Professional Documents
Culture Documents
1 New
1 New
LIMITED
REPORT
ACKNOWLEDGEMENT
PREFACE
This project gives the opportunity to implement the principle
and knowledge practically. The experience that one gets is
wonderful because one study in book is different from what
one face in field.
2
A project helps a student in getting acquainted with the
manner in which his knowledge being practically used and
this is normally different from what one has learnt from
books. Hence one switches from the process of learning to
that of implementation of his knowledge, he finds an abrupt
change. This is why industrial training during B. Tech
curriculum is important
INDEX
1 Introduction 6
3
2 Casting Yard 8
3 Batching Plant 9
5 Fabrications 17
6 Reinforcement 18
7 Concrete 22
8 Grade Of concrete 23
9 Casting Process 24
10 Curing 25
11 Deshuttering 27
4
12 Lifting and Storing in Bay. 29
13 Segment 31
16 Launching girders 38
17 Pre stressing 40
18 Conclusion 42
(1).INTRODUCTION
6
Alignment (Proposed by
Detail Route
DMRC)
Alignment-2 East – West From Prajapati Nagar, along Central Avenue Road, Railway Feeder
Corridor (19.407 km, 20 Road, Munje Square, Jhansi Rani Square, North Ambajhari Road,
stations) Hingna Road, Lokmanya Nagar
7
Stock bins for aggregate, cement, pre stressing material.
Water tank capacity 15000 litres – 2 nos.
Laboratory
Office blocks
Access roads
Gantry 60 T capacity (1 no’s) and 20 T capacity (1nos).
8
Tests conducted for materials are:
1) FOR CEMENT
a) Specific gravity
b) Consistency
2) FOR SAND
a) Moisture content
b) Sieve Analysis
c) Bulk density
3) FOR CONCRETE
a) Compression strength
b) Slump test
c) Permeability
SLUMP TEST
9
AIM : To determine the workability of fresh concrete by
slump test as per IS 1199-1959
APPARATUS
1) Slump cone
2) Tamping Rod
PROCEDURE
10
Types of Concrete Slump Test Results
11
COMPRESSIVE STRENGTH TEST
PROCEDURE
Placing the specimen in the testing machine the bearing
surface of the testing machine shall be wiped clean and any
loose sand or other material removed from the surface of the
specimen. Which are to be in contact with the compression
plates. In the case of cubes the specimen shall be placed in the
machine in such a manner that the load shall be applied to
opposite sides of the cubes as cast, that is, not to the top and
bottom. The axes of the specimen shall be carefully aligned
with the centre of thrust of the spherically seated platen.
13
M25 25 N/mm2
M30 30 N/mm2
M35 35 N/mm2
M40 40 N/mm2
M45 45 N/mm2
M50 50 N/mm2
M55 55 N/mm2
M60 60 N/mm2
M65 65 N/mm2
M70 70 N/mm2
M75 75 N/mm2
M80 80 N/mm2
(5) FABRICATIONS
(6). REINFORCEMENT
PLACEMENT OF REINFORCEMENT
15
Reinforcements are placed according to type of structure
and loading conditions.
In beams, for example, steel bars may be required more
in lower sections and in fixed beams.
The horizontal reinforcements are often tied up with
stirrups.
These stirrups also provide additional strength to the
reinforced cement concrete against shearing stresses.
The reinforcement requires minimum prescribed
covering of concrete.
The covering is essential to protect the reinforcement
from deterioration under attack from weathering agencies
and also from casual fires.
The concrete covering varies from 25mm to 80 mm
depending on the environment in which RCC number has
been placed.
It is important that reinforcement must be clear of rust,
dust, and grease at the time of placement.
This will ensure a better bond between concrete and
reinforcement.
SOME ADVANTAGES OF RCC
Structures made from Reinforced concrete are durable:
It has high compressive strength(due to concrete)
It has high tensile strength (due to reinforcement)
It is resistant to fire and other climate changes.
Easily available almost everywhere in world.
Reinforcement cage
17
(7) CONCRETE
19
Casting of segment by short line method
1) Long line method: All segment of span are
manufactured on a fixed bed with framework moving
along the bed for successive casting operations.
(10) CURING
The exposed concrete surfaces is covered with moist Hessian
Cloth and be maintained moist over entire curing period.
During de-shuttering. Care is taken not to disturb the position
of drainages spouts, shear key and holes for lifting
arrangement. Minimum wet curing is for seven days followed
by moist curing by spraying water which is maintained up to a
total period of 21 days from the date of casting.
20
As an alternative, the segments can also be cured by applying
curing compound duly approved for use. After casting the
segment curing compound shall be applied
On all exposed surface after initial set is achieved and the
21Surf ace is moist and free surface water has disappeared
from concrete surface.
Deshuttering
Sequence of deshuttering
22
The outer form are released by the turn buckles and
moved outwards.
23
Lifting of segment
24
(13) SEGMENT
Pre-casted segment
Segment Launching
26
The method is environment friendly as no concreting
work is carried at site for the superstructure.
27
Female shear keys
29
The economical span (i.e. with optimum pre-stressing
ratio) will be designed for the 25m situation. Standard
span up to 28.0m will be provided throughout the
viaduct as far as possible. At crossings, where spans
require being increased upto 31.0m, simply supported
spans will be provided.
The location where the open foundations are possible,
the spans of 16m are provided.
For major crossing having spans greater than 31.0m,
special units normally of 3 –span construction or steel
girders have been envisaged.
Substructure
30
The transverse spacing between bearings would be 3.2
m.
31
Sequence of Operation during Launching-
1. Assembly of Launching Girder is placed on the top of
pier cap.
2. Segments are lifted by the lifting Beam.
3. Hang the segments by vertical suspender on Sliding
beam.
4. Stressing of Cable is done.
5. After Prestressing, load is transferred to the bearing.
6. Remove the Suspender bar and thus launching of one
span is completed.
32
4. In this method, similar 4. In this method, products are
prestressed members are changed according to structure.
prepared.
(18) CONCLUSION
33
34