You are on page 1of 24

Color profile: Disabled

Composite Default screen

3 Cost and time modelling

Summary
This chapter seeks to establish that a need exists for both the simplifi-
cation and the rationalisation of the bill of quantities (BoQ) cost
model. The present day uses of the BoQ are compared to those for
which it was originally intended. This comparison demonstrates
that, in practice, the BoQ and its current uses are at variance with, or
have exceeded, original intentions.
Having established the need for new improved cost models in
Chapter 2, this chapter looks at some of the methods used by academic
researchers and practitioners to, firstly, overcome the difficulties faced
by the BoQ and, secondly, to integrate cost with time. The methods are
compared and critically evaluated. The evidence supports the proposi-
tion that simplification using “significance theory” alone simplifies the
BoQ, but does not improve or enhance its role in the systematic quanti-
fication of delay and disruption claims. In short, simplification using
significance theory does not make the BoQ capable of fulfilling the
various tasks required of today’s cost model. Because most problems
associated with the conventional BoQ exist because it fails to model
work items and cost realistically, it is proposed that improvement and
increasing the realism within the BoQ can best be achieved by simpli-
fying the method of measurement or by a change from work items
towards “work packages” or “operational groups”.

3.1. Introduction
The BoQ has been in use for a number of centuries. Originating in the
UK, evolved significantly in the nineteenth century, mainly as a
result of the growth in transport such as canals and railways. The
evolution of the BoQ was accompanied by amendments to condi-
tions of contract, which were in turn revised in line with changes in
case law and statute. Case law at this time centred on liability for

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:37 PM
Color profile: Disabled
Composite Default screen

28 Quantifying and managing disruption claims

inaccurate BoQs, measurement rules, errors in composite descrip-


tions, and alleged omissions of items, e.g. Moon v. Witney Union.1
“Measurement problems” probably led to standardisation and
development of the first standard methods of measurement.
According to a Royal Institute of Chartered Surveyors (RICS)
report in 1993, the BoQ is used in approximately 50 % of all construc-
tion contracts by value. This figure is nearly a decade old, and the
use of traditional contracting has been reduced by the increased use
of the design and build, BOOT and BOO procurement routes, PFI/
PPP arrangements, and partnering and alliancing relationships.
However, the 50 % figure is probably low, since it does not appear to
take into account the wide use of BoQs in the above procurement
options such as design and build. The BoQ is still the cost model
used by the parties in estimating cost in the iterative process of
refining the design and specification and for appointing sub-
contractors. This reliance, or continued use of the BoQ even in these
untraditional procurement routes, lies in the fact that estimators,
quantity surveyors and cost accountants all appear to use the stan-
dard methods of measurement. Reliance upon detailed standard
methods of measurement means that estimators, quantity surveyors
and the cost accountants, naturally, develop or compile detailed and
lengthy BoQs. Pricing or estimating such BoQs is then carried out
using “norms” or data from either long-established commercial
databases or using the contractor’s/estimator’s own, equally long-
established “book of rates”. The practical problem is that although
the popularity of BoQs may not have changed, the uses to which
they are now put have, in contrast, changed dramatically.

3.2. The original purpose of the BoQ


The BoQ was originally designed to:
• Provide an equal basis for tendering.
• Convey the client’s requirements.
• Save contractor’s time and cost in preparation.
• Act as a payment document during the construction phase.
Professor John Uff QC, in his recent paper Are we all in the wrong job?
Reflections on construction dispute resolution,2 when discussing the rise
of the quantity surveyor, says:

1 Moon v. Witney Union (1837) 3 Bing NC 814.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:38 PM
Color profile: Disabled
Composite Default screen

Cost and time modelling 29

Bills of quantities then took on more significant roles both as a vehicle for calcula-
tion of interim payments and doubling as the specification, under the Joint
Contracts Tribunal (JCT) with quantities forms of building contracts. These are
still lump sum contracts, but for the Institution of Civil Engineers (ICE) and other
types of contract, the bill of quantities later acquired full contract status, the work
becoming subject to “remeasurement”. In the past few decades both natural
evolution in forms of procurement and conscious policy have led to a move
against bills of quantities, towards milestone interim payments and lump sum
contracts of an increasingly turnkey nature. No one today wants to incur the cost
of interim measurements, nor to run the risk of interim payment disputes.

Even though the use of interim measurements may be decreasing,


the BoQ still remains a very useful document, so much so that the
BoQ and its present day diverse practical uses are clearly at variance
with its original theoretical objectives, see Table 3.1.

Table 3.1. Present day uses of BoQs


Client Is an aid to defining employer’s requirements/material
specification.
Allows comparison of tenders.
Allows costing of alternative designs.
(In traditional contracting) construction supervision,
(remeasurement).

Contractor Estimating and tendering.


Obtaining quotations for materials.
Planning.
Cost control.
Cashflow prediction.
Construction site management.
Contractual interface Interim payment valuation.
Valuation of variations.
Work remeasurement.

As early as 1980,3 surveys had concluded that, in practice, most use


was made of the BoQ during the construction and final account

2 Are we all in the wrong job? Reflections on construction dispute resolution. Uff J. A
Society of Construction Law Paper based on the talk given to a joint meeting of the
Society of Construction Law and the Society of Construction Arbitrators in London,
3 July 2001.
3 The Contractor’s Use of Bills. Skinner DWH and Jepson B. Chartered Quantity
Surveyor, pp. 63–68, September 1980.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:38 PM
Color profile: Disabled
Composite Default screen

30 Quantifying and managing disruption claims

phases, and not at the tendering stage as was initially intended. This
is not surprising, since once the BoQ is used in the tendering stage, it
adopts its contractual purpose during the construction phase. The
contractual purpose of the BoQ appears to be to produce a cost
model for payment purposes during the construction contract.
However, because the BoQ is the only contract document concerned
with detailed financial issues, in practice it is often used in all
matters involving money and naturally becomes the central vehicle
for the financial control of civil engineering and building works.
In short, experience and academic surveys appear to indicate that
the BoQ is now used as a cost estimating model, tendering model,
planning model and a contractor’s site cost control model, lies at the
centre of most payments, and is used in the valuation of variations
and claims (including those for delay and disruption). The important
question involves an analysis of whether the BoQ adequately fulfils
the varied requirements of the industry. In other words, let us investi-
gate if the BoQ warrants improvement, total replacement or commen-
dation. As a starting point, the positive and negative aspects of the
BoQ are evaluated.

