You are on page 1of 11

Professionals’ views of material

wastage on construction sites


and cost overruns

Ameh Oko John Daniel Emmanuel Itodo


Department of Building, University Department of Building, University
of Lagos, Akoka, Yaba, Lagos of Lagos, Akoka, Yaba, Lagos
oameh@unilag.edu.ng itododan@yahoo.com

DOI 10.5592/otmcj.2013.1.11 It is believed that building material wastage on construc-


Research paper tion sites account for cost overruns and any improvement
in building materials management on construction sites
has the potential to enhance the construction industry’s
performance with cost-saving benefits. The purpose of this
study is to identify the most wasteful building material during
construction operation. It also sets out to assess the level of
material wastage with various subcontracting options, the
percentage contribution of material wastage to project cost over-
run, identify factors contributing to material waste on building
sites and to examine the relationship between subcontracting
options, project cost overrun and the level of waste generated
from building material. A survey research design was employed.
Responses from 56 site based professionals representing 70%
of the respondents were analysed using both descriptive and
inferential statistics. Results indicate that the most wasteful
building material during construction operation is mortar from
plastering/rendering; labour-only subcontracting options have
high contribution to material wastage. Furthermore, the study
revealed that the average percentage contribution of building
material wastage to project cost overrun is between 21-30%;
Poor supervision, re-work, and poor material handling were
identified as dominant factors that have high contribution to
material wastage on sites. Finally, the result also shows that
Keywords there is a relationship between subcontracting options, cost
Material wastage, overrun and waste generated from building material during con-
Cost overruns, struction. Measures to reduce material wastage on construction
Contractual options, sites were proposed.Improvement in building materials man-
Construction, Nigeria agement on construction sites has the potential to enhance the
construction industry’s performance with cost-saving benefits.

j. o. ameh · e. d. itodo · professionals’ views of material wastage on construction sites and cost overruns · pp 747-757 747
INTRODUCTION therefore follows that wastage of mate- struction, renovation and demolition
It has been observed that the construc- rials will lead to increase in total cost of work places or sites of building and civil
tion industry remains a major economic building project. This assertion is sup- engineering structures. Formoso, Isatto,
sector, but the pollution generated from ported by Teo et al. (2009) who opined and Hirota (1999) defines construction
construction activities continuously that building material wastage on con- waste as any inefficiency that results in
present a major challenge to environ- struction sites contributes to cost over- the use of equipments, labour, materi-
mental management (Tam, Shen and run. This implies that any improvement als, or capital in larger quantities other
Tam, 2007). Construction waste has in building material wastage level on than those considered in the produc-
caused serious environmental prob- construction sites has the potential to tion of a building. According to Shen
lems in many large cities (Bagum et al. enhance the construction industry per- et al. (2002), building material wastage
2006; Chan et al. 2002; Teo and Loose- formance with cost-saving benefits. is defined as the difference between
more, 2001). Teo, Abdelnasar and Abdul Numerous studies on construction the value of materials delivered and
(2009) observed that extra construction material wastage have been carried out accepted on site and those properly
materials are usually purchased due to in various countries. Previous studies used as specified and accurately mea-
material wastage during construction. in Nigeria, centers on waste manage- sured in the work, after deducting the
Previous studies from various countries ment practice (Akinkurolere and Frank- cost saving of substituted materials
have confirmed that waste represent rel- lin 2005; Dania, Kehinde and Bala, 2007 transferred elsewhere, in which unnec-
atively larger percentage of production and Ajayi et al, 2008). Shen, Tam, Ho essary cost and time may be incurred by
cost. For example, Skoyles in Tam et al. and Tam (2002) observed that in Hong material wastage. Formoso, Soibelman,
(2007) in a UK study reported an addi- Kong, construction and demolition De Cesare, and Isatto (2002) observed
tional cost of 15% to construction proj- activities generate thousand tones of that the notion of waste is directly asso-
ects cost overruns as a result of mate- solid waste every year. In another study ciated with the debris removed from site
rial wastage. A study conducted by the in Hong Kong, Chu (2004) identified the and disposed off in land fills. Formoso et
Hong Kong Polytechnic and the Hong contribution of the following materi- al. (2002) asserts that the main reason
Kong Construction Association (1993) als waste to the total project cost: con- for this relatively narrow view of waste
put material waste contribution to cost crete 4%, block work 10%, waste from is perhaps the fact that it is relatively
overruns at 11%. Bossink and Bounw- screeding and plastering 15%, packag- easy to see and measure. Although as
ers (1996) in a similar study of mate- ing 5% and that of formwork is based important as such concept is from envi-
rial wastage in the Netherlands con- on the number of times it is re-used. ronmental perspectives, this idea has
cluded that material wastage account Rogoff and William (1994) pointed out been criticized since the beginning of
for between 20-30% of project cost that 29% of the solid wastes in the USA industrial engineering.
overruns. are construction waste, and these waste Keal, (2007) further stressed that
Hore, Kehoe, McMillan and Penton remains at an average of 15% growth any substance or object that are dis-
(1997) cited in Ajayi, Koleoso, soyingbe every year. carded, intend to be discarded, or are
and Oladiran (2008) opined that in every Based on these, identifying the required to be discarded is waste and
100 houses built; there is enough waste extent of waste generated by the vari- such is subject to a number of regula-
material to build another 10 houses. ous building material and their implica- tory requirement. Dania et al. (2007)
Over 70 million tonnes of waste is pro- tion on final project cost in the Nigerian assert that Construction and Demoli-
duced in the UK construction industry building industry will be of immense tion waste is a complex waste stream,
each year. This amounts to 24kg per benefits both to the environment and made up of a wide variety of materials
person, per week in the UK, about four the construction industry of develop- which are in the form of building debris,
times the rate of household waste pro- ing economies. Hence the need for the rubble, earth, concrete, Steel, timber,
duction (CIRIA, 1999). It is therefore present study which aims at examining and mixed site clearance materials, aris-
glaring that the economic losses from the effect of material wastage on con- ing from various construction activities
construction material wastage could struction sites on cost overruns. including land excavation or formation,
pose a great threat to the economic civil and building construction site,
growth of a nation. Concept of material waste clearance, demolition activities, road-
There is a growing consensus within There are different views held by work, and building renovation. Accord-
the built environment in Nigeria that researchers as to what constitute con- ing to Formoso et al. (2002) the concept
building materials account for over 50% struction waste. Cheung (1993) defined of material wastage in lean production
of the total cost of a building project construction wastes as the bye- prod- paradigm is seen as resources that do
(Akinkurolere and Franklin, 2005). It uct generated and removed from con- not add value to the final product.

