tested, commissioned and operational.
Drain flow test complete.
Security camera installed at each door; one inside the room and one outside the room both with a view of the door. (Not operational)
Card reader/pinpad at primary door wired to access control system. (Not operational)
No shutdowns will be accepted, with the exception of the Pull The Plug Tests (minimum 5 days notice to technology and all work needs to be
fully coordinated before proceeding). This test should not impact the critical power in the MER/TR due to the UPS system, but cooling units,
lighting and other non‐UPS equipment may be temporarily shut down until the generators come on line.
Exceptions WTS
Plan Date Actual Date Inspection Item Description (CORP-CAB GRE
EURC # / RSO / GTI-RES PM)
Power strips mounted to rear of racks or cabinets where they will not interfere with patching, equipment mounting, or cabling; connected to
branch circuit outlets, and labeled as per the WTS standard.
Structured cabling installation complete on IT room side.
Shell Ready punch list performed and remediation completed on IT room side.
Any armored communications cable jackets have been bonded/grounded (if required).
Racks, cabinets, fiber enclosures, and patch panels labeled as per the WTS standard.
The switch chassis bonding strap has been provided for future connection to the Network Switch Chassis.
Cabling and wallphone plate installed for wall phone(s).
Cabling installed, routed and supported utilizing strain relief in a neat manner that does not block equipment mounting space or interfere with
other systems.
Carrier cabling is pulled into room, terminated, tested, and labeled. (If appropriate).
Acceptance Sign-Off
WTS: Date:
(first and last name of approver)
GRE: Date:
(first and last name of approver)
Comments
Section / Row Number
Exceptions WTS
Plan Date Actual Date Inspection Item Description (CORP-CAB GRE
EURC # / RSO/ GTI-RES PM)
Unique lock core has been changed to JPMC lock core.
Room signage outside the room (name and number) has been installed as per the WTS standard.
Final data clean has been completed.
Secondary door signage has been installed. (If required)
Exceptions WTS
Plan Date Actual Date Inspection Item Description (CORP-CAB GRE
EURC # / RSO/ GTI-RES PM)
Fire extinguisher(s), if required by code, have been installed.
BMS system to all equipment in MER/TR, with monitoring operational.
Card readers/pin pads are online and programmed in Passport with the RSO manager assigned as the approver.
Security cameras are online, calibrated, and viewable in Nice Vision.
Door alarms are programmed to monitor for immediate forced open and door held open (60 second alarms).
Exceptions WTS
Plan Date Actual Date Inspection Item Description (CORP-CAB GRE
EURC # / RSO/ GTI-RES PM)
All technology equipment racked in their final positions.
Floorplan mounted to a wall of the Technology Space (MER/TR).
All technology equipment patched.
All patching utilizes cable management pathways and is neatly managed.
Port replication cables are routed into the switch, neatly managed, with minimal slack. (If required).
Patch cable slack does not exceed more than 1’ on either end of the cable.
No cables are blocking fan trays or blocking equipment mounting spaces.
Structured cabling has received and reviewed structured cabling test results.
Any punch list items found upon cable test review have been corrected.
All equipment connected with the appropriate colored power cords, and neatly managed.
The switch chassis bonding strap has been connected to the Network Switch Chassis.
Wall phone installed inside room and operational.
No plastic tiewraps used to manage power or communications cabling slack or bundles.
Carrier equipment is installed and tested by the carrier and JPMC Network Engineer in its designated position.
All powered IT equipment, aside from audio‐visual or carrier equipment, must be labeled with the devices hostname and a yellow asset tag on the
front (cold aisle) side of the device. A machine generated label indicating the serial number of the device shall also be placed on the front (cold aisle)
side of the device.
All cabinets must have a yellow asset tag at the top of the front door and all racks must have a yellow asset tag at the top front in a visible area that
can be easily accessed with a barcode scanner.
All GTI systems have been entered into TAMS and the equipment inventoried in the room matches the inventory in TAMS.
All RSO signage has been installed within the room.
The red box for media storage has been installed within the room.
Acceptance Sign-Off
WTS: Date:
(first and last name of approver)
GRE: Date:
(first and last name of approver)
Comments
Section / Row Number
Variance Variance
Original New Planned Actual from new from original
Milestone Completion Completion planned milestone
Index Room Acceptance Stage Date Work to Complete Assigned To Date Date completion Verified By Verified On date
1 0 0
2 0 0
3 0 0
4 0 0
5 0 0
6 0 0
7 0 0
8 0 0
9 0 0
10 0 0
11 0 0
12 0 0
13 0 0
14 0 0
15 0 0
16 0 0
17 0 0
18 0 0
19 0 0
20 0 0
21 0 0
22 0 0
23 0 0
24 0 0
25 0 0
26 0 0
27 0 0
28 0 0
29 0 0
30 0 0
31 0 0
32 0 0
33 0 0
34 0 0
35 0 0
36 0 0
37 0 0
38 0 0
39 0 0
40 0 0
41 0 0
42 0 0
43 0 0
44 0 0
45 0 0
46 0 0
47 0 0
48 0 0
49 0 0
50 0 0
51 0 0
52 0 0
53 0 0
54 0 0
55 0 0
56 0 0
57 0 0
58 0 0
59 0 0
60 0 0
61 0 0
62 0 0
63 0 0
64 0 0
65 0 0
66 0 0
67 0 0
68 0 0
69 0 0
70 0 0
71 0 0
72 0 0
73 0 0
74 0 0
75 0 0
76 0 0
77 0 0
78 0 0
79 0 0
80 0 0
81 0 0
82 0 0
83 0 0
84 0 0
85 0 0
86 0 0
87 0 0
88 0 0
89 0 0
90 0 0
91 0 0
92 0 0
93 0 0
94 0 0
95 0 0
96 0 0
97 0 0
98 0 0
99 0 0
100 0 0
Appendix B
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
1. Critical Systems ‐ MERs (Main Equipment Rooms)
LOB, GRE,
Utility System N+1 (Diverse routing into facility) GRE Y Y Y
WTS
Generator LOB, GRE,
N GRE Y Y Y
System WTS
LOB, GRE,
UPS System N+1 GRE Y Y Y
WTS, GNS
Primary LOB, GRE,
N+1 with mechanical conveyance at N GRE Y Y Y
Cooling Plant WTS
Emergency power off devices, if required, are to be
installed with up protective cover as part of dual action
Emergency
station to reduce false activation; are normally
Power LOB, GRE,
open/normally closed dry contact and shall change GRE Y Y
Shutdown WTS
state upon EPO activation, and be properly labeled, i.e.,
Management
Emergency Power Off (EPO), Remote Emergency Power
Off (REPO), Remote Emergency Module Office (REMO).
LOB, GRE,
N+1 GRE Y Y Y
WTS
Must be designed to maintain humidity within the
recommended range for all “A Classes” per ASHRAE
TC9.9 2011 (Thermal Guidelines for Data Processing
CRAH/CRAC Environments).
Units LOB, GRE,
GRE Y Y Y
Humidity Range, Non‐Condensing: 20% to 80% Relative WTS
Humidity with 17⁰C (62.6⁰F) Maximum Dew Point
Additional restrictions as applicable to site.
When secondary electrical distribution is deployed,
Static Transfer utilize Static Transfer Switches, with 2N redundancy, in LOB, GRE,
GRE Y Y
Switches the output path of UPS systems to enhance electrical WTS
system maintainability.
Redundant and diversely fed. Must be dedicated
circuits with dedicated neutral and equipment
Branch Circuit grounding conductor (EGC). No Isolated Ground (IG) LOB, GRE,
GRE Y Y
Distribution circuits unless required for specific equipment. WTS
Protected by Transient Voltage Surge Suppression
(TVSS) device effective at breaker panel level.
All equipment must be dual corded. The primary choice
is 208V/3‐phase power/30A, with 208V/single phase/20
Any
or 30A being allowable based on site specific
equipment
requirements, or its country specific equivalent, must
provider (i.e. LOB, GRE,
Equipment be provided at every cabinet footprint. In North Y
LOB, GNS, WTS
America 120V power must also be provided at the PDU
Transport,
(power strip) level. Proper load balancing must be
Voice, Media)
planned and maintained to prevent excessive phase
unbalance.
Generator supported, but if no generator is present,
lighting must be on battery‐backup. Lighting
occupancy sensors providing coverage throughout
LOB, GRE,
Lighting entirety of room is preferred. Must not be on dimmer GRE Y Y
WTS
switches or on same electrical panel as equipment.
Must be at least 305 mm (12 in) from cable pathways,
racks, cabinets, and equipment.
Installed to the extent necessary to detect critical alarm
Critical conditions (i.e. temperature, humidity, fire/smoke,
LOB, GRE,
System critical equipment malfunction). Requirements will be GRE Y Y
WTS
Monitoring determined by those owning and operating these
systems.
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
1. Critical Systems ‐ MERs (Continued)
A condensate containment pan and/or curbing wall
Leak with leak detection is required for floor/wall supported
Detection for CRAH/CRAC units. A drip pan with leak detection is
required for ceiling mounted CRAH/CRAC units. Ceiling LOB, GRE,
Mech GRE Y Y
mounted cooling units should be installed outside the WTS
equipment/
Piping room and ducted in.
Pre‐Action sprinkler with protective cage to prevent
accidental contact and activation. Each critical
Fire LOB, GRE,
technology room must be designated as a separate fire GRE Y Y Y
Suppression WTS
zone. Gaseous fire suppression must be installed when
required by local authority having jurisdiction (AHJ).
Carrier
Diversely routed in rigid conduit (RMC). Flexible LOB, GRE,
Entrances Transport Y Y Y
metallic conduit must not be used. WTS
(PoE)
Access
LOB, GRE,
provider Diversely routed in rigid conduit (RMC). Transport Y Y Y
WTS
Entrances
For access provider space (carrier room)‐to‐MER
cabling, routed in rigid conduit, with separate conduit
from each carrier to each MER. For MER‐to‐TR cabling
in multi‐tenant buildings, routed in rigid conduit, for
buildings occupied exclusively by JPMC, routed exposed Structured LOB, GRE,
Backbone Y Y Y
through sleeves vertically and through conduit, tray etc. Cabling WTS
horizontally. Wherever telecommunications conduit is
installed for backbone or access provider cabling, it
shall be pre‐provisioned with flexible fabric innerduct
(e.g. MaxCell).
For equipment requiring DC power, provide the
following:
* Power provided from diverse electrical facilities
* 48VDC Power or 3 Phase AC (dependent upon facility)
DC power (if LOB, GRE,
* Bulk DC Power (100 – 600 AMP power feeds typical GRE Y Y
required) WTS
terminated from facility to JPMC BDCBB(s)
* JPMC prefers vendor provides the largest cable size
possible (ex. 750 MCM) to JPMC; This will allow power
upgrades without replacing power cables
2. Ancillary Systems ‐ MERs (Main Equipment Rooms)
Provide Racks and Cabinets to match the following
purposes;
* 4‐post open frame racks to be used for Cabling and
Network equipment
* 19 or 23 in 2‐Post unequal flange racks to be used for WTS,
Racks / Carrier equipment, per Carrier requirements Structured
Structured Y Y
Cabinets * Server Cabinets to be used for Cabling and Server Cabling
Cabling
equipment
Existing/legacy rooms: If a carrier rack is not available,
carrier equipment should be wall mounted.
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
2. Ancillary Systems ‐ MERs (Continued)
Provide the following for network device and cabling
equipment: 19 in. 4‐post open rack with fixed rails and
minimum depth 740 mm (29 in) outside of front rail to
outside of rear rail. Vertical cable managers shall be
sized based on cable counts and fill factors. Structured WTS,
Structured
cabling engineer to determine appropriate size based Structured Y Y
Cabling
on site requirements. Be equipped with appropriate Cabling
air baffles if equipment is mounted side by side in
adjacent racks.
Racks to be bolted to floor. Seismic bracing where
applicable. Typical rack/cabinet height is 45 RU.
Provide the following for server equipment: 700 mm
(28 in) to 800 mm (32 in) wide x 1175 mm (46 in.) to
1200 mm (48 in) deep enclosed cabinet with air dam kit
and perforated single front and double rear perforated
Racks /
doors, each with a lock. 4 in (100 mm) wide lacing bars
Cabinets WTS WTS Y Y
on both sides at front (cold aisle/intake side). 2 x PDU
mounting and vertical cable management on rear.
Cabinets to be fastened to the slab, and bayed
together. Seismic bracing where applicable. Typical
rack/cabinet height is 45 RU.
Provide the following for carrier equipment. 19 or 23 in
2‐Post unequal flange rack with Vertical cable managers
shall be sized based on cable counts and fill factors.
Structured cabling engineer to determine appropriate
size based on site requirements. 45 RU rack height. Structured WTS,
Y Y
Racks to be bolted to slab. Based on requirements from Cabling Transport
Transport. Seismic bracing where applicable. If a free
standing carrier rack is not available, carrier equipment
should be wall mounted. Carrier equipment to be
mounted in quad racks in APAC.
All connectivity/patching shall be performed within any Structured
LOB, WTS Y Y
given rack/cabinet and not between rows. Cabling
Connectivity
Fiber links are field terminated, with LC
WTS,
connectors. Connector adaptation (e.g. ST, SC) are
WTS Structured Y Y
accomplished through the use of suitable patch cords
Cabling
when required.
All chassis based copper access switches to be port
replicated into centralized patching field (only is
approved by the OPR or management). All stackable Structured
WTS Y Y
switching to follow WTS patching diagram (see Cabling
Appendix I of the WTS Cable Design and Engineering
Standards).
Patching All patching to be supported, address bend radius, and
utilize cable management solely intended for its use.
Power and data patching to utilize separate pathways. WTS,
Patching shall not be of excessive length, planning for 1' WTS Structured Y Y
of service loop on each end, and be routed neatly Cabling
providing free access for maintenance of equipment
and cabling infrastructure.
Hot/Cold Aisle: GRE,
Coordinate placement of CRAC/CRAH components Structured
GRE Y Y
delivering cool air and capturing return air with the Cabling,
layout of racks and cabinets. WTS
Layout Hot/Cold Aisle: Equipment intakes at the front of racks
GRE,
are not facing rear‐equipment exhaust from a
Structured Structured
neighboring row. Side mounted air baffles must be Y Y
Cabling Cabling,
installed in the instances where equipment is mounted
WTS
side by side in adjacent racks.
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
2. Ancillary Systems ‐ MERs (Continued)
Rack/cabinet elevations to be planned for growth at
Structured
switch and patching frames, and growth at server GRE, WTS Y Y
Cabling
cabinets.
3 ft (915 mm) minimum service clearance from the
Layout front of equipment in racks or cabinets. 3 ft (915 mm)
minimum service clearance from the rear of equipment
Structured
in racks or cabinet. 4 ft (1829 mm) minimum service GRE, WTS Y Y Y
Cabling
clearance on one side of the row of racks or cabinets.
1 ft (305 mm) additional service clearance in front of
telco wall field.
In access floor environments at least one full floor tile
must be free of obstruction nearest to the front and in Structured
GRE, WTS Y
back of each rack or cabinet in a row to allow under Cabling
floor access.
2 ft (610 mm) service clearance above racks and
Structured
cabinets. Cable support systems shall be the only GRE, WTS Y Y
Cabling
allowable obstruction.
Racks and cabinets must be located away from
potential sources of electromagnetic interference
Clearances
(EMI). They should be kept at least 1.22 m (4ft) away
from transformers, motors, and other potentially strong Structured
GRE, WTS Y Y Y
sources of EMI. Their location should not compromise Cabling
associated cabling pathways with regard to EMI related
separation requirements and guidelines of the
ANSI/TIA‐569 standard.
Fill planned for growth not to exceed 50% fill maximum;
bend radius of cables will be compliant with the Structured
WTS Y Y
ANSI/TIA‐568 group of standards, or manufacturer’s Cabling
requirements if those are stricter.
Conduits and sleeves for carrier media not to be shared Structured
WTS Y Y
with JPMC structured cable media. Cabling
Structured
Service loops are not allowed in the MER WTS Y
Cabling
Metallic Cable Trays:
Should be independently supported from ceiling or
walls, not preferred from cabinets and racks.
Installation must be electrical Code compliant.
Structured
Must be bonded to ground. When tray sections are not WTS Y Y
Cabling
mechanically continuous, or if section connecting
Pathways hardware is not approved as a means for providing
ground continuity, bonding conductors must be
installed across the sections.
Non Metallic Raceways and Cable Routing Assemblies
(e.g., Fiber Runner):
May be attached to cabinets and racks when intended
for patching or other local connections within a row.
Structured
Otherwise must be independently supported as per WTS Y Y
Cabling
metallic cable tray requirements.
Must be fire rated as required by electrical code (i.e.
plenum, riser, etc.) and must be UL2024 or UL2024A
listed (as appropriate to application).
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
2. Ancillary Systems ‐ MERs (Continued)
Single point of entry into the room with a card reader/
LOB, GRE,
pin pad on the ingress and card reader only on the egress GRE Y Y
WTS, GSMA
side of the door. See Appendix J – Security Standard
Card Reader entry door lock must be fail secure in case of
power outage or fire alarm system activation unless LOB, GRE,
GRE Y Y
dictated otherwise by local code. See Appendix J – WTS, GSMA
Security Standard
Card Reader entry door lock must be fail secure in case of
power outage or fire alarm system activation unless LOB, GRE,
GRE Y Y
dictated otherwise by local code. See Appendix J – WTS, GSMA
Security Standard
Security
Cameras covering the entrance door and any other
LOB, GRE,
secondary exits from inside and outside See Appendix J – GRE Y Y
WTS, GSMA
Security Standard
Any secondary doors that lead into the room must be
treated as emergency exits and must have a door
LOB, GRE,
contact, local alarm sounder, signage, no handle on GRE Y Y
WTS, GSMA
hallway side of door, and crash bar on inside of door. See
Appendix J – Security Standard
All doors leading into the MER must be monitored for
LOB, GRE,
immediate forced open and door held open (60 Second) GRE Y Y
WTS, GSMA
alarms. See Appendix J – Security Standard
ITSM/PDPA required upon Production Ready stage and
LOB, GRE,
after for access. Card reader/pin reader will be system GSMA Y
WTS, GSMA
of record for access. See Appendix J – Security Standard
Receptacles mounted on a separate c‐channel
independently supported below ladder rack and above
rack. The receptacle facing the rack/cabinet in hot aisle
(equipment air exhausts side of cabinet, with
GRE GRE, WTS Y
electrical sockets facing the hot aisle, not the ceiling
or floor). If power routed under floor, power to be
mounted on bracket installed between pedestals in hot
Power
aisle, or per local code.
Distribution
Where diverse power feeds are deployed A‐side panel
circuits shall use black on white labels to designate the
circuit on the faceplate and B‐side panel circuits to utilize GRE GRE, WTS Y
white on black labels to designate the circuit on the
faceplate.