3.3. Positive aspects of the BoQ


• Allows contractors to tender on a common basis.
• Because the BoQ is produced only once, costs to the employer
may be ultimately minimised.
• It is a convenient method to price provisional sums and other
parts of the work that are not designed before tenders are
sought.
• The BoQ unit rates generally provide a “pre-agreed” basis for
the preparation of interim valuations, pricing (certain, simple)
variations and for preparation of the final account.

3.4. Negative aspects of the BoQ

3.4.1. Estimating

3.4.1.1. Unit rate or operational estimating?


BoQs usually describe the type and net quantity of material to be
used in the construction process. Some estimators believe that the
material price is relatively simple and will have little effect on the
overall price for the site work operation. For example, “a brick is a
brick and will cost the same wherever it may be incorporated into
the structure”. Equally true is the fact that probably all the contrac-

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:38 PM
Color profile: Disabled
Composite Default screen

Cost and time modelling 31

tors will be able to purchase the bricks at similar prices. However, a


contractor could seek advantage over its competitors by minimising
material wastage.
Because the material cost can, in some cases, represent up to 50 % of
the total project cost profile, the estimator needs to be careful when
predicting the wastage allowance. Experience shows that typically,
most contractors simply use handbooks to calculate/predict wastage.
Interestingly, a report on material wastage found that although the
mean actual wastage on construction sites in 1993 was 12.3 %, the
mean wastage allowance used by estimators was only 6.6 %.4
In contrast, the estimation of labour and plant costs is more complex,
subjective and will depend upon the location and, in practice, each
contractor’s chosen method of site construction. Harris and McCaffer,5
Moyles,6 Merriefield7 and Harrison8 all suggested that labour and plant
usage/costs are best estimated using an “operational” method. Opera-
tional estimating involves calculating the total direct cost of resources
based on the total time the resources are required, whereas unit rate
estimating involves calculating costs based on the outputs of each indi-
vidual resource. The considered view of the above writers was that,
certainly for civil engineering works, operational estimating links very
well with site planning and is effective in allowing for idle time, which
is common in plant-intensive civil engineering work. For this reason,
such writers concluded that the operational estimating method was
more reliable and, in practice, more realistic than the unit rate methods.
Indeed, over 30 years ago in 1971, operational estimating was begin-
ning to be reported as gaining in popularity: Barnes9 wrote that opera-
tional estimating’s “superiority for describing the cost of interrelated
mechanised operations stems from the more realistic representation
of the variables affecting their cost”.

4 Organizational Productivity – A Case Study of Materials Management in UK


Construction Firms. Proverbs D, Olomolaiye P and Harris FC. Construction Papers,
No. 44, edited by Peter Harlow, the Chartered Institute of Building, Ascot, 1995.
5 Modern Construction Management. Third Edition. Harris F and McCaffer R. Blackwell
Science, 1989.
6 An Analysis of the Contractor’s Estimating Process. Moyles BF. M.Sc. Thesis,
Loughborough University of Technology, 1973.
7 Construction Estimating. Merriefield CM. Management of Contracts and Projects,
Project Management Group, Department of Civil and Structural Engineering, UMIST,
13–17 May 1991.
8 Operational Estimating. Harrison RS. Construction Papers, No. 33, edited by Peter
Harlow, the Chartered Institute of Building, Ascot, 1994.
9 Civil Engineering Bills of Quantities. Barnes NML. CIRIA Research Report No. 98.
Department of Civil and Structural Engineering, UMIST, 1971.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:38 PM
Color profile: Disabled
Composite Default screen

32 Quantifying and managing disruption claims

Today, there appears to be a distinct shortage of empirical data/


records on the use of operational estimating. However, it is clear, or
rather assumed, that because increases in mechanisation promote
operational estimating, it may be reasonable to suggest that since the
former has increased, then operational estimating would also have
found greater use, certainly with civil engineering estimators.
However, the problem for such estimators is that they need to
subjectively manipulate the operational estimate to become commen-
surate with the detail in the typical BoQ. In practice, the estimator is
required to group together various BoQ items to form what he or she
believes represents an actual site work operation, e.g. laying a section of
sewer. This group of BoQ items may be represented in the construction
programme as one or more activities. Typically, the estimator assumes
a total duration and then selects the labour/resources to be used for
that site activity. This total site activity duration is then used to calculate
the time-related costs of that activity. Paradoxically, because the cost
model, the BoQ, is so detailed, the operationally estimated site activity
cost is then “assigned” back to each detailed BoQ item. This means that
whilst a group/section of BoQ unit rate items may be estimated using a
realistic approach, the BoQ itemisation encourages/requires a diver-
gence between actual site costs and BoQ unit rates.
Harris and McCaffer10 suggested that the “method of assignment” is
open to each estimator and that the simplest method is to apportion the
cost pro rata with the item quantity. But, in practice, experience shows
that contractors and estimators usually produce another cost model,
based on operations, solely for their estimating and planning purposes.
They typically call this manipulation of the BoQ “reworking and adapta-
tion”. In practice, this means that from a construction site’s point of view,
the employer’s BoQ is totally unsuitable for the contractor’s site planning
and construction of the works. Barnes’s11 empirical research reinforces
the above. He stated, “The conventional BoQ appears to be imposing an
unrealistic model of the factors influencing construction costs upon
financial control due to its adherence to the quantity-proportional
hypothesis”. He went on to report that the estimator man-hours
involved in manipulation and “assignment” procedures could be signifi-
cant, and stated, “This conversion process would have been unnecessary
if the bill items had themselves been operationally grouped”.
Further, it is better to provide operational estimates to site
management so that each site operation is controlled and resourced

10 See Footnote 5.
11 See Footnote 9.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:39 PM
Color profile: Disabled
Composite Default screen

Cost and time modelling 33

effectively and efficiently and is at least commensurate with the esti-


mator’s assumptions. In practice, site contract managers do not want
information on BoQ work items for their purposes – they want to
control, pay for and resource actual site operations. In short, their
interest is very different from that of the estimator, and BoQ items
discourage any useful sharing of information.
In practice, experience tells us that whilst many contractors may
(in private) admit that the current BoQ system is not suitable for
accurate/realistic estimating and planning, they quite willingly
manipulate the BoQ unit items in order to develop their own cost
models based on proposed site operations. So although, in practice,
the structure and associated complexity of the BoQ may not be a
“perceived” problem, when situations arise where delays and varia-
tions need to be evaluated, conflict arises simply because the BoQ
does not reflect the true manner in which the fixed, time-related and
other resource costs are actually planned to be incurred on site.

3.4.1.2. Level of detail in the BoQ

Too many low-value items


It is widely accepted that BoQs contain many low-value items. The
academic starting point for this proposition was Lichtenberg,12 who
highlighted the “problem of overwhelming detail” in the BoQ. The
BoQ is so detailed because it acts as a specification, a long list of all
the materials to be incorporated and, most importantly, because it is
developed by applying the rules from, typically, a standard method
of measurement. As a consequence, employers seek to provide as
much detail as possible, confusing hundreds of pages in a BoQ with
being precise. The standard methods of measurement simply cate-
gorise or specify at such detail that reliance on them, in practice,
generates very lengthy BoQs.
The level of detail chosen for itemisation in the method of measure-
ment has a direct effect on the level and on the number of BoQ items. For
example, the methods of measurement “itemise” each time there is a
new material description, e.g. a change from 16 mm diameter reinforce-
ment to 20 mm diameter reinforcement. Barnes stated, “If the method of
measurement were to be revised, the opportunity should be taken of
structuring the rules for itemisation and classifying them more precisely,

12 The Successive Principle, Procedures for a Minimum Degree of Detailing.


Lichtenberg S. Sixth Annual Proceedings of the Project Management Institute, Washington,
pp. 570–578, 1974.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:39 PM
Color profile: Disabled
Composite Default screen

34 Quantifying and managing disruption claims

so it can be simplified”. However, in practice, some employers justify the


large amount of detail in the BoQ, claiming that the BoQ helps to “build
up a picture of the complex nature of the project”.
Others in the industry suggest that, in practice, drawings and the
actual specification provide a complete description of the works; hence,
the BoQ needs to concentrate only on the features that significantly
affect cost. Not surprisingly, the Royal Institute of Chartered Surveyors
in its Principle of Measurement (International) for Works of Construc-
tion (POMI) adopted this less detailed approach. In the POMI, the
items are more composite in nature than in a traditional BoQ and much
of the work, which would normally be described as separate items, is
deemed to be included in the major items. Similarly, in practice (and in
private), some estimators admit, especially in relation to tendering to
DB, BOOT and PFI/PPP projects, that they amend the common
methods of measurement, either by direct omission or by amalgam-
ation, with the result that their BoQs contain at least 50 % less items.
In the 1970s, it was perceived that 2.5 % of the total project cost of
civil engineering projects was consumed by the compiling and admin-
istration of BoQs (excluding the negotiation of claims). Not surpris-
ingly, subsequent academics and certain estimators in contracting
entities sought to reduce the costs of compiling and pricing BoQs by
reducing their sheer complexity by concentrating on the most impor-
tant BoQ items or the “significant items” in the BoQ.

Estimating accuracy
There is a correlation between the estimating accuracy and the value
of each BoQ item. More specifically, high-value BoQ items are, in
practice, estimated to a higher degree of accuracy than low-value
items, and as the relative value of the BoQ item falls so does the accu-
Accuracy level

Design process


Fig. 3.1. The relationship between estimating accuracy and the design process

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:40 PM
Color profile: Disabled
Composite Default screen

Cost and time modelling 35

racy with which it is estimated. This may be because, perhaps, low-


value items simply receive low priority or because low-value items
generally relate to abstract work.
Accuracy level

Cost of estimating as percentage of cost of job

Fig. 3.2. Estimating accuracy against the cost of estimating

It is generally well known that the accuracy of a cost estimate will


improve as the level of design detail increases (see Fig. 3.1). Accu-
racies quoted for the feasibility estimate for civil work range from
±20 % to ±40 %.13 Interestingly, and perhaps not so well known is
that if an estimator has priced a certain number of items, there is
little increase in accuracy to be gained by pricing any further items
(see Fig. 3.2).14 As Lichtenberg commented, “It is of major impor-
tance not to waste effort in detailing to a greater degree than can be
justified by the accuracy of the total”.15

3.4.2. Valuation of change, delay and disruption


Barnes16 has commented, “One of the principal shortcomings of the
traditional BoQ was that it was only a BoQ of the permanent work

