Gasifier 6_ March'16

ID Task Task Name Duration Start Finish Predecessors % Complete


Mode 08 May '16 22 May '16 05 Jun '16 19 Jun '16 03 Jul '16 17 Jul '16
T M F T S W S T M F T S W S T M F T S W
37 Assembly of Breaker drum & Ring 1 day 08/06/16 6:00 PM 09/06/16 6:00 PM 36 0% 0%
38 Assembly of Plough carrier 2 days 09/06/16 6:00 PM 11/06/16 6:00 PM 37 0% 0%
39 Assembly of 705 Segment 12 hrs 11/06/16 6:00 PM 12/06/16 6:00 AM 38 0% 0%
40 Assembly of Cap agent 6 hrs 12/06/16 6:00 AM 12/06/16 12:00 PM 39 0% 0%
41 Assembly of Middle support ring and 704 12 hrs 12/06/16 12:00 PM 13/06/16 12:00 AM 40 0% 0%
42 Segment
Assembly of 703 Segment and Top support 12 hrs 13/06/16 12:00 AM 13/06/16 12:00 PM 41 0% 0%
43 Ring
Assembly of 702 and 701 Segment 6 hrs 13/06/16 12:00 PM 13/06/16 6:00 PM 42 0% 0%
44 Grate Rotation test 4 hrs 13/06/16 6:00 PM 13/06/16 10:00 PM 43 0% 0%
45 Bosman skirt Repair 2 days 13/06/16 10:00 PM 15/06/16 10:00 PM 0% 0%
46 Scaffolding modification for BS Repair 6 hrs 13/06/16 10:00 PM 14/06/16 4:00 AM 44 0% 0%
47 Repair of Bosman skirt 1.5 days 14/06/16 4:00 AM 15/06/16 4:00 PM 46 0% 0%
48 Hydrojetting of scrapper Nozzle 4 hrs 15/06/16 4:00 PM 15/06/16 8:00 PM 47 0% 0%
49 Removal of Scaffolding & House keeping 6 hrs 15/06/16 4:00 PM 15/06/16 10:00 PM 47 0% 0%
50 Gasifier Box Up 3.83 days 15/06/16 10:00 PM 19/06/16 6:00 PM 0% 0%
51 Installation of AL, AL Condenser & associated 36 hrs 15/06/16 10:00 PM 17/06/16 10:00 AM 49 0% 0%
52 piping
CL installation ,assy of associated piping & 18 hrs 17/06/16 10:00 AM 18/06/16 4:00 AM 51 0% 0%
53 Platform
CFC installation & piping and hydraulic 8 hrs 18/06/16 4:00 AM 18/06/16 12:00 PM 52 0% 0%
54 installation
manhole Box up 12 hrs 18/06/16 12:00 PM 19/06/16 12:00 AM 53 0% 0%
55 Deblinding of gasifier lines 18 hrs 19/06/16 12:00 AM 19/06/16 6:00 PM 54 0% 0%
56 Gasifier Handover 2 days 19/06/16 6:00 PM 21/06/16 6:00 PM 0% 0%
57 Leak test 2 days 19/06/16 6:00 PM 21/06/16 6:00 PM 55 0% 0%
58
59 PWHE 0%
60 Blinding of PWHE Lines & Gasifier Jacket 0%
61 Removal of PSV-2 nos 0%
62 Testing of PSV & Calibration 0%
63 Hydrotest 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline