NORMS:

CEMENT PLANT: CONCRETE QUANTITY (SUBSTRUCTURE + SUPERSTRUCTURE) 0.35-0.45 M3/M2


SHUTTERING (SUBSTRUCTURE + SUPERSTRUCTURE) 10-12 M2/M3
REBAR 85KG/M3
STRUCTURAL STEEL ( WITHOUT CRANE) 50KG/M2
STRUCTURAL STEEL ( WITH CRANE) 190KG/M2
2/9/2010
COLONY: CONCRETE QUANTITY (SUBSTRUCTURE + SUPERSTRUCTURE) 0.5-0.6 M3/M2 0.45
SHUTTERING (SUBSTRUCTURE + SUPERSTRUCTURE) 8-9 M2/M3 5
REBAR 100KG/M3 80
FOUNDATION AT DEPTH 2-3M
SBC = 25 T/M2

CONCRETE NORMS FOR G+1 STOREY

TOTAL CONCRETE FOR STRUCTURE: 0.42 M3/M2


1 0.14M3/M2 SLAB
2 0.15M3/M2 BEAM/COLUMNS
3 0.13M3/M2 FOUNDATION/PLINTH BEAM

SHUTTERING
1 FOUNDATION 5M2/M3 7
2 SUPERSTRUCTURE 8M2/M3 11

PLASTER (TOTAL INTERNAL + EXTERNAL )/ BUILT UP AREA 5-8 M2/M2

loading and packing norms 8/9/2010 9/9/2010 10/9/2010


slab 0.171 0.178 0.15
beams 0.149 0.125
clumns 0.148 0.151
footing+plintb beam 0.055 0.137
total 0.524 0.591