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable to Exception Design Review Stage
/ System Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
2. Ancillary Systems ‐ MERs (Continued)
Where diverse power feeds are deployed equipment to
have special ordered white cords plugged into A‐side GRE,
GRE Y
power connections and black cords plugged into B‐side WTS
power connections.
PDUs (Power Strips) (see Appendix E, of the WTS Cable
Design and Engineering Standards) shall adhere to the
following requirements:
‐ 208V/3‐phase 30A, with 208V/single phase/20 or 30A
being allowable based on site specific requirements, (or
country specific equivalent) (In North America 120V
Power
power must also be provided at the local Power
Distribution
Distribution Unit (PDU) level.
GRE,
‐ Minimum (24) C‐13 receptacles WTS Y
WTS
‐ Minimum (6) C‐19 receptacles
‐ Minimum (2) 5‐20 receptacles (in NA only)
‐ Locking input power cords
‐ Integral breakers or fuses when required by Code
‐ Ability for metering (including each phase with true
RMS reading of current and voltage)
‐ Ethernet port allowing remote readout of PDU
parameters.
3. Room Construction ‐ MERs (Main Equipment Rooms)
Naming Convention:
‐ Building abbreviations should also come from and
coordinated with GRE
‐ Room Type should reflect Technology room definitions
as identified in the space classification document (TR for GRE,
Room Signage Telecommunication Room or MER for Main Equipment GRE WTS, Y
Room) LOB
‐ Identifier should be included if there are more than one
TR located on the floor and can be listed in Numbers,
Letters, or Colors (i.e. 1, 2, A, B, Orange, Blue, etc.)
‐Updated signage should also accompany the activation
of any new technology rooms. The room signage should
be in compliance with existing standards as provided by
facilities. It should not change the look and feel of the
existing floor signage within the office space, but should
clearly indicate the room names in accordance with the
GTI technology space classification.
When applicable to the site, sign characteristics must
comply with requirements of the Americans with
Disabilities Act (ADA).
GRE,
For secondary exits:
GRE WTS, Y
On the ingress side sign stating “No Entry – Emergency
LOB
Exit Only”
On the egress side sign stating “Emergency Exit Only –
Alarm Will Sound”
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
3. Room Construction ‐ MERs (Continued)
Built deck to deck/slab to slab. All metal wire mesh
GRE GRE, WTS Y Y
cages must extend slab to slab.
Minimum 1 hour fire‐rated or greater if local code is
GRE GRE, WTS Y Y
more stringent.
All penetrations firestopped to maintain fire rating of
walls, and must be firestopped per the requirements of
GRE GRE, WTS Y Y
this Standard, ATSM E814, UL1479, and the
manufacturer.
Where no equipment is intended to be mounted to the
wall, the drywall must be taped, spackled and sanded to
GRE GRE, WTS Y
a smooth finish. The wall must be painted a light color
to enhance room lighting.
Walls
At least two contiguous sheets of plywood 1.22 m (4 ft)
wide and 2.43 m (8 ft) high and beginning 153 mm (6 in)
above the finished floor must be installed on a wall in a
location best suited for their use.
Plywood to be:
‐ compliant with Codes
‐ kiln dried (15% max. moisture)
‐ 19 mm (¾”) thick A‐C grade (mounted with best side GRE GRE, WTS Y Y
facing the room)
‐ fastened securely to a wall
‐ Either fire rated (with a UL FR‐S classification), or if
non‐fire‐rated ‐ and if acceptable to the AHJ ‐ covered
with two coats of fire retardant paint on both sides and
edges. For fire‐rated plywood the classification stamp
must not be obscured.
Doors must be a minimum of 3 ft (915 mm) wide and 8
ft. (2.44 m) high minimum w/ no center support and
hinged to open outward (when permitted by Code).
The door must be fitted with a lock. An integrated
GRE GRE, WTS Y Y
strike must be included to accommodate electronic
access control. Doors must be equipped with floor
sweeps to contain conditioned air, minimize dust
infiltration, and minimize escape of noise.
Doors
Automatic closer GRE GRE, WTS Y Y
Quantity of doors defined by codes, as well as access
GRE GRE, WTS Y Y
and egress requirements.
Swinging doors must be fire rated with a UL
classification label, and have been tested compliant
GRE GRE, WTS Y Y
with the UL10C standard. In no case must a door in a 1
hour fire rated wall have less than a 1 hour fire rating.
‐ Suspended ceiling must not be installed in an MER.
‐ Slab to slab height must be at least 10 ft (3.05 m) and
unobstructed height at least 9 ft. (2.74 m). These
heights must be even higher if needed for cable
Ceiling pathways, or for maintenance functions, or for proper GRE GRE, WTS Y Y
air flow to and from air conditioning units.
‐‐ Exposed ceilings and sprayed on fireproofing in an
exposed ceiling must be treated (sealed) to mitigate
dust.
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
3. Room Construction ‐ MERs (Continued)
A minimum of 500 lux (50 foot‐candles) in the
horizontal plane and 200 lux (20 foot‐candles) in the
vertical plane measured 1 m (3 ft) above the finished
floor in middle of all rack and cabinet aisles. The
lighting must be controlled by one or more switches
located near the entrance door(s) to the
Lighting room. Emergency lighting and signs must be properly GRE GRE, WTS Y Y
placed per Code or AHJ such that an absence of primary
lighting will not hamper emergency exit. Lighting
fixtures must not be powered from the same electrical
distribution panel as information and communication
technology equipment in the MER. Dimmer switches
must not be used.
Raised Access Floor or Static Dissipative VCT (106 to 109
ohms) based on design requirements to cool initial and
future IT loads.
A structural engineer shall be consulted during the
design to specify the floor loading limit. The minimum
distributed floor loading capacity shall be 7.2 kPa (150
lbf/ ft2). The recommended distributed floor loading
capacity is 12 kPa (250 lbf/ ft2). Floors must be
appropriately reinforced if equipment exceeding these
specifications is anticipated. This requirement also
Flooring applies in the case of relocation of equipment at a later GRE GRE, WTS Y Y Y
time. If extensive relocation is anticipated, the entire
floor must be appropriately reinforced.
The floor must have a minimum of 1.2 kPa (25 lb/ft2)
capacity for supporting loads that are suspended from
the bottom of the floor (for example, cable ladders
suspended from the ceiling of the floor below). The
recommended minimum hanging capacity of the floor is
2.4 kPa (50 lb/ft2). Access floor support elements must
have similar load carrying capabilities. VCT should be
bonded to ground.
If access floor is installed, the access floor tiles must be
GRE GRE, WTS Y Y
finished with a high‐pressure laminate (HPL).
In MERs with access floor, power conduit and
associated cabling should be routed below the floor and
all telecommunications cable should be routed in cable
Access Floor, conveyance overhead.
if applicable If, as an exception, telecommunications cabling and
power wiring are both run below the access floor, an GRE GRE, WTS Y Y
under floor cable tray system should be used for the
routing of telecommunications cabling. Wherever
practicable, power and communications cables should
cross at right angles, and telecommunications cables
should be located in tray above power cables.
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
3. Room Construction ‐ MERs (Continued)
Stringers to be installed as per the selected raised floor
design to support rolling load and seismic loading.
Pedestals and stringers must be grounded. GRE GRE, WTS Y Y
Materials must either be non‐combustible or have a
flame spread index of 25 or less.
Access Floor,
if applicable Must comply with design requirements for depth of
floor.
GRE GRE, WTS Y Y
Power shall be installed below access floor and routed
in a manner that avoids blockage of airflow.
Under floor smoke detection required, where required
GRE GRE, WTS Y Y
by code.
The floor, walls, and ceiling must be sealed to reduce
Dust dust. If access floor is installed, the area under the GRE GRE, WTS Y Y
access floor must be sealed.
Fire extinguishers should be installed in rooms based on
local codes, and/or must have ready access to a listed
portable fire extinguisher compliant with the NFPA 10
Fire Safety standard, local Codes and OSHA requirements. GRE GRE, WTS Y
Must not use dry chemicals, and must have a suitable
tank capacity, and appropriate fire type category
ratings.
All through‐penetrations and membrane‐penetrations
of fire rated walls and floors must be firestopped.
Installation methods and firestopping materials and
systems must be qualified for the specific circumstances
under which they will be used. Firestopping must, as a
minimum, preserve the fire rating of the penetrated
Firestopping surface(s). GRE GRE, WTS Y Y
Must comply with Codes and manufacturer’s required
and recommended procedures
“F”, “T”, and “L” ratings must be chosen as required by
Code and/or an AHJ, and must be appropriate to the
situation. Where water penetration is of concern, the
firestop should have a “W” rating as well.
Grounding (Earthing) and bonding must conform to
applicable NEC requirements, local codes and bonding GRE GRE, WTS Y Y
systems specified by ANSI/TIA‐607.
Bare metal contact is required for all bonding
GRE GRE, WTS Y Y
connections.
Metallic Structures (including racks, cabinets, cable
pathways, armored comms cable jackets). All open
frame racks shall be equipped with rack mounted GRE GRE, WTS Y Y
ground busbars, for the grounding of network
Bonding and
equipment.
Grounding
(Earthing)
Systems grounded (earthed) as required by
manufacturer, standards, and codes
An MER must contain at least one Secondary bonding
busbar (SBB), and may contain a Primary bonding
busbar (PBB) depending upon the room’s location and
GRE GRE, WTS Y Y
function at a site. All open frame racks shall be
equipped with horizontal rack mounted ground busbars
(RBB), for the grounding of network equipment.
Horizontal rack mounted ground busbar shall be
mounted on the rear of the cabinet/rack.
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
3. Room Construction ‐ MERs (Continued)
Chilled water or glycol piping shall be routed outside
the room and penetrate the MER at the shortest path LOB, GRE,
GRE Y Y
to connect to CRAC/CRAH units. Routing shall avoid all WTS
racks, cabinets and cable pathways.
If sprinklers are required within the equipment area,
fire sprinkler head location must be coordinated with
room layout so that heads shall be 18 in. (457.2 mm)
clear of any obstructions and piping routed in aisle ways
Piping as per fire codes. Sprinklers and piping must not be LOB, GRE,
GRE Y Y
routed directly above IT equipment or enclosures and WTS
must be routed in aisle ways instead for optimal
clearance. Above racks and cabinets there shall be no
joints to prevent against the potential for leaks from
wet systems.
If sprinklers are required within the equipment area,
LOB, GRE,
the fire sprinkler heads must be provided with wire GRE Y Y
WTS
cages to prevent accidental operation.
5‐20 duplex convenience outlets on utility power only
to be located at typical outlet height on walls GRE WTS Y
throughout the room.
Wall phones to be strategically placed for technician
access. The outlet mounting height must ensure that
Convenience the phone keypad and controls will be no greater than
GTI WTS Y
Outlets 1,372 mm (54 in) above the finished floor to comply
with requirements of the Americans with Disabilities
Act (ADA).
JPMC wireless network access inside the room (where
GTI WTS Y
wireless access is deployed)
Secured storage and staging room should be planned in
Storage and close proximity to MER that should include a 6’w (1.83
GTI WTS Y Y Y
Staging m) x 3'd (0.91 m) work surface and one 7'h (2.13 m) x
4'w (1.22 m) shelving unit.
4. Labeling and Administration ‐ MERs (Main Equipment Rooms)
Labels to be affixed to top front and top rear of rack or
cabinet
Structured
Nomenclature: WTS Y
Cabling
Racks / <Row Letter><Position Number>
Cabinets Example: A01 means first row, first position
Type: 1.5 in. (38 mm) text lamacoid; machine printed Structured
WTS Y
text. White text on black background. Cabling
1.5 in. (38 mm) tall text placed in visible location on Structured
WTS Y
plastic bushing or on the conduit itself near the end. Cabling
Data Cable
Conduit Nomenclature <size>.<path A/B>to<Distant end room
Structured
ID>. Example: 4” A to 06TR‐B WTS Y
Cabling
Sleeves shall be labeled "Sleeve"
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
4. Labeling and Administration ‐ MERs (Continued)
Cabinet/rack positions shall be identified by an alpha‐
numeric identifier where a letter shall identify the row
and a number shall identify the cabinet position within Structured
WTS Y
the row. Future positions left vacant shall have their Cabling
Cabinet / Rack identifiers reserved. <Row Letter><Position Number>.
Identification Example: A01. (first row, first position)
Label to be affixed to top of cabinet in the front and Structured
WTS Y
rear. Text on labels shall be at least 1 in. (26 mm) tall. Cabling
All Copper
Nomenclature:
Patch Panels
<RU><Top RU of panel > labeled on the left side of the Structured
and Fiber WTS Y
panel. Cabling
Enclosures
Example: RU38
Panel ID
All Copper
Patch Panels
serving intra‐ To Rack/Cabinet<Distant End Rack/Cabinet
Structured
room tie ID>Panel<Panel ID>Ports<End Location Port Range> WTS Y
Cabling
cabling Example: To Rack AB01 Panel RU34 Ports 25‐48
connectivity
labeling
All Copper
Patch Panels
serving intra‐ Where route diversity is employed designation strips
Structured
room tie located on termination panels for each route shall be of WTS Y
Cabling
cabling distinctly different colors.
connectivity
labeling
All Copper To<Distant End Room ID>Rack/Cabinet<Distant End
Patch Panels Rack/Cabinet ID>Panel<Panel ID>Ports<End Location Structured
WTS Y
serving inter‐ Port Range> Cabling
room tie Example : To 04TR‐B Rack AA01 Panel RU31 Ports 01‐24
cabling Where route diversity is employed designation strips
connectivity Structured
located on termination panels for each route shall be of WTS Y
labeling Cabling
distinctly different colors.
All Copper
Patch Panels <TR Designation><Panel Sequence>
serving Example: 04A‐34
Structured
workstation Panel jacks must be labeled, and include port labeling WTS Y
Cabling
cabling reflecting the Workstation ID or the Grid Location
connectivity number.
labeling
All Fiber
Enclosures <Fiber Type>to Rack/Cabinet<Distant End Rack/Cabinet
serving intra‐ ID>Panel<Panel ID>Slot<End Location Slot>Ports<End
Structured
room tie Location Port Range> WTS Y
Cabling
cabling Example: OM4 to Rack AA04 Panel RU38 Slot A Ports
connectivity 01‐12
labeling
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
4. Labeling and Administration ‐ MERs (Continued)
All Fiber
Enclosures
serving intra‐ Where route diversity is employed designation strips
Structured
room tie located on termination panels for each route shall be of WTS Y
Cabling
cabling distinctly different colors.
connectivity
labeling
<Fiber Type>to<Distant End Room ID>Rack/Cabinet
All Fiber <Rack/Cabinet ID>Panel<Panel ID>Slot<End Location
Enclosures Structured
Slot>Ports<End Location Port Range> WTS Y
serving inter‐ Cabling
Example: OM4 to 03TR‐A Rack AA06 Panel RU32 Slot A
room tie Ports 01‐12
cabling
connectivity Where route diversity is employed designation strips
Structured
labeling located on termination panels for each route shall be of WTS Y
Cabling
distinctly different colors.
All patch cables to be labeled with wrap‐around (not
flag) Brady‐type labels indicating the following on both
sides.
Patch Cables WTS WTS Y
From (on line 1): <Rack ID‐Panel ID‐Port>or<Rack ID‐
Top RU of Switch‐Blade‐Port> To (on line 2): <Rack ID‐
Panel ID‐Port>or<Rack ID‐Top RU of Switch‐Blade‐Port>
PDU (Power Strip) shall be labeled with the breaker
Power
panel ID it is served from. When cabinets are served by
Distribution
PDUs (power strips) from different sources the label for
Units (PDU) GRE GRE, WTS Y
each source shall be distinctly different colors. A white
label shall be used to designate source A while a black
(Power Strips)
label shall designate source B.
Secondary Bonding Busbar (SBB)
<Room ID> SBB<SBB # if more than one in a room>
Example: 07TR‐A SBB2
Primary Bonding Busbar (PBB)
Grounding
<Room ID>PBB GRE GRE, WTS Y
Busbars
Example: 01MER‐1 PBB
Labels for SBB and PBB must either be affixed to a
visible ‐ non‐interfering ‐ location on the busbar, or to
the wall near the busbar.
Labeling and administration will be per GRE direction to
MEP Systems GRE GRE, Y
meet design requirements and value objectives.
All powered IT equipment, aside from audio‐visual or
carrier equipment must be labeled with the devices
hostname and a yellow asset tag on the front (cold Any
aisle) side of the device. A machine generated label equipment
indicating the serial number of the device shall also be provider (i.e. LOB, GRE,
IT Equipment Y
placed on the front (cold aisle) side of the device. All LOB, GNS, WTS
cabinets must have a yellow asset tag at the top of the Transport,
front door and all racks must have a yellow asset tag at Voice, Media)
the top front in a visible area that can be easily
accessed with a barcode scanner.
Minimum of one MER per building. Each building shall
Room
be evaluated for risk and resiliency expectations with LOB, GRE,
Quantity and GRE Y Y Y
project stakeholders and business units to determine WTS
Size
any MER redundancy requirement.
MERs (Main Equipment Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
5. MER Room Planning ‐ MERs (Continued)
The MER should be positioned so that locations that are
restricted by building components that limit expansion
such as elevators, core, outside walls, or other fixed
building walls are avoided. Large trunk ductwork and LOB, GRE,
GRE Y Y Y
piping or other items should be avoided. For the WTS
delivery of large equipment, location decisions should
factor in the need for accessibility. It is desirable to
locate the MER close to the backbone pathways.
The MER should never be located below grade, in flood
zones, or near spaces that may present a threat of
water infiltration unless preventive measures against LOB, GRE,
GRE Y Y Y
water infiltration are employed. The room must be free WTS
of water or drain pipes not directly required in support
of the equipment within the room.
Room
Location The room must be located away from sources of
electromagnetic interference. Special attention should
LOB, GRE,
be given to electrical power supply transformers, GRE Y Y Y
WTS
motors and generators, x‐ray equipment, radio or radar
transmitters, and induction sealing devices.
Equipment not related to the support of the MER (e.g.,
LOB, GRE,
piping, ductwork, pneumatic tubing, etc.) shall not be GRE Y Y Y
WTS
installed in, pass through, or enter the MER.
MER rooms must not be a pass through to other rooms,
LOB, GRE,
and MER rooms must not be located behind other GRE Y Y Y
WTS
rooms that act as a pass through.
MER Rooms shall not be located in areas susceptible to LOB, GRE,
GRE Y Y Y
heat gain WTS
Room Rooms must not have any windows. GRE LOB, GRE,
Y Y Y
Location WTS
Condensate containment pans/curbing with leak
CRAC/CRAH detection required for floor/ wall supported CRAC units.
GRE GRE, WTS Y Y
Units Drip pan with leak detection required for ceiling
mounted CRAC units.
Fire
Suppression Located in GRE controlled space GRE GRE GRE, WTS Y Y Y
Systems
AutoCAD is the minimum required design software. The
project engineer must identify to the project team the
AutoCAD save version necessary to share files
Design Tools When shared electronically, documents must be GRE GRE, WTS Y Y Y
provided in both PDF and DWG file formats. All
drawings must be scaled and the drawing must identify
the scale that is used.
13 of 36 Revision Date: July 1, 2018 Version: 1.0.2
Appendix B
TRs (Telecommunications Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
1. Critical Systems ‐ TRs (Telecommunications Rooms)
Single Source, except for locations where there are
LOB, GRE,
Utility System Traders, Call Centers, or where LOB requirements GRE Y Y Y
WTS
demand them.
Not Required, except for locations where there are
Generator LOB, GRE,
Traders, Call Centers, or where LOB requirements GRE Y Y Y
System WTS
demand them.
Not required, except for locations where there are
LOB, GRE,
UPS System Traders, Call Centers, or where LOB requirements GRE Y Y Y
WTS, GNS
demand them.
N with mechanical conveyance at N – Portable air
conditioning unit(s) must be provided an L630R
Primary receptacle along with associated means for LOB, GRE,
GRE Y Y Y
Cooling Plant exhausting hot air and disposing of condensate. WTS
These units must not be stored in a TR or in an
MER.
Emergency power off devices, if required, are to be
installed with up protective cover as part of dual action
Emergency
station to reduce false activation; are normally
Power LOB, GRE,
open/normally closed dry contact and shall change GRE Y Y
Shutdown WTS
state upon EPO activation, and be properly labeled, i.e.,
Management
Emergency Power Off (EPO), Remote Emergency Power
Off (REPO), Remote Emergency Module Office (REMO).
CRAH/CRAC LOB, GRE,
N GRE Y Y Y
Units WTS
Must be designed to maintain humidity within the
recommended range for all “A Classes” per ASHRAE
TC9.9 2011 (Thermal Guidelines for Data Processing
Environments).
CRAH/CRAC LOB, GRE,
GRE Y Y
Units Humidity Range, Non‐Condensing: 20% to 80% Relative WTS
Humidity with 17⁰C (62.6⁰F) Maximum Dew Point
Additional restrictions as applicable to site.
Redundant and diversely fed A/B circuits to racks.
Lowest acceptable level of redundancy is two circuits
diversely routed from a common breaker panel, but
more redundancy should be provided if practical.
Branch Circuit Circuits must be dedicated including dedicated neutral LOB, GRE,
GRE Y Y
Distribution and equipment grounding conductor (EGC). WTS
No Isolated Ground (IG) circuits unless required for
specific equipment.
Protected by Transient Voltage Surge Suppression
(TVSS) device effective at breaker panel level.
All equipment should be dual corded.
The primary choice is 208V/3‐phase power/30A, with
Any
208V/single phase/20 or 30A being allowable based on
equipment
site specific requirements, or its country specific
provider (i.e. LOB, GRE,
Equipment equivalent, must be provided at every cabinet Y
LOB, GNS, WTS
footprint. In North America 120V power must also be
Transport,
provided at the PDU (power strip) level. Proper load
Voice, Media)
balancing must be planned and maintained to prevent
excessive phase unbalance.
TRs (Telecommunications Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
1. Critical Systems ‐ TRs (Continued)
A minimum of 500 lux (50 foot‐candles) in the horizontal
plane and 200 lux (20 foot‐candles) in the vertical plane
measured 1 m (3 ft) above the finished floor in middle of
all rack and cabinet aisles. The lighting must be
controlled by one or more switches located near the
entrance door(s) to the room. Emergency lighting and LOB, GRE,
Lighting GRE Y Y
signs must be properly placed per Code or AHJ such that WTS
an absence of primary lighting will not hamper
emergency exit. Lighting fixtures must not be powered
from the same electrical distribution panel as
information and communication technology equipment
in the TR. Dimmer switches must not be used.
Installed to the extent necessary to detect critical alarm
conditions (i.e. temperature, humidity, fire/smoke, critical
Critical
equipment malfunction). LOB, GRE,
System GRE Y Y
Requirements will be determined by those owning and WTS
Monitoring
operating these systems.
A condensate containment pan and/or curbing wall with
Leak leak detection is required for floor/wall supported
Detection for CRAH/CRAC units. A drip pan with leak detection is LOB, GRE,
Mech required for ceiling mounted CRAH/CRAC units. Ceiling GRE Y Y
WTS
equipment / mounted cooling units should be installed outside the
Piping room and ducted in.
Wet Fire Suppression Sprinkler permitted; Pre‐Action
Fire Suppression Sprinkler not required. Sprinkler to
Fire have protective cage to prevent accidental contact LOB, GRE,
and activation Gaseous fire suppression must be GRE Y Y Y
Suppression WTS
installed when required by local authority having
jurisdiction (AHJ).
For MER‐to‐TR cabling in multi‐tenant buildings, routed
in rigid conduit. For buildings occupied exclusively by
JPMC, routed exposed through sleeves/slots vertically
Structured LOB, GRE,
Backbone and through rigid conduit, tray etc. horizontally. Y Y
Cabling WTS
Wherever telecommunications conduit is installed for
backbone cabling, it shall be pre‐provisioned with
flexible fabric innerduct (e.g. MaxCell).
2. Ancillary Systems ‐ TRs (Telecommunications Rooms)
Provide the following for network device and cabling
equipment: 19 in. 4‐post open rack with fixed rails and
minimum depth 740 mm (29 in) outside of front rail to
outside of rear rail. Vertical cable managers shall be
sized based on cable counts and fill factors.
Structured cabling engineer to determine WTS,
Structured
Racks appropriate size based on site requirements. Be Structured Y Y
Cabling
equipped with appropriate air baffles if Cabling
equipment is mounted side by side in adjacent
racks. Racks to be bolted to floor. Seismic bracing
where applicable. 45 RU rack height. Network racks
are not to be used for servers.
TRs (Telecommunications Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
2. Ancillary Systems ‐ TRs (Continued)
All connectivity/patching shall be performed within
any given rack/cabinet and not between rows. Structured
LOB, WTS Y Y
Cabling
All patching to be supported, address bend radius, and
utilize cable management solely intended for its use.
Power and data patching to utilize separate pathways.
Patching shall not be of excessive length, planning for Structured
Patching WTS Y Y
1' of service loop on each end, and be routed neatly Cabling
providing free access for maintenance of equipment
and cabling infrastructure.
Hot/Cold Aisle:
GRE,
Coordinate placement of CRAC/CRAH components
Structured
delivering cool air and capturing return air with the GRE Y Y
Cabling,
layout of racks. WTS
Hot/Cold Aisle: Equipment intakes at the front of racks
are not facing rear‐equipment exhaust from a GRE,
Layout neighboring row. Side mounted air baffles must be Structured Structured
Y Y
installed in the instances where equipment is mounted Cabling Cabling,
side by side in adjacent racks. WTS
Rack/cabinet elevations to be planned for growth at
Structured
switch and patching frames, and growth at server GRE, WTS Y Y
Cabling
cabinets.
3 ft (915 mm) minimum service clearance from the
front of equipment in racks or cabinets. 3 ft (915
mm) minimum service clearance from the rear of
equipment in racks or cabinet. 4 ft (1829 mm) Structured
WTS Y Y Y
minimum service clearance on one side of the row of Cabling
racks or cabinets. 1 ft (305 mm) additional service
clearance in front of telco wall field.
Clearances
In access floor environments at least one full floor tile
must be free of obstruction nearest to the front and Structured
in back of each rack or cabinet in a row to allow under WTS Y
Cabling
floor access.
2 ft (610 mm) service clearance above racks and
cabinets. Cable support systems shall be the only Structured
WTS Y Y
allowable obstruction. Cabling
TRs (Telecommunications Rooms)
Fill planned for growth not to exceed 50% fill maximum;
bend radius of cables will be compliant with the Structured
WTS Y Y
ANSI/TIA‐568 group of standards, or manufacturer’s Cabling
requirements if those are stricter.
Conduits and sleeves for carrier media not to be shared Structured
WTS Y Y
with JPMC structured cable media Cabling
Service loops for cabling to telecommunications
outlets to be stored at telecommunications outlet and Structured
WTS Y
not in the TR. Cabling
Metallic Cable Trays:
Must be independently supported from ceiling or walls,
not from cabinets and racks.
Installed with at least 12 in (305 mm) clearance above
tray.
Pathways Installed 4 in – 6 in (101.6mm – 152.4 mm) above rack
or cabinet. Structured
WTS Y Y
Installation must be electrical Code compliant. Cabling
Must be bonded to ground. When tray sections are not
mechanically continuous, or if section connecting
hardware is not approved as a means for providing
ground continuity, bonding conductors must be
installed across the sections.
Non Metallic Raceways and Cable Routing Assemblies:
May be attached to cabinets and racks when intended
for patching or other local connections within a row.
Otherwise must be independently supported as per Structured
metallic cable tray requirements. WTS Y Y
Cabling
Must be fire rated as required by electrical code (i.e.
plenum, riser, etc.) and must be UL2024 or UL2024A
listed (as appropriate to application).
Single point of entry into the room with a card reader/
pin pad on the ingress and card reader only on the LOB, GRE,
GRE Y Y
egress side of the door. WTS, GSMA
Card Reader entry door lock must be fail secure in
case of power outage or fire alarm system activation LOB, GRE,
GRE Y Y
Security unless otherwise dictated by local code. WTS, GSMA
Cameras covering the entrance door and any other LOB, GRE,
GRE Y Y
secondary exits from inside and outside. WTS, GSMA
Any secondary doors that lead into the room must be
treated as emergency exits and must have a door LOB, GRE,
contact, local alarm sounder, signage, no handle on GRE Y Y
WTS, GSMA
hallway side of door, and crash bar on inside of door.
TRs (Telecommunications Rooms)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
2. Ancillary Systems ‐ TRs (Continued)
All doors leading into the TR must be monitored for GRE LOB, GRE,
immediate forced open and door held open (60 Second) WTS, GSMA Y Y
Security alarms.
GSMA LOB, GRE,
Access logs will not be required in rooms. Card WTS, GSMA Y
reader/pin reader will be system of record for access.
Receptacles mounted on a separate c‐channel
independently supported below ladder rack and
above rack. The receptacle facing the rack/cabinet in
hot aisle (equipment air exhaust side of cabinet,
GRE GRE, WTS Y
with electrical sockets facing the hot aisle, not
the ceiling or floor). If power routed under floor,
power to be mounted on bracket installed between
pedestals in hot aisle.
Receptacles labeled with panel ID and circuit #.
GRE GRE, WTS Y
Where diverse power feeds are deployed A‐side panel
circuits shall use black on white labels to designate the
circuit on the faceplate and B‐side panel circuits to
GRE GRE, WTS Y
utilize white on black labels to designate the circuit on
the faceplate.
PDU (Power Strip) shall be labeled with the breaker
panel ID it is served from. When racks are served by
PDUs (power strips) from different sources the label for
each source shall be distinctly different colors. A white GRE GRE, WTS Y
Power label shall be used to designate source A while a black
Distribution label shall designate source B.
Where diverse power feeds are deployed equipment to
have special ordered white cords plugged into A‐side
power connections and black cords plugged into B‐side GRE GRE, WTS Y
power connections.
PDUs (Power Strips) (see Appendix E, of the WTS Cable
Design and Engineering Standards) shall adhere to the
following requirements:
‐ 208V/3‐phase 30A (or country specific equivalent) ( In
North America 120V power must also be provided at
the local Power Distribution Unit (PDU) level.
‐ Minimum (24) C‐13 receptacles
‐ Minimum (6) C‐19 receptacles
WTS GRE, WTS Y
‐ Minimum (2) 5‐20 receptacles (in NA only)
‐ Locking input power cords
‐ Integral breakers or fuses when required by Code
‐ Ability for metering (including each phase with true
RMS reading of current and voltage)
- ‐ Ethernet port allowing remote readout of PDU
parameters.
TRs (Telecommunications Rooms)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
3. Room Construction ‐ TRs (Telecommunications Rooms)
Naming Convention:
‐ Building abbreviations should also come from and
coordinated with GRE
‐ Room Type should reflect Technology room definitions as
identified in the space classification document (TR for
Telecommunication Room or MER for Main Equipment GRE GRE, WTS, LOB Y
Room Signage
Room)
‐ Identifier should be included if there are more than one
TR located on the floor and can be listed in Numbers,
Letters, or Colors (i.e. 1, 2, A, B, Orange, Blue, etc.)
‐Updated signage should also accompany the activation of
any new technology rooms. The room signage should be
in compliance with existing standards as provided by
facilities. It should not change the look and feel of the
existing floor signage within the office space, but should
clearly indicate the room names in accordance with the
GTI technology space classification.
To be placed outside every TR entrance
When applicable to the site, sign characteristics must
comply with requirements of the Americans with
Disabilities Act (ADA).
For secondary exits: GRE GRE, WTS, LOB Y
Room Signage
On the ingress side sign stating “No Entry – Emergency Exit
Only”
On the egress side sign stating “Emergency Exit Only –
Alarm Will Sound”
All penetrations firestopped to maintain fire rating of
walls, and must be firestopped per the requirements of
GRE GRE, WTS Y Y
this Standard, ATSM E814, UL1479, and the manufacturer.
Where no equipment is intended to be mounted to the
wall, the drywall must be taped, spackled and sanded to a
GRE GRE, WTS Y
smooth finish. The wall must be painted a light color to
enhance room lighting.
At least one sheet of plywood 1.22 m (4 ft) wide and 2.43
Walls m (8 ft) high and beginning 153 mm (6 in) above the
finished floor must be installed on a wall in a location best
suited for its use.
Plywood to be:
‐ compliant with Codes
‐ kiln dried (15% max. moisture)
‐ 19 mm (¾”) thick A‐C grade (mounted with best side GRE GRE, WTS Y Y
facing the room)
‐ fastened securely to a wall
‐ Either fire rated (with a UL FR‐S classification), or if non‐
fire‐rated ‐ and if acceptable to the AHJ ‐ covered with two
coats of fire retardant paint on both sides and edges. For
fire‐rated plywood the classification stamp must not be
obscured.
TRs (Telecommunications Rooms)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
3. Room Construction ‐ TRs (Continued)
Doors must be a minimum of 3 ft (915 mm) wide and 8 ft.
(2.44 m) high minimum w/ no center support and hinged
to open outward (when permitted by Code). The door
must be fitted with a lock. An integrated strike must be
Doors included to accommodate electronic access control. Doors GRE GRE, WTS Y Y
must be equipped with gaskets floor sweeps to contain
conditioned air, minimize dust infiltration, and minimize
escape of noise.
Automatic closer
GRE GRE, WTS Y Y
Quantity of doors defined by codes, as well as access and
egress requirements. GRE GRE, WTS Y Y
Rated to maintain fire rating of room, but no less than 1 ½
hour for 1 hour rated walls and no less than ¾ hour for 1
GRE GRE, WTS Y Y
hour rated walls.
Doors
Ceiling ‐ Suspended ceiling must not be installed in a TR.
‐ Slab to slab height must be at least 10 ft (3.05 m) and
unobstructed height at least 9 ft. (2.74 m). These heights
must be even higher if needed for cable pathways, or for
maintenance functions, or for proper air flow to and from GRE GRE, WTS Y Y
air conditioning units.
‐ Exposed ceilings and sprayed on fireproofing in an
exposed ceiling must be treated (sealed) to mitigate dust.
A minimum of 500 lux (50 foot‐candles) in the horizontal
plane and 200 lux (20 foot‐candles) in the vertical plane
measured 1 m (3 ft) above the finished floor in middle of
all rack and cabinet aisles. The lighting must be controlled
by one or more switches located near the entrance door(s)
to the room. Emergency lighting and signs must be
Lighting properly placed per Code or AHJ such that an absence of GRE GRE, WTS Y Y
primary lighting will not hamper emergency exit. Lighting
fixtures must not be powered from the same electrical
distribution panel as information and communication
technology equipment in the TR. Dimmer switches must
not be used.
TRs (Telecommunications Rooms)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
3. Room Construction ‐ TRs (Continued)
Raised Access Floor or Static Dissipative VCT (106 to 109
ohms) based on design requirements to cool initial and
future IT loads.
A structural engineer shall be consulted during the design to
specify the floor loading limit. The minimum distributed
floor loading capacity shall be 7.2 kPa (150 lbf/ ft2). The
recommended distributed floor loading capacity is 12 kPa
(250 lbf/ ft2). Floors must be appropriately reinforced if
equipment exceeding these specifications is anticipated.
This requirement also applies in the case of relocation of
Flooring equipment at a later time. If extensive relocation is GRE GRE, WTS Y Y Y
anticipated, the entire floor must be appropriately
reinforced.
The floor must have a minimum of 1.2 kPa (25 lb/ft2)
capacity for supporting loads that are suspended from the
bottom of the floor (for example, cable ladders suspended
from the ceiling of the floor below). The recommended
minimum hanging capacity of the floor is 2.4 kPa (50 lb/ft2).
Access floor support elements must have similar load
carrying capabilities. VCT should be bonded to ground.
If access floor is installed, the access floor tiles must be
finished with a high‐pressure laminate (HPL). GRE GRE, WTS Y Y
In TRs with access floor, power conduit and associated
cabling should be routed below the floor and all
telecommunications cable should be routed in cable
conveyance overhead.
If, as an exception, telecommunications cabling and power
wiring are both run below the access floor, an under floor
GRE GRE, WTS Y Y
cable tray system should be used for the routing of
telecommunications cabling. Wherever practicable, power
and communications cables should cross at right angles, and
Access Floor, if telecommunications cables should be located in tray above
applicable power cables.
Materials must either be non‐combustible or have a flame
spread index of 25 or less.
Stringers to be installed as per the selected raised floor
GRE, WTS
design to support rolling load and seismic loading. GRE
Pedestals and stringers must be grounded.
Must comply with design requirements for depth of floor.
Power shall be installed below access floor and routed in a GRE GRE, WTS Y Y
manner that avoids blockage of airflow.
Under floor smoke detection, where required by code. GRE GRE, WTS Y Y
The floor, walls, and ceiling must be sealed to reduce dust. If
access floor is installed, the area under the access floor
Dust GRE GRE, WTS Y
must be sealed.
Fire extinguishers to be installed in rooms based on local
codes, and/or must have ready access to a listed portable
fire extinguisher compliant with the NFPA 10 standard, local
Fire Safety Codes and OSHA requirements. GRE GRE, WTS Y
Must not use dry chemicals, and must have a suitable tank
capacity, and appropriate fire type category ratings.
TRs (Telecommunications Rooms)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
3. Room Construction ‐ TRs (Continued)
All through‐penetrations and membrane‐penetrations of
Firestopping fire rated walls and floors must be firestopped. GRE GRE, WTS Y Y
Installation methods and firestopping materials and systems
Grounding (Earthing) and bonding should conform to
applicable NEC requirements, local codes and bonding GRE GRE, WTS Y Y
systems specified by ANSI/TIA‐607.