748 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 5(1)2013


Previous studies on material fill annually with 15.4 million tonnes argued that the best way to minimise
wastage from construction and demolition waste is to prevent it from occurring
Previous studies have confirmed that waste, which account for 23% of total in the first instance. In view of this,
the construction industry generates waste disposed in the landfill (Yu et al, Perry and Kristy, (2007) undertook a
high level of waste from material 2012; EPD, 2010). Tam et al, (2007) con- research on the Australia construction
usage. For instance, the construction ducted a research in Hong Kong aimed industry which was aimed at assessing
industry consumes 3 billion tonnes at assessing the wastage levels of dif- brick waste on domestic construction
of raw materials annually while one ferent building material on construc- site with a goal to identifying possibil-
quarter of the world timber is used in tion sites. The specific objectives of the ity of minimisation of its occurrence in
the construction industry (UNEP, 2007; study were to identify the most waste- the future. The study was conducted
WGBC, 2010). In reality, some of these ful material on Hong Kong construction on 23 medium density housing and 20
material will eventually end up as con- site, with specific focus on concrete, detached building project in Sidney.
struction and demolition waste. block, tiles, reinforcement and form- Quantitative and qualitative approach
In the United States, 136 million work and to also determine how public was used by the researchers in collect-
tonnes of construction and demolition and private projects and subcontract- ing the data. The study concluded that
waste are sent into the landfill annually ing options affect the levels of mate- waste from brick is the highest waste
which amounts to about 30% waste rial wastage on sites in Hong Kong. To by weight generated on domestic con-
from the industry (Mclaren, 2009). achieve these, 19 construction proj- struction site in Australia. The study
According to (Napier, 2012), waste in ect were investigated between 2003 further confirmed that 75% of the waste
construction occurs in various con- and 2005 and quantitative approach from bricks is due to cutting and it was
struction stages ranging from foun- was used. The study identified the fol- recommended that a change in design
dation works to finishing and they lowing percentage wastage in the fol- of bricks could reduce the amount of
emanate from wooden materials, con- lowing building materials with labour waste generated on site. Although
crete, gravels, aggregate, masonry, only subcontracting option; concrete waste from brick/blocks can be reused
metals, plastic, plumbing and electri- 8.99%, reinforcement 7.7%, form- or recycled, the construction industry
cal fixtures, glass and material han- work, 20%, block/brick 8.9%, and could also device strategy for prevent-
dling. A more recent study in the United tiles 15.58%. The study concluded that ing it from occurring.
State between (2009-2010) from the the most wasteful material on Hong In Brazil, various researchers have
processing of 20,000 tonnes of con- Kong construction site is wood form- attempted to investigate material
struction and demolition waste iden- work while labour only subcontracting waste on construction site (Formoso
tified the following percentage wast- option and public project generates et al. 2002; Junior, 2009; Saraiva et al.
age of some building materials; wood the highest level of waste. However, 2012). Although at the general level,
30%, concrete 5%, gravels, aggregate the Government of Hong Kong has now Brazil has not established the quantity
and fines, 20%, dry wall 3%, Asphalt implemented the Construction Waste of construction and demolition waste
roofing 5%, ferrous and non-ferrous Disposal Charging Scheme (CWDCS) to that goes to landfill annually, informa-
metals, 9%, plastic 1%, cardboard help regulate the amount of waste that tion exist for the amount of C&D waste
and paper 3% and disposal as refuse can be taken to landfill (Yu et al. 2013). from major locations of the country
5% (Napier, 2012). Although the study This initiatives will not only minimise (Angulo et al. 2009; Junior et al. 2009).
concluded that the predominant waste the quantity of waste generated on site Brazil construction industry consumes
stream in the United States comes from but will also help the construction par- 75% of its natural resources, 44% of
wood, wood however presents a high ticipants develop a holistic approach total energy in use and accounts for
potential for reuse in construction and to construction waste elimination and 40% of the total waste generated in the
in other industry such as manufactur- management. According to Yu et al. country (Saraiva et al. 2012). A study
ing. The US Government in its effort to (2012) the first three implementation by Brito Filho (in Junior et al. (2009)
reduce the impact of building material of CWDCS has recorded a significant observed that the average waste mate-
waste on the environment has imple- reduction in construction and demoli- rial on construction site in Brazil com-
mented the green rating criteria for tion waste (C& D) in Hong Kong. posed of; 33% concrete and mortar,
all building project to further improve The Australia construction industry 32% soil, 30% ceramics and 5% others.
the environmental performance (Ama- generates about 13,000 million tonnes Similarly, (Angulo et al. 2003; Angulo
truda, 2012). of waste which amounts to about 42% et al. 2009) further confirmed that
In Hong Kong, an increasingly large of the total waste generated in Austra- almost all C&D waste in Brazil come
quantity of waste are sent into the land- lia (ABS, 2013). Baldwin et al. (2009) from masonry and concrete material.