13 Design Phase Estimating: State of the Art. Ogunlana O and Thorpe T. International
Journal of Construction Management and Technology, Volume 2, No. 4, pp. 34–47, 1987.
14 Probabilistic Approach to Estimating and Cost Control. Vergera AJ and Boyer LT.
ASCE Journal of Construction Division, Volume 100, pp. 543–552, 1974.
15 The Successive Principle, Procedures for a Minimum Degree of Detailing.
Lichtenberg, S. Sixth Annual Proceedings of the Project Management Institute,
Washington, pp. 570–578, 1974.
16 Civil Engineering Standard Method of Measurement. Third Edition. Barnes NML. The
Institution of Civil Engineers. Handbook, Thomas Telford, London 1992.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:40 PM
Color profile: Disabled
Composite Default screen

36 Quantifying and managing disruption claims

left behind when the contractor’s men and machines had moved
on”. The BoQ was originally introduced in a labour-intensive
building industry and did not take account of plant and temporary
works. As the industry developed, the use of plant increased but the
BoQ rates still compounded all the resource costs and relied on the
principle that quantity is proportional to cost. Barnes suggested that
this situation could be tolerated, so long as the “work was never
varied after tenders were accepted”. However, most practitioners
would agree that variations and delay and disruption claims are
simply inevitable. It is in the evaluation of changes, delay and
disruption that unit rates (compounding all costs) primarily fall
down; those BoQ items that are not quantity-proportional are often
evaluated on a totally unsystematic, inaccurate or unrealistic basis.
In 1971, Barnes found that 70 % of all claims required consideration
of the distinction between costs. Five years later in 1976, Barnes intro-
duced the concept of method-related charges (MRC) to the Civil Engi-
neering Standard Method of Measurement (CESMM). It was now possible
for contractors to price certain work items that they considered not to
be simply quantity-proportional. Three charges were available to esti-
mators: (1) the quantity-proportional charge, (2) the time-related
method-related charge and (3) the fixed method-related charge. It
was intended that the three types of charge would be more closely
related to the manner in which costs were intended to be actually
incurred on site. Accordingly, it was hoped that the MRCs would
allow the automatic evaluation of variations and increase the realism
of quantifying claims for delay and disruption. It was decided that the
MRCs were a function of each contractor’s own method of working
and therefore should not be set against predetermined items and the
MRCs were not mandatory. As a consequence, in practice, MRCs
were not commonly used in the UK, and in 1992 Barnes conceded that
the “three price bill does not model value perfectly because it does not
model all the many variables which can affect cost”. The problems
that MRCs were initially designed to overcome still remain today.

3.4.3. BoQ unit rate abuse


Because the unit rate in the BoQ does not reveal the way in which a
contractor’s price builds up, in practice the pricing of BoQ items is
open to manipulation. “Tricks of the trade” such as “front-end loading”,
designed to improve the contractor’s cash flow, demonstrate the
“smokescreen” between the realistic costs of construction and BoQ
item rates. This smokescreen surrounding the contractor’s resource
assumptions also allows “claims spotting” to go undetected. This

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:40 PM
Table 3.2. Summary of effective uses of BoQ

Use Success Remarks


Color profile: Disabled
Composite Default screen

Client: Aid to define client’s requirements. Partial Drawings and specification may be more suitable.
Costing of alternative designs. Fail Unit rate does not link the design and costing exercises. Large variances between
work items rates and tender, therefore use by clients to estimate is questionable.

Friday, November 15, 2002 3:07:41 PM


Construction supervision. Partial The BoQ requires “conversion” into site activities. No integration of
estimating and planning is promoted.
Comparison of tenders. Partial Unit rate manipulation makes this difficult. Need to increase tender realism.
Contractor: Estimating and tendering. Partial Unit rate restricts use of operational estimating. Too many low-value items.
Obtaining quotations. Good Sub-contractors like the materials detail. Main contractors simply

Thomas Telford\Quantifying and Managing Disruption Claims


photocopy BoQ and send out for enquiry.
Planning. Partial BoQ based on materials to be incorporated, for planning function of site
activities BoQ requires subjective conversion.
Cost control. Partial BoQ items and rates are converted into site operations. Control is “crude”
and feedback non-existent.
Cashflow prediction. Fail BoQ not directly linked to time model. Even the “S” curve approach is
approximate.
Site management. Fail Control model is different from payment model. Too many work items in
work operation hence no effective control.
Contractual Interim payment valuations. Partial Measurement is based on material components installed.
interface:.
Cost and time modelling

Valuation of variations and claims. Fail BoQ rates promote “cost is proportional to quantity” idea. No link to time
model, unit rate compounds all types of cost.
37

Work remeasurement. Partial Time-related and other charge are not acknowledged in payment.
Color profile: Disabled
Composite Default screen

38 Quantifying and managing disruption claims

may be described as a process by which contractors decrease their


rates on items they believe to have been overmeasured, and increase
the rates for items they consider to be undermeasured. In practical
terms, employers very often fail to detect such devices because the
actual variances between each contractor are simply much greater
than can be attributed to the effect of loading.

3.4.4. Summary of BoQ uses


Table 3.2 provides a summary of the uses of the BoQ in each of the roles
for which it is now typically employed. The proposition in this book is
that the BoQ now fails to fulfil its various desired uses and that improved
cost models should aim to satisfy the original use for which the BoQ was
developed (tendering on an equal basis) but must also overcome the
deficiencies in the BoQ caused by its varied and extended use. Table 3.3
provides a summary of the requirements of an “ideal cost model”. The
next section recounts previous attempts made to simplify and rationalise
the way costs are modelled in the construction process in order to
develop a direct link with time as typically modelled in the programme.

Table 3.3. Ideal cost model requirements


Cost model requirement
Client Allow tendering on a common basis.
Allow contractor flexibility in method and pricing.
Provide transparency in pricing in order to aid tender
evaluation/comparison.
Contractor Improve and simplify estimating; encourage realistic
planning.
Facilitate integration between the cost model and time model.

Allow and promote effective site control.


Contractual interface Allow realistic measurement and valuation.
Facilitate the quick and automatic evaluation of variations
and claims involving delay and disruption.