Bare metal contact is required for all bonding connections.
GRE GRE, WTS Y Y
Metallic Structures (including racks, cabinets, cable
pathways, armored comms cable jackets). All open frame
racks shall be equipped with rack mounted ground busbars, GRE GRE, WTS Y Y
Bonding and
Grounding for the grounding of network equipment.
(Earthing) Systems grounded (earthed) as required by manufacturer,
standards, and codes. A TR must contain at least one
Secondary Bonding Busbar (SBB). All open frame racks shall
be equipped with horizontal rack mounted ground busbars GRE GRE, WTS Y Y
(RBB), for the grounding of network equipment. Horizontal
rack mounted ground busbar shall be mounted on the rear
of the cabinet/rack.
Chilled water or glycol piping shall be routed outside the
room and penetrate the MER at the shortest path to
connect to CRAC/CRAH units. Routing shall avoid all racks, GRE LOB, GRE, WTS Y Y
cabinets and cable pathways.
If sprinklers are required within the equipment area, fire
sprinkler head location must be coordinated with room
layout so that heads shall be 18 in. (457.2 mm) clear of any
obstructions and piping routed in aisle ways as per fire
GRE LOB, GRE, WTS
codes. Sprinklers and piping must not be routed directly Y Y
Piping above IT equipment or enclosures and must be routed in
aisle ways instead for optimal clearance.
If sprinklers are required within the equipment area, the fire
sprinkler heads must be provided with wire cages to prevent GRE LOB, GRE, WTS Y
accidental operation.
5‐20 duplex convenience outlets on utility power only to be
located at typical outlet height on walls throughout the GRE WTS Y
room.
Wall phones to be strategically placed for technician access.
The outlet mounting height must ensure that the phone
Convenience
keypad and controls will be no greater than 1,372 mm (54 GTI WTS Y
Outlets
in) above the finished floor to comply with requirements of
the Americans with Disabilities Act (ADA).
JPMC wireless network access inside the room (where
wireless access is deployed) GTI WTS Y
4. Labeling and Administration ‐ TRs (Telecommunications Rooms)
Labels to be affixed to top front and top rear of rack or
cabinet
Nomenclature: Structured
WTS Y
<Row Letter><Position Number> Cabling
Example: A01 means first row, first position
Racks
Type: 1.5 in. (38 mm) text lamacoid. White text on black Structured
background. WTS Y
Cabling
Nomenclature <size>.<path A/B>to<Distant end room
ID>. Example: 4” A to 06TR‐B Structured
WTS Y
Sleeves shall be labeled "Sleeve"" Cabling
TRs (Telecommunications Rooms)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
4. Labeling and Administration ‐ TRs (Continued)
1.5 in. (38 mm) tall text placed in visible location on plastic
bushing or on the conduit itself near the end.
Data Cable Structured
WTS Y
Conduit Cabling
Rack positions shall be identified by an alpha‐numeric
identifier where a letter shall identify the row and a number
shall identify the cabinet position within the row. Future Structured
positions left vacant shall have their identifiers reserved. WTS Y
Rack Cabling
Identification <Row Letter><Position Number>. Example: A01. (first row,
first position)
Label to be affixed to top of cabinet in the front and rear. Structured
Text on labels shall be at least 1 in. (26 mm) tall. WTS Y
Cabling
All Copper Patch Nomenclature:
Panels and Fiber Panel ID ‐ <RU><Top RU of panel > labeled on the left side of Structured
WTS Y
Enclosures Panel the panel. Example: RU38 Cabling
ID
All Copper Patch To Rack/Cabinet<Distant End Rack/Cabinet ID>Panel<Panel Structured
Panels serving ID>Ports<End Location Port Range> Cabling
WTS Y
intra‐room tie Example: To Rack AB01 Panel RU34 Ports 25‐48
cabling Where route diversity is employed designation strips
connectivity Structured
located on termination panels for each route shall be of WTS Y
labeling Cabling
distinctly different colors.
To<Distant End Room ID>Rack/Cabinet<Distant End
All Copper Patch Rack/Cabinet ID>Panel<Panel ID>Ports<End Location Port Structured
Panels serving WTS Y
Range> Cabling
inter‐room tie Example : To 04TR‐B Rack AA01 Panel RU31 Ports 01‐24
cabling
Where route diversity is employed designation strips
connectivity Structured
located on termination panels for each route shall be of WTS Y
labeling Cabling
distinctly different colors.
All Copper Patch <TR Designation><Panel Sequence>
Panels serving
workstation Example: 04A‐34 Structured Structured
Y
cabling Cabling Cabling, WTS
connectivity Panel jacks must be labeled with Workstation ID
labeling
<Fiber Type>to Rack/Cabinet<Distant End Rack/Cabinet
ID>Panel<Panel ID>Slot<End Location Slot>Ports<End
All Fiber Location Port Range> Structured
Enclosures serving Example: OM4 to Rack AA04 Panel RU38 Slot A Ports 01‐ WTS Y
Cabling
intra‐ room tie 12Ports 01‐12
cabling
connectivity Where route diversity is employed designation strips
labeling located on termination panels for each route shall be of Structured
WTS Y
distinctly different colors. Cabling
<Fiber Type>to<Distant End Room ID>Rack/Cabinet
<Rack/Cabinet ID>Panel<Panel ID>Slot<End Location
All Fiber Structured
Slot>Ports<End Location Port Range> WTS Y
Enclosures serving Cabling
Example: OM4 to 03TR‐A Rack AA06 Panel RU32 Slot A
inter‐ room tie
Ports 01‐12
cabling
connectivity Where route diversity is employed designation strips
labeling located on termination panels for each route shall be of Structured
WTS Y
distinctly different colors. Cabling
TRs (Telecommunications Rooms)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
4. Labeling and Administration ‐ TRs (Continued)
All patch cables to be labeled with wrap‐around (not flag)
Brady‐type labels indicating the following on both sides.
From (on line 1): <Rack ID‐Panel ID‐Port>or<Rack ID‐Top
Patch Cables RU of Switch‐Blade‐Port> To (on line 2): <Rack ID‐Panel ID‐ WTS WTS Y
Port>or<Rack ID‐Top RU of Switch‐Blade‐Port>
PDU (Power Strip) shall be labeled with the breaker panel
Power ID it is served from. When cabinets are served by PDUs
Distribution Units (power strips) from different sources the label for each
source shall be distinctly different colors. A white label GRE GRE, WTS Y
(PDU)
(Power Strips) shall be used to designate source A while a black label shall
designate source B.
Secondary Bonding Busbar (SBB)
<Room ID>SBB<SBB # if more than one in a room>
Grounding Example: 07TR‐A SBB2
Label for SBB must either be affixed to a visible ‐ non‐ GRE GRE, WTS Y
Busbars
interfering ‐ location on the busbar, or to the wall near the
busbar.
Labeling and administration will be per GRE direction to
MEP Systems meet design requirements and value objectives. GRE GRE, WTS Y
All powered IT equipment, aside from audio‐visual or
carrier equipment must be labeled with the devices
hostname and a yellow asset tag on the front (cold aisle)
side of the device. A machine generated label indicating
Any equipment
the serial number of the device shall also be placed on the provider (i.e.
IT Equipment front (cold aisle) side of the device. All cabinets must have Y
LOB, GNS,
a yellow asset tag at the top of the front door and all racks Transport, Voice, LOB, GRE,
must have a yellow asset tag at the top front in a visible WTS
Media)
area that can be easily accessed with a barcode scanner.
5. TR Room Planning ‐ TRs (Telecommunications Rooms)
There must be a minimum of one TR per floor and it shall
house equipment and cabling for the floor, or floor area, it
Room Quantity serves. TR's shall be aligned vertically in multi‐floor
LOB, GRE, Y Y Y
and Size buildings and be rectangular in shape. Quantity per floor GRE
WTS
shall be based on cable distance limitations.
TRs are for use of JPMC and in some cases their business
partners. Common telecommunications rooms are located
Common in the building core of multi‐tenant buildings, are for
Telecommunicatio shared use of all building tenants, and shall not be used as LOB, GRE, Y Y Y
GRE
n Rooms a location for JPMC equipment or connections. WTS
TRs (Telecommunications Rooms)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
5. TR Room Planning ‐ TRs (Continued)
The TR should be positioned so that locations that are
restricted by building components that limit expansion such
as elevators, core, outside walls, or other fixed building
Y Y Y
walls are avoided. Large trunk ductwork and piping or other GRE LOB, GRE, WTS
items should be avoided. For the delivery of large
equipment, location decisions should factor in the need for
The TR should never be located below grade, in flood zones,
or near spaces that may present a threat of water
Y Y Y
infiltration unless preventive measures against water GRE LOB, GRE, WTS
infiltration are employed. The room must be free of water
The room must be located away from sources of
electromagnetic interference. Special attention should be
Y Y Y
GRE LOB, GRE, WTS
Room Location given to electrical power supply transformers, motors and
d d
Equipment not related to the support of the TR (e.g., piping,
ductwork, pneumatic tubing, etc.) should not be installed in, GRE LOB, GRE, WTS Y Y Y
pass through, or enter the TR.
TRs must be positioned in an accessible area on each floor,
e.g., a common hallway. GRE LOB, GRE, WTS Y Y
TR rooms must not be a pass through to other rooms, and
TR rooms must not be located behind other rooms that act GRE LOB, GRE, WTS Y Y
h h
TR Rooms shall not be located in areas susceptible to heat
gain GRE LOB, GRE, WTS Y Y Y
Rooms must not have any windows.
GRE LOB, GRE, WTS Y Y Y
Condensate containment pans/curbing with leak detection
required for floor/ wall supported CRAC units. Drip pan with
leak detection required for ceiling mounted CRAC units.
CRAC/CRAH Units GRE GRE, WTS Y Y
Y
Fire Suppression Located in GRE controlled space
GRE GRE, WTS Y Y Y
Systems
AutoCAD is the minimum required design software. The
project engineer must identify to the project team the
AutoCAD save version necessary to share files
Design Tools When shared electronically, documents must be provided in GRE GRE, WTS Y Y Y
both PDF and DWG file formats. All drawings must be scaled
and the drawing must identify the scale that is used.
Colocation Facilities (Co‐Lo)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
1. Critical Systems ‐ Colocation Facilities (Co‐Lo)
N+1 (Diverse routing into facility)
Utility System GRE LOB, GRE, WTS Y Y Y
N
Generator System GRE LOB, GRE, WTS Y Y Y
N+1 LOB, GRE,
UPS System GRE Y Y Y
WTS, GNS
Primary Cooling N+1 with mechanical conveyance at N
GRE LOB, GRE, WTS Y Y Y
Plant
Emergency power off devices, if required, are to be
installed with up protective cover as part of dual action
Emergency Power station to reduce false activation; are normally
open/normally closed dry contact and shall change state
Shutdown Y Y
GRE LOB, GRE, WTS
Management upon EPO activation, and be properly labeled, i.e.,
Emergency Power Off (EPO), Remote Emergency Power
Off (REPO), Remote Emergency Module Office (REMO).
N+1
GRE LOB, GRE, WTS Y Y Y
Must be designed to maintain humidity within the
recommended range for all “A Classes” per ASHRAE TC9.9
2011 (Thermal Guidelines for Data Processing
Environments).
CRAH/CRAC Units
Humidity Range, Non‐Condensing: 20% to 80% Relative GRE LOB, GRE, WTS Y Y
Humidity with 17⁰C (62.6⁰F) Maximum Dew Point
Additional restrictions as applicable to site.
When secondary electrical distribution is deployed, utilize
Static Transfer Static Transfer Switches, with 2N redundancy, in the
output path of UPS systems to enhance electrical system GRE LOB, GRE, WTS Y Y Y
Switches
maintainability.
Redundant and diversely fed. Must be dedicated circuits
with dedicated neutral and equipment grounding
Branch Circuit conductor (EGC). No Isolated Ground (IG) circuits unless
GRE LOB, GRE, WTS Y Y
Distribution required for specific equipment.
Protected by Transient Voltage Surge Suppression (TVSS)
device effective at breaker panel level.
All equipment must be dual corded. The primary choice
is 208V/3‐phase power/30A, with 208V/single phase/20
or 30A being allowable based on site specific Any equipment
requirements, or its country specific equivalent, must be provider (i.e.
provided at every cabinet footprint. In North America LOB, GNS, Y
Equipment LOB, GRE, WTS
120V power must also be provided at the PDU (power Transport, Voice,
strip) level. Proper load balancing must be planned and Media)
maintained to prevent excessive phase unbalance.
Generator supported. Install lighting occupancy sensors
providing coverage throughout entirety of room. Must
not be on dimmer switches or on same electrical panel as
Lighting GRE LOB, GRE, WTS Y Y
equipment. Must be at least 305 mm (12 in) from cable
pathways, racks, cabinets, and equipment.
Installed to the extent necessary to detect critical alarm
conditions (i.e. temperature, humidity, fire/smoke,
Critical System critical equipment malfunction).
GRE LOB, GRE, WTS Y Y
Monitoring Requirements will be determined by those owning and
operating these systems.
26 of 36 Revision Date: July 1, 2018 Version: 1.0.2
Appendix B
Colocation Facilities (Co‐Lo)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
1. Critical Systems ‐ Colocation Facilities (Continued)
A condensate containment pan and/or curbing wall with
leak detection are required for floor/wall supported
Leak Detection for CRAH/CRAC units. A drip pan with leak detection is required
LOB, GRE,
Mech equipment for ceiling mounted CRAH/CRAC units. Ceiling mounted GRE Y Y
WTS
/ Piping cooling units should be installed outside the room and
ducted in.
Pre‐Action sprinkler with protective cage to prevent
accidental contact and activation. Each critical technology
room must be designated as a separate fire zone. Gaseous LOB, GRE, Y Y Y
Fire Suppression GRE
fire suppression must be installed when required by local WTS
authority having jurisdiction (AHJ).
For equipment requiring DC power, provide the following:
Power provided from colocation providers diverse
electrical facilities
48VDC Power or 3 Phase AC (dependent upon facility)
Bulk DC Power (100 – 600 AMP power feeds terminated
Y Y
from facility to JPMC BDCBB(s)
DC power (if LOB, GRE,
JPMC prefers colocation vendor provides the largest cable GRE
required) WTS
size possible (ex. 750 MCM) to JPMC; This will allow power
upgrades without replacing power cables
2. Ancillary Systems ‐ Colocation Facilities (Co‐Lo)
Provide the following for network device and cabling
equipment: 19 in. 4‐post open rack with fixed rails and
minimum depth 740 mm (29 in) outside of front rail to
outside of rear rail. Minimum 300 mm (12 in) vertical
cable managers at the front (cold aisle/intake side) on both
WTS, Y Y
sides. Be equipped with appropriate air baffles if
Structured Cabling Structured
equipment is mounted side by side in adjacent racks.
Cabling
Racks to be bolted to floor. Seismic bracing where
applicable. 45 RU rack height. Network racks are not to be
used for servers.
Racks/Cabinets
Provide the following for server equipment: 700 mm (28
in) to 800 mm (32 in) wide x 1175 mm (46 in.) to 1200 mm
(48 in) deep enclosed cabinet with air dam kit and
perforated single front and double rear perforated doors,
each with a lock. 4 in (100 mm) wide lacing bars on both Y Y
sides at front (cold aisle/intake side). 2 x PDU mounting WTS WTS
and vertical cable management on rear. Cabinets to either
be installed on leveling feet or fastened to the slab.
Seismic bracing where applicable. 45 RU rack height.
Colocation Facilities (Co‐Lo)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
2. Ancillary Systems ‐ Colocation Facilities (Continued)
Provide the following for network device and cabling
equipment: 19 in. 4‐post open rack with fixed rails and
minimum depth 740 mm (29 in) outside of front rail to
outside of rear rail. Vertical cable managers shall be sized
based on cable counts and fill factors. Structured cabling
engineer to determine appropriate size based on site Y Y
Structured WTS,
Racks/Cabinets requirements. Be equipped with appropriate air baffles if Cabling Transport
equipment is mounted side by side in adjacent racks.
Racks to be bolted to slab. Seismic bracing where
applicable. Typical rack/cabinet height is 45 RU.
All cabinets equipped with blanking panels / no open racks Structured
for containment builds WTS Y Y
Cabling
All connectivity/patching shall be performed within any
Structured Y Y
given rack/cabinet and not between rows. LOB, WTS
Cabling
Connectivity Fiber links are field terminated, with LC
connectors. Connector adaptation (e.g. ST, SC) are
accomplished through the use of suitable patch cords Structured Y Y
WTS
when required. Cabling
All chassis based copper access switches to be port
replicated into centralized patching field (only if approved
by the OPR or management). All stackable switching to
Structured Y Y
follow WTS patching diagram (see Appendix 1 of the WTS WTS
Cabling
Cable Design and Engineering Standards).
All patching to be supported, address bend radius, and
Patching utilize cable management solely intended for its use.
Power and data patching to utilize separate pathways.
Patching shall not be of excessive length, planning for 1' of
Y
service loop on each end, and be routed neatly providing WTS WTS Y
free access for maintenance of equipment and cabling
infrastructure.
Hot/Cold Aisle: GRE,
Coordinate placement of CRAC/CRAH components Structured
delivering cool air and capturing return air with the layout Y Y
GRE Cabling,
of racks and cabinets. WTS
Hot/Cold Aisle: Equipment intakes at the front of racks are
Layout GRE,
not facing rear‐equipment exhaust from a neighboring
row. Side mounted air baffles must be installed in the Structured Structured Y Y
instances where equipment is mounted side by side in Cabling Cabling,
adjacent racks. WTS
Rack/cabinet elevations to be planned for growth at switch Structured
and patching frames, and growth at server cabinets. GRE, WTS Y Y
Cabling
3 ft (915 mm) service clearance from the front of
equipment in racks or cabinets. 3 ft (915 mm) service
clearance from the rear of equipment in racks or cabinet.
4 ft (1829 mm) service clearance on one side of the row of Structured Y Y
GRE, WTS
racks or cabinets. 1 ft (305 mm) additional service Cabling Y
clearance in front of telco wall field.
Clearances
In access floor environments at least one full floor tile
must be free of obstruction nearest to the front and in
Structured Y
back of each rack or cabinet in a row to allow under floor GRE, WTS
Cabling
access.
28 of 36 Revision Date: July 1, 2018 Version: 1.0.2
Appendix B
Colocation Facilities (Co‐Lo)
Infrastructure Requirement Accountable Exception Design Review Stage
/ System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
2. Ancillary Systems ‐ Colocation Facilities (Continued)
2 ft (610 mm) service clearance above racks and
cabinets. Cable support systems shall be the only allowable Structured
WTS Y Y
obstruction. Cabling
Racks and cabinets must be located away from potential
sources of electromagnetic interference (EMI). They should
Clearances
be kept at least 1.22 m (4ft) away from transformers,
motors, and other potentially strong sources of EMI. Their Structured
WTS Y Y
location should not compromise associated cabling Cabling
pathways with regard to EMI related separation
requirements and guidelines of the ANSI/TIA‐569 standard.