j. o. ameh · e. d. itodo · professionals’ views of material wastage on construction sites and cost overruns · pp 747-757 749
Gihan, Ahmed, and Andel’s (2010) Variable Frequency % cumulative %
study in Egypt focused on minimising
Nature of Organization
and controlling the incidence of mate-
rial waste from its source. Due to the Contractors 36 64.3 64.3
absence of an accurate database on Client/property developers 17 30.4 94.6
the rates and causes of material waste
All of the above 3 5.3 100
in the Egyptian Construction Industry,
the authors found it essential to build Duration of operation
their research on an in-depth study that
Below 5years 8 14.3 14.3
would cover the current situation. The
study revealed that the highest waste 5-10 years 10 17.9 32.1

rates (13% in average) were related to 11-15 years 11 19.6 51.8


timber frameworks. However, its impact
16-20 years 5 8.9 60.7
on the environment is less negative than
for other materials since it is sold at Above 20 years 22 39.3 100
the end of the project to scrap dealers
which in turn use them for minor jobs. Table 1 Respondents’ Organizational Details
Steel, and cement waste rates seem to
be within the average allowable rates terwork. Others are cement (10.3%), the level of waste generated from vari-
of 7% and 5% respectively. This may be common bricks (7.4%), mortar in brick ous building material during construc-
due to their high cost in the bill of quan- work (7.2%), face bricks (6.9%) and tion on site.
tities which would have led to higher concrete (5.7%).Ayarkwa and Adinyira
effort from contractors to control their (n.d cited in Agyekum, Ayarkwa and Research method
waste. Previous results from cement Adinyira, 2012) report of a wide varia- A questionnaire was used as the prin-
waste seem to contradict national data tion in wastage rates between 5% and cipal instrument for eliciting responses
on cement consumption which suggest 27% of total materials purchased for on the levels of material wastage on
that 50 % of cement consumption is construction projects in Ghana. construction site from the target respon-
unaccounted for. Uncompleted design dents. The survey instrument consists
and untrained labour were among the Research hypothesis of two sections. Section (A) sought to
most dominant causes of waste gen- Two hypotheses were postulated for this know the profile of the respondents and
eration. Ignorance of specifications, study. First, the study sought to know that of their organization. Information
resource surplus, and theft actions if any significant relationship exists on section (A) are meant to moderate
showed minor effect on waste genera- between the types of subcontracting the main part (section B). In section
tion rates for the study. arrangements used and level of mate- B, the respondents were required to
Akanni’s (2007) study of 146 building rial wastage generated on site. Hence, identify the frequency of use of four
projects in Nigeria identified percent- hypothesis one states: subcontracting arrangements identi-
age contributing of various sources to H0: There is no significant relation- fied using five point Likert scale rang-
material wastage on site. These include: ship between labour only, direct labour, ing from 1- 5, (where 1= not at all, 2=
site storage (43%), transportation and material & labour and direct labour & rarely 3= sometimes 4 = frequently 5 =
delivery to site (14%), pilfering and theft labour only subcontracting arrange- very frequently). The respondents were
(14%), wrong specification (6%), intra- ments and the level of wastes gener- also required to indicate from experi-
site transit (5%), fixing (5%), wrong use ated from building materials during ence, the extent each of the four sub-
(5%), conversion waste (3%), negligence construction on sites. contracting arrangements contribute to
(3%) and management (2%). The limita- The study also sought to know if material wastage on site by responding
tion of Akanni’s(2007) study is that it is there is a relationship between project to 5 point Likert scale ranging from 1=
based on perception rather than objec- cost overrun and the level of material “very low”, 2 = “low”, 3 = “medium”,
tive measure of waste from the sources wastage for various building materials 4= “high”, 5= “very high”. The respon-
mentioned. In a related study conducted on construction sites. For this purpose dents were also required to rate four-
on 12 building sites in Botswana, Urio hypothesis two of the study was postu- teen (14) identified building materials in
and Brent (2006) reported an average lated and states thus: the order of their level of wastage during
percentage waste of 13% for sand, 11% H0: There is no significant relation- construction activities on site based on
for stone and 11% for mortar in plas- ship between project cost overrun and their experience using 5 point Likert