3.5. Previous attempts to rationalise the BoQ

3.5.1. Significant items approach


In order to reduce the number of items in the BoQ and also increase
estimating/planning attention on the higher-value items (thus

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:41 PM
Color profile: Disabled
Composite Default screen

Cost and time modelling 39

increasing the overall estimating accuracy), various academics and


practitioners have used two practices: the “successive principle” and
the “80/20 principle”. The pattern underlying the 80/20 principle
was discovered in 1897 by Italian economist Vilfredo Pareto (1848–
1923). Pareto discovered that 80 % of the wealth of a nation is in the
hands of only 20 % of the population. The 80/20 rule has been found
to apply to many situations, and it has long been known that 80 % of
the value of a BoQ is contained in approximately 20 % of the items.

3.5.1.1. Successive principle


Empirical research by Lichtenberg17 concluded that maximum esti-
mating accuracy was obtained by concentrating estimating effort on
the major items with greatest variance. He used this principle to
develop the method of “successive estimating”. In this procedure, a
project is divided into a small number of main work items or work
operations. Each work item/operation is quantified and three esti-
mates (maximum, minimum, most likely) made of the costs. Similar
to the PERT method, the mean and the variance can be “approxi-
mated” for each item. Items with a large variance are subdivided
and the variance recalculated. This procedure is repeated until the
estimator is satisfied that the “variance derived from items cannot be
estimated with greater accuracy than the variance achieved”.
The underlying philosophy in Lichtenberg’s work is that there is
little sense wasting time and effort in estimating items that do not
improve overall accuracy. However, the process of selecting the
“major items” is highly subjective and, in practice, will vary between
contractors and estimators. Further, Lichtenberg made no attempt to
model or compensate for low-value sections of the work. Lichtenberg’s
study did not relate directly to BoQ unit items, instead his “work
items” reflected site tasks. Lichtenberg’s analysis was aimed at reducing
the BoQ complexity, purely to optimise the accuracy, cost and effort
associated with estimating. The need for site control, cost and time
integration, and systematic evaluation of the effects of delay and
disruption claims were not investigated.

17 See Footnote 12.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:41 PM
Color profile: Disabled
Composite Default screen

40 Quantifying and managing disruption claims

3.5.1.2. Significant items estimating

Short (1970)18
At the Institute of Municipal Engineers’ conference, Short discussed
the concept of cost-significant items. He highlighted earlier research
conducted at the University of Manchester that had established that
90 % of total project costs were consumed by 10 % of the BoQ items.
Short concluded that it might be beneficial to tender only the 10 % of
significant items and negotiate a lump sum cost for the remaining
10 % of the project cost. He believed that this method would remove
the cost associated with estimating the abstract and low-value items
such as “fillets in manholes vertically downward”.
19
Barnes (1971)
Barnes used “Pareto’s law” and concluded that 20 % of the total cost
in a BoQ was occupied by 75 % to 95 % of the BoQ items. Neverthe-
less, Barnes suggested that the low-value items were necessary to
convey the detail of the proposed work. However, because his
empirical research had concluded that the low-value items had little
influence on the final account, Barnes concluded that they could be
eliminated from the financial control of the contract. Barnes noted
the inadequacy of the standard form methods of measurement used
to compile BoQs, stating, “It is one of the paradoxes of the contrac-
tual system that the BoQ contains prices for fixing components of the
work which are so small that their fixing cost cannot economically be
defined”. As discussed above, Barnes espoused the many advan-
tages of operational estimating and the need to adapt standard form
methods of measurement to encourage operational estimating.
20
Moyles (1973)
Moyles’s investigation into items in the BoQ “proved the existence
of a Pareto distribution”. Accordingly, he suggested that this 80/20
relationship be used to simplify BoQs. The method used by Moyles
to select the high-value items in the BoQ or the cost-significant items

18 Summing Up. Short GS. Second Conference on Contracting in Civil Engineering since
Banwell. EDC for Civil Engineers and Municipal Engineers, National Economic
Development Office, 1970.
19 See Footnote 9.
20 An Analysis of the Contractor’s Estimating Process. Moyles BF. M.Sc. Thesis,
Loughborough University of Technology, 1973.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:41 PM
Color profile: Disabled
Composite Default screen

Cost and time modelling 41

was still laborious and involved pricing all the BoQ items and
ranking them in descending order. When 80 % of the total value was
reached, the corresponding items were selected.
21
Harmer (1983)
Harmer, with the Property Services Agency (PSA), also decided to
make use of Pareto’s law. The PSA developed an estimating system
using significance theory, basing it on the rationale that “by restricting
the measurement and pricing to significant items and using data
with reasonable sample sizes it was considered that the unreliability
of rates from the BoQ would be minimised”. Harmer reported that,
on average, 20 % of the BoQ items in a work classification (e.g. exca-
vation, brickwork, concrete) represented 69–89 % of the work section
total value.
22
Saket (1986)
Saket used an earlier finding that the cost-significant items were
those whose value was greater than the average value, and devel-
oped what he termed “iterative estimating”. This method of esti-
mating did not require all the BoQ items to be priced; instead,
attention was focused on the cost-significant items.
23
Allman (1988)
Allman, like Harmer, researched the simplification of the BoQ within
the PSA. Allman’s review of the significant items estimating system
highlighted that results analysed by the PSA and checked independ-
ently by the Building Research Station (BRS) “indicated significant
items estimating as being the most accurate method in use within
the PSA”. The PSA published a “significant items booklet” that set
out the estimating procedure and contained details relating to the
percentage cost of insignificant items in each trade. The PSA also
produced a computer programme that incorporated Monte Carlo
simulation to increase estimating accuracy.

21 Identifying Significant BoQ Items. Harmer S. Chartered Quantity Surveyor, pp. 95–96,
October 1983.
22 Cost Significance Applied to Estimating and Control of Construction Projects. Saket MM.
Ph.D. Thesis, The University of Dundee, 1986.
23 Significant Items Estimating. Allman I. Chartered Quantity Surveyor, pp. 24–25,
September 1988.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:42 PM
Color profile: Disabled
Composite Default screen

42 Quantifying and managing disruption claims

24
Betts and Gunner (1993)
Betts and Gunner reported undertaking similar research in Singapore,
which “revealed that the 80/20 relationship remains constant over a
wide variety of building functions”. They highlighted the growing
popularity of cost-significant item estimating worldwide and reported
that in Singapore, the Construction Industry Development had begun
issuing tender price indices based upon significant items.
25
McGowan (1994)
McGowan further refined the cost significance technique in order to
develop models based on the principle of “resource significance”. A
resource-significant item was identified as any item in a BoQ that had
a labour, plant or material resource value (cost and hours) greater
than the mean labour, plant or material resource value. McGowan
developed a model for reinforced concrete bridges and a model for
roads (flexible construction), which accounted for a consistent and
high (typically 80–90 %) proportion of the resources and costs. The
primary failure of such models was that they were project-specific
and extremely sensitive to change.

3.5.1.3. Positive aspects of using significant items approach


Low-value items, which are often associated with large variances in
accuracy but which still require time and effort to price, are no
longer required to be estimated. The significant-items approach
appears to provide a cheaper method of estimating whilst preserving
sufficient accuracy.

3.5.1.4. Negative aspects of using significant items approach


1. Still leads to producing a BoQ – and still encourages unit rate
estimating.
2. Still relies on detailed standard methods of measurement.
3. Still leads to BoQ unit rates based on materials.
4. BoQ items are not related to site operations or work packages.
5. Cost and time are not directly linked, and realistic planning
and site construction process control are not encouraged.

24 Financial Management of Construction Projects: Cases and Theory in the Pacific Rim.
Betts M and Gunner J. Longman Inc., White Plains, New York, USA, 1993.
25 Integrated Cost and Time Models for Measuring, Valuing and Controlling Construction
Projects. McGowan PH. Ph.D. Thesis, The University of Dundee, 1994.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:42 PM
Color profile: Disabled
Composite Default screen

Cost and time modelling 43

6. Low-value BoQ items are still required to be purchased and hence


need to be unambiguously itemised in the contract documents.
The principle of significance does, of course, lead to simpler, less
detailed cost models. Such models are still as accurate in predicting
total cost as is a BoQ containing 100 % of the items. However, cost-
significant items (CSIs) retain the same BoQ item definition, based
upon detailed methods of measurement. CSIs are not work pack-
ages, i.e. they certainly do not represent work operations or activities
on a programme; neither did any of the proponents of significant
items estimating purport that CSIs were capable of being such work
packages or operations. In short, CSIs are all about reducing the
number of items that an estimator needs to price.
The number of items in a BoQ is clearly dependent upon:
1. The degree of detail required in the particular method of measure-
ment.
2. Format or structure of the BoQ, e.g. elemental, sectionalised
bills usually have greater duplication of items.
3. The complexity and repeatability of the design.
4. The size of the project (obviously!)
The proposition in this book is simply that because all BoQs are
required to be compiled using a method of measurement, simplifica-
tion of the cost model can only come about by reducing the level of
detail in the methods of measurement. Further, in order to allow site
construction process control, the cost model must contain work
packages that are directly linked to site activities. Further still, to
define these work packages, additional criteria are needed: signifi-
cance theory alone appears to be insufficient. In short, it appears that
in order to simply reduce the complexity of BoQs for estimating
purposes, the significant items approach is sufficient, but that the
integration of time with cost, thus facilitating realistic planning and
site control, can, in practice, only be realistically achieved by
reducing the detail of measurement in the method of measurement.
In short, simplification and rationalisation of BoQs must begin with
changing the way standard form methods of measurement generate
the vast number of BoQ items.

3.5.2. Work packaging or “operational grouping”


This method involves grouping similar BoQ items and considering
them as one. Like items may be grouped into work operations such
as fixing steel reinforcement or fixing formwork. Prior to a compar-
ison of the relative advantages of the two “simplification” methods,

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:42 PM
Color profile: Disabled
Composite Default screen

44 Quantifying and managing disruption claims

let us take a look at the historical development of the school of


thought behind the “operational” or work packaging methodology.
26
Skoyles (1968) – operational bill
Skoyles stressed that the BoQ system “is based on labour cost being
related to the physical measurement of materials” and suggested
that, in contrast, the estimation of labour/plant costs should be
related to site operations. He argued that the BoQ was simply a
description of the completed project rather than the work to be done,
and therefore did not allow any form of construction process
control. Skoyles believed that cost models should instead reflect the
manner in which costs are actually incurred on site, and hence relate
to site activities or operations. He suggested these site operations or
work packages would naturally encourage operational estimating,
increase overall estimating realism and also facilitate the integration
of cost with time. Cost models alone cannot allow systematic evalua-
tion of change, and hence Skoyles encouraged project programmes
to be produced based on operations (pre-defined in the cost model).
Skoyles also concluded that changes to the standard method of
measurement were necessary to drive the changes in the BoQ.
However, he was cautious, and cited the inertia of the industry to
change in his decision to “retain familiar methods of measurement
and rely on pricing unit rates”. Because the items in the cost model
were still differentiated by material function, abstract and low-value
items still remained in the operational bill. Indeed, the operational bill
format created more items, because it separated items further by indi-
vidual elements and sections of the project. The bill format failed to
encourage operational estimating and hence the original estimating
problems relating to complexity, time and cost of estimating were still
prominent. In fact, it was found that some quantity surveyors
reported 80 % increases in the time required to produce such bills and
that the pre-defined precedence diagram was greeted with contempt
by the industry. Contractors simply thought it was “too restrictive”.27
The Building Research Station (BRS) developed the operational bill
(OB), and the government agency encouraged its use on some
projects to demonstrate its intended benefits. In the early termination
of a contract, Skoyles and Lear28 demonstrated the benefits of using