Fill planned for growth not to exceed 50% fill maximum;
bend radius of cables will be compliant with the ANSI/TIA‐ Structured
568 group of standards, or manufacturer’s requirements if WTS Y Y
Cabling
those are stricter.
Conduits and sleeves for carrier media not to be shared with Structured
JPMC structured cable media WTS Y Y
Cabling
Service loops are not allowed in Co‐Lo. Structured
WTS
Cabling Y
Metallic Cable Trays:
Must be independently supported from ceiling or walls, not
from cabinets and racks.
Installed with at least 12 in (305 mm) clearance above tray. Structured
Pathways WTS Y Y
Cabling
Installed 4 in – 6 in (101.6mm – 152.4 mm) above rack or
cabinet.
Installation must be electrical Code compliant.
Non Metallic Raceways and Cable Routing Assemblies (e.g.,
Fiber Runner):
May be attached to cabinets and racks when intended for
patching or other local connections within a row. Otherwise
must be independently supported as per metallic cable tray Structured
WTS Y Y
requirements. Cabling
Must be fire rated as required by electrical code (i.e.
plenum, riser, etc.) and must be UL2024 or UL2024A
listed (as appropriate to application).
Single point of entry into the room with a card reader/ pin
pad on the ingress and card reader only on the egress .side
LOB, GRE,
of the door GRE Y Y
WTS, GSMA
Card Reader entry door lock must be fail secure in case of
power outage or fire alarm system activation unless dictated LOB, GRE,
GRE
otherwise by local code WTS, GSMA Y Y
Cameras covering the entrance door and any other LOB, GRE,
Security GRE
secondary exits from inside and outside. WTS, GSMA Y Y
All doors leading into the cage must be monitored for
LOB, GRE,
immediate forced open and door held open (60 Second) GRE Y Y
WTS, GSMA
alarms
Access logs will not be required in rooms. Card reader/pin LOB, GRE,
pad will be system of record for access. GSMA
WTS, GSMA Y
Colocation Facilities (Co‐Lo)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
2. Ancillary Systems ‐ Colocation Facilities (Continued)
Receptacles mounted on a separate c‐channel
independently supported below ladder rack and above
rack. The receptacle facing the rack/cabinet in hot aisle
(equipment air exhausts side of cabinet, with electrical
GRE GRE, WTS
sockets facing the hot aisle, not the ceiling or floor). If Y
power routed under floor, power to be mounted on
bracket installed between pedestals in hot aisle.
PDUs (Power Strips) (see Appendix E, of the WTS Cable
Design and Engineering Standards) shall adhere to the
following requirements:
‐ 208V/3‐phase 30A, with 208V/single phase/20 or 30A
being allowable based on site specific requirements, (or
country specific equivalent) (In North America 120V power
must also be provided at the local Power Distribution Unit
(PDU) level.
Power ‐ Minimum (24) C‐13 receptacles
GRE GRE, WTS
Distribution ‐ Minimum (6) C‐19 receptacles Y
‐ Minimum (2) 5‐20 receptacles (in NA only)
‐ Locking input power cords
‐ Integral breakers or fuses when required by Code
‐ Ability for metering (including each phase with true RMS
reading of current and voltage)
- ‐ Ethernet port allowing remote readout of PDU
parameters.
3. Room Construction ‐ Colocation Facilities (Co‐Lo)
Coordinate with Co‐location facility provider.
Room Signage GRE GRE, WTS, LOB Y
Built deck to deck/slab to slab. All metal wire mesh cages
must extend slab to slab. GRE GRE, WTS Y Y
Minimum 1 hour fire‐rated or greater if local code is more
stringent. If the Co‐location space is contained within a
metal wire mesh cage, the space in the facility in which the GRE GRE, WTS Y Y
Walls (if required) cage is contained must have at least 1 hour fire rated walls.
All penetrations firestopped to maintain fire rating of
walls, and must be firestopped per the requirements of
this Standard, ATSM E814, UL1479, and the manufacturer. GRE GRE, WTS Y Y
Colocation Facilities (Co‐Lo)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
3. Room Construction ‐ Colocation Facilities (Continued)
Doors must be a minimum of 3 ft (915 mm) wide and 8 ft.
(2.44 m) high minimum w/ no center support and hinged
to open outward (when permitted by Code). The door
must be fitted with a lock. An integrated strike must be
included to accommodate electronic access control. Doors
GRE GRE, WTS
must be equipped with floor sweeps to contain Y Y
conditioned air, minimize dust infiltration, and minimize
Doors (if escape of noise.
applicable) Automatic closer GRE GRE, WTS Y Y
Quantity of doors defined by codes, as well as access and
egress requirements GRE GRE, WTS Y Y
A minimum of 500 lux (50 foot‐candles) in the horizontal
plane and 200 lux (20 foot‐candles) in the vertical plane
measured 1 m (3 ft) above the finished floor in middle of
all rack and cabinet aisles. The lighting must be controlled
by one or more switches located near the entrance door(s)
to the room. Emergency lighting and signs must be
properly placed per Code or AHJ such that an absence of
Y Y
Lighting primary lighting will not hamper emergency exit. Lighting GRE GRE, WTS
fixtures must not be powered from the same electrical
distribution panel as information and communication
technology equipment in the MER. Dimmer switches must
not be used.
Raised Access Floor or Static Dissipative VCT (106 to 109
ohms) based on design requirements to cool initial and
future IT loads.
A structural engineer shall be consulted during the design
to specify the floor loading limit. The minimum distributed
floor loading capacity shall be 7.2 kPa (150 lbf/ ft2). The
recommended distributed floor loading capacity is 12 kPa
(250 lbf/ ft2). Floors must be appropriately reinforced if
equipment exceeding these specifications is anticipated.
This requirement also applies in the case of relocation of
Flooring equipment at a later time. If extensive relocation is GRE GRE, WTS Y Y Y
anticipated, the entire floor must be appropriately
reinforced.
The floor must have a minimum of 1.2 kPa (25 lb/ft2)
capacity for supporting loads that are suspended from the
bottom of the floor (for example, cable ladders suspended
from the ceiling of the floor below). The recommended
minimum hanging capacity of the floor is 2.4 kPa (50
lb/ft2). Access floor support elements must have similar
load carrying capabilities. VCT should be bonded to
ground.
Colocation Facilities (Co‐Lo)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
3. Room Construction ‐ Colocation Facilities (Continue)
If access floor is installed, the access floor tiles must be
finished with a high‐pressure laminate (HPL). GRE GRE, WTS Y Y
In cages with access floor, power conduit and associated
cabling must be routed below the floor and all
telecommunications cable should be routed in cable
conveyance overhead.
If, as an exception, telecommunications cabling and power
wiring are both run below the access floor, an under floor
cable tray system should be used for the routing of
telecommunications cabling. Wherever practicable, power GRE GRE, WTS Y Y
and communications cables should cross at right angles,
and telecommunications cables should be located in tray
above power cables.
Access Floor, if
applicable Materials must either be non‐combustible or have a flame
spread index of 25 or less.
Stringers to be installed as per the selected raised floor
design to support rolling load and seismic loading.
Y Y
Pedestals and stringers must be grounded.
Surface of floor supporting access tiles must be sealed to
minimize dust. GRE GRE, WTS
Must comply with design requirements for depth of floor.
Power shall be installed below access floor and routed in a
manner that avoids blockage of airflow. GRE GRE, WTS Y Y
Colocation Facilities (Co‐Lo)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
3. Room Construction ‐ Colocation Facilities (Continue)
Chilled water or glycol piping shall be routed outside the
room and penetrate the cage at the shortest path to LOB, GRE,
connect to CRAC/CRAH units. Routing shall avoid all racks, GRE
WTS Y Y
cabinets and cable pathways.
If sprinklers are required within the equipment area, fire
sprinkler head location must be coordinated with room
layout so that heads shall be 18 in. (457.2 mm) clear of any
Piping obstructions and piping routed in aisle ways as per fire LOB, GRE,
codes. Sprinklers and piping must not be routed directly GRE Y Y
WTS
above IT equipment or enclosures and must be routed in
aisle ways instead for optimal clearance.
If sprinklers are required within the equipment area, the
fire sprinkler heads must be provided with wire cages to LOB, GRE,
GRE Y
prevent accidental operation. WTS
5‐20 duplex convenience outlets on utility power only to
be located at typical outlet height on walls throughout the
GRE WTS
room. Y
Wall phones to be strategically placed for technician
Convenience access. The outlet mounting height must ensure that the
Outlets
phone keypad and controls will be no greater than 1,372
GTI WTS Y
mm (54 in) above the finished floor to comply with
requirements of the Americans with Disabilities Act (ADA).
JPMC wireless network access inside the room (where
wireless access is deployed) GTI WTS Y
Secured storage and staging room should be planned in
proximity to the cage that should include a 6’w (1.83 m) x
3'd (0.91 m) work surface and one 7'h (2.13 m) x 4'w (1.22
m) shelving unit. For CoLo's built to house above 20 rack
Storage and or cabinet positions, secured storage and staging room
GTI WTS Y Y Y
Staging should be at least160 sqft (14.86 sqm). For CoLo's built to
house below 20 rack or cabinet positions, secured storage
and staging room should be 100 sqft (9.29 sqm). Room
shall be outfitted with an ingress card reader.
4. Labeling and Administration ‐ Colocation Facilities (Co‐Lo)
Labels to be affixed to top front and top rear of rack or
cabinet
Nomenclature: Structured Cabling WTS Y
<Row Letter><Position Number>
Racks/Cabinets Example: A01 means first row, first position
Type: 1.5 in. (38 mm) text lamacoid. White text on black
background. Structured Cabling WTS Y
1.5 in. (38 mm) tall text placed in visible location on plastic
Data Cable
bushing or on the conduit itself near the end. Structured Cabling WTS Y
Conduit
Nomenclature <size>.<path A/B>to<Distant end room
Data Cable ID>. Example: 4” A to B206
Structured Cabling WTS
Conduit Sleeves shall be labeled "Sleeve" Y
Colocation Facilities (Co‐Lo)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
4. Labeling and Administration ‐ Colocation Facilities (Continued)
Cabinet/rack positions shall be identified by an alpha‐
numeric identifier where a letter shall identify the row and
a number shall identify the cabinet position within the
Cabinet/Rack row. Future positions left vacant shall have their Structured Cabling WTS Y
Identification identifiers reserved. <Row Letter><Position Number>.
Example: A01. (first row, first position)
Label to be affixed to top of cabinet in the front and rear.
Text on labels shall be at least 1 in. (26 mm) tall. Structured Cabling WTS Y
All Copper Patch Nomenclature:
Structured
Panels and Fiber <RU><Top RU of panel > labeled on the left side of the Structured Cabling Y
Cabling, WTS
Enclosures Panel panel. Structured Cabling
Example: RU38 WTS
ID
To Rack/Cabinet<Distant End Rack/Cabinet ID>Panel<Panel
All Copper Patch
ID>Ports<End Location Port Range> Structured Cabling WTS
Panels serving Y
Example: To Rack AB01 Panel RU34 Ports 25‐48
intra‐room tie
cabling Where route diversity is employed designation strips
connectivity located on termination panels for each route shall be of Structured Cabling
WTS
labeling Y
distinctly different colors.
To<Distant End Room ID>Rack/Cabinet<Distant End
Rack/Cabinet ID>Panel<Panel ID>Ports<End Location Port
All Copper Patch Range>
Panels serving Example for cable run to room B206): Structured Cabling WTS
Y
inter‐room tie To B206 Rack AA01 Panel RU31 Ports 01‐24
cabling
connectivity Where route diversity is employed designation strips
labeling located on termination panels for each route shall be of Structured Cabling
WTS
distinctly different colors. Y
All Copper Patch <CoLo Room Designation><Panel Sequence>
Panels serving Example (for CoLo room B132): B132‐34
Structured
workstation Panel jacks must be labeled with Workstation ID Structured Cabling
Cabling, WTS Y
cabling
connectivity
<Fiber Type>to Rack/Cabinet<Distant End Rack/Cabinet
ID>Panel<Panel ID>Slot<End Location Slot>Ports<End
All Fiber
Location Port Range> Structured Cabling WTS
Enclosures serving Y
Example: OM4 to Rack AA04 Panel RU38 Slot A Ports 01‐
intra‐ room tie
12
cabling
connectivity Where route diversity is employed designation strips
labeling located on termination panels for each route shall be of
Structured Cabling WTS
distinctly different colors. Y
<Fiber Type>to<Distant End Room ID>Rack/Cabinet
<Rack/Cabinet ID>Panel<Panel ID>Slot<End Location
All Fiber Slot>Ports<End Location Port Range>
Enclosures serving Example for cable run to room B206): Structured Cabling WTS
Y
inter‐ room tie OM4 to B206 Rack AA06 Panel RU32 Slot A Ports 01‐12
cabling
connectivity Where route diversity is employed designation strips
labeling located on termination panels for each route shall be of
Structured Cabling WTS
distinctly different colors. Y
All patch cables to be labeled with wrap‐around (not flag)
Brady‐type labels indicating the following on both sides.
From (on line 1): <Rack ID‐Panel ID‐Port>or<Rack ID‐Top
Patch Cables RU of Switch‐Blade‐Port>
WTS WTS Y
To (on line 2): <Rack ID‐Panel ID‐Port>or<Rack ID‐Top RU
of Switch‐Blade‐Port>
34 of 36 Revision Date: July 1, 2018 Version: 1.0.2
Appendix B
Colocation Facilities (Co‐Lo)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
4. Labeling and Administration ‐ Colocation Facilities (Continued)
PDU (Power Strip) shall be labeled with the breaker panel
Power ID it is served from. When cabinets are served by PDUs
Distribution Units (power strips) from different sources the label for each
GRE GRE, WTS Y
(PDU) source shall be distinctly different colors. A white label
(Power Strips) shall be used to designate source A while a black label shall
designate source B.
Labeling and administration will be per GRE direction to
MEP Systems meet design requirements and value objectives. GRE GRE, WTS Y
All powered IT equipment, aside from audio‐visual or
carrier equipment must be labeled with the devices
hostname and a yellow asset tag on the front (cold aisle)
side of the device. A machine generated label indicating
the serial number of the device shall also be placed on the Any equipment
IT Equipment front (cold aisle) side of the device. All cabinets must have provider (i.e.
LOB, GRE,
a yellow asset tag at the top of the front door and all racks LOB, GNS,
WTS Y
must have a yellow asset tag at the top front in a visible Transport, Voice,
area that can be easily accessed with a barcode scanner. Media)
5. Colocation Space Planning ‐ Colocation Facilities (Co‐Lo)
The CoLo space should be positioned so that locations that
are restricted by building components that limit expansion
such as elevators, core, outside walls, or other fixed
building walls are avoided. Large trunk ductwork and
LOB, GRE,
piping or other items should be avoided. For the delivery GRE
WTS Y Y Y
of large equipment, location decisions should factor in the
need for accessibility.
The CoLo space should never be located below grade, in
flood zones, or near spaces that may present a threat of
water infiltration unless preventive measures against
water infiltration are employed. The room must be free of LOB, GRE,
GRE
water or drain pipes not directly required in support of the WTS Y Y Y
equipment within the room.
The CoLo space must be located away from sources of
electromagnetic interference. Special attention should be
Room Location given to electrical power supply transformers, motors and
LOB, GRE,
generators, x‐ray equipment, radio or radar transmitters, GRE Y Y Y
WTS
and induction sealing devices.
Equipment not related to the support of the CoLo (e.g.,
piping, ductwork, pneumatic tubing, etc.) should not be LOB, GRE,
GRE
installed in, pass through, or enter the Colo. WTS Y Y Y
CoLo rooms must not be a pass through to other rooms,
and CoLo rooms must not be located behind other rooms LOB, GRE,
GRE
that act as a pass through. WTS Y Y Y
Co‐Lo shall not be located in areas susceptible to heat gain LOB, GRE,
GRE Y Y
WTS
Rooms must not have any windows. LOB, GRE,
GRE Y Y Y
WTS
Condensate containment pans/curbing with leak detection
CRAC/CRAH Units required for floor/wall supported CRAC units. Drip pan GRE GRE, WTS
Y Y
with leak detection required for ceiling mounted CRAC
Fire Suppression Located in Co‐Lo controlled space
GRE GRE, WTS Y Y Y
Systems
Colocation Facilities (Co‐Lo)
Infrastructure / Requirement Accountable Exception Design Review Stage
System to Meet Approval
Requirement
Schematic Design Construction
Design Development Documents
Initial Set Final Set
5. Colocation Space Planning ‐ Colocation Facilities (Co‐Lo)
AutoCAD is the minimum required design software. The
project engineer must identify to the project team the
AutoCAD save version necessary to share files
When shared electronically, documents must be provided
Design Tools in both PDF and DWG file formats. All drawings must be GRE GRE, WTS Y Y Y
scaled and the drawing must identify the scale that is
used.
Note: Label both the top of rack and the bottom foot of the racks with;
xxx = three alpha numeric characters identifying the Technology Space (TR or MER)
yy = two alpha numeric characters identifying the row and rack
Note: Do not block the manufacturing port label on the patch panel.
Note: Label both the top of rack and the bottom foot of the racks with;
xxx = three alpha numeric characters identifying the Technology Space (TR or MER)
yy = two alpha numeric characters identifying the row and rack
D. Wrap Around Cable Label –Grid and Non-Grid Outlet Numbering Schemes
Source and Destination End (see Figures 1 & 2)
xxx-yy-zz-##
Where:
xxx = three alpha numeric characters identifying the Technology Space (TR or MER)
yy = two alpha numeric characters identifying the row and rack
zz = two numeric characters, rack unit number (upper left of installed patch panel), uniquely
identifying the patch panel rack position
## = numeric characters designating the manufacturers port number on a patch panel
Backbone optical fiber consists of Source and Destination ends, where the Source is typically located in
the MER and the Destination is typically located in a TR. The labeling requirements are provided for 4RU
and 1RU fiber optical panels, where;
Figure 3 depicts sample labeling for the source end (MER) of a 4RU fiber panel, with panel
labeling and cassette labeling
Figure 4 depicts sample labeling for the destination end (TR) of a 1RU fiber panel, with panel
labeling and cassette labeling.