750 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 5(1)2013


Levels of material wastage and sub-contracting options
result presented in Figure 1 shows that
Labour only sub-contracting option
3.5 (mean = 3.41) have high contribution
to material wastage on construction
3 sites, this was followed by labour only
& direct labour option and direct labour
2.5 only with mean response of 2.96 and
2.88 respectively. The results also
2 reveal that material and labour option
with mean response of 2.55 have
1.5 medium contribution to material wast-
age on construction sites. It’s not sur-
1 prising that labour only subcontracting
option contribute highest to material
0.5 wastage. This is because the main con-
tractor bears cost of waste generated in
0 this arrangement as identified in Tam
et al. (2007).
Labour Direct Material & Labour Only &
Only Labour Labour Direct Labour Degree of building material wastage
on construction sites.
Figure 1 Levels of material wastage and sub-contracting options
The study sought to know the most
wasteful material during building
scale ranging from 1= “very low”, 2 = Results and discussion construction activities on sites. The
“low”, 3 = “medium”, 4= “high”, to 5= respondents were required to rate
“very high”. Furthermore, the respon- Organizational details of the identified materials in the order
dents were required to indicate the per- respondents. of their level of wastage during build-
centage contribution of each of the four- The study sought to know the details ing construction activities on site
teen (14) identified building materials of the respondents’ organization. This based on their experience by respond-
wastage to project cost overrun based is presented in Table 1. The analysis ing on a 5-point Likert scale ranging
on their experience on a Likert scale of shows that 64.3% are contracting orga- from 1- 5 [1= “very low”, 2 = “low”, 3 =
0-5 where 0= below 10%, 1 = 10-20% nization, 30.4% are client organization “medium”, 4= “high”, 5= “very high”].
2= 21-30% 3 = 31-40% 4= 41- 50% 5 while 5.3% practice both. The result of the analysis is presented
= above 50%. Finally, the respondents Only 14.3% of the companies have in Table 2. The result reveals that out of
were required to rate sixteen (16) identi- below 5 years experience in construc- 14 most frequently used building mate-
fied factors that contributes to material tion, 17.9% have been in operation for rials investigated, mortar from plas-
wastage on site in order of magnitude 5-10 years, 19.6% have been in opera- tering/rendering top the list of most
based on their experience by respond- tion for 11-15 years, 8.9% have been wasteful material with mean score
ing on scale 1-5 [1= “very low”, 2 = operation for 16-20 years while those of 3.32. This was followed by timber
“low”, 3 = “medium”, 4= “high”, 5= with over 20 years experience in opera- formworks, with mean score of 3.23,
“very high”,]. tion has the highest response of 39.3%. sandcrete blocks, with mean score
Questionnaire were distributed by This implies that the respondents orga- of 3.16, concrete with mean score of
hand to construction managers, site nization have adequate experience 2.79 and ceramic/vitrified tiles with
managers, chief estimators, site engi- in construction operation and hence mean score of 2.70 in that order. The
neers, project managers and other information on material wastasge results also reveal building materials
key personnel involved in construc- obtained from them will be reliable. that have low wastage level during con-
tion operations using random sam- struction activities on sites. These are
pling technique. First, population was Material wastage and Steel formwork with mean score of 1.5,
stratified based on organisational types sub-contracting arrangement Long span aluminum roofing sheet with
(client, and contracting organisations), The study sought to know how each mean score of 1.88, Iron bar with mean
followed by simple random sampling sub-contracting arrangements contrib- score of 2.14, Paints with mean score
utes to material wastage on sites. The of 2.16 and fibre cement roofing sheet

j. o. ameh · e. d. itodo · professionals’ views of material wastage on construction sites and cost overruns · pp 747-757 751
Mean is buttressed by a study in Egypt by
Building materials N Rank
response Gihan, Ahmed, Adel (2010) which reveal
Mortar from plastering /rendering 56 3.32 1
that steel reinforcement has low per-
centage of wastage of about 5% com-
Timber formworks 56 3.23 2 pare to 20% for sand in their study.

Sandcrete blocks 56 3.16 3 Percentage contributions of material


wastage to cost overrun
Concrete 56 2.79 4
The study sought to know the percent-
Ceramic/Vitrified tiles 56 2.70 5
age contributions of wasted building
material to project cost overrun. The
Clay tiles 56 2.66 6 respondents were required to indicate
the percentage contribution of each of
Wood used for flooring 56 2.52 7 the identified building materials wast-
age to project cost overrun based on
PVC tiles 56 2.36 8
their experience by responding on
Bricks 56 2.27 9 Likert scale ranging from scale 0-5 [0=
below 10%, 1 = 10-20% 2= 21-30% 3 =
Fibre- cement roofing sheets 56 2.21 10 31-40% 4= 41- 50% 5 = above 50%].The
weighted mean average is used in the
Paints 56 2.16 11 interpolation of the percentage for each
of the building material. (i.e. building
Iron bars 56 2.14 12
material with mean response average
Long span aluminum roofing sheets 56 1.88 13 = 0.5 will be on scale 1, while those
with mean response average =1.5 will
Steel formworks 56 1.50 14 be on scale 2, in that order). The result
of the analysis is presented in Tables
Table 2 Rank order of material wastage on construction site 3. The result in Table 3 shows the mean
and percentage contribution of each
with mean score of 2.21. The finding work 10%, and packaging 5%. Formoso building material to project cost over-
reported in this study tends to sup- et al (2002) observed that wastage in run. The results reveal four building
port the outcome of earlier studies that concrete could also occur as a result materials that have between 31-40%
the most wasteful building material of failure in formwork and means of contributions to project cost overrun
on construction sites is mortar from transportation. Non adherence to mix from it wastage during construction
plastering/rendering (Formoso et al. design can also contribute to wastage activities on sites. These are concrete
2002). Formoso et al’s (2002) study in concrete. Tam et al (2007) noted that with mean score of 3.0, which ranked
attributed the high wastage level in the cause of wastage in timber form- first. This was followed by mortar from
mortar from plastering/ rendering to work is due to natural deterioration plastering/rendering with mean score
lack of modular coordination in the and waste from cutting. The wast- of 2.6, sandcrete block with mean of
structural elements and deviation from age level in timber formwork can be 2.5, and timber formwork with mean
the actual design. This implied that as high as 20% in foundation works. score of 2.5, in that order. The results
more mortar will be used on such ele- The high wastage level of timber form- also reveal other categories of building
ments such as beams and column that work in foundation could be due to the materials that has percentage contri-
have deviated from the initial design. wet nature of most foundation works, bution of between 21-30% to project
Excessive mortar could also be used in which encourage the deterioration of cost overrun. Majority of the building
block work joints if the blocks are not timber It is worthy of note that both dry material are in these categories. These
uniform in their sizes. Chu (2004) in a and wet weather has effect on timber are Iron bars with mean score of 2.4,
similar study in Hong Kong identified formwork. The result also revealed that Ceramic/ vitrified tiles with mean score
the percentage contribution of vari- the building materials with low level of 2.3, Clay tiles, Fibre cement roofing
ous construction materials to waste on of wastage are made from Steel. This sheets, wood used for Flooring and
site. These include mortar from plaster- could be due to their durability and the Bricks with mean score of 2.1apiece,
ing/ screeding 15%, concrete 4%, block ease of re-use over time. This point PVC tiles with mean score of 2.0, Paints

752 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 5(1)2013


with mean score of 1.9 Long span alu- Building materials Percentage N Contribution Mean Rank
minum roofing sheets with mean score
of 1.9 and Steel formwork with mean Concrete 56 31-40 3.0 1
score of 1.7, which ranked least. Table
3 shows the percentage contribution Mortar from plastering /rendering 56 31-40 2.6 2
of various building material wastage
on construction site to project cost Sandcrete blocks 56 31-40 2.5 3

overrun. A recent study in Nigeria by


Timber formwork 56 31-40 2.5 3
Ameh, Soyingbe and Odusami (2010)
identified waste on sites as one of Iron bars 56 21-30 2.4 5
the factors that contribute to project
cost overrun. From Table 3 the four (4) Ceramic/Vitrified tiles 56 21-30 2.3 6
top ranked building material that has
high percentage contribution to proj- Clay tiles 56 21-30 2.1 7

ect cost overrun are concrete (mean


Fibre- cement roofing sheets 56 21-30 2.1 7
= 3.0), Mortar from plastering (mean
=2.6), sandcrete block (mean = 2.5) and Wood used for flooring 56 21-30 2.1 7
timber formwork (mean = 2.5) in their
order of importance. The percentage Bricks 56 21-30 2.1 7
contribution from these building mate-
PVC 56 21-30 1.0 11
rials wastage to project cost overrun
is between 31-40%. From literature it
Paints 56 21-30 1.9 12
has been observed that waste from
plastering is ranked highest. Two inde- Long span aluminum roofing
56 21-30 1.9 13
pendent studies by Pinto and Agopyan sheets

(1994) and Soibelman (1994) in Brazil, Steel formworks 56 21-30 1.7 14


identified highest wastage level of 46%
and 48% for mortar, and 12% & 2% for Table 3 Percentage Contributions of material wastage to cost overrun
concrete respectively. Although mortar
has been identified as the most waste- always avoidable .It occurs throughout The result of the analysis presented
ful material on construction sites, it the industry irrespective of the size of in Table 4 reveal five high contributory
does not have the highest percentage the building, organization, the value factors to material wastage on con-
contribution to project cost overrun but and duration of the contract or variety struction sites. These are poor super-
concrete does as it is showed in their of the building types. It is worth noting vision, which ranked first with mean =
mean average. This could be so since that the least and the highest percent- 3.79, followed by re-work with mean=
the cost of producing (1m3) of concrete age contribution of material wastage to 3.75, and poor material handling,
could produce (10 m3) of mortar. This cost overrun is between 21-30% and design related errors, and inadequate
implied that wastage from concrete 31-40% respectively. The average per- workers’ skill with mean = 3.71, 3.59
contribute more to project cost over- centage contribution of building mate- and 3.54 respectively. The remaining 10
run even at very low wastage rate. rial wastage to project cost overrun is identified factors have medium contri-
The percentage contribution of between 21-30% this finding tends to bution to material wastage during con-
majority of the building materials wast- support the assertion of Bossink and struction activities on site. This find-
age to cost overrun is between 21-30% bornwers (1996) who observed that ing is consistent with an earlier study
and none of the identified building 20-30% of building material purchased in Nigeria (Dania et al. 2007) in which
materials has a percentage contribu- end up as waste on site which can be poor supervision, poor workmanship,
tion below 20%.This is a clear evidence viewed as their percentage contribu- facilities for storage and re-work were
that wastage and it resultant effects of tion to project cost overrun. identified as having high contribution
additional cost on project is present in to on- site material wastage. This find-
every building material, although the Factors that contributes to material ing shows the need for proper train-
extent may varies from one building wastage on construction sites. ing for all site personnel ranging from
material to another. According to Teo The study sought to know the factors the site manager to various work pack-
et al.(2009) material wastage is not that contribute to material wastage. ages headsmen on material wastage

j. o. ameh · e. d. itodo · professionals’ views of material wastage on construction sites and cost overruns · pp 747-757 753
Material wastage Mean
N Rank
Contributory factors response According to Skoyles and Skoyles as
cited by Tam et al (2007) different sub-
Poor supervision 56 3.79 1
contracting arrangements could cause
Re-work 56 3.75 2 different extents of material wastage.
Hypothesis two was tested at
Poor material handling 56 3.71 3 p-value ≤ 0.01. The result as presented
in Table 6, indicates that the rho value
Design related errors 56 3.59 4
= 477*** and p-value = (0.000). This
p-value is less than the critical p-value
Inadequate workers’ skill 56 3.54 5
(0.01) .Therefore the alternate hypoth-
Inappropriate specification 56 3.29 6 esis is accepted. It implied that the
higher the level of material wastage
Buildability problems 56 3.27 7 the higher the project cost overrun.
According to Hammassaki and Neto
Improper packaging 56 3.25 8
(1994) and Pinto and Agopayan (1994),
Lack of management of 20-30% of construction material are
56 3.14 9
the design process wasted during construction opera-
tion. The equivalent of these materials
Construction related error/omission 56 3.12 10
must be purchased to make up for the
Theft and vandalism 56 3.11 11 waste which amount to additional cost
to the project. Akinkurolere and Frank-
Lack of integration of waste lin (2005) stated that material wast-
reduction- plan in the design and 56 3.09 12
construction proces age brings extra cost to the construc-
tion project as well a reduction in con-
Negligence and care free attitude
56 3.04 13 tractor’s profit. In this study, mortar,
of management
timber formwork, sandcrete block and
Lack of waste management plan 56 2.79 14 concrete ranked as the most wasteful
material during construction opera-
Absence of site waste manager 56 2.68 15
tion on site whilst concrete, mortar
sandcrete block and timber formwork
Table 4 Factors that Contributes to material Wastage on Construction site
ranked as the most contributory factor
to cost overrun.
on site. According to Enakayake and relationship exist between labour only,
Ofori (2000) the best way to control direct labour, material & labour and
waste is to prevent it occurrence in the direct labour and labour only subcon- Summary of study
first place. tracting arrangements and the level of Consensus is that the cost of building
wastes generated from building materi- material alone constitute over 50% of
Test of hypotheses als during construction on sites. construction project cost in Nigeria.
Hypothesis one was tested using chi- This result is consistent with an ear- In Nigeria, the construction industry
square test at p ≤ 0.05.The result of the lier study in Hong Kong by Tam et al accounts for 70% of the gross domes-
test is presented in Table 5. As shown, (2007) which shows that waste gener- tic product. It is generally believed
the chi-square values ( x2) for labour ated on construction sites has a direct that building material wastage during
only, direct labour, material & labour link with subcontracting arrangements. construction operations contributes to
and direct labour and labour only Labour only subcontracting arrange- project cost overrun. This means that
are 9.536, 19.179, 17.214 and 25.857 ments tends to generate more waste on any improvement in building material
respectively while their p-value are site since labour only subcontractors wastage level on construction sites
0.049, 0.001, 0.002 & 0.000 respec- do not pay for the wastage but main has the potential to enhance the con-
tively. These p-values are less than contractor does (Tam et al, 2007). It’s struction industry’s performance with
the critical p-value = 0.05. Therefore worth noting that no matter the type cost-saving benefits. To achieve the
the alternate hypothesis is accepted. of subcontracting arrangement chosen objective of the study, the following
The result indicate that a significant material wastage will still occur. research questions were formulated:

754 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 5(1)2013


tion to material wastage on sites. The
Variables compared X2-value df p-value Decision
study further established that signifi-
Labour only & level of waste cant relationship exist between sub-
9.536 4 0.049 Accept H1
generated contracting options, cost overrun and
Direct labour only and level waste generated from building material
19.214 4 0.002 Accept H1
of waste generated during construction.
Material & labour and level
17.214 4 0.001 Accept H1 CONCLUSIONS
of waste generated
The findings of this study serve
Labour only & direct labour
25.857 3 0.000 Accept H1 as the basis for making the following
and level of waste generated
conclusions:
Table 5 Chi-square test (X 2) of independence computed for the relationship XX The most wasteful building material
between sub-contracting arrangements and level of waste during construction operations on
generated on site site is mortar from plastering/ren-
dering and it is due to lack of modu-
lar coordination in the structural ele-
Wastage Cost overrun ments and deviation from the actual
design.
Wastage level Pearson Correlation 1 0.477 XX Labour only subcontracting options
contribute most to building material
Sig.(2-tailed) 0.000 wastage during construction activi-
ties on sites as compared with other
Cost overrun Pearson correlation 0.477 1
options.
Sig(2-tailed) 0.000 XX Material and labour subcontracting
options has low contribution to mate-
** Correlation is significant at p ≤ 0.01 level (2-tailed) rial wastage on construction sites.
Table 6 Pearson Correlation test showing the relationship between the level XX The average percentage contribution
of material wastage on site and project cost overrun of building material wastage to proj-
ect cost overrun is between 21-30%.
XX None of the identified building mate-
which of the building material consti- contractors and private developers rials wastage has below 20% contri-
tute the most wasteful construction within Lagos metropolis. Fifty six (56) bution to project cost overrun.
material on site, what is the percent- questionnaires were completed and XX There is significant relationship
age contribution of material wastage returned representing an aggregate between the level of waste gener-
to cost overrun, What are the factors response rate of 70%. Frequency, per- ated from various building materials
that contribute to material wastage on centages, mean score, Pearson cor- on construction sites and the types
sites and to what extent does subcon- relation coefficient, and Chi-square of subcontracting arrangement used
tracting options contributes to material were used in analysis data collected by the contractor.
wastage on site? for the study.
Two hypothesis were postulated Findings show that the most waste- Study limitation
for the study to test the relationship ful building material during construc- This study adopts a survey research
between subcontracting options, tion operation is mortar from plaster- design and relies on profession-
project cost overrun and the level of ing/rendering. It further reveals that als’ perception of material wastage
waste generated from building mate- labour only subcontracting options during construction operation which
rial during construction operations. have high contribution to material is considered a subjective assessment.
A cross-sectional survey research wastage. The study show that the Future study should adopt a case study
design was adopted for the study. average percentage contribution of research design and actual measure-
Questionnaires were used as the prin- building material wastage to project ment of materials wastage and associ-
cipal instrument for collecting the pri- cost overrun is between 21-30%. Poor ated cost overruns.
mary data from the respondents. Total supervision, re-work, and poor mate-
samples of eighty (80) respondents rial handling in that order were identi-
were drawn from register of building fied as factors that have high contribu-

j. o. ameh · e. d. itodo · professionals’ views of material wastage on construction sites and cost overruns · pp 747-757 755
References of precasting methods and traditional Macmillan press Ltd London.

(ABS) Australia Bureau for Statistics, 2013. construction”, Renewable energy, 34(9), Junior, A.C., L., and Fucale, S. (2009),
The Waste Wise Construction Programme. pp2067-2073. “Quantitative Assessment of Waste
[online]. Available :http://www. Bossink, B.A.G. and Brouwers, H. J.H. (1996), Management in Brazilian Construction
abs.gov.au/ausstats/abs@.nsf/ “Construction Waste Quantification and Sites”, Proceedings Sardinia 2009, Twelfth
Previousproducts/1301.0Feature%20Article2 Source Evaluation”, ASCE Journal of International Waste Management and
52003?opendocument&tabname=Summary& Construction Engineering and Management, Landfill Symposium, S. Margherita di Pula,
prodno=1301.0&issue=2003&num=&view= 122(1), pp55-60. Cagliari, Italy.
[Accessed: 26/05/2013] Cheung, C.W. (1993), “Reduction of Construction Keal L. (2007), “Reducing material wastage in
Agyekum, K., Ayarkwa, J. and Adinyira, E.(2012). Waste”, Final Report. The Hong Kong construction”. Available (online) at www.
“Consultants’ perspectives on materials Polytechnic University, Hong Kong. wrap .org.uk/construction.
waste reduction in Ghana”, Engineering Chu, E. (2004), “Waste Minimization”, Building Accessed: 10/3/2010.
Management Research, 1(1), pp138-150. and environment, 39 (7), pp851-861. McLaren, W., (2009) US Buildings Account for
Akanni, P. O. (2007). “An empirical survey of the CIRIA (1999), “Waste Minimization and Recycle in 40% of Energy and Materials Use. [online].
effect of materials wastage on contractors’ Construction”, Boardroom Handbook. Available at: http://www.treehugger.com/
profit level in construction projects”, The sustainable-product-design/us-buildings-
Dania, A.A., Kehinde, J.O. and Bala, K. (2007),
professional Builders, pp35-46. account-for-40-of-energy-and-materials-
“A study of construction material waste
Akinkurolere, O.O. and Franklin, S.O. (2005), use.html, Accessed: 25/05/2013
management practices by construction
“Investigation into waste Management on firms in Nigeria”, Building Research Reports Napier, T., (2012). “Construction Waste
Construction sites in South Western Nigeria”, series, Caledonia University, Scotland UK, Management”, National Institute of Building
American Journal of Applied Sciences, 2 pp121-129 Science, Available [online]. at :http://www.
(5),pp980-984. wbdg.org/resources/cwmgmt.php
Ekanayake, L.L. and Ofori, G. (2000),
Ajayi, O.M., Koleoso, H.A., Soyingbe, A.A. Accessed: 25/05/2013].
“Construction Material Waste Evaluation”
and Oladiran O. J. (2008), “The practice of in Proceedings of strategies for sustainable Perry, F., and Kirsty, M. (2007), “Assessing
waste management in construction sites Built Environment, Pretoria, South Africa, brick waste on domestic construction sites
in Lagos state; Nigeria”, The construction pp23-25.(EPD) Environmental Protection for future avoidance” Available [online]
and building research conference of the Department, (2010), “Monitoring Solid Waste at: http://epress.lib.uts.edu.au/research/
Royal Institute of Charted Surveyors, Dublin in Hong Kong”, Waste Statistics for 2009. handle/10453/11232?show=full [Accessed:
Institute of Technology 4-5 September. EPD, Hong Kong SARG. 25/05/2013]

Amatruda, J., (2012), “Evaluating and Formoso, C. T., Isatto, E. L., and Hirota, E. H. Pinto T. P. and Agopayan.V. (1994),
Selecting Green Products”, Available (1999). “Method for waste control in the “Construction Waste as raw Materials for Low-
[online] at: http://www.wbdg.org/ building industry”, In Proceedings IGLC cost Construction Products”, 1st Conference
resources/greenproducts.php, [Accessed: (Vol. 7, p. 325). of Charted Institute of Building. Centre for
25/05/2013]. Construction and Environment, Gainesville
Formoso, C. T., Soibelman, L., De Cesare, C.,
Ameh, O.J., Soyingbe, A. A and Odusami, K.T. pp335-342.
and Isatto, E. L. (2002), “Material waste
(2010), “Significant Factors Causing Cost in building industry: main causes and Rameezdeen, R. and Kulatunga, U. (2004),
Overrun in Telecommunication Projects prevention”, Journal of Construction “Material wastage in construction sites:
in Nigeria”, Journal of Construction in Engineering and Management, 128(4), 316- identification of major causes”, Journal
Developing Countries, 15(2), pp 49-67. 325. of Built-Environment Sri Lanka, Vol. 4(2),

Angulo, S. C., John, V. M., Kahn, H. and Ulsen, C. pp35-41.


Gihan L.G., Ahmed R. A, and Adel, E.G (2010),
(2003), “Characterisation and recyclability “Material Waste in Egyptian Construction Rogoff, M. J. and William, J. F. (1994), Approaches
of construction and demolition waste in to Implementing Solid waste Recycling
Industry” PhD Thesis at the Faculty of
Brazil”, In international conference on the Facilities, Park Ridge, N.J. Noyes.
Engineering, University of Cairo, Egypt.
environmental and technical implications Saraiva, T. S., Borges, M.M., and Filho, A.C.,
Hammassaki L.T. and Neto, C.S. (1994),
with alternative materials, ISCOWA, San (2012), “The Importance of Recycling of
“Technical and Economic aspect of
Sebastian. Construction and Demolition Waste”,
Construction demolition Waste Utilization”, PLEA2012 - 28th Conference, Opportunities,
Angulo, S. C., Ulsen, C., John, V. M., Kahn, H.,
Sustainable Construction, 1st Conference of Limits & Needs Towards an environmentally
and Cincotto, M. A. (2009), “Chemical–
mineralogical characterization of C&D waste Charted Institute of Building. Centre for responsible architecture Lima, Perú 7-9
recycled aggregates from São Paulo, Brazil”, Construction and Environment, Gainesville November 2012
Waste management, 29(2), pp721-730. pp395-403. Shen, L.Y., Tam, V.W.Y., Tam, C.M. and Ho, S.
Baldwin, A., Poon, C. S., Shen, L. Y., Austin, S., Hore, A. V., Kehoe, J. G., Mumumllan, R. (2002), “Material Wastage in Construction
and Wong, I. (2009), “Designing out waste and Penton, M. R. (1997), “Construction Activities— A Hong Kong Survey”, CIBW107:
in high-rise residential buildings: Analysis Management Finance Measurement”, Creating a sustainable construction industry

756 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 5(1)2013


in developing countries 11- 13 November,
125-132.

Soibelman, L. (1994), “As perdas de materiais


na construcao de edifica-coes: suaincidencia
e seu controle. (Material waste in building
construction: occurrence and control)”, M.Sc
dissertation Federal Univ. of Rio Grande do
Sul, Porto Alegre, Brazil (in Portuguese).

Tam, V. W., Shen, L. Y., and Tam, C. M. (2007),


“Assessing the levels of material wastage
affected by sub-contracting relationships
and projects types with their correlations”,
Building and Environment, 42(3), 1471-1477.

Teo, S.P., Abdelnaser, O. and Abdul, H. K. (2009),


“ Material wastage in Malaysian construction
industry”, International conference on
Economic and Administration, Faculty of

Administration University of Bucharest


Romania, pp257-264. (UNEP) United Nations
Environment Program. (2007). Buildings and
Climate Change:

Status, Challenges and Opportunities. Available


[online] at: http://www.unep.org/sbci/pdfs/
BuildingsandClimateChange.pdf [Accessed:
25/05/2013]

Urio, A. F. and Brent, A. C. (2006), “Solid waste


management strategy in Botswana: the
reduction of construction waste”, Journal
of the South African Institute of Civil
Engineering. Technical paper 585, 48(2),
pp18-22

(WGBC) World Green Building Council, (2010),


Green Building Facts and Figures. Available
[online] at: http://www.ukgbc.org/system/
files/private/documents/Statistics%20
on%20Green%20Buildings,%20Building%20
Sector%20and%20Climate%20Change.pdf
[Accessed: 25/03/2013]

Yu, A. T., Poon, C. S., Wong, A., Yip, R., and


Jaillon, L. (2012), “Impact of Construction
Waste Disposal Charging Scheme on work
practices at construction sites in Hong Kong”.
Waste Management. pp 138–146

j. o. ameh · e. d. itodo · professionals’ views of material wastage on construction sites and cost overruns · pp 747-757 757

You might also like