PRESUPUESTO DESAGREGADO DE GASTOS DE GESTION

OBRA:

PLAZO DE EJECUCION (EXP. TEC.+OBRA): 3.5 MESES COSTO DIRECTO: S/868,993.98


FECHA:
TIEMPO/ COSTO
ITEM DESCRIPCION UND. PARTIC. PARCIAL TOTAL
CANTIDAD UNITARIO

1 HONORARIOS/SUELDOS Y SALARIOS (INC. LEYES SOCIALES)


1.00 COORDINADOR TECNICO MES 3.50 1.00 3,900.00 13,650.00
1.00 COORDINADOR ADMINISTRATIVO MES 3.50 0.50 2,480.00 4,340.00
TOTAL 01 17,990.00
2 ALQUILERES Y SERVICIOS
1.00 GASTOS NOTARIALES Glb 1.00 500.00 500.00
1.00 MOBILIARIO Y EQUIP. DE OFICINA Glb 1.00 250.00 250.00
1.00 GASTOS DIVERSOS mes 3.50 500.00 1,750.00
1.00 IMPLEMENTOS DE SEGURIDAD und. 2.00 120.00 240.00
TOTAL 02 2,740.00
3 MATERIALES Y UTILES DE OFICINA
1.00 UTILES DE OFICINA mes 3.50 198.53 694.85
1.00 COPIA REPRODUCCIONES E IMPRESIONES GLB 1.00 300.00 300.00
TOTAL 03 994.85
TOTAL GASTOS DE GESTION 21,724.85

PORCENTAJE GESTION DEL PROYECTO / COSTO DIRECTO OBRA 2.50%