26 Introducing Bills of Quantities (Operational Format). Skoyles ER. Current Paper 62,
Building Research Station, 1968.
27 Operational Bills: Users Comments. Abbot B, et al. The Architect’s Journal, pp. 617–620,
March 1970.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:43 PM
Color profile: Disabled
Composite Default screen

Cost and time modelling 45

work operations in the measurement and valuation. They suggested


that operations allowed easier measurement since it was easy to relate
the cost (or payment) model to site operations. They maintained that
if a BoQ (as previously prepared) had been used, the process of termi-
nation would have “been much more complex, involving a good deal
of remeasuring and greater liability to dispute”.
29
Barnes (1971) – operational grouping
Barnes sought to develop a cost model that was site-realistic and
encouraged operational estimating. His approach was to group
similar BoQ items to form site activities. Barnes reported that a 40 %
reduction in the number of BoQ items to be priced could be achieved
by “changing descriptions and amalgamating items”. Barnes’s oper-
ational grouping did not group work performed by one gang
working with one productivity, but was simply related to site activi-
ties. For example, Barnes did not group concrete placing, steel rein-
forcement fixing and formwork erection separately, but together to
form the activity of “constructing a concrete foundation”.

3.5.2.1. Positive aspects of using work packages


1. Work packages are directly related to site operations and
encourage, even allow, operational estimating. If operational
estimating is more realistic, better estimating accuracy may be
expected. Operational estimating reflects realistic resource
usage commensurate with developing cost-sensitive charges.
2. The work package definition is identical in the cost and time
models, so integrated planning and control is feasible.
3. Work packages relating to site activities may allow effective
site control, which in turn generates feedback, which can
contribute to more accurate or realistic estimates.
4. Work packages and a work breakdown structure (WBS) are
essential for cost and time integration, thereby generally
allowing objective, systematic evaluation of a greater number
of variations and delay and disruption claims.
5. Practical experience indicates that grouping of work items into
work packages is currently common practice within larger

28 Practical Application of Operational Bills Two. Skoyles ER and Lear RF. Current
Paper Series, Building Research Station, 1968.
29 See Footnote 9.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:43 PM
Color profile: Disabled
Composite Default screen

46 Quantifying and managing disruption claims

contracting organisations, and hence, in practice, should face


less inertia to change.

3.6. Time in construction contracts


Pickavance30 defines programming as merely deciding when and
where work will be performed and how it is to be sequenced in rela-
tion to other activities. By necessity, programmes involve decisions
concerning the duration of the work, who will perform the work, the
labour/plant resources to be applied, how the work will be moni-
tored, and how the programme will be updated. A number of
authors are dismissive of the role of the programme in evaluating
the effects of changes and delays and disruption (Fenwick-Elliot,31
Duncan-Wallace).32 The reasons given for this are:
1. Because the programme is not stated in the forms of contract to
be a contract document, it could be no more than a statement of
best endeavours.
2. Because, historically, construction programmes have tended to
be prepared as simple bar charts without apparent construction
logic, the effect of one activity upon another cannot be predicted.
Ideally, programmes should be realistic and reflect the contractor’s
optimum working method, and should be the most economically
beneficial for the contractor. Pickavance has suggested that there is a
need for contractors to have access to adequate databases in order to
plan realistically. Currently, “bills of quantities are not generally
produced in a form which will assist them”. Similarly, in practice,
contractors have stated that a “realistic estimation of the produc-
tivity of gangs” is a main factor in a successful programme.
The importance of the role of a realistic programme in the assess-
ment of extension-of-time claims caused by delays was highlighted
in Barker Construction Ltd v. London Portman Hotel Ltd [1996] 12 Const
LJ 277. This case held that in order to calculate a fair and reasonable
extension of time, the engineer/architect must:
1. Apply the rules of the contract.
2. Recognise the effects of the constructive change.

30 Delay and Disruption in Construction Contracts. Pickavance, K. First Edition. Construction


Practice Series, LLP Reference Publishing, 1997.
31 Building Contract Litigation. Fourth Edition. Fenwick-Elliot R. Longmans, 1993.
32 Construction Contracts: Principles and Policies in Tort and Contract. Duncan-Wallace I.
Sweet and Maxwell, London, 1986.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:43 PM
Color profile: Disabled
Composite Default screen

Cost and time modelling 47

3. Make a logical analysis, in a methodical way, of the effect of


delay event on the contractor’s programme.
4. Calculate rather than make an impressionistic assessment of the
time taken up by the delaying event.
This case demonstrates the importance of realistic and resourced
programmes for the contractor, employer and the contract adminis-
trator. However, there is no consistency of approach to the require-
ments for programming in the standard forms of contract. For example,
the Agreement for Minor Building Works, MW 80, does not require
any programme from the contractor. The JCT 80, whilst requiring a
programme, gives no definition of its content or how it is to be
prepared and monitored.
A realistic programme that is directly linked to the cost model and
allows simple, sufficiently accurate, monitoring of site progress is
vital in order to allow systematic evaluation of the effects of delay. For
example, consider delays caused by failure to provide drawings,
instructions and details (breach of JCT 80 Clause 25.4.6). If these
delays are to constitute a compensational delay event, then by defini-
tion the information must be requested at a time not too distant from
nor too close to the time at which the contractor actually needs it, and
not the time he might reasonably be expected to need it if everything
went to plan (London Borough of Merton v. Stanley Hugh Leach [1985] 32
BLR 68). The contractor’s actual need must be considered in the light
of actual progress, not the theoretical progress that might have been
made had the contractor been proceeding efficiently.
Realistic programmes that allow resource monitoring would be
especially important in cases where the contractor alleges that addi-
tional costs have been suffered as a result of disruption, or that the
progress of the work has had to be accelerated (constructive acceler-
ation). The contractor must be able to demonstrate that in the event
of the delaying factor, the resources, or lack of them, were not a
cause or principal cause of the delay and, secondly, where accelera-
tion has been alleged, the contractor must prove that the reasonable
resources have been increased beyond the resources planned at the
time of tender.
This “ideal” of the role of the programme is reflected in the Delay
and Disruption Protocol issued by the Society of Construction Law in
October 2002. Core Principle 1 of the Protocol states that the:
“Contractor should prepare and the Contract Administrator (CA) should accept a
properly prepared programme showing the manner and sequence in which the
Contractor plans to carry out the works. The programme should be updated to
record actual progress and any extensions of time (EOT) granted.”

