1.1 Project Details


M/s. Venus Organics proposes Dyes & dye intermediates manufacturing unit at Plot No.
81/9, Phase-1, GIDC-Estate, Vatva, Ahmedabad – 382445.

1.1.1 List of Products with their Production Capacity

Sr. Product CAS No./CI No Quantity


No. MT/ Month
REACTIVE REACTIVE ORANGE 2R ORANGE 7
1 ORANGE REA.G YELLOW HR ORANGE 12 15
REACTIVE ORANGE H2R /P2R 12225-85-3/ORANGE 13
REACTIVE ORANGE 3R 12225-88-6/ORANGE 16
REACTIVE GOLDEN YELLOW RNL ORANGE 107
REACTIVE ORANGE ME2RL ORANGE 122
2 REACTIVE REACTIVE RED PBN RED 24
RED REACTIVE P6B/P2B RED 218/ RED 45
REACTIVE RED H8B RED 31
REACTIVE RED 6BX/ BS RED 76/ RED 111
REACTIVE RED HE3B/HE7B/HE8B RED 120/RED 141/RED 152
REACTIVE RED ME3BL/ME4BL /ME6BL RED 194/RED 195/RED 196/250
3 REACTIVE REACTIVE YELLOW 42 (FG) 12226-63-0/ YELLOW 42
YELLOW REACTIVE YELLOW 145 (MERL) 93050-80-7/ YELLOW 145
REACTIVE G YELLOW R/ RR -
4 REACTIVE REACTIVE BLUE HERD/HER/ ME2GL/ 71872-76-9/BLUE 160 /77907-32-5/ 40
BLUE RGB/P2R BLUE 171 / BLUE 194/ BLUE 250
REACTIVE BLUE BB BLUE 220
REACTIVE BLUE H5R BLUE 13
5 REACTIVE REACTIVE BLACK HN 12225-26-2
BLACK REACTIVE BLACK B 12225-25-1
REACTIVE BLACK HFGR -
REACTIVE BLACK RL(31) 12731-63-4/ BLACK 31
6 REACTIVE REACTIVE BROWN 9 12225-66-0/BROWN 9
BROWN (REA.RED BROWN H4R)
REACTIVE BROWN 11
7 REACTIVE REACTIVE PURPLE H3R VOILET 1
VOILET REACTIVE MAGENTA HB VOILET 13
Total 55
1.2 Water Requirement, Waste Water Generation and Treatment
Total water requirement will be 10.6 KL/day which will be met through GIDC water
supply.
Total Ind. wastewater generation will be 4.7 KL/day. Industrial Waste water @ 4.7 KLD:
will be sent to Common Evaporation Facility (M/s. Clean & Green Environment Society
Naroda) after primary treatment in ETP for further treatment.
Domestic effluent @ 1.6 KLD will be disposed off in Septic Tank / Soak Pit.

1.3 Air Pollution Source and Control Management


There will be emission from Boiler (1 Nos.) & Hot Air Generator (2 Nos.). Adequate air
pollution control equipments i.e. MCS will be provided as APCM. Dust Collector will be
provided with Spray Dryer.

1.4 Hazardous Waste


Sr. Type/Name Source of Category and Quantity Disposal Method
No. of generation Schedule as (MT/Annum)
Hazardous per HW Rules.
waste
1 ETP Waste ETP 35.3 12.0 Collection, Storage,
Transportation &
Disposal At TSDF
(Ecocare Infrastructure
Pvt. Ltd.)
2 Discarded Raw Mat. 33.1 48.0 Collection, Storage,
Container/ Supplier Decontamination,
Empty Bags Transportation &
Disposal By Selling To
Authorized Recycler
3 Used Oil Utility 5.1 0.025 Collection, Storage &
Reused As Lubricant In
Plant
1.5 Green Belt
Total 1103 m2 land area is available at site; out of this 150 m2 will be developed as
greenbelt and other forms of greenery.

1.6 Power & Fuel Requirements


Power requirement will be 75 HP which will be taken from Torrent Power.
Fuel: Agro Waste/White Coal= 5 MT/Day

1.7 Estimated Project cost along with analysis in terms of economic viability of the
project.
Total cost of proposed project activity will be Rs. 1.8 Crore. Capital cost for EMS
(Environmental Management System) will be Rs. 0.25 Crore per annum.