Backbone copper and fiber cable shall be labeled to depict their Source and Destination endpoints.
xxx-yy-zz-##/##-TTT
Where:
xxx = three alpha numeric characters (maximum) identifying the Technology Space (TR or MER)
yy = two alpha numeric characters identifying the row and rack
zz = two numeric characters, rack unit number (upper left of installed patch panel), uniquely identifying
the patch panel rack position
##/## = starting strand or pair number / ending strand or pair number
TTT = cable type
Specified Technologies, Inc. 6” Firestop Device Kit (square or round mount) EZDP44S EA
Specified Technologies, Inc. Radius Control Modules (One Pair (2) radius control modules) RCM33 EA
Specified Technologies, Inc. Individual Cable EZ firestop grommet RFG2 (10 pack)
Specified Technologies, Inc. Smoke and Acoustical Pathway Device NEZ33 2 Pack
Specified Technologies, Inc. Smoke and Acoustical 2 gang kit (2 Devices & plates) NEZDP233 4 Pack
Specified Technologies, Inc. Smoke and Acoustical 4 gang kit (4 Devices & plates) NEZDP433 EA
Specified Technologies, Inc. Plates for 2 gang (no devices) NEZP233 PAIR
Specified Technologies, Inc. Plates for 4 gang (no devices) NEZP433 PAIR
SECTION 27 05 26 — GROUNDING (EARTHING) INFRASTRUCTURE COMPONENT DESCRIPTION MFG PART NUMBER UNIT
SECTION 27 05 28.29 — NON-CONTINUOUS CABLE SUPPORTS COMPONENT DESCRIPTION MFG PART NUMBER UNIT
Lasermark (www.lasermark.co.uk/) Cisco 4510 Switch Template Cisco 4510 Switch Template EA
SECTION 27 11 23 — RELAY RACKS / CABLE MANAGEMENT COMPONENT DESCRIPTION MFG PART NUMBER UNIT
EQUIP RACKS-CBL MGT CONFIDENTIAL AND PROPRIETARY TO JPMORGAN CHASE AND CO. 8 of 35
Appendix E_Materials_1Jul2018
EVOLUTION G2 VERTICAL CABLE MANAGER RAISED FLOOR BRUSH KIT TWO‐
PIECE BRUSH‐SEALED GROMMET FOR BOTTOM OF DOUBLE‐SIDED 12"W
Chatsworth EVOLUTION G2 VERTICAL CABLE MANAGER BRUSH OPENING IS 8‐1/2"W X TS1004414 EA
22‐1/4"L BRUSH SIDE WALL EXTENDS DOWNWARD AND IS NEAR‐FLUSH
WITH BOTTOM OF CABLE MANAGER SECURES TO CABLE MANAGER VIA
EXISTING RACK MOUNTING HOLES BLACK FINISH
VERTICAL CABLE MANAGEMENT ACCESSORIES COMPONENT DESCRIPTION
SOLID MID PANEL FOR 6" DOUBLE SIDED EVOLUTION VERTICAL
Chatsworth 35497-x702 EA
MANAGER
SOLID MID PANEL FOR 10" DOUBLE SIDED EVOLUTION VERTICAL
Chatsworth 35497-x708 EA
MANAGER
SOLID MID PANEL FOR 12" DOUBLE SIDED EVOLUTION VERTICAL
Chatsworth 35497-x711 EA
MANAGER
EQUIP RACKS-CBL MGT CONFIDENTIAL AND PROPRIETARY TO JPMORGAN CHASE AND CO. 9 of 35
Appendix E_Materials_1Jul2018
EQUIP RACKS-CBL MGT CONFIDENTIAL AND PROPRIETARY TO JPMORGAN CHASE AND CO. 10 of 35
Appendix E_Materials_1Jul2018
SECTION 27 11 23.10 — LADDER RACK, CABLE TRAY COMPONENT DESCRIPTION MFG PART NUMBER UNIT
LADDER - BASKET TRAY CONFIDENTIAL AND PROPRIETARY TO JPMORGAN CHASE AND CO. 11 of 35
Appendix E_Materials_1Jul2018
LADDER - BASKET TRAY CONFIDENTIAL AND PROPRIETARY TO JPMORGAN CHASE AND CO. 12 of 35
Appendix E_Materials_1Jul2018
LADDER - BASKET TRAY CONFIDENTIAL AND PROPRIETARY TO JPMORGAN CHASE AND CO. 13 of 35
Appendix E_Materials_1Jul2018
Berk Tek 10059632- Hyper+5e, CAT5E, CMP, UTP, 25 Pr., Gray Reel (Plenum) 10059632 MF
Berk Tek 10089521- Hyper+5e, CAT5E, CMP, UTP, 25 Pr., White Reel (Plenum) 10089521 MF
BERK-TEK / LEVITON CATEGORY 6 CABLE CMR WHITE (Riser-rated), PULL BOX LANmark 6E+, CAT6, CMR, UTP, GRTP, 11100786 MF
BERK-TEK / LEVITON CATEGORY 6 CABLE CMR GRAY (Riser-rated), PULL BOX LANmark 6E+, CAT6, CMR, UTP, GRTP, 11100709 MF
BERK-TEK / LEVITON CATEGORY 6 CABLE CMP WHITE (Plenum-rated), PULL BOX LANmark 6E+, CAT6, CMP, UTP, GRTP, 11100785 MF
BERK-TEK / LEVITON CATEGORY 6 CABLE CMP GRAY (Plenum-rated), PULL BOX LANmark 6E+, CAT6, CMP, UTP, GRTP, 11100708 MF
BERK-TEK / LEVITON 1-PORT SINGLE GANG STAINLESS STEEL TELEPHONE FACEPLATE 4108W-1SP EA
BERK-TEK / LEVITON CATEGORY 6 PLENUM MODULAR PATCH CORD (FOR CAMERAS) GRAY U6PPP-xxS EA
COMMSCOPE M106, FLUSH MOUNTED MODULAR FRAME, FOUR PORT WHITE 106622285 EA
COMMSCOPE 4-PORT ADJUSTABLE FURNITURE FACEPLATE, WHITE (.5 INCH DEEP) 700191588 EA
COMMSCOPE PLENUM SURFACE MOUNT BOX, 2-Port (WHITE) for WAPs. 760067207 EA
COMMSCOPE NON-PLENUM SURFACE MOUNT BOX, 2-Port (WHITE) for user outlets. 107984056 EA
COMMSCOPE NON-PLENUM SURFACE MOUNT BOX, 6-Port (WHITE) for user outlets. 107431538 EA
COMMSCOPE CATEGORY 6 MODULAR PATCH CORD GRAY 5 FT. CPC3312-03 GS8E-DG (enter length variable in search) EA
COMMSCOPE CATEGORY 6 MODULAR PATCH CORD GRAY 7 FT. CPC3312-03 GS8E-DG (enter length variable in search) EA
COMMSCOPE CATEGORY 6 MODULAR PATCH CORD GRAY 10 FT. CPC3312-03 GS8E-DG (enter length variable in search) EA
COMMSCOPE CATEGORY 6 MODULAR PATCH CORD GRAY 15 FT. CPC3312-03 GS8E-DG (enter length variable in search) EA
COMMSCOPE CATEGORY 6 MODULAR PATCH CORD GRAY 20 FT. CPC3312-03 GS8E-DG (enter length variable in search) EA
COMMSCOPE CATEGORY 6 MODULAR PATCH CORD GRAY 25 FT. CPC3312-03 GS8E-DG (enter length variable in search) EA
BERK-TEK / LEVITON CATEGORY 6A CABLE CMR WHITE (Riser-rated) 11089906 (Reel in a box) MF
BERK-TEK / LEVITON CATEGORY 6A MODULAR PATCH CORD WHITE 15 FT. - PLENUM UAPPP-xxW EA
SYSTIMAX 360 CAT 6A PATCH PANEL FOR RACKS ANGLED 19” 24-
COMMSCOPE 760151324 EA
PORT T568B (SILVER)
SYSTIMAX 360 CAT 6A PATCH PANEL FOR RACKS ANGLED 19” 48-
COMMSCOPE 760151779 EA
PORT T568B (SILVER)
SYSTIMAX 360 CAT 6A PATCH PANEL FOR CABINETS FLAT 19” 24-
COMMSCOPE 760152587 EA
PORT T568B (SILVER)
SYSTIMAX 360 CAT 6A PATCH PANEL FOR CABINETS FLAT 19” 48-
COMMSCOPE 760152595 EA
PORT T568B (SILVER)
CATEGORY 6A HORIZONTAL-Termination Hardware MER/TR SPECIALTY ITEMS
COMMSCOPE PLENUM SURFACE MOUNT BOX, 2-Port (WHITE) for WAPs. 760067207 EA
COMMSCOPE NON-PLENUM SURFACE MOUNT BOX, 2-Port (WHITE) for user outlets. 107984056 EA
COMMSCOPE NON-PLENUM SURFACE MOUNT BOX, 6-Port (WHITE) for user outlets. 107431538 EA
SECTION 27 13 24 — MULTIMODE FIBER BACKBONE COMPONENT DESCRIPTION MFG PART NUMBER UNIT
CORNING - OM3
CORNING - OM4
CORNING FIELD TERM LC, UNICAM MMF (50 µm) CONNECTOR, (1/PK) 95-050-99-X EA
CORNING FIELD TERM LC, UNICAM MMF (50 µm) CONNECTOR, (25/PK) 95-050-99-X-Z EA
CORNING MOUNTING BRACKET KIT FOR 23" FRAME - 1U CONNECTOR HOUSING CDF-01U-23-BKT EA
CORNING MOUNTING BRACKET KIT FOR 23" FRAME - 4U CONNECTOR HOUSING CDF-04U-23-BKT EA
CORNING FIELD TERM ANAEROBIC ADHESIVE & PRIMER, 500 LC CONNECTORS 1101045-01 EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 1 METER UNIVERSAL OM3 050502T5116001M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 2 METER UNIVERSAL OM3 050502T5116002M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 3 METER UNIVERSAL OM3 050502T5116003M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 5 METER UNIVERSAL OM3 050502T5116005M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 6 METER UNIVERSAL OM3 050502T5116006M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 10 METER UNIVERSAL OM3 050502T5116010M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 1 METER UNIVERSAL OM3 055702T5120001M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 2 METER UNIVERSAL OM3 055702T5120002M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 3 METER UNIVERSAL OM3 055702T5120003M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 5 METER UNIVERSAL OM3 055702T5120005M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 6 METER UNIVERSAL OM3 055702T5120006M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC,10 METER UNIVERSAL OM3 055702T5120010M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 1 METER UNIVERSAL OM4 050502Q5116001M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 2 METER UNIVERSAL OM4 050502Q5116002M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 3 METER UNIVERSAL OM4 050502Q5116003M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 5 METER UNIVERSAL OM4 050502Q5116005M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 6 METER UNIVERSAL OM4 050502Q5116006M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO LC, 10 METER UNIVERSAL OM4 050502Q5116010M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 1 METER UNIVERSAL OM4 055702Q5120001M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 2 METER UNIVERSAL OM4 055702Q5120002M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 3 METER UNIVERSAL OM4 055702Q5120003M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 5 METER UNIVERSAL OM4 055702Q5120005M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 6 METER UNIVERSAL OM4 055702Q5120006M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC,10 METER UNIVERSAL OM4 055702Q5120010M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 1 METER EDGE OM4 577902QD120001M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 2 METER EDGE OM4 577902QD120002M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 5 METER EDGE OM4 577902QD120005M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC, 6 METER EDGE OM4 577902QD120006M EA
CORNING PATCH CORD 50/125 mm CMR, LC TO SC,10 METER EDGE OM4 577902QD120010M EA
SECTION 27 13 24 — SINGLEMODE FIBER BACKBONE COMPONENT DESCRIPTION MFG PART NUMBER UNIT
CORNING MOUNTING BRACKET KIT FOR 23" FRAME - 1U CONNECTOR HOUSING CDF-01U-23-BKT EA
CORNING MOUNTING BRACKET KIT FOR 23" FRAME - 4U CONNECTOR HOUSING CDF-04U-23-BKT EA
CORNING FIELD TERM ANAEROBIC ADHESIVE & PRIMER, 500 LC CONNECTORS 1101045-01 EA
CORNING UNIVERSAL
SECTION 33 82 53 — CABLE PULLING LUBRICANTS COMPONENT DESCRIPTION MFG. PART NUMBER UNIT
POWER CORD -
POWER CORD
SECTION 26 27 33 - POWER STRIPS COMPONENT DESCRIPTION MFG PART NUMBER UNIT DEFAULT FOR NEW POWER INPUT OUTLET PRESENTATION LENGTH / Monitored
POSITION
PLUG
GEIST Vertical rack mountable PDU strip MN02X4W1-36MT79-3TL21A0D03-S-0W (White) EA 30A, 120/208V WYE, 8.6kW 24 x C13 x 6 x C19 x 6 x 5-20R 3' - L21-30P BOTTOM Yes
GEIST Vertical rack mountable PDU strip MN02X41-36MT79-3TL21A0D03-S (Black) EA 30A, 120/208V WYE, 8.6kW 24 x C13 x 6 x C19 x 6 x 5-20R 3' - L21-30P BOTTOM Yes
GEIST Vertical rack mountable PDU strip MN02X4W1-34MX09-3TL14A0D03-S (Black) EA 30A, 120/208V WYE, 4.9kW 24 x C13 x 6 x C19 x 4 x 5-20R 3' - L14-30P BOTTOM Yes
GEIST Vertical rack mountable PDU strip MN02X4W1-34MX09-3TL14A0D03-S-0W (White) EA 30A, 120/208V WYE, 4.9kW 24 x C13 x 6 x C19 x 4 x 5-20R 3' - L14-30P BOTTOM Yes
CPI Vertical rack mountable PDU strip TS1032034 (White) EA 208v - 30a - 3 Phase 24 x C13, 6 x C19, 6 x 5-20R 3' - L21-30P TOP Yes
CPI Vertical rack mountable PDU strip TS1034387 (Black) EA 208v - 30a - 3 Phase 24 x C13, 6 x C19, 6 x 5-20R 3' - L21-30P TOP Yes
CPI Vertical rack mountable PDU strip P3-1K0K4 (Black) EA 208v - 30a - 1 Phase 24 x C13, 6 x C19, 6 x 5-20R 10' - L14-30P BOTTOM Yes
CPI Horizontal PDU strip TS1027868 EA 120/208V - 30A - 3 PhASE 18 X C13, 3 x C19, 3 x 5-20R
RARITAN Vertical rack mountable PDU strip PX3-1261U-A7 (Black) EA 30A, 208V WYE, 8.6kVA 24 x C13, 3 x C19, x 6 x 5-20R 1m - L21-30P TOP Yes
RARITAN Vertical rack mountable PDU strip PX3-1261U-A7K7 (White) EA 30A, 208V WYE, 8.6kVA 24 x C13, 3 x C19, x 6 x 5-20R 1m - L21-30P TOP Yes
Chatsworth VERTICAL PDU MOUNT WHITE (4-POST Rack applications) TS1033583A EA 4-POST RACK
Chatsworth VERTICAL PDU MOUNT BLACK (4-POST Rack applications) TS1030523 EA 4-POST RACK
JPMC WTS Corporate Real Estate EMEA Appendix E - SCE Authorised Product List and Part Numbers
Corning Fibre CCHE-CP24-AD CCHE Panel, LC Duplex 24f 50/125 (OM4) shuttered
Corning Fibre CCHE-CP24-AE CCHE Panel, LC Duplex 24f SM (OS2) shuttered
Corning Fibre 95-050-99-X UniCam Connector LC 50/125 (OM4)
Corning Fibre 95-200-99 UniCam Connector LC SM (OS2)
Corning Fibre PCH-01U Pretium Connector Housing (PCH) 1RU - Holds 2 x 24c CCH Panels
Corning Fibre PCH-02U Pretium Connector Housing (PCH) 2RU - Holds 4 x 24c CCH Panels
Corning Fibre PCH-04U Pretium Connector Housing (PCH) 4RU - Holds 12 x 24c CCH Panels
Corning Fibre 012T8X-36198E2C MIC® Tight Buffer Indoor Cable 12F G50 MMF ClearCurve® OM4 0.9mm TB3 B2ca,s1,d1,a1
Corning Fibre 012Z8X-36125E2C MIC® Tight Buffer Indoor Cable 12F E9 SMF-28e+® 0.9mm TB3 B2ca,s1,d1,a1
Corning Fibre 024T8X-36198E2C MIC® Tight Buffer Indoor Cable 24F G50 MMF ClearCurve® OM4 0.9mm TB3 B2ca,s1,d1,a1
Corning Fibre 024Z8X-36125E2C MIC® Tight Buffer Indoor Cable 24F E9 SMF-28e+® 0.9mm TB3 B2ca,s1,d1,a1
Corning Fibre 012T8Z-32198E2G MIC® Tight Buffer Indoor Cable 12F G50 MMF ClearCurve® OM4 0.9mm TB3 Cca,s1,d1,a1
Corning Fibre 012E8Z-32125E2G MIC® Tight Buffer Indoor Cable 12F E9 SMF-28e+® 0.9mm TB3 Cca,s1,d1,a1
Corning Fibre 024T8Z-32198E2G MIC® Tight Buffer Indoor Cable 24F G50 MMF ClearCurve® OM4 0.9mm TB3 Cca,s1,d1,a1
Corning Fibre 024E8Z-32125E2G MIC® Tight Buffer Indoor Cable 24F E9 SMF-28e+® 0.9mm TB3 Cca,s1,d1,a1
Corning Fibre E787802GNZ20001M Patch Cord SM LC TO LC, 1 Meter
Corning Fibre E787802GNZ20002M Patch Cord SM LC TO LC, 2 Meter
Corning Fibre E787802GNZ20003M Patch Cord SM LC TO LC, 3 Meter
Corning Fibre E787802GNZ20005M Patch Cord SM LC TO LC, 5 Meter
Corning Fibre E797902QNZ20001M Patch Cord OM4 LC TO LC, 1 Meter
Corning Fibre E797902QNZ20002M Patch Cord OM4 LC TO LC, 2 Meter
Corning Fibre E797902QNZ20003M Patch Cord OM4 LC TO LC, 3 Meter
Corning Fibre E797902QNZ20005M Patch Cord OM4 LC TO LC, 5 Meter
GigaSPEED XL® 3071 Category 6 U/UTP Cable, LSZH, white jacket, 1000 ft (305 m) Reel
Commscope Copper 760237882 Cca,s1,d1,a1
GigaSPEED XL® 3071 Category 6 U/UTP Cable, LSZH, white jacket, 1000 ft (305 m) Reel
Commscope Copper 760237883 B2ca,s1,d0,a1
Commscope Copper 700206725 MGS400 Cat6 Information Outlet White
Commscope Copper 760187872 M12D-F-262 Faceplate, 2-port, White
Commscope Copper 760187880 M14D-F-262 Double Faceplate, 4-port, White
Commscope Copper 760161067 LF80 Shuttered Clip
Commscope Copper 760206797 1100A-U-GS3-24 Category 6 Straight Patch Panel
Commscope Copper 760206813 1100A-U-GS3-24 Category 6 Angled Patch Panel
Commscope Copper 760206821 1100A-GS3-48 Category 6 Angled Patch Panel
Commscope Copper CPC3392-03Fxxx GigaSPEED XL® GS8E Patch Cord, Dark Gray Jacket -xxxft LSZH
EMEA PRODUCT LIST CONFIDENTIAL AND PROPRIETARY TO JPMORGAN CHASE AND CO. 33 of 35
Appendix E_Materials_1Jul2018
Commscope Copper CPC3392-08Fxxx GigaSPEED XL® GS8E Patch Cord, White Jacket -xxxft LSZH
GigaSPEED X10D 3091B Cat6A 4-Pair U/UTP LSZH White Jacket Cable 1000 ft (305m) reel
Commscope Copper 760237624 Cca,s1,d1,a1
GigaSPEED X10D 3091B Cat6A 4-Pair U/UTP LSZH White Jacket Cable 1000 ft (305m) reel
Commscope Copper 760237884 B2ca,s1,d0,a1
Commscope Copper 760152587 SYSTIMAX 360 1100GS6 Evolve 24-Port Patch Panel
Commscope Copper 760151324 SYSTIMAX 360 1100GS6 Evolve 24-Port Angled Patch Panel
Commscope Copper 760092429 GigaSPEED X10D MGS600 White Information Outlet
Commscope Copper CPCSSZ2-08FXXX GigaSPEED X10D 360GS10E LSZH Solid Modular White Patch Cord - xxxft
GigaSPEED X10D 360GS10E LSZH Solid Modular White Patch Cord - xxxft For Harness Links
Commscope Copper CA1SSS2-08FXXX Only, B2ca,s1,d0,a1
CPI - 15214-E03 45U Adjustable Quadra Rack, Square Punched, 925mm to 1075mm, White
CPI - 35524-E03 12" Vertical Cable Manager, White
CPI - 34537-E00 1U Blank Panel, White
CPI - 34538-E00 2U Blank Panel, White
CPI - 35441-E01 1U Horizontal Manager, White
CPI - 35441-E04 4U Horizontal Manager, White
CPI - 10250-E18 18" Universal Cable Runway, White
CPI - 13392-E11 (-E12) Runway Dividers White 5 Pack (25 Pack)
CPI - 11421-E18 Wall Angled Support
CPI - 10506-E06 Cable Runway Elevation Kit For Racks; 4"- 6" High,1 Pair; White
CPI - TS1038355 Double Cable Radius Drop - Cross Member, White
CPI - 35502-E02 Solid Side Panel
CPI - TS1034299 2 Piece PDU Mounting Bracket (Adjustable QuadraRack Only)
CPI - 13676-001 Koldlok - Frames & Cabinets
CPI - TS1034193 Vertical Busbar Kit - Cabinets Only - Includes 20 No. 2 Hole Compression Lugs
CPI - TS1007096 19" Horizontal Busbar Kit - Includes 10 No. 2 Hole Compression Lugs
CPI - 40162-901 2 Hole Compression Lug 1/4" Hole
- - MTMPHM40CM80P000 M4 8MM Screw for Compression Lug (Cisco 4510 Connection)
CPI - 40164-001 Cable Runway Ground Strap Kit
JPMC Cable lashing Manager set for AQR/ASR 45U 500mm. Should include JPMC Cable lashing
CPI - TS1026952 Manager Support (2 piece set) for AQR. Rack depth must be set to 925mm.
CPI - TS1032071 JPMC Cable lashing Manager Support (2 piece set) for AQR. Rack depth must be set to 925mm
Austin Hughes - AHH026041000213111 PDU - 4xC13, 2xSchuko, 16A 3m lead - Horizontal 1U Single Feed
Austin Hughes - AHH026041000313111 PDU - 4xC13, 2xSchuko, 32A 3m lead - Horizontal 1U Single Feed
Austin Hughes - AHH025041000213111 PDU - 4xC13, 2xUK, 16A 3m Lead - Horizontal 1U Single Feed
Austin Hughes - AHH025041000313111 PDU - 4xC13, 2xUK, 32A 3m Lead - Horizontal 1U Single Feed
Austin Hughes - AHH065081022213111D PDU - 8xC13, 6xUK, 16A 3m Lead - Horizontal 2U Dual Feed
Austin Hughes - AHH065081022313111D PDU - 8xC13, 6xUK, 32A 3m Lead - Horizontal 2U Dual Feed
EMEA PRODUCT LIST CONFIDENTIAL AND PROPRIETARY TO JPMORGAN CHASE AND CO. 34 of 35
Appendix E_Materials_1Jul2018
Austin Hughes - AHH066081022213111D PDU - 8xC13, 6xSchuko, 16A 3m Lead - Horizontal 2U Dual Feed
Austin Hughes - AHH066081022313111D PDU - 8xC13, 6xSchuko, 32A 3m Lead - Horizontal 2U Dual Feed
Austin Hughes - AHV046121042213121 PDU - 12xC13, 4xSchuko, 4xC19, 16A 3m lead, top feed
Austin Hughes - AHV046121042313121 PDU - 12xC13, 4xSchuko, 4xC19, 32A 3m lead, top feed
Austin Hughes - AHV043121042213121 PDU - 12xC13, 4xUK 45 Degrees, 4xC19, 16A 3m lead, top feed
Austin Hughes - AHV043121042313121 PDU - 12xC13, 4xUK 45 Degrees, 4xC19, 32A 3m lead, top feed
Austin Hughes - AHV044121042213121 PDU - 12xC13, 4xUK 135 Degrees, 4xC19, 16A 3m lead, top feed
Austin Hughes - AHV044121042313121 PDU - 12xC13, 4xUK 135 Degrees, 4xC19, 32A 3m lead, top feed
Lasermark - sales@lasermark.co.uk All traffolyte labelling as detailed on drawings T4.01 & T4.02
Lasermark - sales@lasermark.co.uk Rack mountable acrylic switch port templates
EMEA PRODUCT LIST CONFIDENTIAL AND PROPRIETARY TO JPMORGAN CHASE AND CO. 35 of 35
THIS PAGE INTENTIONALLY BLANK
JPMorgan Chase and Co. APPENDIX F – Data Clean Specification & Cleaning Policy For
MERs and TRs
1. Overview
a. This document outlines the standards for cleaning technology rooms,
inclusive of Main Equipment rooms (MERs) and Technology Rooms
(TRs).
b. Work shall be done by qualified vendor personnel who specialize and
have significant experience in the cleaning of server environments and
appropriate training with the materials and operational procedures
specified in this document.
c. The vendor will provide proof of insurance and bonding.
d. Means and methods must be approved by the owner prior to
commencement.
e. Testing will be conducted post-cleaning to confirm appropriate measures
of cleanliness have been met.
2. Pre-cleaning Preparation
a. A meeting and walk-through of the all data rooms must be scheduled prior
to the cleaning. Attendees are to include the owner, a cleaning vendor
representative, and the cleaning vendor’s work crew supervisor who will
be present during the work.
b. The owner will review the data room Standards of Operation and
designate what building areas workers are authorized to be in.
c. The contractor shall provide tool power plan to the owner for approval for
the vendor’s use while cleaning. No other outlets may be used by vendor
personnel.
3. Standards of Operation
a. Cleaning vendor personnel are required to observe the data room
Standards of Operations at all times. At a minimum, this includes:
i. No food or drink in the room
ii. No propping data room doors
iii. No interfering with the operation of data room equipment
iv. No unauthorized/un-badged personnel in data room
v. Checking in with Operations Command Center when vendor
personnel start and complete work for the day.
b. Workers must wear clothing that easily identifies them as members of the
cleaning company.
c. During the cleaning, workers are responsible for conducting themselves in
such a manner as to protect the owner’s equipment and infrastructure and
to avoid creating hazards for employees who enter the work area.
d. Signage or safety cones should be used to surround open floor tiles,
electrical cords strung along the floor, and any areas that are being damp-
mopped.
12. Schedule
a. The room cleaning will be scheduled with Building Operations and the
Technology Facilities Supervisor.
Version 6.0.1
July 1, 2018
WTS Cable Design and Engineering
TABLE OF CONTENTS
List of Figures
1. Background
JP Morgan Chase (JPMC) has standardized on Cisco Aironet 2700 and 3800 series wireless access
points. For proper signal coverage, APs shall be placed per the PRE survey report. APs are typically
mounted to the drop ceiling grid. The Cisco 2700 and 3800 series APs are plenum-rated devices suitable
for such locations.
The initial Planner Report shall only be used in the initial Structured Cabling Design package in
order to obtain pricing from the bidders.
Once the PRE Survey Report is available, the Structured Cabling Design package shall be updated
to reflect the AP Numbering and specific location information for the installation of the APs.
The Cable vendor shall identify the MAC addresses of the installed APs matching the PRE Survey
AP Numbering.
The Cable vendor patches WAPs in the Technology Space and verifies LED on AP is lit.
The WiFi Services engineer configures the wireless LAN controllers (if required).
The Network Engineer programs the APs and points them to wireless LAN controller using the
MAC to AP spreadsheet.
The LOB performs the UAT testing to verify WiFi network is operational.
The Professional Services vendor conducts the POST Survey which will reflect the actual required
mounting points required to achieve optimal coverage.
Per the POST Survey some AP locations may require repositioning by the Cable vendor.
2. Power
This product shall be connected to a power-over-Ethernet (PoE) IEEE 802.3at 30W compliant power
source. Each access point requires one dedicated full-duplex 1000 Mb/s switch port.
Verify cable.
3. Cabling
APs use a single cable for both signal and power (POE); the JPMC Global Structured Cabling Standard
specifies two Cat6A white cable runs from the Telecommunication Room (TR) to each access point. The
first cable is used to extend the device’s console connection in order to provide out of band access in case
of a configuration error or outage. This first cable terminates to the patch panel and is not connected to the
LAN switch. The second Cat6A white cable is used for both signal and power. The second cable
terminates to the patch panel and is connected to the LAN switch.
This junction box is the termination point for the cables run back to the TRs and their connectors are also
color-coded. The white cables correspond to the console and Ethernet connectors on the access points.
This helps prevent improper connections during installation. The following figure shows the cabling
arrangement for the access points in detail. See Figure 1 for a typical cabling schematic.
Note All work shall be performed in accordance with the prevailing version of
the JP Morgan Chase Global Structured Cabling Standard.
4. Access Points
The 2702E model access point has external antenna connectors and the LED indictor on the top of the
model, as shown in Figure 2. The 2702I model access point has integrated antennas and does not have
external connectors on the top of the unit; however, it does have the LED indicator on top of the unit, as
shown in Figure 3.
1 LED indicator
The ports and connections on the bottom of the access point are shown in Figure 4.
Figure 4 - Access Point Ports and Connections (bottom)-AIR2702E and 2702I Models
Note The Auxiliary Ethernet port is disabled. Do not connect this port to a PoE switch. Connecting the
primary and auxiliary ports to a PoE switch will not provide additional power.
AP Module connector if Figure 8 is a special purpose port, currently not used but may be utilized in future
deployments.
Figure 9 - Smart Antenna Connector on the Right Side of the 3802E Model
5. Mounting
5.1. Introduction
The mounting instructions describe the steps for mounting Cisco Aironet 3800, and 2700 series APs in
several configurations, including on a suspended ceiling, on a hard ceiling or wall, on an electrical or
network box.
Note: The normal and preferred AP mounting method is to a dropped ceiling grid. This mounting practice
will better accommodate the weight of the AP. Drop Ceiling mounting, APs with integrated antennas are
designed to be mounted horizontally from the ceiling below lighting fixtures and HVAC ducting. Typical
install is 8’ to 10’ from the floor. If there is a requirement to mount the AP in any other manner, advance
approval and direction from the Wi-Fi team is required.
Mounting hardware for access points consists of brackets, which connect to the bottom of the access point,
and ceiling grid clips, which connect the bracket to a suspended ceiling. The bracket that you need
depends on the mounting location for the access point. The ceiling grid clip that you need depends on the
type of suspended ceiling where you need to install the access point. You don't need ceiling grid clips if you
are mounting the access point to a hard-surface ceiling or a wall.
The JPMC standard mounting bracket, AIR-AP-BRACKET-2, is deployed for new builds, with AIR-AP-
BRACKET-1 deployed only on an exception basis:
• The universal bracket (AIR-AP-BRACKET-2) , the JPMC standard bracket, is versatile (it works with
electrical boxes, can be used for wall mounting, and adapts to ceiling installations), increases compatibility
with future access point models, and allows for installation of the expansion module on the back of the
access point. Figure10 shows the universal bracket installed on an access point.
• The low-profile bracket (AIR-AP-BRACKET-1), which provides a tight fit between the access point and
the ceiling but does not accommodate network/electrical box or wall mounting. Figure11 shows the low-
profile bracket installed on an access point.
Ceiling grid clips are used to mount the access point to a suspended ceiling grid. The ceiling grid clip
needed depends on the ceiling tile installed at the site.
There are two types of ceiling grid clips:
• Ceiling Grid Clip, Recessed (AIR-AP-T-RAIL-R)—If the ceiling tile hangs below the ceiling grid, the
recessed clip provides the best fit between the AP and the ceiling.
• Ceiling Grid Clip, Flush (AIR-AP-T-RAIL-F)—If the ceiling tiles are flush with the ceiling grid, this clip
provides a snug fit between the AP and the ceiling.
Figure 12 shows a ceiling grid clip.
The most common type of ceiling rail (the supports for the ceiling tiles) is the T-rail. You can attach a ceiling
grid clip directly to a T-rail ceiling rail. However, other types of ceiling rails, such as channel rails and beam
rails require an additional adapter clip (AIR-CHNL-ADAPTER). You need two adapter clips for each access
point. Set screws on the clips hold them securely on the ceiling rail.
Figure 13 shows the three types of ceiling rails: T-rail, channel, and beam. Figure 14 shows an access
point installed with mounting bracket, ceiling grid clip, and adapter clips.
Follow these steps to mount the access point below a standard or recessed suspended ceiling. Figure 15
shows an access point mounted on a T-rail ceiling rail using a ceiling grid clip.
Follow these steps to mount the access point below a suspended ceiling.
Step 1 Decide where you want to mount the access point on your suspended ceiling.
Step 2 Open the ceiling grid clip completely.
Step 3 Place the ceiling grid clip over the T-rail and close it to the appropriate detent (A, B, or C).
Step 4 Use a screwdriver to tighten the two ceiling grid clip locking screws to prevent the clip from sliding
along the T-rail.
Step 5 Observe the ceiling grid clip width detent letter (A, B, or C) that corresponds to the T-rail width.
Step 6 Align the corresponding holes (A, B, or C) on the mounting bracket over the mounting holes on the
ceiling grid clip.
Step 7 Hold the mounting bracket and insert a 6-32 x 1/4 in. screw into each of the four corresponding
holes (A, B, or C) and tighten.
Step 8 If necessary, drill or cut a cable access hole in the ceiling tile large enough for the Ethernet and
power cables. Pull the cables through the access hole until you have about 1 foot of cable
protruding from the hole.
Step 9 (Optional) Use the ground screw to ground the access point to a suitable building ground. See
Section 5.9 for general grounding instructions.
Step 10 Connect the Ethernet and power cables to the access point.
Step 11 Align the access point feet over the keyhole mounting slots on the mounting bracket. If you
created a hole for the cables make sure the access point is positioned so that the cables reach
their respective ports.
Step 12 Gently slide the access point onto the mounting bracket until it clicks into place.
This procedure describes the steps required to mount the access point on a ceiling constructed of 3/4-in
(19.05-mm) or thicker plywood using #8 fasteners using the universal mounting bracket (AIR-AP-
BRACKET-2).
Follow these steps to mount the access point on a solid ceiling or wall.
Step 1 Use the mounting bracket as a template to mark the locations of the mounting holes on the
bracket. Figure 16 shows details of the mounting bracket.
Caution Be sure to mark all four locations. To ensure a safe and secure installation, make sure you are
using adequate fasteners and mount the access point using no less than four fasteners.
Caution Do not use plastic wall anchors or the keyhole slots on the mounting bracket for ceiling
installations. When mounting the access point on a hard ceiling, use four fasteners capable of maintaining
a minimum pullout force of 20 lbs (9 kg).
1 Bracket locking post (used when attaching the bracket to a 4 Cable access
previously mounted bracket) cover
2 Access point mounting keyholes 5 Security hasp
3 Grounding post
Step 2 Use a #29 drill (0.1360-in. [3.4772 mm]) bit to drill a pilot hole at the mounting hole locations you
marked.
Note The pilot hole size varies according to the material and thickness you are fastening. Cisco
recommends that you test the material to determine the ideal hole size for your mounting application.
Step 3 (Optional) Drill or cut a cable access hole near and below the location of the mounting bracket
cable access cover large enough for the Ethernet cable, building ground wire, and power cables.
Step 4 Pull approximately 9 inches of cable through the hole. Route the Ethernet and power cables
through the bracket before you attach the bracket to the ceiling or wall. Route the cables through
the main cable access hole and then through the smaller access hole as shown in Figure 17.
Step 5 (Optional) Use the ground screw to attach the building ground wire to the mounting bracket. See
Section 5.9 for general grounding instructions.
Step 6 Position the mounting bracket mounting holes (with indents down) over the pilot holes.
Step 7 Insert a fastener into each mounting hole and tighten.
Step 8 Connect the Ethernet and power cables to the access point.
Step 9 Align the access point feet with the large part of the keyhole mounting slots on the mounting plate.
When positioned correctly, the cable access cover will fit inside the access point connector bay.
Step 10 Gently slide the access point onto the mounting bracket keyhole slots until it clicks into place.
Follow these steps to mount an access point to a network box or an electrical box.
Step 1 Position the universal mounting bracket (AIR-AP-BRACKET-2) over the existing network or
electrical box and align the bracket mounting holes with the box holes.
Step 2 Hold the mounting bracket in place and insert a 6 x 32 x 1/4-in pan head screw into each of the
mounting holes and tighten.
Step 3 Pull approximately 9 inches of Ethernet and power cable through the hole. Route the cables
through the bracket before you attach the bracket to the ceiling. Route the cables through the main
cable access hole and then through the smaller access hole as shown in Figure 17.
Step 4 (Optional) Use the ground screw to attach the building ground wire to the mounting bracket. See
Section 5.9 for general grounding instructions.
Step 5 Connect the Ethernet and power cables to the access point.
Step 6 Align the access point feet over the keyhole mounting slots on the optional mounting bracket.
Step 7 Slide the access point onto the optional mounting bracket until it clicks into place.
Grounding is not always required for indoor installations because Cisco Aironet access points are classified
as low-voltage devices and do not contain internal power supplies. However, Cisco recommends that you
check your local and national electrical codes to see if grounding is a requirement. If grounding is required
in your area or you wish to ground your access point, follow these steps.
Step 1 Find a suitable building grounding point as close to the access point as possible.
Step 2 Connect a user-supplied ground wire to the building grounding point. The wire should be a
minimum of #14AWG assuming a circuit length of 25 ft (30.5 cm). Consult your local electrical
codes for additional information.