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:44 PM
Color profile: Disabled
Composite Default screen

48 Quantifying and managing disruption claims

The Society goes on to suggest that, if this is done, “the programme


can be used as a tool for managing change, determining EOTs and
periods of time for which compensation may be due”.
At the time of writing, it is simply too soon to comment on what
“properly prepared” means. However, the guidance and the model
clause in the Protocol make reference to the Programme being
constructed and accepted in accordance with a Method Statement
“describing in detail how the Contractor intends to construct the
works, and the resources …it intends to use to do so”. As we shall see
in Chapter 4, the Protocol’s approach is similar to the role of the
programme envisaged in this book. However, the method in this
book goes much further in specifying how the work operations on a
method statement must relate to work activities (work packages) on
the contractor’s programme.

3.6.1. Damages and delay


Where a contractor loses money by virtue of the construction project
being delayed, it is trite law that losses can only be recovered from the
employer/guilty party if and to the extent that party has been the cause
of the delay. Put simply, the law of contract applies a “fivefold” test:
1. Was the loss caused by the default/delay event? (The causation
issue.)
2. Was the loss foreseeable as the consequence of the breach? (The
foreseeability issue.)
3. Is the loss too remote from the delay event? (The remoteness
issue.)
4. Was the loss contributed to by the default of the contractor?
(The contribution issue.)
5. Did the contractor take reasonable steps in an attempt to avoid
the loss? (The mitigation issue.)

3.7. Practical conclusions


1. BoQs were initially developed to provide an equal basis for
tendering and for interim payment purposes, typically on a
remeasurement basis. The present day uses of the BoQ have
exceeded its original objectives.
2. Today, the BoQ has a role in estimating, tendering, planning
and control and also has a vital role in the evaluation of the
monetary consequences of variations, delays and disruption.
The majority of the negative comments about the BoQ are
related to the level of detail. Too many low-value items exist

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:44 PM
Color profile: Disabled
Composite Default screen

Cost and time modelling 49

which have little influence on the estimating accuracy of the


overall BoQ, yet which still consume cost and effort in their
pricing.
3. The BoQ does not encourage operational estimating, which is
considered to be more realistic to the manner in which costs are
actually incurred in the construction process, and therefore
capable of generating estimates of greater accuracy.
4. Because the work items are based on the materials to be incor-
porated, they do not require the contractor to reflect the factors
to which the costs are actually sensitive, and the systematic
evaluation of variations is, in practice, limited to changes in
quantity. The automatic evaluation of the cost effects of disrup-
tion is beyond the scope of the current BoQ.
5. Previous improvements in the BoQ as a cost model have come
in two forms. Both have sought to reduce the complexity of the
BoQ, thereby increasing the estimating accuracy and reducing
the costs and time involved with its production (Table 3.4).

Table 3.4. Summary of research attempts to improve the BoQ


Significant items Operational modelling
Short (1970) Skoyles (1968)
Barnes (1971) Barnes (1971)
Moyles (1973)

Harmer (1983)
Saket (1986)
Allman (1988)

Betts and Gunner (1993)


McGowan (1994)

6. The significant items approach to estimating is effective. It


reduces the number of items to be estimated and model factors
can be used to account for the insignificant items. However,
significant items retain the description based on materials to be
incorporated and are still based on a detailed method of
measurement. They still advocate a unit rate type of estimating
and do not readily link cost with time. Significant work items
alone cannot be isolated and controlled in practice. The real
practical problem is that the structure of the work described in
a BoQ cost model needs to be improved.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:44 PM
Color profile: Disabled
Composite Default screen

50 Quantifying and managing disruption claims

7. Improvements need to take account of the fact that the low-


value items, whilst not strictly necessary for estimating, must
be itemised somewhere in the contract. There is a need to
increase the realism of estimating and to create a direct link
between cost and time. The approach in this book seeks to allow
the direct effects of delay and disruption to be evaluated both
in terms of cost and time. It also facilitates sufficiently accurate
construction site control. Further, the approach does not restrict
the contractor’s flexibility in deciding methods of construction
and pricing, and allows tendering on an equal basis.
8. Resource/labour productivity is at the centre of estimating, the
planning process, site control and the evaluation of delays and
disruption. The proposition is that resource productivity should
be used to develop a new approach to modelling cost and time.
In short, a cost model composed of work packages related to
site operations, linked to a time model composed of the identical
work packages, would form a direct tangible link between cost and
time. A single labour and/or plant productivity would characterise
the work package.
Chapter 4 demonstrates the development of such “characteristic
productivity” work package models. The process represents a
synthesis of the operational modelling and significant items
approaches with the distinct advantage that the models are not
project-specific and do not involve highly sensitive model factors.

Thomas Telford\Quantifying and Managing Disruption Claims


Friday, November 15, 2002 3:07:44 PM

You might also like