Step 3 Route the ground wire to the access point.
Step 4 Attach the wire to a suitable grounding O-ring lug.
Step 5 Crimp or solder the wire to the lug.
Step 6 Insert the grounding post screw into the O-ring lug and install it on the mounting bracket as shown
in Figure 18.
Step 7 Use a Phillips screwdriver to tighten the ground screw.
Version 6.0.2
July 1, 2018
WTS Cable Design and Engineering – Patching
Standard
Table of Contents
1 EXECUTIVE SUMMARY ............................................................................................... 3
1.1 PURPOSE AND AUDIENCE ................................................................................................. 3
1.2 SCOPE .......................................................................................................................... 3
1.3 PRINCIPLES AND METHODOLOGIES ..................................................................................... 3
1.4 COMPLIANCE, REQUIREMENTS, AND DATES ......................................................................... 3
2 STANDARD OVERVIEW ............................................................................................... 4
2.1 GENERAL INFORMATION .................................................................................................. 4
2.2 HISTORY ....................................................................................................................... 4
2.3 CURRENT STATE ............................................................................................................. 4
2.4 FUTURE STATE ............................................................................................................... 4
2.5 REGIONAL VARIATIONS .................................................................................................... 4
2.6 ARCHITECTURE GUIDELINES .............................................................................................. 4
2.7 ASSUMPTIONS ............................................................................................................... 4
2.8 RISKS/ISSUES ................................................................................................................. 4
3 INTRODUCTION .......................................................................................................... 5
4 PATCHING STANDARD SUMMARY ............................................................................. 6
5 COPPER PATCHING STANDARD .................................................................................. 7
5.1 PLANNING ..................................................................................................................... 7
5.2 PREPARATION ................................................................................................................ 8
5.3 PATCHING ..................................................................................................................... 8
5.4 VALIDATION .................................................................................................................. 9
6 FIBER PATCHING STANDARD .................................................................................... 10
6.1 PLANNING ................................................................................................................... 10
6.2 PATCHING ................................................................................................................... 11
6.3 VALIDATION ................................................................................................................ 12
7 APPENDIX A – OPTICAL FIBER CLEANING STANDARD ............................................... 14
8 APPENDIX B – FIBER CLEANING PRODUCTS .............................................................. 16
9 APPENDIX C – PATCHING DIAGRAM ......................................................................... 17
Tables
Table 1 ‐ Fiber Optic Patch Cord Color Coding ................................................................. 10
Table 2 ‐ Fiber Cleaning Products ‐ Corning ...................................................................... 16
Table 3 ‐ Fiber Cleaning Products ‐ CommScope .............................................................. 16
1 EXECUTIVE SUMMARY
This Standard was created to promote an appropriate level of diligence during
fiber and copper patching, including planning and validation.
1.2 Scope
This Standard is broken into the following categories:
Summary – Key points associated with fiber and copper patching, in a 1-
page “cheat sheet” form.
Copper patching Standard – Description of planning, preparation,
patching, and validation associated with copper patching.
Fiber patching Standard – Description of planning, patching, and
validation associated with fiber patching.
Optical fiber cleaning Standard – Created by consensus with Infrastructure
and Design Engineering team and structured cabling manufacturers.
Fiber cleaning products – Specified by JPMC structured cabling
manufacturers.
This Standard is applicable regardless of the presence or absence of intelligent
patching (e.g. iPatch). Accordingly, it is silent on the subject.
2.2 History
In a 2009 post mortem of a failed data center SAN deployment, it was
determined that there had been a significant volume of connectivity failures that
could have been avoided if support personnel had been familiar with proper
patching practice. This document was created to address that shortfall.
2.7 Assumptions
Fiber optic patching can only be effective if appropriate cleaning materials are at
hand. The fiber cleaning products list found in Appendix C is a sampling of
suitable products that are available in the marketplace, and a supply of cleaning
products must always be readily available.
This Standard is most effective when it is uniformly adopted in technology spaces
including, but not limited to Main Equipment Rooms (MERs),
Telecommunications Rooms (TRs), and Co-Locations (Co-Los).
2.8 Risks/Issues
Failure to follow guidance in this Best Practice will increase risk.
When direction in this document is
consistently followed, overall risk
to JPMC technology spaces is
reduced.
All personnel working in JPMC
technology spaces are expected to
consistently follow processes and
procedures defined in this
Standard.
5.2 Preparation
To minimize disconnect time, do as much preparation as possible before performing patching
activities.
Study Administrative Records
Locate the ports that must be connected or reconnected. Ensure you have all the information you
need.
Inspect Cords
It is essential to ensure cords are of the right type and quality, and that they are clean and in good
condition, especially when re-using patch cords.
Patch Cords shall be inspected for physical damage including:
stress marks from bending on the sheath
pullout of conductors from the plug
pin contamination on the plug end
bent or missing pins on the plug end
damaged or missing retention clip (the retention clip is the plastic clip that locks the patch
cord in the jack)
5.3 Patching
Use best practices at each stage:
Cord Handling
Kinks, snags, pinches and poor contacts can dramatically reduce the performance of a patch
cord. The following factors are important in avoiding these problems.
Bend Radius
The minimum bend radius specified by standards is four times the cable diameter under no-
load for Category 5e and Category 6 cable. Anything less may change the relative position of
conductors to the point where transmission performance is affected.
Cord Pulling and Stress
Be careful not to use excessive force during the patching process. This can stress cords and
connectors, reducing their performance. If you need to use force when placing a cord,
something is wrong. Find the problem and fix it before proceeding.
Bundling
Bundling and tying cords gives the panel a neat appearance, but tight bundling increases the
risk of crosstalk and can slow the process of tracing a patch cord. If you decide to bundle,
take care not to tighten bundles to the point where individual cords cannot rotate freely at the
bundling point. Use only products manufactured for this purpose, with preference to use of
Velcro® and equivalent re-usable cable ties. Do not use plastic cable ties because they can
easily be over-tightened… an over-tightened plastic cable tie can damage the cable and
affect the performance of the connection.
Where PoE is deployed utilize a maximum of 25 cables to a bundle.
Routing Cords through Cable Pathways
If the existing cord is the right length, it may be possible to re-use it. If this is the case,
remove the cord completely and re-run it through the cable pathways. This is the only way to
ensure there are no tangles, kinks or strains in the cord.
5.4 Validation
Inspect the Connection
Patching must be right the first time since mistakes can cause costly disruption and re-work. The
time taken to make a final visual check of connections is a good investment. When patch panels
are located in cabinets, ensure they are securely latched, making sure that cord slack is not
snagged or pinched by the door.
Update Documentation
The final step is to update the documentation to the reflect changes and close the work order
associated with the completed change request.
6.1 Planning
Search the Records
Once a request for connectivity is received, search the records to identify the circuit path.
Diagrams provided by the system designer will help you understand cable types, sizes, location,
routing, and layout. Any changes or additions made since your cabling infrastructure was installed
must also be documented.
Check Design Guidelines and Match Cords
Make sure you know the specifications and design of your fiber cabling. Ensure you use patch
cords that are matched to the installed cabling – optical fiber cords of different types must never
be mixed. See Table 1 for guidance in matching the patch cord to the structured cabling. To
ensure optimum performance and warranty coverage, the manufacturer of the patch panel and
the manufacturer of the patch cord should always be the same.
Table 1 ‐ Fiber Optic Patch Cord Color Coding
Fiber Core Cable Jacket Connector Strain Relief and/or
Type
Diameter Color Adapter Housing Color
OM1 Multimode 62.5 µm Orange/Gray Beige
OM2 Multimode – non‐laser
50 µm Orange Black
optimized
OM3 Multimode – laser optimized 50 µm Aqua Aqua
OM4 Multimode – laser optimized 50 µm Aqua Aqua
OS1 & OS2 Single‐mode 9 µm Yellow Blue
Efficient Routing
To establish the correct cord length, first find the best route between the ports to be connected.
This is usually the shortest route through horizontal and vertical cable guides that does not
obstruct or interfere with other cords and connectors in the panel. See Appendix C (in this
document) for a patching diagram.
Avoid routing cords through cable pathways that are already congested.
Examples of cable pathways include:
horizontal patch cord management channels
vertical cable management channels
cable trays and basket trays
Vertical and Horizontal Sizing
Having established the best route for the cord, find the minimum required length by adding the
horizontal and vertical distances.
Minimizing Slack
Use correctly sized patch cords every time. Patch cord length must not be excessive, and
requires planning for no more than 0.305 m (1 ft) of slack on either end. When selecting a cord,
avoid excessive slack and provide a neat appearance. Tight cords will pull on connectors, and too
6.2 Patching
Use best practice at each stage:
6.3 Validation
Final Visual Inspection and Panel Closure
Cleanliness of fiber optic connections is critical to the performance of optical communication networks. Contamination on
a connector end face, even if only at the microscopic level, can create severe problems. Single-mode fiber optic core
diameters are approximately 9 microns (0.00035 inches). By comparison, a human hair is 50 microns or larger in
diameter. Contamination that blocks the fiber core generates strong back reflections (Return Loss), and may effect
attenuation (Insertion Loss). Loose contamination on the connector end face that does not block the core may move
during de-mating, or may prevent physical glass-to-glass contact required for proper signal transmission. Rigid
contamination trapped between connector end faces may permanently damage the fiber core(s). Dry contaminants are
relatively simple to remove compared to oils and films which naturally occur with human contact, vapor condensation, and
solvent evaporation. If you clean only the connector and not the adapter, pre-existing contaminants on the adapter will be
transferred to the connector, spreading the problem instead of reducing it.
DO NOT ASSUME THAT THE FIBER PATCH CORD IS CLEAN. Though patch cords in factory packaging should be
clean, it is essential that each and every patch cord be cleaned before making every connection, every time. Making a
habit of cleaning fiber patch cords before connecting results in a reliable, successful outcome.
JP Morgan Chase identifies fiber structured cabling products manufactured by Corning and CommScope, who sell the
fiber cleaning products listed below. Fiber cleaning products from other manufacturers may be as effective and less
costly, only products listed below are supported by the manufacturer of the fiber should be used. These products are
available through many distribution channels.
Table 2 ‐ Fiber Cleaning Products ‐ Corning
Part Number Description Notes
Can be used with either standard or shuttered LC
CLEANER-PORT-LC LC Port Cleaning tool
adapters
2104466-01 MTP Port Cleaning Tool For MTP connection only
200FM 200x Microscope Includes adapter for 2.5 µm ferrules
FMFA-U12 Adapter for 200FM allows visual inspection of 1.25 µm ferrules
FMFA-MTP Adapter for 200FM allows visual inspection of MTP Connectors
TKT-CLEAN-SFC Cleaning Kit for Single Fiber Connectors Cleaning Kit only, no scope or adapters
TKT-CLEAN-MFC Cleaning Kit for Multi Fiber Connectors Cleaning Kit only, no scope or adapters
CLEANER-CONN-REEL Single Fiber Connector Cleaning Reel Single fiber connectors only
CLEANER-UNIV-CASS Universal Connector Cleaning Cassette Single or Multi fiber connectors
FCC-WIPES Fiber Cleaning Wipes 90 per tub
CLEAN-STICKS-125 LC Cleaning sticks--1.25mm ferrule 10 per pak
CLEAN-STICKS-250 ST, SC, FC Cleaning sticks--2.5 mm ferrule 10 per pak
Table 3 ‐ Fiber Cleaning Products ‐ CommScope
Part
Description Notes
Number
760053199 Fiber Optic Contents:
Connector - Westover probe microscope and display
Clean/Inspect Kit - NTT-ATT cleaning cassette for cleaning ST, SC, LC and MPO(f) connectors in hand
- Noyes 1.25 mm and 2.5 mm swabs for cleaning ST, SC, LC connectors through the bulkheads
- US Conec IBC cleaner for cleaning MPO(m) and MPO(f) connectors both in hand and through
the bulkhead
- MicroCare Fiber Optic Cleaning Solution
- SYSTIMAX cleaning instructions
760053207 Fiber Optic Contents:
Connector - NTT-AT Optipop reel cleaner refill
Cleaning and - MPO-MTP internal bulkhead cleaner
Consumables Kit - 1.25 mm swabs (green label)
- 2.5 mm swabs (blue label)
- Fiber optic cleaning solution
- Instruction Sheet
Standard
Main Equipment Room (MER),
Technology Room (TR) and Technology
Lab Security Design Standard
Current Effective Date: July 13, 2016
CHIEF ADMINISTRATIVE OFFICE – GLOBAL SECURITY & INVESTIGATIONS, TECHNICAL SECURITY
TABLE OF CONTENTS
1. Summary ....................................................................................................................................... 2
2. Changes from Previous Version ...................................................................................................... 2
3. Scope ................................................................................................................................................ 2
3.1. Scope/Exceptions ................................................................................................................... 2
4. Roles and Responsibilities ............................................................................................................... 2
5. Technology Standards ..................................................................................................................... 2
6. People Standards Overview .......................................................................................................... 3
7. MER Design Standard...................................................................................................................... 3
8. TR Design Standard ......................................................................................................................... 4
9. Technology Lab Room Design Standard ....................................................................................... 4
10. Defined Terms ......................................................................................................................... 5
11. Firm References ............................................................................................................................... 5
12. Document Information ...................................................................................................................... 5
1. Summary
JPMorgan Chase & Co.’s (JPMC, or the Firm) Global Security & Investigations (GSI) Technical
Security department establishes these global technical security design standards for all JPMC Main
Equipment Rooms (MER) and Technology Rooms (TR). These standards focus on technical
security design areas for housing JPMC computer systems, servers and/or voice/data network
facilities or exposure and breach to the Firm’s network.
3. Scope
CHIEF ADMINISTRATIVE OFFICE – GLOBAL SECURITY & INVESTIGATIONS, TECHNICAL SECURITY
Locations All
3.1. Scope/Exceptions
Local regulations or data protection legislation may dictate deviations to this Standard, which must
be incorporated into the design. Any exceptions will be clearly defined and documented within the
JPMC Controls Framework.
5. Technology Standards
GSI integrates various technologies and people with processes to form the depth and layered
approach to security, which monitors, records and deters potential malicious activity. The
technology that is used will vary depending on the space protected, variations include:
a. Access Control:
JPMC Regional Access Control Systems provide employees and contingent workers the
ability to access JPMC premises across the globe. Controlling and managing this access
ensures a safe and secure work environment and guards against potential risks to the
company's people, facilities, information and assets. An Information Custodian or
designee must authorize access. A record of the authorization must be maintained for at
least thirty-six (36) months,
b. CCTV:
The JPMC CCTV systems are in place to assist security personnel in detecting safety
and/or security violations, investigate and verify alarms.
c. Intrusion Devices:
Door contacts are used to monitor all emergency exits, roof hatches and appropriate
access panels.
CHIEF ADMINISTRATIVE OFFICE – GLOBAL SECURITY & INVESTIGATIONS, TECHNICAL SECURITY
d. Biometric Readers:
These readers must be used in card plus fingerprint mode. This creates a dual
authentication using the hardware.
b. Card Reader entry door lock should be fail secure in case of power outage or fire alarm
system activation unless dictated by local code.
c. Cameras covering the entrance door and any other secondary exits from inside and
outside.
d. Any secondary doors that lead into the room must be treated as emergency exits and
must have a door contact (remotely monitored) and local alarm sounder.
e. All doors leading into the MER should be monitored for immediate forced open and door
held open (60 Second) alarms.
f. The MER and TR demising walls must be slab-to-slab construction.
8. TR Design Standard
The following must be in place to secure and monitor a TR Room:
a. Single point of entry into the room with a PIN and card reader on the ingress and card
reader only on the egress side of the door.
b. Card Reader entry door lock should be fail secure in case of power outage or fire alarm
system activation unless dictated by local code.
c. Cameras covering the entrance door and any other secondary exits from inside and
outside.
d. Any secondary doors that lead into the room must be treated as emergency exits and
must have a door contact (remotely monitored) and local alarm sounder.
CHIEF ADMINISTRATIVE OFFICE – GLOBAL SECURITY & INVESTIGATIONS, TECHNICAL SECURITY
e. All doors leading into the TR should be monitored for immediate forced open and door
held open (60 Second) alarms.
a. Each entry into the room shall have a standard card reader on the ingress side of the
door
b. Card Reader entry door lock shall have a fail secure electric strike or lockset, for normal
card access ingress, to maintain a secure environment in case of power outage or fire
alarm system activation. This design permits free egress at all times
c. Perimeter walls of a Technology Lab Room, are not required to be slab to slab
d. Cameras covering the entrance door and any other secondary exits from inside and
outside
e. Any non-card access doors that lead into the room must be treated as emergency exits
and must have a door contact (remotely monitored) and local alarm sounder
f. All card reader doors leading into the Technology Lab Room shall be monitored for
immediate forced open and door held open (60 Second) alarms
g. Exterior windows should be avoided where possible, but if they exist they must be either
shatter resistant or fitted with protective film
4 © 2016 JPMorgan Chase & Co. All Rights Reserved. Confidential And Proprietary For
Internal Use Only
APPENDIX J – Main Equipment Room (MER), Technology
Room (TR) and Technology Lab Security Design Standard
Main Equipment Room consists of technology assets containing servers with applications
MER
being run on them within JPMC controlled space. The facility in which this room resides may
be leased or owned. These rooms differ from a Technology Room (TR) since they have
outside communication circuits terminated within the space and do not contain servers with
applications being run on them.
A Technology Room consists of technology assets in a single room within JPMC controlled
TR
space. The facility in which this room resides may be leased or owned. These rooms are used
to distribute communications to the workstations or offices within a JPMC controlled
environment. TRs contain horizontal distribution switches only; they do not contain outside
communication circuit termination, nor servers with applications run on them.
Standards Owner / Primary Michael Forlenza, Jon Denial, GSI, Russell Ang, Ernest D’Souza,
Contact / Secondary GSI, EMEA Director, GSI, Standard
Contact/Standards Manager NAMR/LATAM APAC Manager
Procedure Owner’s Function or Global Security & Investigations , Global Security, NAMR/LATAM
Line of Business/Region/Country
5 © 2016 JPMorgan Chase & Co. All Rights Reserved. Confidential And Proprietary For
Internal Use Only
THIS PAGE INTENTIONALLY BLANK
Appendix K
Step 2: Click on Exception Approval - GTI-EUS Global Standard for Critical Technology Space Builds
Step 3: Check Action details, Request the Product Details.
Step 4: *
1. Enter all information with . (IF MULTIPLE EXCEPTIONS ARE REQUIRED FOR ONE PROJECT EACH EXCEPTION MUST BE
SUBMITTED SEPERATELY).
2. Statement from Standard Where Exception is required: This can be found within the WTS handbook at the following link:
https://confluence.uk.jpmorgan.com/confluence/display/RSO/1.+Introduction
3. Supporting documentation can be added and attached at the bottom.
4. Click Save Details.
Step 4: Check Out: